This is Amendment 0001 to Solicitation SPRRA2-26-R-0022, issued by the Defense Logistics Agency (DLA), Aviation and Missile Center (AMCOM) at Redstone Arsenal, Alabama. The amendment modifies the set-aside requirement and extends the solicitation closing date. The set-aside has been changed from Women-Owned Small Business (WOSB) to 100% Small Business Set-Aside. The solicitation closing date has been extended to 4:00 PM Central Standard Time on March 19, 2026, from the previously established deadline of March 20, 2026 at 5:00 PM.

The solicitation pertains to the supply of Patriot weapon system components under a Firm Fixed Price contract type. Three contract line items (CLINs) are included: CLIN 0001AA for Contractor First Article Testing of cable assemblies (1 unit), CLIN 0001AB for Production Quantity of cable assemblies (19 units), and CLIN 0001AC for First Article Test Report submission. All items are identified under PRON D15H0886D1 (Amendment 04). Packaging requirements mandate MIL-STD-129 markings, Military preservation level, and Packing Level B, with wood packaging material compliance to WPM-15 standards. Inspection and acceptance occur at origin for CLINs 0001AA and 0001AB (FOB Destination) and at origin inspection with destination acceptance for CLIN 0001AC (FOB Destination). The contract incorporates extensive technical requirements including soldering standards (ANSI/J-STD-001, Class 3), parts control programs, counterfeit risk management, lead-free control plans, and first article test procedures. Payment processing is to be conducted through Wide Area WorkFlow (WAWF) using the specified DoDAAC SPRRA2 for routing.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req No. 5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code) 9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print) 16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Firm Fixed Price

SPRRA2

DEFENSE LOGISTICS AGENCY

5201 MARTIN ROAD/DLA-AVN-AH

REDSTONE ARSENAL AL 35898-7340

DARIN BRANCH

EMAIL: DARIN.BRANCH@DLA.MIL

SPRRA2-26-R-0022

2025SEP10

X

X 2026MAR20 05:00pm

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 15

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: DARIN BRANCH

Buyer Office Symbol/Telephone Number: AHD/AHD2/(256)924-7901

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

Weapon System: Patriot

*** End of Narrative A0000 ***

A-1. THE PURPOSE OF AMENDMENT 0001 TO SOLICITATION SPRRA2-26-R-0022 IS TO CHANGE THE SET ASIDE AND EXTEND THE SOLICITATION CLOSING DATE.

A-2. AS A RESULT, THE SET ASIDE HAS BEEN CHANGED

FROM: WOMEN-OWNED SMALL BUSINESS (WOSB) SET-ASIDE

TO: 100% SMALL BUSINESS SET-ASIDE

A-3. THE SOLICITATION CLOSING DATE HAS BEEN EXTENDED. THE SOLICITATION SHALL CLOSE AT 4:00 PM CENTRAL STANDARD TIME (CS) ON 19 MARCH

2026.

A-4. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.

*** END OF NARRATIVE A0002 ***

2 15

SPRRA2-26-R-0022

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

0001AA CONTRACTOR FIRST ARTICLE TESTNG 1 EA $ $ _______________________________ ______________ __________________

COMMODITY NAME: CABLE ASSEMBLY,FIBE

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: D15H0886D1 PRON AMD: 04

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 MARKINGS SHALL APPLY

UNIT PACK: 001 INTERMEDIATE PACK: 000

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Packaging and Marking: _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 Markings Shall Apply

UNIT PACK: 001

INTERMEDIATE PACK: 000

LEVEL PRESERVATION:

Military

LEVEL PACKING: B

ALL WOOD PACKAGING MATERIAL(WPM) MUST BE WPM-15

COMPLIANT.

