SSC SYD88 _Strategic_SATCOM_RFI_28 Jan 26.pdf

PDF 408 KB Posted

Attached to
Strategic SATCOM Space Segment Request for Information (RFI)
Solicitation number
FA8807-STRATSAT-RFI1
Issued by

About this file

RFI Summary: Space Systems Command (SSC) System Delta (SYD) 88 - 2026 Strategic SATCOM Space Segment Reverse Industry Day

This document is a Request for Information (RFI) white paper submission guidance for the Space Systems Command's System Delta 88 (SYD 88) program focused on Strategic Satellite Communications (SATCOM) capabilities using the eXtended Data Rate (XDR) waveform. The RFI, issued for market research and planning purposes only, does not constitute a solicitation or commitment to contract. The submission deadline is February 13, 2026 by 1200 Pacific Time. Responses should be submitted via email to Ms. Tanya Arellano (tanya.arellano@spaceforce.mil) and Mr. Bryce Smyth (bryce.smyth@spaceforce.mil), with copies to the SYD 88 Org Box (syd88.sx.rid@spaceforce.mil). Respondents are advised that submission does not guarantee future contract opportunities, one-on-one meetings, or further engagement, and all participation costs are the vendor's responsibility.

The government seeks industry capabilities and innovations addressing three key technology areas: high-availability XDR communications, resilient architectures, and advanced infrastructure. White papers must not exceed six pages (excluding attachments) and should follow specific formatting requirements (Times New Roman, 12-point, single-spaced, one-inch margins). Required content includes company overview and security readiness, innovation and capability alignment, system integration and technical contribution details, and capability decomposition mapped to system-to-segment requirement elements provided in Appendix B. Respondents must identify which of the three Focus Areas their innovation addresses and provide Technology Readiness Level (TRL), timeline from Authority to Proceed to delivery, and key dependencies. The government will use submitted white papers to inform acquisition planning, evaluate corporate capabilities for classified work, identify capability gaps, and guide potential follow-on engagement. Classified responses may be submitted separately with appropriate coordination. All proprietary information must be clearly marked, and respondents should note any objections to non-government advisor access by contractors such as The Aerospace Corporation, MITRE Corporation, and Booz Allen Hamilton.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

Space Systems Command (SSC) System Delta (SYD) 88 2026 Strategic SATCOM Space Segment Reverse Industry Day

Request for Information (RFI) White Paper Submission Guidance

DISCLAIMER: This RFI is issued solely for information and planning purposes (i.e., market research). This RFI does not constitute a solicitation (Request for Proposal (RFP) or Request for Quotations (RFQ)) or a promise to issue a solicitation in the future. This RFI does not commit the Government to contract for any supply or service whatsoever. Responses to this RFI are not offers and cannot be accepted by the Government to form a binding contract. Furthermore, the Government is not at this time seeking proposals and will not accept any unsolicited proposals. Respondents are advised that the Government will not pay for any information or administrative costs incurred in response to this RFI. All costs associated with responding to this RFI will be solely at the responding party’s expense. Not responding to this RFI does not preclude participation in any future solicitation, if any is issued. Any information submitted by respondents to this RFI is strictly voluntary. Proprietary information will be safeguarded in accordance with the applicable Government regulations. Proprietary information or trade secrets shall be clearly identified.

POINTS OF CONTACT:

Ms. Tanya Arellano: tanya.arellano@spaceforce.mil

Mr. Bryce Smyth: bryce.smyth@spaceforce.mil

CONTRACTING OFFICE ADDRESS:

483 N. Aviation Blvd El Segundo, CA 90245 mailto:tanya.arellano@spaceforce.mil mailto:bryce.smyth@spaceforce.mil

1. Overview Space Systems Command (SSC) / System Delta 88 (SYD 88) will be conducting a reverse industry day in March 2026 to explore achievable innovations that advance technical and operational capabilities for future Strategic Satellite Communications (SATCOM), specifically capabilities making use of the eXtended Data Rate (XDR) waveform. The Strategic SATCOM Reverse Industry Day market research will be structured across the following key technology areas: high-availability XDR communications, resilient architectures, and advanced infrastructure.

