Statement of Objectives FRC Return Fan Upgrades.pdf
PDF 102 KB Posted
- Attached to
- Federal Regional Center Return Fan Upgrades Federal contract opportunity
- Solicitation number
- 70FBR023Q00000003
- Issued by
- Federal Emergency Management Agency
About this file
This statement of work outlines requirements for replacing return fans at a Federal Emergency Management Agency regional facility. The contractor shall remove existing fans and install new fan wall arrays meeting specified airflow and control requirements to fit available space. The contractor must submit a project timeline and site work schedule for review prior to starting. All work shall be completed at the FEMA Federal Regional Center in Bothell, Washington within the period of performance stated in the purchase order. The related federal contract opportunity is a solicitation from FEMA seeking these return fan upgrades with a solicitation number of 70FBR023Q00000003. Work hours are from 7 AM to 4 PM Monday through Friday excluding federal holidays, and the contractor must coordinate work with the FEMA facility manager.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DOL Wage Rates Construction.pdf | ||
| 60-02-01 Pg 49.pdf | ||
| Best Value Qualifications V.pdf | ||
| Fan Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL EMERGENCY MANAGEMENT AGENCY | REGION 10
REGION 10 FRC RETURN FAN UPGRADES
STATEMENT OF WORK
AUGUST 2023
A. PROJECT TITLE
Federal Emergency Management Agency (FEMA) Region 10 Federal Regional Center (FRC) Return Fan Upgrades.
B. BACKGROUND
FEMA FRC Bothell has a requirement for replacement of the existing Return Fans which have reached their End of Life.
C. OBJECTIVE
The Contractor shall provide FEMA - Region 10 with all labor, parts and materials to perform work related to remove existing return fans and install new fan wall arrays. Before coming on-site, contact will be made with the Facilities team to ensure FEMA is given a report on every visit with what is completion at the job site.
D. REQUIREMENTS
Contractor to provide construction and renovation services to include:
- Design/manufacture QPAC Fan Array to meet the following requirements.
o CFM & Control requirements for existing HVAC system.
Drawing: Air Supply and Exhaust Schematic Flow Diagram.
o Fit in space available.
Drawing: 60-02-01 page 49 Sections A, B, E, F
- Removal of existing Fan units o Disconnect power o Demo existing fans o Remove existing VFD’s as necessary o Inspect existing power supply from VFD to electrical panel
Replace power wires as necessary.
o Relocate electrical as necessary for new fan arrays
- Installation of new fan arrays o Assemble & Install Fan Arrays o Connect power to Fan Arrays
Electrical work to include the connection to the new QPAC Fans via new Motor Safety Panel with disconnect and controls transformer.
o Connect controls to Fan Arrays Coordinate with FEMA Control Vendor to connect controls o Start up and commissioning of new QPAC Fan Arrays.
E. DELIVERABLE AND DELIVERY SCHEDULE
Project timeline & site work schedule must be submitted to the government prior to start for review. The Contractor must call if there are any changes to the schedule and give a minimum 1-day notice before coming on-site or will not be allowed to enter the facility. All work will be reviewed and accepted by the government upon completion of project milestones. Project shall be completed within the period of performance as stated in the Purchase Order.
F. GOVERNMENT-FURNISHED EQUIPMENT AND INFORMATION
Any work or action indicated to be accomplished by the Contractor, including the furnishing of materials therefore unless otherwise specified, shall be at the Contractor’s expense.
G. PLACE OF PERFORMANCE
The Contractor shall perform work at the following FEMA Region 10 location:
FEMA Federal Regional Center (FRC) Region 10 130 228th ST SW Bothell, WA 98021
H. PERIOD OF PERFORMANCE
The period of performance to be as stated on Purchase Order.
I. SITE SECURITY REQUIREMENTS
Security requirement of this facility grounds include but are not limited to a 100% identification check. All toolboxes, machinery, etc. are subject to random search, and shall not be left unattended in public areas, except by prior approval of the FEMA Region 10 Facility Manager or designee. Such containers and toolboxes shall be locked and secured when unattended and shall be clearly labeled to indicate general contents and a point of contact in case of emergency. The Contractor shall make available and keep a current roster of employees working at the FEMA Region 10 site.
J. SAFETY REQUIREMENTS
In order to provide safety controls for protection of the life and health of employees and other persons; for prevention of damage to property, materials, supplies, and equipment; and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all applicable Federal laws and regulations with such additional measures as the government may deem necessary.
All tools and personal protective equipment required to be provided by the Contractor. The Contractor shall ensure all tools, equipment, and machinery are in good working order.
K. PROJECT WORK HOURS AND SITE ACCESS
Working hours of the building occupants designated to assist with this project are from 7:00AM to 4:00PM
– Monday through Friday, excluding Federal holidays. Work performed under this contract shall be performed during these hours designated above, unless otherwise approved in advanced by the FEMA Region 10 Facility Manager or designee. The Contractor shall coordinate the contracted and/or related work items with the FEMA Region 10 Facilities Manager or designee. The Contractor shall make request for exception to the work hours indicated above to the FEMA Region 10 Facility Manager or designee, at least 48 hours prior to the proposed deviation from the above work hours.