STA UMPQUA RIVER TOWER REPAIR SOW.pdf
PDF 373 KB Posted
- Solicitation number
- 30499PR240000010
About this file
The document provided is a Scope of Work (SOW) for the repair of the electrical panels and wiring at the U.S. Coast Guard Station Umpqua River Watchtower.
The key details are:
- The contractor shall provide all personnel, equipment, tools, transportation, supervision, and other items and services necessary to conduct the repair of the electrical panels and wiring.
- The work includes removing and replacing the main disconnect panel, exterior subpanel, and damaged breakers, as well as replacing the conduit and conductors to the tower.
- The work must be performed in accordance with OSHA, NFPA 70 National Electrical Code, and other applicable safety standards.
- The solicitation number is 30499PR240000010 and is issued as a Request for Quotation (RFQ) with a LPTA award basis. The small business set-aside opportunity is due on June 10, 2024 at 2:00 pm PDT.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1449 30499PR240000010.pdf | ||
| Wage Rates Douglas County Oregon.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
U.S. COAST GUARD
USCG Station Umpqua River Tower Main and Subpanel Repair
SECTION 1 – GENERAL INFORMATION
1.1 Scope of Work:
The contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to conduct the repair of the electrical panels and wiring located at Station Umpqua River Watchtower. The contractor must perform to the standards in this Scope of Work (SOW) contract.
1.1.1 Place of Performance:
1.1.1.1 Unit: Station Umpqua River
Location: 335 Beach Blvd Winchester Bay, OR 97467
1.1.2 Contracting Officer:
1.1.3.1 Name: CWO Edward Csech
Unit: Base Det. North Bend
PH: (571) 607-6100
E-mail: Edward.L.Csech@uscg.mil
1.1.3 Contracting Officers’ Point of Contact (POC):
1.1.4.1 Name: CPO Timothy Labar
Unit: Station Umpqua River
PH: (804) 384-7774
E-mail: timothy.r.labar@uscg.mil
1.1.4 Contact for questions:
1.1.4.1 Any questions regarding scope of work must be directed to the Contracting Officer.
1.1.4.2 Unless specifically annotated below all requests for site visits must be scheduled through the POC.
Requests can be submitted via phone call or e-mail.
1.1.4.3 A site visit is highly suggested but not mandatory.
1.2 Contractor Personnel
1.2.1 Contract Manager:
The contractor must provide a contract manager who must be responsible for the performance of the work.
The name of this person, and an alternate or alternates, who must act for the contractor when the manager is absent, must be designated in writing to the contracting officer.
1.2.1.1 The contract manager or alternate must have full authority to act for the contractor on all contract matters relating to daily operation of this contract.
1.2.1.2 The contact manager and alternate or alternates must be able to read, write, speak, and understand the English language.
1.2.2 Contractor Employees:
The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.
1.2.2.1 Contactor personnel must present a neat appearance and be easily recognized as contractor employees.
1.2.2.2 The contractor must not employ any person who is an employee of the U. S. Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U. S. Coast Guard unless such person seeks and receives approval according to U. S. Coast Guard regulations.
1.2.3 Security Requirements: Due to heightened Security at USCG Facilities, a list of all contractor employees performing tasks related to this scope of work, while onboard a Coast Guard facility, shall be provided to the POC at least 24 hours prior to arrival on the job site. Time spent undergoing entrance to USCG facilities will not be considered a government delay of work or differing site condition.
1.3 Hours of Operation:
The contractor must perform the tasks as required by the SOW under this contract during the following hours: Monday through Friday between 08:00am and 4:00pm unless other time is specified.
1.3.1 Holidays: If applicable.
1.3.2 Special event, or adjusted work hours: If circumstances should arise wherein the contractor desires a different work schedule as required in section 1.3 above, the contractor must request the same in writing.
Submit written request to the Contracting Point of Contact (POC) a minimum of 24 hours before the requested adjusted work schedule. If the desired schedule change is to be effective on a Monday, the request must be submitted to the (POC) prior to 9:00am on the Friday prior to commencement of work.
1.4 Award:
It is the governments’ intent to make award to the low cost responsive offered through issuance of a firm fixed price contract.
1.5 Invoicing:
All invoices from the Contractor shall be submitted electronically IAW FAR 52.232-33, Payment by Electronic Funds Transfer-System for Award Management.
1.4.1 Definitions. As used in these instructions:
1.4.1.1 “Payment request” means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must: comply with the requirements identified in FAR 32.905(b), “Content of Invoices” and the applicable Payment clause included in this contract. In addition, discount offerings and small business status if available shall be stated. If travel was allowable and approved, components in accordance with FAR 31.205-46 shall be provided.