Because innovation often happens with non-traditional participants, industry should structure technical and partnering approaches to continuously enable new entrant and non-traditional innovations to contribute to capability in the XDR waveform.

SYD 88 invites interested companies to submit a white paper that outlines their value proposition, relevant experience, and potential approach to addressing one or more of the Focus Areas in Appendix A.

Classified and Unclassified white papers submitted in connection with these events are for market research and planning only. These white papers are not proposals and will not be evaluated for award or procurement purposes.

2. Engagement Objectives

• Seek Industry capabilities and innovations that could result in the rapid deployment of enhanced end-to-end communications capabilities to warfighters through the use of existing industry infrastructure;

rapid prototyping and production of industry-designed hardware or software; or the accelerated incorporation of Industry-developed science & technology into the next-generation of edge and backhaul satellite communications systems.

• Learn about the maturity of industry technologies and capabilities.

• Determine the initial set of capability innovations SYD 88 should focus on for a potential future

Strategic SATCOM acquisition.

3. How the Government Will Use Submitted White Paper

• Inform topic understanding and potential capability gaps.

• Support future acquisition planning (including technology maturation funding where applicable).

• Guide follow-on engagement opportunities where applicable.

• Evaluate corporate capabilities through a structured vetting process for classified strategic communications work.

4. Participation Conditions

• Submission of a white paper does not guarantee a one-on-one meeting, future contract opportunity, or further engagement.

• Participation is voluntary and at the vendor's discretion and expense.

• Submittals including proprietary information SHALL be clearly marked. Respondents shall indicate whether their responses contain any proprietary information if the respondents wish for the responses to be handled as such. The Government shall NOT be held liable for any damage incurred if proprietary information is not properly identified.

5. Submission Instructions and Questions Submission deadline: 13 February 2026 by 1200 Pacific Time. Responses received after the due date may not be considered in the Government’s analysis. Verbal responses will not be accepted.

Questions - Any questions related to the RFI shall be submitted in writing to the SYD 88 Org Box and the Points of Contact (POCs) listed below. The Government cannot guarantee that questions received after 09 February 2026 by 1700 PT will be answered.

Response classification - Respondents shall provide an UNCLASSIFIED, non-confidential, and non-proprietary response to the maximum extent practicable. Responses shall be submitted via email to the POCs and the SYD 88 Org Box identified below. All submissions shall include company name and point of contact information including name, position, telephone number, and email address. No portion of the RFI response delivered to the POCS below shall contain classified information.

CLASSIFIED: SECRET-LEVEL: Email POCs below for coordination. If RFI respondents wish to provide classified white papers, then the Government will provide instructions for delivery on a case-by-case basis. Do not include classified information in your initial response. If companies require classified delivery via certified mail or hand-carry, please contact the POCs below for coordination.

Deliveries must be identified with Company Facility Security Officer, CAGE code, and Security Management Office Code.

POINTS OF CONTACT:

Ms. Tanya Arellano: tanya.arellano@spaceforce.mil Mr. Bryce Smyth: bryce.smyth@spaceforce.mil

SYD 88 Org Box: syd88.sx.rid@spaceforce.mil

The Government may subsequently contact respondents for clarification on the information submitted.

6. Additional Information SAM.gov will be the repository for all information related to this RFI. Respondents are encouraged to monitor the RFI page for any additional details provided by the Government. Optional one-on-one meetings will be held in-person and can be held up to the Secret-level. Further details regarding the one-on-one meetings will be provided at a later date.

7. White Paper Formatting

• Microsoft Office 2007 or later products and/or Adobe Acrobat

• Font: Times New Roman, 12-point.

• Length: No more than six (6) pages (Excluding attachments). The attachments listed below will not count against the page limit.