THE FOLLOWING MIL-STD-2073-1,

APPENDIX J CODES SHALL APPLY:

JI/A/MP [41] JII/CD [1]

JIII/PM [00] JIV/WM[00]

JV/CD [NA] JVI/CT [A]

JVII/UC [ED] JVII/IC [00]

JIX/A/PK [F] JX/SM [00]

JVIIIA/OPI [M]

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES)

WT [5.5]

LN [18.0]

WD [18.0]

DP [14.0]

SUPPLEMENTAL PACKAGING INSTRUCTIONS: COIL CABLE

CAP/CUSHION CONNECTORS

3 15

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Government Approval/Disapproval Days: 30

(End of narrative F001)

0001AB Production Quantity 19 EA $ $ ___________________ ______________ __________________

COMMODITY NAME: CABLE ASSEMBLY,FIBE

PRON: D15H0886D1 PRON AMD: 04

Packaging and Marking _____________________

Packaging and Marking:

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 Markings Shall Apply

UNIT PACK: 001

INTERMEDIATE PACK: 000

LEVEL PRESERVATION:

Military

LEVEL PACKING: B

ALL WOOD PACKAGING MATERIAL(WPM) MUST BE WPM-15

COMPLIANT.

THE FOLLOWING MIL-STD-2073-1,

APPENDIX J CODES SHALL APPLY:

JI/A/MP [41] JII/CD [1]

JIII/PM [00] JIV/WM[00]

JV/CD [NA] JVI/CT [A]

JVII/UC [ED] JVII/IC [00]

JIX/A/PK [F] JX/SM [00]

JVIIIA/OPI [M]

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES)

WT [5.5]

LN [18.0]

WD [18.0]

DP [14.0]

SUPPLEMENTAL PACKAGING INSTRUCTIONS: COIL CABLE

CAP/CUSHION CONNECTORS

4 15

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

0001AC FIRST ARTICLE TEST REPORT 1 EA $ ** NSP ** $ ** NSP ** _________________________ ______________ __________________

COMMODITY NAME: CIRCUIT CARD ASSEMB

CLIN CONTRACT TYPE:

Firm Fixed Price

Packaging and Marking _____________________

FIRST ARTICLE TEST REPORT WILL BE SENT ELECTRONICALLY

TO: DLAHSVPOSTAWARDTEAM@DLA.MIL

IF THE FILE IS TOO LARGE OR ENCRYPTION IS NEEDED, A

DOD SAFE LINK WILL BE SENT TO YOU FOR UPLOAD USING

HTTPS://SAFE.APPS.MIL/ PLEASE USE THE

DLAHSVPOSTAWARDTEAM@DLA.MIL EMAIL ADDRESS TO REQUEST THE LINK".

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

5 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION G - CONTRACT ADMINISTRATION DATA

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

G-1 CHANGED 252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023) JAN/2023

(a) Definitions. As used in this clause

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003 , Electronic Submission of Payment Requests and

Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003 , Electronic Submission of Payment Requests and

Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov ; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice

Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the

WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer

Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

COMBINATION INVOICE/RECEIVING REPORT

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

CLINS 0001AA & 0001AB:

ORIGIN/ORIGIN

FOB DESTINATION

CLIN 0001AC:

ORIGIN/DESTINATION

FOB DESTINATION

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

6 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC N/A

Issue By DoDAAC SPRRA2

Admin DoDAAC** N/A

Inspect By DoDAAC N/A

Ship To Code W90BTD

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) N/A

Service Acceptor (DoDAAC) N/A

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or

"Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

N/A

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

7 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H-6.

1. Notwithstanding any other provision contained in any part of this contract to the contrary, the minimum requirements/standards for soldering electrical and electronic assemblies shall be the non-military joint industry standard, ANSI/J-STD-001, Class 3. The revision of ANSI/J-STD- 001 in effect on the effective date of the contract shall govern the hardware produced hereunder. A copy of ANSI/J-STD-

001 may be obtained from the Institute for Interconnecting and

Packaging Electronic Circuits (IPC), 3000 Lakeside Drive, 105N, Bannockburn, IL, 60015, https://www.ipc.org.

2. The contractor shall establish and maintain an electronic/electrical parts control program and shall maintain and make available to the Government records and data which will provide visibility and traceability of all parts used in the production of the equipment under this contract. This selection of parts shall not be construed to relieve the contractor of meeting specified performance of the end item in which the part is used.

