Answers to Site Visit Questions

View the file

Other files

File Type Posted
loading dock ceiling-Model.jpg JPG image
SOW Supply Building Repairs-Revised.doc DOC document
Pre Proposal Conference Notes.pdf PDF
Amendment 3 Cover Sheet.pdf PDF
Answers to Site Visit Questions 2.doc DOC document
Amendment 1 Cover Sheet.pdf PDF
PostAward Documents.doc DOC document
MD100037 Wage Determination.pdf PDF
RFTOP-1st Task Order.doc DOC document
MD10001 Wage Determination.pdf PDF
SOW Supply Building Repairs.doc DOC document
SSA-RFP-10-1039.doc DOC document
Solicitation Cover Sheet.pdf PDF
Reference Documents.doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.) Can you give the "Manufacturer's name & Mech. & Electr. capacities" for the (8) eight Hot Water Heaters?

This is in the new SOW.

2.) Can you confirm that (1) one layer of 5/8" FC drywall is required or (2) two?

This is in the new SOW.

3.) Can you specif. for the painting-latex, epoxy or custom colors? How many coats?

This is in the new SOW.

4.) Can you confirm what locations for the new wall mount Thermostats? The existing HW Heater controls are all "Strap-on-aquastats" for controlling the HW Heaters, do you still want the aquastats as controllers or new T'stats only?

To match existing.

5.) Can we use 18 x 18 or larger Access Panels for the electrical JB's?

This is in the new SOW.

6.) Does the drywall track/grid need to be UL or any fire rated (hours)?

This is in the new SOW.

7.) Do the HW Heaters or piping contain any asbestos, lead paint, or any contaminants or hazardous materials?

This will be examined and cleaned before the start of the project by our environmental team.

8.) Can you give the "Manufacturer's name & Electr. capacities" for the (8) eight THERMOSTATS for the new Hot Water Heaters?

This in the new SOW.

9.) What type of construction is the existing "rook/deck" slab-(concrete, DOX plank, poured gypsum, etc.?

This is in the new SOW.

10.) What is the thickness of the existing deck?

This is in the new SOW.

11.) Can we remove "some pieces" of the existing board insulation to install anchoring for the metal track?

Yes.

12.) Can you give an approximate location-or lineal footages-for the T'stat locations & conduit runs?

See print for location. Existing conduits can be reused with new wire.