1.4.1.2 Except as provided in paragraph 1.4.1.3 of this clause, the contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP). Information regarding IPP, including IPP Customer Support contact information, is available at www.ipp.gov or any successor site.
1.4.1.3 The contractor may submit payment requests using a method other than IPP only when the contracting officer authorizes alternate procedures in writing in accordance with Coast Guard procedures.
1.4.1.4 If alternate payment procedures are authorized, the contractor shall include a copy of the contracting officer's written authorization with each payment request.
1.4.1.5 IPP enrollment information is at https://www.uscg.mil/fincen/IPP/.
SECTION 2 – DEFINITIONS
2.1 General Definitions:
When the scope of work, solicitation provision, or contract clause uses a word or term that is defined in the Federal Acquisition Regulations (FAR), the word or term has the same meaning as the definition as contained in section 2.101 of the FAR. The FAR index is available via the Internet at http://www.acqnet.gov at the end of the FAR, after the FAR Appendix.
2.1.1 Defective Service: A service or commodity output that does not meet the standard of performance requirement specified in the contract for that service or commodity.
2.1.2 Quality Assurance: A planned and systematic pattern of all government actions necessary to provide confidence that adequate technical requirements are established; products and services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the government assurance functions for a contracted service.
2.1.2 Quality Control Plan: Those actions taken by a contractor to control the production of outputs to ensure that they conform to the contract requirements.
2.1.3 Technical Definitions: Not applicable to contract.
SECTION 3 – GOVERNMENT FURNISHED PROPERTY AND SERVICES
3.1 General Information:
The Government must provide the facilities, equipment, materials, and services listed here:
3.1.1 Government Furnished Facilities: None.
3.2.1 Government Furnished Equipment: None.
3.3.1 Government Furnished Material: None.
SECTION 4 – CONTRACTOR FURNISHED ITEMS AND SERVICES
Except for those items, services, or commodities specifically stated in section 3 as government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.
SECTION 5 - SPECIFIC TASKS/REQUIREMENTS
5.1 General:
The Contractor shall remove and replace damaged main disconnect, adjacent exterior subpanel, and damaged breakers. Contractor shall also replace conduit from exterior subpanel to where conduit connects to conduit on tower base. Contractor shall replace conductors from exterior subpanel to subpanel inside tower.
5.2 Main Disconnect Panel:
5.2.1 The contractor shall replace main disconnect panel with one 200-amp exterior disconnect and two 100-amp fuses. Contractor shall replace with Stainless Steel panel with appropriate NEMA rating for saltwater, sand, rain environment.
5.3 Exterior Sub Panel:
5.3.1 Contractor shall replace exterior subpanel with Stainless Steel panel with appropriate NEMA rating for saltwater, sand, rain environment.
5.3.2 The contractor shall install new breakers to match conductors.
5.4 Conduit and Conductors to Tower:
5.4.1 Contractor shall bury and install new conduit from exterior subpanel to where conduit attaches to tower base and ascends the tower.
5.4.2 Contractor shall install new matching conductors from exterior subpanel to subpanel inside of tower.
5.4.3 All wiring connections, conductor splices or conduit modifications shall be performed IAW current electrical code.
5.5 Interferences:
The contractor shall be responsible for removal and reinstallation or replacement of any/all interferences that may be encountered while completing this SOW.
5.6 Safety:
All work shall be conducted in a safe manner and shall comply with all applicable Federal, State, and local safety standards and requirements. Sector North Bend reserves the right to inspect for compliance with safety standards and requirements. The Contractor shall comply with all Federal, State, and local laws, including OSHA.
5.7 Operations and Storage Facilities:
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the on-site representative with the concurrence of the Contracting Officer.
The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.
SECTION 6 – APPLICABLE PUBLICATIONS AND FORMS
Publications and forms that apply to the PWS are listed below. The publications and forms have been designated as either mandatory or informational. The contractor is obliged to follow those publications and use those forms designated as mandatory to the extent specified in other sections of this scope of work. The contractor must be guided by those publications or use those forms designated as informational to the extent necessary to accomplish requirements in this scope of work.
6.1 Publications:
6.1.1 Mandatory Publications:
6.1.1.1 OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for Construction
6.1.1.2 NFPA 70, National Electrical Code (NEC)
6.1.2 Informational Publications:
File details come from the government source that posted it. Updated .