• Spacing: Single space

• Margins: One inch

• Page size: 8 1/2 X 11 inches

• Attachments include:

o Cover Page and front matter o Executive Summary o Completed Matrix found in Appendix B: Capability Decomposition and Subsystem

Coverage Table o Discussion addressing integration cohort participation

• Email subject line: “Strategic SATCOM RFI – (Company Name)”

• File Name: Company Name_2026 Strategic SATCOM RID RFI Whitepaper

8. White Paper Requested Content A. Company Overview and Security Readiness

• Provide your Company’s name and Parent Company (if applicable), Cage Code (if registered), point of contact (email, address and phone number), and size (small/large business designation; foreign owned/partnered with foreign entity).

• Technical and/or integration background (pedigree enabling provision of innovative technology to the Strategic SATCOM problem space).

• Company infrastructure enabling work in support of national security objectives.

• Examples of current Government contracts relevant to Strategic SATCOM, space communications, resilient networking, or contested operations.

• Facility and Personnel clearance level or Roadmap to address any evident shortcomings in clearance, cleared personnel, facilities, or security-qualified infrastructure.

• Insert the following info only when applicable (Optional):

o Examples of relevant experience supporting nuclear command, control, and communications (NC3) missions or strategic SATCOM challenges (clearly identify scope: application layer, terminal hardware, waveform/signal processing, network services, integration).

o Descriptions of previous experience with survivable communications systems supporting “nuclear deterrence and the nation’s survival in, though, and after war” applications.

B. Innovation and Capability Alignment

• Identify the innovation and where it fits in the Strategic SATCOM system of systems (architecture, subsystem/component, waveform/signal processing, integration, operations, etc.).

• Identify which Market Research Focus Area(s) are addressed and provide a short mapping of the innovation to those areas (see Appendix A: Market Research Focus Areas).

• Describe the value the company brings to Strategic SATCOM acquisition challenges.

• Describe the anticipated contribution to the overall end-to-end capability, including partnerships, integration opportunities, or areas of technical leadership.

• Highlight capabilities supporting contested environment operations (AJ, LPI/LPD/LPG, EMI resistance, cyber resiliency, survivability, assured access).

• Innovative solutions for allied integration into strategic SATCOM architecture

• Maturity of the innovation (TRL/MRL), roadmap to TRL 6 where applicable, and the top risks to successful maturation (technical, schedule, integration, security, supply chain).

• Estimated timeline from Authority to Proceed (ATP) to delivery of a prototype/first unit/capability:

Describe the technology development timelines.

C. System Integration and Technical Contribution

• Outline how the innovation integrates into the Strategic SATCOM system of systems; state what interface and integration details are known vs. what must be developed/discovered (ICDs, message formats, crypto, timing/synchronization, spectrum/bands, command/control).

• Identify current or planned teaming arrangements and how teaming benefits Government objectives (speed, resiliency, interoperability, transition risk reduction).

• Identify dependencies for successful integration (collaboration with other companies, ICD availability, modifications to adjacent systems/components, Government Furnished Equipment/Information (GFE/GFI/GFX), data and test access).

• Identify assumptions or external needs (GFE/GFI, data rights, range access, classified test environments, escrowed keys, waveform labs, terminal availability).

• Describe integration approach with existing strategic user and command terminals (FAB-T, In-Band C2, Out-of-Band C2) where applicable.

D. Capability Decomposition and Subsystem Coverage (from System-to-Segment Requirements)

• State which portion(s) of the end-to-end capability the company can provide (space segment, payload, antennas/beamforming, crosslinks, TT&C, autonomy, survivability/hardening, ground entry points, ground stations, networks, user terminals, waveform/signal processing, cyber).

• Map capabilities to the System-to-Segment requirement elements found in Appendix B: Capability Decomposition and Subsystem Coverage Table

9. Integration Cohort Participation The Government is exploring an acquisition strategy for Strategic SATCOM utilizing the concept of an integration cohort. Companies are made aware that this includes:

• Participation in a Government-facilitated integration cohort with other selected vendors under mutual

NDAs and controlled information-sharing processes.

• Expectation to collaborate on interface definition, ICD maturation, MBSE artifacts, and integration test planning with a designated prime/integrator.

• Cohort success measured on end-to-end capability performance (integration of subsystem contributions into an operationally relevant capability), not on standalone component demonstration.

