This is a Memorandum for Use of Other Than Full and Open Competition for an Acquisition Under the Simplified Acquisition Threshold for a Guard Building to be installed on the USNS POINT LOMA (EPF-15). The document justifies sole-source procurement from Guard Buildings, Inc. for a guard building with a delivery date of 01 MAY 2025, intended for Anti-Terrorism/Force Protection (ATFP) and maritime domain awareness onboard the ship.

The memorandum cites multiple justifications for single-source procurement, including proprietary rights to drawings, standardization with existing T-EPF Class Vessels, and the Navy's lack of manufacturing and technical information to evaluate alternative service and replacement parts. The procurement is driven by the need for compatibility with existing Navy Model 668.6 equipment, with specific maintenance parts and procedures already developed and supported by Military Sealift Command (MSC) personnel and training policies.

View the file

Other files for this federal contract opportunity

Other files attached to USNS POINT LOMA - GUARD SHACK, newest first.
File Type Posted
Combined_Synopsis_Solicitation_25Q2291.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Ver 2.0 (01 June 2018)

Date: 23 JANUARY 2025

MEMORANDUM

Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION UNDER

THE SIMPLIFIED ACQUISITION THRESHOLD

Ref: (a) USNS POINT LOMA (EPF-15) PR Number(s): N2979850374001_1301227459

I. BACKGROUND:

1. In considering the references, FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contacting Officers may solicit from one source if the Contracting Officer determines that, under the circumstances of the contract action, only one source is reasonably available (e.g., urgency, exclusive licensing, brand-name, or industrial mobilization).

2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition because only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.

II. DESCRIPTION OF ITEM OR SERVICE:

1. Provide a description of the item or service required, to include

GUARD BUILDING

a) the name of the required source or brand name

GUARD BUILDINGS, INC

b) the required delivery date/period of performance and

01 MAY 2025

c) its intended use.

ATFP and Maritime domain awareness onboard the ship.

2. List the source(s) or known vendor(s) who are able to provide the above-described item or service.

GUARD BUILDINGS, INC

III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED

ON THE FOLLOWING (select all that apply):

A. __X_ Only one responsible source (select all that apply):

1. _X___ RESTRICTIVE RIGHTS: the source has established proprietary rights, limited rights in data, patent rights, copyrights, or secret processes in the item or service.

a. Explain what is subject to the restrictive rights.

GUARD BUILDINGS LLC OWNS PROPRIETARY RIGHTS TO THE

DRAWINGS OF THE MATERIAL

2 Ver 2.0 (01 June 2018)

b. If drawings are included, who is identified as “owning” the drawings.

GUARD BUILDINGS, INC.

2. _____ EXCLUSIVE LICENSING AGREEMENTS: The item or service is only available from the Original Equipment Manufacturer (OEM), or there is ONLY ONE authorized distributor or technical representative for the OEM.

a. Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.

b. Identify the distributor / authorized technical representative for the item or service.

Provide evidence of the exclusive licensing agreement as an attachment to this document.

(NOTE: If there is more than one distributor / authorized technical representative, then use Part B – Brand Name.)

3. __X__ OTHER REASON:

a. _____ CRITICAL SHIP EQUIPMENT: The required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew or the environment.

i. SMS Procedure Number: ___________________________

b. __X__ STANDARDIZATION / BRAND NAME: Per MSCs standardization initiative, only the specified make/model of the equipment/parts will satisfy the Government’s needs for additional units or replacement items.

i. Identify Make / Model Number(s): GUARD BUILDINGS, INC

ii. Identify other vessels with this Make / Model:

T-EPF Class Vessels / AEL 2-92001M099, HSC 6931116

c. _____ FORM, FIT, AND FUNCTION: Item is direct replacement parts / components for existing equipment and must be compatible in terms of form, fit, and function with existing equipment / configurations.

i. Identify Make / Model of existing equipment:

MODEL: NAVY 668.6

ii. Describe how the equipment must be compatible with the existing configuration.

ABOVE MODEL HAS SPECIFIC MAINTENANCE PARTS,

EQUIPMENT, AND PROCEDURES ALREADY DEVELOPED AND

SUPPORTED BY MSC PERSONNEL AND TRAINING POLICIES.

3 Ver 2.0 (01 June 2018)

d. __X_ OTHER:

MSC DOES NOT HAVE MANUFACTURING AND TECHNICAL

INFORMATION REQUIRED TO EVALUATE AND DETERMINE WHETHER

NON-OEM SERVICE AND REPLACEMENT PARTS OFFERED ARE

EQUIVELANT TO THE OEM COMPONENTS AND REPLACEMENT PARTS.

4. _____ UNUSUAL AND COMPELLING URGENCY: The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits. Urgent requirements are supplies or services that will result in work stoppage, or are mission critical and the routine processing time would injure the Government. The determination that the procurement for the above is an urgent and compelling requirement is based on the following:

a. Date on which the requirement was identified: ______________________________

b. Required delivery date / Period of Performance: _____________________________

c. If the difference between a. and b. is more than one week, explain the delay in submitting the requirement.

d. Estimated production lead time:

e. Explanation of why delivery / commencement of services by the date required is needed: (explain the impact to the mission, any special circumstances or conditions, etc.)

f. CASREP Number: _____________________________________________________

IV. ANTICIPATED DOLLAR VALUE OF PROCURMENT: