This is a Statement of Work (SOW) for environmental health and safety services at the National Institutes of Health (NIH), specifically focused on asbestos, lead, and radon management and data handling across NIH-owned and leased facilities.

The contractor must perform surveys, monitoring, sampling, and analysis of hazardous materials at multiple NIH locations including the Main Campus in Bethesda, MD (306 acres, 60 buildings, 5.5 million square feet); the Animal Center in Poolesville, MD (500 acres, 188,000 square feet); leased facilities; Bayview campus at Johns Hopkins University in Baltimore, MD; Rocky Mountain Laboratories in Hamilton, Montana; and Research Triangle Park, NC. The primary deliverables include six core tasks: (1) project estimation and cost proposals with hazmat monitoring and record-keeping; (2) design and permitting documentation including sampling and analysis plans, health and safety plans, and pest management plans; (3) development of Asbestos, Lead, and Radon Management Plans with locations, material descriptions, friability assessments, and chain of custody records; (4) implementation and upkeep of management plans including sampling analysis and contamination mapping; (5) project management and administration support services; and (6) monthly electronic status reports to the Contracting Officer and Contracting Officer's Representative detailing active buildings, costs by task order, and work performed. All work must comply with EPA, OSHA, and Clean Air Act regulations, particularly NESHAP asbestos handling standards. The contractor must furnish all labor, equipment, tools, materials, and transportation; maintain calibrated instruments with documentation every six months; provide spill prevention and control kits; submit quality control plans within thirty days of award; and provide overall health and safety plans, personnel certificates, and invoices within specified timeframes. Services shall be performed during standard business hours (7:00 am to 5:00 pm) with flexibility for non-work hours when required by NIH. The contractor must have hazardous waste certifications, demonstrated experience with biomedical research facility decommissioning, knowledge of asbestos, lead-based paint, lead, and radon contaminants, and expertise in construction debris recycling and hazardous waste minimization. Personnel resumes documenting three years of employment history must be submitted for approval prior to work commencement and when any new personnel are assigned.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Institutes of Health Asbestos and Lead Management

Statement of Work

INTRODUCTION:

The National Institutes of Health (NIH) conducts the world’s largest biomedical research programs. NIH is one of eight health agencies within the Department of Health and Human Services and is comprised of twenty-seven different institutes and centers. All the institutes and centers work together under the Director of NIH to pursue the primary mission of biomedical research.

The Division of Environmental Protection (DEP) is a support unit at NIH that is responsible for providing environmental compliance services pursuant to various federal, state, and local laws or regulations. One of the required compliance services is the development and upkeep of Asbestos and Lead Management Plans. These plans are to be in compliance with the regulations established in the Clean Air Act (CAA), particularly under the National Emission Standards for Hazardous Pollutants – Asbestos (NESHAP) which mandates strict procedures for handling asbestos during demolition, renovation, and disposal to prevent airborne contamination. All work pertaining to the management plans needs to be completed in compliance with applicable Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA), and Clean Air Act (CAA) regulations.

The purpose of this acquisition is to obtain the services of a qualified and experienced contractor to assist the NIH DEP with facility asbestos, lead, and radon data management and field surveys at NIH-owned and leased campuses/facilities.

Additionally, where necessary, other activities related to surveying and sampling of hazardous environmental materials may be necessary to support the program. The contractor shall conduct surveys and maintain records of hazmat data collected as directed by the Contracting Officer (CO) and Contracting Officer’s Representative (COR) of this contract. The primary work is anticipated to be the identification, classification, and documentation of both suspected and confirmed hazards as may be required for the decontamination of NIH spaces to be renovated, having the lease terminated, or demolition.

DEFINITIONS

• ACM: Asbestos-containing materials

• AST: Above ground tank – fuel storage

• Contaminant: A substance whose presence is potentially harmful, hazardous or creates a nuisance

• Decommissioning: The process of evaluation and remediation

• Decontamination: Removal of contamination such that the space meets acceptable environment standards for the next user.

• DPPA: Division of Policy and Program Assessment

• DFOM: Division of Facilities Operation and Maintenance

• DOHS: Division of Occupational Health & Safety, a division of ORS

• DRS: Division of Radiation Safety, a division of the ORS

• ESA: Environmental Site Assessment

• HSA: Historical Site Assessment

• MARSSIM: Multi-Agency Radiation Survey and Site Investigation Manual

• MDE: Maryland Department of the Environment.

• ORF: Office of Research Facilities Development and Operation

• ORS: Office of Research Services

• Remediation: Phase 3 of the Environmental Site Assessment and Remediation

• Selective demolition: Non-structural removal of any item potentially masking contamination

• UST: Underground storage tank – fuel storage

• XRF: X-ray fluorescence

GENERAL REQUIREMENTS

The contractor shall furnish all necessary resources, including labor, management, tools, materials, equipment, and transportation to perform services described herein. Contractor shall meet or exceed the requirements under the federal, state, or local regulations.

Facility drawings, specifications, and other reports may be provided for the development of cost estimates, proposals, and contract modifications. The drawings are diagrammatic and may not show the exact location of all existing mechanical, electrical, controls, and architectural/structural work. Available technical specifications will accompany requests for proposals. The contractor shall provide appropriate documentation to indicate how services will be performed and an estimate of the tasks required to complete the services. The contractor is required to submit permits or documents as required by NIH, federal, state, or local regulations.

The contractor shall maintain a local telephone number and email address where a contractor representative can be reached by the CO or COR. All contract personnel working at NIH facilities shall have the COR’s name and telephone number and shall immediately present this information upon request by appropriate NIH personnel (i.e. NIH Police, security staff).

TASKS

Task 1- Project Estimation and Cost Proposal: Contractor shall perform surveys, monitor hazmat activities, and maintain records of hazmat data. All information shall be sent to the CO and COR.

Task 2 – Design and Permitting: Contractor shall generate and submit necessary documents and/or designs. The documents and designs shall be written for appropriate NIH personnel (i.e. Health and Safety officials, Technical Review officials). Permitting and design may require the completion of studies (i.e. ground-penetrating radar, sampling and analysis plans, health and safety plans, pest management plans). Contractor shall submit clarification comments to the COR to verify the completion of all design and permitting requirements. All information will be sent to the CO and COR first and then forwarded to appropriate personnel unless explicit permission is granted for the documents and/or designs to be directly forwarded to the appropriate approving authority.

Task 3 – Development of Asbestos, Lead, and Radon Management Plan

• Locations of asbestos-containing materials o Building name/address, date of inspection, presence/absence of asbestos-containing building materials (ACBM), to include clear diagrams/blueprints or annotated floor plans showing the location of ACBM (or presumed ACBM)

• Condition of materials o To include friability assessment

• Description of materials, e.g. thermal system insulation, surfacing material, vinyl-asbestos tiles, color, patterns, textures, etc. condition, friability, and any sampling/analyses done (including lab name, certification, date).

• Measures to prevent fiber release

• Potential Response actions (removal, encapsulation, repair)

• Plans for future inspections and recordkeeping

• Chain of custody record-keeping, to include but not limit to name/address of lab, date of analysis, names/signatures of microscopist(s), proof of accreditation

Task 4 – Implementation and Upkeep of Asbestos, Lead, and Radon Management Plan The contractor shall follow the guidelines that are presented in a general form so as to allow flexibility. The purpose of this task is to evaluate potential contaminants, conduct monitoring, sampling, and analysis to determine if (a) contaminants are present, (b) levels are above or below levels requiring decontamination, and

(c) the extent of contamination. Further procedures include:

• Complete sampling and analyses following approval of the SAP.

• Conduct review of data to determine:

o Compliance with QA/QC requirements of SAP.

o If the data is adequate to confirm the presence of target contaminants, relationship to action levels, and extent of contamination.

o Need for additional sampling and analysis.

• Prepare report findings and recommendations:

• Determination of whether contaminants are present or absent as determined by the results of the SAP

• Compare contaminant levels to applicable regulatory requirements, industry clean-up standards and risk reduction goals.