• Ability to support rapid integration cycles: technical interchange meetings, lab integration, on-orbit/ground demonstrations where applicable, and timely delivery of interface data and integration support.

• Identification of any constraints on information sharing (proprietary, export control, licensing) and proposed mitigations consistent with NDAs and Government objectives.

10. Disclaimer on Non-Government Advisor Access This RFI is issued solely for information and planning purposes (market research) to inform future Strategic SATCOM requirements. As part of a comprehensive market research and technical review process, please be advised that data and information submitted to the Government for these reverse industry day engagements may be shared with other Government agencies, partners, Federally Funded Research and Development Center (FFRDC), and Advisory and Assistance Services contractors supporting the Government. Non-Government support contractors may be involved in the review and analysis of any responses submitted. Non-Government support contractors may include but are not limited to The Aerospace Corporation (FFRDC), MITRE Corporation (FFRDC), Johns Hopkins University Applied Physics Laboratory, KBR, Booz Allen Hamilton (BAH), Software Engineering Institute at Carnegie Mellon, Tecolote, and their subcontractors

If a Respondent has any objections to a non-Government advisor having access to its data or information, the Respondent SHALL notify the Government immediately and must clearly state this restriction in the cover letter accompanying the RFI response.

Appendix A: Market Research Focus Areas

The Government’s priorities are to:

• Improve resiliency of future strategic SATCOM constellations

• Provide rapidly manufacturable XDR capability

• Establish multi-manifest capabilities to rapidly launch/replenish and lower overall launch cost

• Create resilience through modularity, open systems, and disaggregated architecture

• Improve timeline for materiel adaptation to technology and threat changes

The rest of this Appendix describes areas where Companies can help the Government understand technologies enabling the priorities above.

Focus Area 1: High-Availability XDR Communications

• Advanced interference processing.

• High availability of access and communications: path diversity, robust access link, and increased link margin to disadvantaged users.

• On-board virtualization of critical waveform parameters and, where applicable, complete algorithms.

• Guaranteed throughput in a contested nuclear environment or high-level plasma state.

• Integrated mitigation techniques: physical layer and spatial processing, excision, AI-enabled spectrum threat identification/adaptation, and network-layer repudiation/cyber protection.

• Approaches combining LPD objectives with anti-jam robustness.

• Virtualized and/or reconfigurable processing at mission tempo.

Focus Area 2: Resilient Architecture

• Defensive, zero trust cyber architecture capable of surviving concerted state actor attack on space or ground assets.

• Proliferated, multi-orbit architecture with common bus and diverse payloads.

• Onboard/offboard technologies that mitigate threats.

• C2 comm path diversity from Resilient Ground Architectures

• Distributed architecture ground entry points, front end processing, RFoF connectivity

Focus Area 3: Infrastructure

• Technology to improve performance and/or cost objectives.

• Improved link performance and ubiquity while resisting EMI attack.

• Reduce satellite delivery schedule and SWAP to meet agile procurement goals.

• Advanced hardening techniques.

Appendix B: Capability Decomposition and Subsystem Coverage Table

Company to use the following table to map capabilities to the System-to-Segment requirement elements.

If the capability/technology is not applicable, the row should be left blank.

Requirement Element

What to Provide

TRL /

Maturity ATP→Delivery

Timeline

Key Dependencies (ICDs, GFE/GFX, Data, Teaming)

Uplink frequencies Bands supported; tunability;

channelization;

regulatory/export limits

Downlink frequencies

Bands supported; tunability;

channelization;

regulatory/export limits

XDR waveform Waveform name/standard;

key characteristics;

interoperability; maturity

Spacecraft reconfiguration timing

Reconfigurable functions;

time-to-reconfigure; triggers;

constraints

Arctic coverage (performance)

Data rates/throughput by scenario; link budgets;

assumptions

Link to Arctic-based ground stations

Supported sites/interfaces;

backhaul; latency; constraints

Minimum required daily coverage

Minutes/day; revisit;

elevation masks; availability assumptions

Crosslinks—data rates

Supported crosslink rates;

scaling; contention approach

Crosslinks— implementation

RF/optical; protocols;

pointing; networking approach

Crosslinks—power levels

Tx/Rx power ranges; duty cycle; thermal impacts

User terminal alignment

Supported terminals/interfaces;

constraints; certification path

Uplink beamforming

Beam agility; steering method; coverage modes;