3. The Technical Data Package (TDP) shall serve as the baseline Program Parts Selection List (PPSL) and the parts and sources listed therein are the standard parts and sources. A Non-Standard Part is defined as a part or source other than that cited in the PPSL. When the contractor desires to use a part or source other than those cited in the PPSL, the change must be approved by the Government via a

Request for Deviation (RFD) as defined elsewhere in this contract. Failure on the part of the contractor to submit such RFDs may result in the replacement of the nonstandard part with the standard part by the Government at the contractor's expense for all affected items.

4. The contractor shall provide objective evidence such as form, fit, function, and interchangeability data that shows the proposed part complies with the requirements of applicable parts documentation. The RFD shall detail the technical justification for the use of the part and advantages of the nonstandard part, if any. Compare the nonstandard part to the standard part whose characteristics are nearest to those required for the application. Include, when applicable:

a. Part Number and Source

b. Size and weight data.

c. Electrical and mechanical characteristics

d. Reliability (with data if requested)

e. Availability of the standard part (delivery schedules, still available etc.)

f. Supplemental data such as existing control drawings, specifications, vendor data sheets, and other pertinent data. Data need not be furnished for nonstandard parts covered by documents listed in the Department of Defense Index of Specifications and Standards (DoDISS) or Standardized Military Drawings (SMD).

5. The Contractor shall maintain a Lead Free Control Plan (LFCP) and make available to the Government upon request. The requirement for a Lead Free Control Plan shall be flowed down to suppliers of equipment that may include lead-free materials. The LFCP shall follow the guidelines set forth in GEIA-STD-0005-1, "Performance Standard for Aerospace and High Performance Electronic Systems Containing Lead-

Free Solder" or its equivalent. In addition, the LFCP shall also include tin whisker mitigation plans in accordance with GEIA-STD-0005-

2, "Standard for Mitigating the Effects of Tin Whiskers in Aerospace and High Performance Electronic Systems" or its equivalent, at control level 2C or equivalent. The Contractor should include in the LFCP any special design considerations, manufacturing process controls, test and qualification requirements, quality inspection and screening, marking and identification, maintenance and repair processes, and other steps taken to mitigate risk.

6. The Contractor shall prepare, or update existing, Counterfeit Risk Management Plan and make available to the Government upon request.

The Plan shall meet the requirements of SAE AS5553 for electronic items. The Contractor shall procure parts from original manufacturers or the original manufacturers' franchised distributors. Contractors shall report counterfeits and suspected counterfeits to the

Government and in the Government Industry Data Exchange Program (GIDEP), in accordance with the GIDEP Operations Manual, SO300-BT-PRO-

010.

H-7. ENGINEERING CHG PROPOSAL, VALUE ENG CHG PROPOSAL, REQUEST

FOR VARIANCE, ENG RELEASE RECORDS, NOTICE OF REVISION, AND

SPECIFICATION CHG NOTICE PREPARATION AND SUBMISSION

INSTRUCTIONS

1. Contractor initiated Engineering Change Proposals (ECPs), Value Engineering Change Proposals (VECPs), and Request for Variance

(RFVs), collectively referred to as "proposals", shall be prepared, submitted and distributed in accordance with paragraphs 2, 3 and 4 below except as specified in paragraph 5 below.

2. Format.

a. Class I ECPs require the "Long Form Procedure" for documenting the change and describing the effects of the change on the suitability and supportability of the Configuration Item (CI). Class I ECPs should be limited to those that are necessary or offer significant benefit to the Government. Class I ECPs are those that affect the performance, reliability, maintainability, survivability, weight, balance, moment of inertia, interface characteristics, electromagnetic characteristics, or other technical requirements in the specifications and drawings. Class I ECPs also include those changes that affect Government Furnished Equipment, safety, compatibility, retrofit, operation and maintenance manuals, interchangeability, substitutability, replaceability, source control specifications and drawings, costs, guarantees or warranties, deliveries, or schedules. Class II ECPs are those that do not affect form, fit and function, cost, or schedule of the system

CI and do not meet the other criteria described above for Class I ECPs.

8 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

b. Long Form Procedure: Class I changes to the CI require that DD Form 1692, pages 1 through 7 (as applicable), be prepared. Use of this procedure assures that all effects of the change on the CI are properly addressed and documented to the necessary detail to allow proper evaluation of the proposed change.

c. Short Form Procedure: ECPs and VECPs, which meet the requirements of Class II

ECPs, shall be prepared using DD Form 1692 (page 1 only). Supplemental pages may be used with the form as necessary. The responsible

Defense Contract Management Agency (DCMA) Contract Management Office (CMO) will validate data entries in Block 5 "Class of ECP", Block6

"Priority", and Block 8 "Justification Codes."

d. The Contractor shall not manufacture items for acceptance by the Government that incorporate a known departure from requirements, unless the Government has approved an RFV. RFVs shall be prepared using DD Form 1694.

e. Each ECP and RFV shall be accompanied by a written and signed evaluation prepared by the responsible Defense Contract Management Agency (DCMA) technical representative. The DCMA written evaluation shall be considered part of the ECP/RFV proposal.

f. Classification of RFVs.

(1) Major RFVs. RFVs written against CIs shall be designated as major when the RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation involving health;

performance; interchangeability; reliability; survivability; maintainability; effective use or operation; weight; appearance (when a factor); or when there is a departure from a requirement classified as major in the contractual documentation.

(2) Critical RFVs. RFVs written against CIs shall be designated as critical when the RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation involving safety or when there is a departure from a requirement classified as critical in the contractual documentation.

(3) Minor RFVs. RFVs written against CIs shall be designated as minor when the RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation which does not involve any of the factors listed above in paragraphs f(1) or g(2), or when there is a departure from a requirement classified as minor in the contractual documentation.

g. Proposals shall include sufficient technical data to describe all changes from existing contract requirements.

h. Proposals shall include sufficient justification for making the change, including a statement of contract impact, if the change is not authorized.

i. Proposals for ECPs shall set forth a "not to exceed" price and delivery adjustment acceptable to the Contractor if the Government subsequently approves the proposal. If approved, the equitable increase shall not exceed this amount.

j. Times allowed for technical decisions for ECP and RFV proposals will be worked out via mutual agreement between the Contractor and the Government.

k. Proposals for VECPs shall set forth a "not less than" price and delivery adjustment acceptable to the Contractor if the Government subsequently approves the proposal. If approved, the savings shall not be less than this amount.

l. The Contractor shall utilize DD Form 2617, "Engineering Release Record" (ERR) to release new or revised configuration documentation to the Government for approval.

m. The Contractor shall utilize DD Form 1695, "Notice of Revision" (NOR) to describe the exact change(s) to configuration documentation specified as a data requirement in the contract. The Contractor shall describe the change using sub-sections entitled "WAS" to describe the current contractual technical requirement and "IS" to describe the proposed new requirement.

3. Submittal. The preferred method of submittal is digitally as a single file in Adobe Acrobat Portable Document Format (PDF). Unless otherwise specified, alternate methods of submittal shall be proposed to and authorized by the PCO prior to submittal. If the hardcopy method is requested and approved, the Contractor shall submit two (2) copies of each proposal to the responsible Administrative

Contracting Officer (ACO). One (1) copy of each proposal shall be returned to the Contractor within (5) working days after receipt by the ACO, stating whether or not the proposal is in compliance with this provision. Any unresolved differences between the ACO and the Contractor concerning ECPs, VECPs, or RFVs will be submitted to the PCO for resolution.

4. Distribution.

a. Electronic Distribution. The preferred method of distribution for unclassified is through the email or DOD safe site

(https://safe.apps.mil) addressed to the PCO. Classified material shall be distributed via SIPERNET or by classified email as determined by the PCO. Microsoft Word is required for use with the transmittal letter (E-mail). Required forms will be attached to the E-mail. All forms may be obtained from the Office of the Secretary of Defense Executive Services Directorate DoD Directives Division website

(http://www.esd.whs.mil/DD/) via the DoD Forms menu. The forms are provided in fillable Adobe Acrobat Portable Document

Format (PDF). In order to access and use the forms, the user must have the "Adobe Acrobat" software installed on their computer.

Drawings may be scanned and sent as an attachment. In some cases, because of size, drawings may have to be sent as hard copies or sent under special electronic instructions provided by the PCO.

5. Alternate Format, Submittal or Distribution Process. Proposals may be prepared in a different format, submitted using a different submittal process or distributed in a different manner than specified in paragraphs 2, 3 and 4 above, so long as the alternate approach is in accordance with a Government approved configuration management plan governed by this contract or the PCO authorizes the alternate format, submittal, or distribution process.

6. Government Acceptance. Acceptance of a proposal by the Government shall be affected by the issuance of a change order or execution of a supplemental agreement incorporating the proposal into the contract unless the PCO authorizes another method of acceptance. The

9 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Government will notify the Contractor in writing if a proposal is determined to be unacceptable.

H-14. NOTICE: ENVIRONMENTAL TEST (AVN & MSL)

Item(s) or components thereof which are subjected to environmental tests of a destructive nature or which otherwise degrade the quality of the item(s) shall not be furnished to the Government in satisfaction of this contract.

H-19. REVISIONS TO DRAWINGS/PART NUMBERS REQUIREMENT (AVN & MSL)

(a) Sources in receipt of this solicitation are requested, at no cost to the Government, to immediately notify the Contracting Officer if they are aware of any change(s)/revision(s) to the drawing(s) or part number(s) in this solicitation which have been approved by the

Government for implementation. Notification of part number changes shall be supported by data which indicates the type of change, approving authority as required by ANSI EIA 649 MIL-STD-973 and date and method of submittal of provisioning documentation and drawings.

If complete data package has not been previously provided, the contractor shall, at no direct cost to the Government, immediately submit applicable drawings, along with a copy of the approval change authority, to the Contracting Officer, at the office symbol and mailing address listed in the "ISSUED BY" block on page one (1) of this document. The minimum acceptable data includes the next higher assembly and the item of Supply Detail Drawings which will allow provisioning, National Stock Number assignment and updating of AMCOM's data records.

(b) The contractor hereby verifies previous contractual submission of technical data:

Contract No.:

Contractor:

Explanation of Data Rights:

(c) The Government is not by this request soliciting, nor is the Government liable for cost incurred by the offeror in preparing or developing modifications, deviations, waivers, or other changes to drawings or part number(s). Furthermore, this request does not authorize changes to the drawing(s) or part number(s) for this acquisition, another contract, or for any other purpose.

Offerors performing any contract awarded as a result of this solicitation must comply with the drawing(s) and specifications as set forth herein, unless this solicitation is amended or any resulting contract is modified by the Contracting Officer.

(d) All proposed part number changes shall be submitted pursuant to the requirements of the requirement entitled, " ENGINEERING CHG

PROPOSAL, VALUE ENG CHG PROPOSAL,REQUEST FOR VARIANCE, ENG RELEASE RECORDS, NOTICE OF REVISION, AND

SPECIFICATION CHG NOTICE PREPARATION AND SUBMISSION INSTRUCTIONS"

H-12. IDENTIFICATION MARKING REQUIREMENTS (AVN & MSL)

Item shall be marked per MIL-STD-130.

H-5. DEFENSE PRIORITY AND ALLOCATIONS SYSTEM (DPAS) RATED AWARDS

Defense Priorities and Allocations System (DPAS) Rated Awards (JUNE 2025)

A DPAS rated order indicates the priority the contractor must give to the performance of the award. There are two priority ratings: "DX" and "DO". All "DX" rated orders have equal priority with each other and take preference over "DO" rated orders and unrated orders. All

"DO" rated orders have equal priority with each other and take preference over unrated orders. (see 15 CFR 700.11 and DoDM 4400.1-M).

Mandatory Contractor Performance Scheduling

A contractor must schedule operations, including the acquisition of all needed production items, in a timely manner to satisfy the delivery requirements of each DPAS rated order. Additionally, contractors are required to use DPAS rated orders with their U.S. suppliers to obtain items needed to fill rated orders (15 CFR 700.15). Contractors may also use DPAS rated orders to obtain replacements of inventoried items used to fill rated orders (see 15 CFR 700.17(b)).