• Map contaminated zones and provide data in a format compatible with NIH DEP standards.

• Recommend remedial efforts in preparation for Phase III or recommend no further action.

The intention of this work is to be as invasive as possible, when possible. However, there may be hard-to-reach or unknown areas that will be uncovered during future activities. If a previously unknown space is revealed and suspect contamination is identified, the contractor shall take appropriate sampling measures of the presumed hazardous material and report findings in an official memo that will follow guidelines outlined in the REPORTING section. Remediation will then address this newly discovered contamination.

Task 5 – Support Services:

The contractor shall provide support services for the following areas:

1. Project management This shall include (but not be limited to) staff, equipment, hardware, and/or software to facilitate project management needs, i.e. reporting, record retention, and/or logistical needs

2. Project administration

This shall include (but not be limited to) staff, equipment, hardware, and/or software to facilitate project administration needs, i.e. project status tracking, cost tracking, deliverable accountability, and/or coordinating update reporting

Task 6 – Reporting: The reports shall support the financial obligation incurred by NIH. The contractor shall provide monthly status reports electronically to the CO and COR and shall include the following: listing of current buildings and rooms active for the contractor, summary of costs by task order, and a general description of services performed.

CONTRACTOR-FURNISHED ITEMS

The Contractor shall provide all facilities, equipment, materials, and services in the performance of the requirements of this agreement. Provide equipment and material of sizes, capacities, power ratings, and dimensions as specified in the individual call order. All equipment supplied shall be compatible with the base building system.

The Contractor shall have available all tools and equipment to perform the work specified herein. No Government owned tools or equipment shall be furnished to the Contractor. The Contractor shall be responsible for the security of his/her equipment and tools.

If a call order requires the use of unusual equipment that the Contractor cannot reasonably be expected to supply, such equipment shall be referred to as "special equipment". The cost to NIH for the Contractor’s use of special equipment will be negotiated as part of the firm fixed price for the call order. Such definition shall be made by the CO.

All work at NIH must be in accordance with applicable standards, including but not limited to Association for Assessment and Accreditation of Laboratory Animal Care (AAALAC); American Institute of Architects (AIA); Americans with Disabilities Act (ADA); Joint Commission for the Accreditation of Healthcare Organizations (JCAHO); International Electrical Testing Association (NETA); National Fire Protection Association (NFPA); NIH Design Policy & Guidelines;

Occupational Safety and Health Administration (OSHA); applicable activity, local, state, and federal standards; and applicable building and safety codes etc.

Other Contractors and/or government forces may be engaged in work in support of the facilities covered by this agreement. The Contractor for this requirement shall coordinate and cooperate with all other contractors to avoid conflicts in work schedules and performance. In the event of conflicts with other contractors that cannot be satisfactorily resolved, the matter shall be referred to the COR for a decision.

Instrumentation Calibration: Calibrate instruments at least every six months or more frequently if required by instrument manufacturer. Keep an updated record of instrument calibration that indicates date of calibration and the name of party performing instrument calibration.

Spill prevention and control kit; the contractor shall have readily available at all times a collection of materials, resources, and/or labor to control or contain a spill, leak, or flooding event. This will include, but not be limited to, caps and valves, wet-vac, flexible tubing, large vessels for storing quantities of liquid, rags, towels, and other items deemed necessary.

CONTRACTOR QUALITY CONTROL

Contractor shall provide a copy of its quality control plan to the COR for review and approval within thirty (30) days after award. The quality control plan shall include the following:

1. A quality control inspection system covering all agreement services.

2. The name(s) and qualifications of the individual(s) tasked to perform the quality control inspections, and the extent of their authority.

3. A method for identifying deficiencies in the quality of services performed and taking corrective actions before the level of performance becomes unsatisfactory.

A file of all quality control inspections, inspection results, and any corrective actions will be maintained by the contractor throughout the duration of the agreement. This file shall be the property of NIH and shall be made available to the CO or COR within one (1) hour of request. The file shall be turned over to the COR within five (5) days after completion or termination of each call order and prior to final payment for each call order.

