This Sources Sought Notice is for the Little Robber Detention Dam Reconstruction project issued by the Bureau of Land Management (BLM) in Carbon County, Wyoming. The project involves comprehensive dam repair and reconstruction, including unwatering the reservoir, excavating existing dam embankments, reconstructing the embankment, constructing new outlet works and toe drain systems, and reclaiming disturbed areas. The anticipated construction magnitude is between $1,000,000 and $5,000,000, with a projected performance period of 395 calendar days after notice to proceed.
The solicitation is seeking market research from both large and small businesses, with a small business size standard of $45 million under NAICS code 237990. BLM plans to issue a request for proposals in May 2025, with responses to this Sources Sought Notice due by 22 April 2025 at 8:00 AM MT. Interested parties are instructed to complete a Microsoft form via a provided web link. The government anticipates requiring bid, performance, and payment bonds, and will use the responses to determine potential small business or socio-economic set-asides for the future solicitation.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
BUREAU OF LAND MANAGEMENT
National Operations Center Denver Federal Center, Building 85
P.O. Box 25047 Denver, Colorado 80225-0047 www.blm.gov
LITTLE ROBBER DETENTION DAM RECONSTRUCTION
140L0625B0005 | Sources Sought Notice
Purpose: This is a Sources Sought Notice for the purpose of conducting market research, to gain knowledge regarding the type of interested businesses and their qualifications. Responses are being requested from both large and small businesses.
Proposals are NOT being requested, nor accepted at this time. The Bureau of Land Management (BLM) will use information obtained through this notice to develop an acquisition strategy.
The government anticipates conducting a competitive acquisition for this requirement. The amount of interest or lack thereof will determine the possibility of a small business or other socio-economic small business set-aside for the solicitation. Quality of responses received will be considered when making any small business set-aside determinations for this requirement.
Not responding to this announcement does not preclude participation in any future solicitation. If a solicitation is released, it will be synopsized on SAM.gov. It is the responsibility of the potential offerors to monitor the site for additional information pertaining to this requirement.
Cost Reimbursement: Response to this announcement is strictly voluntary. No reimbursement will be made for any costs associated with providing information in response to this notice or any follow-up information requests.
Project Description: The Bureau of Land Management (BLM) has a requirement for repairing the Little Robber Dam, located in Carbon County, approximately 11 miles north of Baggs, WY. Major items include:
A. Unwater the reservoir and dewater the construction area. B. Excavate a portion of the existing dam embankment and foundation to remove the existing outlet works structures and construct the new outlet works. C. Excavate the downstream slope of the dam embankment to remove vegetation, and the existing toe drain system. D. Excavate the upstream slope of the dam embankment to remove vegetation and salvage the existing riprap. E. Reconstruct the dam embankment. F.
Construct a toe drain system consisting of drainpipes, precast concrete manholes, flow measurement flumes, and imported sand and gravel. G. Construct new outlet works. H. Excavation, grading, and salvaging existing riprap in the spillway;
placement of salvaged and imported riprap in the spillway channel. I. Place imported road gravel surfacing along the crest of the dam. J. Reclaim (preparation of soil and seeding) all disturbed areas, including construction staging areas and temporary roads.
The work covered by this contract includes furnishing all labor, material, equipment, and incidentals necessary to complete this requirement per the accompanying specifications and drawings.
Anticipated Period of Performance: 395 calendar days after issuance of the notice to proceed.
Magnitude of Construction: Between $1,000,000 and $5,000,000.
North American Industry Classification System (NAICS) code: 237990 | Other Heavy and Civil Engineering Construction.
Small Business Size Standard: $45 million.
Solicitation: The BLM anticipates issuing a request for proposals in May of 2025.
Bonding: The BLM anticipates that bid, performance, and payment bonds will be required.
Submission/Response Contents: Interested parties are encouraged to respond to this Sources Sought by copying and pasting the link below into a web browser; then fill out the associated Microsoft form.
https://forms.office.com/g/J6wLS2gawU
Submittal Due Date/Time: 22 April 2025 8:00 AM MT.