Arctic ops

Downlink beamforming

Beam agility; steering method; coverage modes;

Arctic ops

Spacecraft antenna options

Antenna types; gain;

pointing; size/weight; rad-hard

TT&C—in-band Command & Control (C2) network

In-Band TT&C architectures, interfaces, security; C2 processing, monitoring/telemetry

TT&C—

Government out-of-band SCN network

SCN interface approach;

separation/assurance;

constraints

Ephemeris propagation

Ephemeris sources; update cadence; onboard/ground processing

Constellation management

Planning/scheduling;

autonomy; conflict resolution; tools

Spacecraft autonomy minimum duration

Minimum independent ops duration; degraded modes;

recovery

Survivability requirements

Threats addressed; resilience mechanisms; margins

Endurance

Lifetime; consumables;

degradation; maintenance strategy

Integration with specified external Government ground networks

Network(s) supported;

interfaces; data formats;

accreditation

Cybersecurity

Zero trust posture;

authN/authZ; monitoring;

compliance

Defensive cyber operations protocols

IR processes; patching; key management; logging/audit

System availability Availability targets; drivers;

redundancy; maintenance

Threat response Detect/assess/respond loops;

timelines; automation level

LPI/LPD/LPG Techniques used; tradeoffs;

performance impacts

Anti-jamming Mitigations; sensing;

adaptation; tested results

Shielding—non-contested environment

Baseline environment assumptions; shielding approach

Shielding— contested / anti-jam environment

EMI/EA assumptions;

protection approach;

validation

Shielding—nuclear environment

Hardening approach;

standards; testing heritage

Appendix C: Acronym List AJ — Anti-Jam ATP — Authority to Proceed authN/authZ — Authentication / Authorization BAH — Booz Allen Hamilton EA — Electronic Attack EMI — Electromagnetic Interference FAB-T — Family of Advanced Beyond Line-of-Sight Terminals FFRDC — Federally Funded Research and Development Center FOC — Full Operational Capability FY — Fiscal Year GFE — Government Furnished Equipment GFI — Government Furnished Information GFX — Government Furnished (catch-all term used in the document alongside GFE/GFI) ICD — Interface Control Document IOC — Initial Operational Capability IR — Incident Response KBR — Kellog, Brown and Root (government services contractor) LPD — Low Probability of Detection LPI — Low Probability of Intercept LPG — Low Probability of Geolocation MBSE — Model-Based Systems Engineering MIT — Massachusetts Institute of Technology MRL — Manufacturing Readiness Level NC3 — Nuclear Command, Control, and Communications NDA — Non-Disclosure Agreement PMO — Program Management Office PT — Pacific Time RF – Radio Frequency RFI — Request for Information SATCOM — Satellite Communications SCN — Satellite Control Network SIPRNet — Secret Internet Protocol Router Network SMIL — “.smil.mil” (SIPRNet email domain) SPM — System Program Manager SSC — Space Systems Command SWaP — Size, Weight, and Power SYD 88 — System Delta 88 TRL — Technology Readiness Level TT&C — Telemetry, Tracking, and Command XDR — eXtended Data Rate

1. Overview
2. Engagement Objectives
3. How the Government Will Use Submitted White Paper
4. Participation Conditions
5. Submission Instructions and Questions
6. Additional Information
7. White Paper Formatting
8. White Paper Requested Content
9. Integration Cohort Participation
10. Disclaimer on Non-Government Advisor Access
Appendix A: Market Research Focus Areas
The Government’s priorities are to:
Focus Area 1: High-Availability XDR Communications
Focus Area 2: Resilient Architecture
Focus Area 3: Infrastructure
Appendix B: Capability Decomposition and Subsystem Coverage Table
Appendix C: Acronym List

File details come from the government source that posted it. Updated .