The quality of the contractor's services shall be monitored by the COR through a continuous program of site inspections, contractor's log inspections, and safety inspections performed by other Government agencies. During these inspections, Government personnel may be present as observers but shall not interfere with services.

MANAGEMENT

The Contractor shall manage the total work effort associated with the services required herein to ensure fully adequate and timely completion and permit tracking of work in progress. Such management includes, but is not limited to, planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide staff with the necessary management expertise to assure the performance of the required work.

The Contractor shall arrange work so as not to cause interference with normal occurrence of NIH business. In those cases where some interference is unavoidable, the Contractor shall make every effort to minimize the impact of the interference and its effects. All work schedules required shall be submitted to and approved by the COR. In no event shall the Contractor change approved work schedules without the prior consent of the COR.

The buildings will be occupied during the performance period. Work shall be scheduled and coordinated with the COR so these areas can remain in operation during the entire construction period. Coordinate all system/power outages/ shutdowns with the COR. NIH may require work to be performed during non-work hours, including evening, weekends or holidays, at the convenience of NIH.

Do not begin work until time schedules and manner of operations have been approved by the COR. All interruptions of existing services shall be included in the schedules as approved by the COR.

When non-essential services have been scheduled on the date a holiday occurs, such services shall be performed on the following working day.

DELIVERABLES

The contractor shall provide the following deliverables to the CO after the requirement is awarded:

Additional Contractor Deliverables Timeframe Overall health and safety plan, to include the following:

A. General assessment of risks posed by services.

B. Safety measures to reduce injuries which may occur via identified risks.

C. Any personal protection equipment (PPE) needed.

D. Emergency measures to be taken in event of an injury.

E. Activity Hazard Analyses for the specific activity

1-2 weeks after award

Current personnel certificates as required to perform services.

1-2 weeks after award

Invoice Upon completion of tasks

REPORTING REQUIREMENTS (PER TASK, AS DEFINED IN TASKS ABOVE)

General:

1. Provide in electronic format

2. Each report shall be accompanied by pictures as applicable.

3. Reports will be first submitted as drafts for any revisions required by NIH.

4. Reports shall be compliant with Section 508 of the Rehabilitation Act of 1973. Additional information about testing documents for Section 508 compliance, including guidance and specific checklists, by application, can be found at: http://www.hhs.gov/web/508/index.html under "Making Files Accessible."

Contractor shall include a list of instruments used for procedures, as applicable. The contractor shall include annual calibration reports on all instrumentation (such as an X-ray fluorescence device) in the reports, if required by the NIH.

The contractor will include photos (when applicable) of the work being performed. The contractor will provide a detailed narrative of what work was performed, when it was performed, by whom it was performed, any challenges presented during the work, and any areas that were inaccessible where work could not be performed.

Unless otherwise specified by the Contracting Officer, the preparation and submission of regularly recurring Technical Progress Reports will be required in the agreement resulting from this solicitation. These reports will require descriptive information about the activities undertaken during the reporting period and will require information about planned activities for future reporting periods.

PLACE OF PERFORMANCE

Services will occur at the following locations:

1. NIH Main Campus, Bethesda, MD (306 acres, 60 buildings, over 5.5 million square feet of space).

2. NIH Animal Center, Poolesville, MD (500 acres, 188,000 square feet of space), thirty miles one-way from NIH Main Campus.

3. NIH Leased Facilities

4. Bayview campus, Johns Hopkins University Baltimore, MD.

5. Rocky Mountain Laboratories, Hamilton, Montana.

6. Research Triangle Park, NC.

ORDERING PROCEDURES

Drawings and/or technical specifications will be provided to the contractor by the CO as part of the request for proposal (RFP) for each call order. Prior to the submission of the proposal for an individual call order, the contractor shall visit the job site to ascertain the actual field conditions as it relates to services described herein and shown on the drawings, forms, lists, charts, etc.

PREPARATION OF PROPOSALS

In response to NIH’s RFP, the contractor shall submit a proposal for each potential call order which includes:

1. A complete list of all tasks necessary to perform services,

2. The projected quantity and costs of materials and equipment to perform services.

Proposals shall be returned to the CO within fourteen (14) calendar days after receipt of the RFPs.