Modifying production or delivery schedules is necessary only when required delivery dates for a rated order cannot otherwise be met. Since "DX" indicates the highest rated order, the manufacturer will schedule its production before processing other lower or unrated orders. "DX" rated orders must be given production preference over "DO" rated orders and unrated orders if necessary to meet required delivery dates, even if this requires the diversion of items being processed or ready for delivery against unrated orders. Similarly, "DO" rated orders must be given preference over unrated orders. If an accepted rated order of equal priority status conflicts with other accepted rated orders of equal priority status, the contractor must prioritize the rated orders in the sequence in which the rated orders are to be delivered or performed (see 15 CFR

700.14).

Contractor Acceptance of a DPAS rated order:

[Contractors receiving an award that includes a DPAS rating shall advise DLA via the post award mailbox (DLAHSVPostAwardTeam@dla.mil) , if they cannot perform in accordance with the requirements of the applied DPAS rating. When rejecting an order in full, communication to the contracting officer must include a detailed reason for rejection. If the order can be fulfilled at a later date, the contractor must provide, a) the earliest possible delivery date, b) a detailed reason why the awarded delivery date cannot be met (e.g. reason should not simply state a

10 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

production delay) and, c) an offer to accept the order based on that date. Contractors must advise

DLA within fifteen (15) working days after receipt of a "DO" rated order, and within ten (10) working days after receipt of a "DX" rated order if they cannot perform in accordance with the

DPAS rating. Contractors that do not contact DLA are self-attesting that they acknowledge receipt of the award and will conform to the DPAS rating requirement. If the prescribed response time has passed and the contractor learns that shipment or performance will be delayed, the contractor is still required to notify DLA immediately.

Special Priority Assistance:

Preferential scheduling is a must for DPAS rated orders (see 15 CFR 700.14). If a contractor learns that a shipment or performance will be delayed after the allotted response time has passed or any other issue arises that will affect deliveries during the duration of the contract, the contractor is required to notify DLA immediately through the use of Form BIS-999, Special

Priorities Assistance (SPA). Deviations from schedules cannot be approved without the completion and submission of this form. Once submitted, DLA and its customers will discuss the

SPA for approval. The Department of Commerce requires an approved BIS-999 prior to reprioritizing DPAS rated orders and its schedules (See 15 CFR 700.50). Please contact DLA post award for any SPA questions or concerns.

H-9. FIRST ARTICLE TEST - CONTRACTOR TESTED - ADDITIONAL

REQUIREMENTS (AVN & MSL)

a. The first article shall be inspected and tested by the contractor in accordance with the requirements of the contract. The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement. If applicable, the Contractor or its subcontractor shall produce or demonstrate proof that any fixtures, tool masters, jigs, or similar devices used in the inspection and/or testing of the first article have been subjected to an initial inspection, or other suitable means supporting their accuracy, before being used in the manufacturing/production process.

b. At a minimum, first article inspection and test shall include:

(1) A 100% inspection (or as set forth in relevant specifications) of all physical and functional characteristics, to include but not limited to, any drawings, as well as any other requirements which may be set forth by other applicable specifications, or in any technical data packages, and/or any other special/functional testing as set forth in this contract;

(2) A review of parts, components and/or assemblies for compliance to identification markings;

(3) A review of packaging for compliance to preservation, packaging, packing, and marking requirements;

(4) A review for compliance within the Technical Data Package or as otherwise stated in this contract that approved manufacturing sources have been used for special processes, controlled parts, components, and/or assemblies;

(5) The verification through documented evidence that all inspection, testing, measuring and diagnostic equipment used in the inspection/test of the first article piece(s) have been subjected to an initial inspection, or other means supporting their accuracy, and are maintained in accordance with contractual calibration standards.

c. Unless otherwise specified in the contract, the contractor shall NOT retain the first article provided under this contract to serve as the manufacturing standard of acceptance.

d. A First Article Test Report (FATR) shall be prepared and submitted in accordance with FAR