EMERGENCY REQUIREMENTS

The contractor shall provide emergency services within 2 hours after notice from the CO or COR. To the extent possible, emergency services will be defined but may need site inspection by the contractor. The contractor is expected to provide all necessary personnel, etc. as soon as possible after the site inspection.

DUTY HOURS

Services shall be performed during the normal business hours of 7:00 am to 5:00 pm. However, specific work may require services outside of those hours to minimize interference with NIH operations. (May include CLIN for overtime services)

KEY PERSONNEL

The contractor shall provide and maintain, either digitally or on hard copy, the names and phone numbers of his/her key personnel to be called in various repair situations. The personnel shall be reachable by the government during business hours, and when applicable, during non-business hours. When contractor's first available key personnel selection becomes unavailable to render services, the contractor is responsible for providing a back-up with equal or greater knowledge and experience.

CONTRACTOR PERSONNEL QUALIFICATIONS

Minimum Qualifications for Contractor to handle remediation, abatement, and/or chemical decontamination of laboratories at National Institutes of Health are as follows in the enumerated list.

1. Required certifications or worker and supervisor training with hazardous wastes.

2. Past performance of decommissioning activities, described herein, in biomedical research facilities in similar size and scope to those at NIH

3. Knowledge of sources of contaminants to include but not limited to:

• Asbestos

• Lead-based paint

• Lead

• Radon

4. Demonstrated experience in recycling of non-contaminated construction debris

5. Demonstrated experience in hazardous waste minimization and techniques

6. Explanation of means of detection for the contaminants listed above with emphasis on fast verifiable field techniques (for all applicable contaminants)

Prior to commencement of work under this agreement, detailed resumes containing sufficient information to demonstrate compliance with these requirements shall be submitted to the CO or COR for approval. As a minimum, each resume should contain the following:

1. The full name.

2. A detailed description of the previous three (3) years of employment history.

3. The name(s) and address(es) of the companies for whom he or she worked for the past three (3) years, along with the name(s) and telephone number(s) of his or her immediate supervisor.

In addition, detailed resumes shall also be submitted prior to the assignment of any new or replacement personnel to the contract, for approval by the COR.

DEFINITIONS
GENERAL REQUIREMENTS
The contractor shall furnish all necessary resources, including labor, management, tools, materials, equipment, and transportation to perform services described herein. Contractor shall meet or exceed the requirements under the federal, state, or loca...
Facility drawings, specifications, and other reports may be provided for the development of cost estimates, proposals, and contract modifications. The drawings are diagrammatic and may not show the exact location of all existing mechanical, electrical...
TASKS
CONTRACTOR-FURNISHED ITEMS
CONTRACTOR QUALITY CONTROL
Contractor shall provide a copy of its quality control plan to the COR for review and approval within thirty (30) days after award. The quality control plan shall include the following:
A file of all quality control inspections, inspection results, and any corrective actions will be maintained by the contractor throughout the duration of the agreement. This file shall be the property of NIH and shall be made available to the CO or CO...
The quality of the contractor's services shall be monitored by the COR through a continuous program of site inspections, contractor's log inspections, and safety inspections performed by other Government agencies. During these inspections, Government ...
When non-essential services have been scheduled on the date a holiday occurs, such services shall be performed on the following working day.
DELIVERABLES
REPORTING REQUIREMENTS (PER TASK, AS DEFINED IN TASKS ABOVE)
Drawings and/or technical specifications will be provided to the contractor by the CO as part of the request for proposal (RFP) for each call order. Prior to the submission of the proposal for an individual call order, the contractor shall visit the j...
PREPARATION OF PROPOSALS
In response to NIH’s RFP, the contractor shall submit a proposal for each potential call order which includes:
1. A complete list of all tasks necessary to perform services,
2. The projected quantity and costs of materials and equipment to perform services.
Proposals shall be returned to the CO within fourteen (14) calendar days after receipt of the RFPs.

File details come from the government source that posted it. Updated .