52.209-3. The report will include all necessary documentation to demonstrate and support full compliance with the first article inspection and test requirements as set forth in this contract

(including supplier's and vendor's inspection records and certifications, when applicable). The

FATR shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specifications and/or Quality

Assurance Provision (QAP) requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. The FATR shall contain sufficient narrative content, technical data, illustrations or photographic evidence, and an objective determination by the contractor to allow the designated Government representative to determine that the First Article test was successfully completed.

e. Additional first article testing may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of 3 years, or (iii) whenever a change occurs in place of performance, manufacturing locations or processes, material used, drawing, specification or source of supply.

When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for the additional first article sample or

11 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Should the Government require additional first article testing the Contractor may be entitled to an equitable adjustment.

H-20. SOURCES ELIGIBLE FOR AWARD CONSIDERATION (AVN & MSL)

(a) Competition under this solicitation is restricted to the following sources:

(1) Approved Sources listed in Section B -- sources that have been approved by the prime manufacturer or the Government for supply of item(s) listed in this solicitation, to assure the requisite safe, dependable, effective operation and support of military equipment.

(2) Sources that have been approved prior to award -- other than approved sources listed in

Section B.

(3) Non-manufacturers--offers from non-manufacturers (distributors) will only be considered for award if the required item(s) is new material and has been or will be obtained from a source of supply which has been approved prior to award. The source and part number of the item the offeror intends to supply must be stated in the offer.

(b) Only offers submitted by the above sources will be considered for award under this solicitation.

(c) Offerors (prospective manufacturers or non-manufacturers [distributors]) who wish to become an approved source of supply for an item listed in this solicitation should proceed per the instructions set forth in paragraph (d) below. It is noted that offeror requests for source approval in conjunction with this procurement will not be a cause for delay in this solicitation action.

However, if it is determined that additional sources will clearly benefit the Government and that any delay incident to their approval would not impact readiness, a reasonable delay may be entertained. Whether or not such delay will occur will be solely at the discretion of the

Government, and the time set for opening of the Invitation for Bids or the closing date of the

Request for Proposals may or may not be extended. An extension will be witnessed by issuance of an amendment to this solicitation.

(d) Offerors (prospective manufacturers or non-manufacturers [distributors]) seeking to obtain source approval, must submit a Source Approval Request (SAR) package, for review and approval, to the Systems Readiness Directorate (SRD), Aviation and Missile Center, DEVCOM.

Source approval must be obtained prior to being considered for contract award. Approvals are made on an individual part number basis for a specific manufacturing location (CAGE). SAR instructions can be found at https://www/avmc.army.mil/Directorates/SRD/SAR/. Questions concerning SAR submissions can be directed to the SRD SAR Team at usarmy.redstone.devcom-avmc.mbx.amr-m-sar@army.mil.

(e) The Aviation and Missile Lifecycle Management Command (AMCOM) may require additional data, testing, or plant visits before it is able to completely evaluate a SAR. This may require the offeror (at no expense to the Government) to supply parts for testing, engine run up, or flight tests. In that event, the requestor will be so advised. AMCOM reserves the right to approve a contractor for award prior to completion of physical testing of the offered item. In such cases, the contractor shall perform any outstanding tests and provide all required documentation at no cost to the Government prior to entering upon full production. Lack of successful performance within the specified timeframe shall be grounds for a no cost termination.

(f) When a SAR is received, it will be processed for evaluation. If the evaluation and approval

(including preparation or update of the requisite technical data package (TDP)) occurs before award, the requestor will be considered for award if a proposal was submitted per (d) above. If the evaluation/TDP preparation has not been completed prior to award, AMCOM will continue the process until complete. If the requestor's SAR becomes approved, the requestor will be eligible for consideration on all future solicitations for the item.

(g) All approval or disapproval notices shall be officially provided to the contractor by the appropriate technical official.

(h) Non-manufacturers (distributors) seeking to supply an item from a non-approved source must first ensure that the source becomes approved in accordance with (d) above prior to contract award.

H-22. WOOD PACKING MATERIALS REQUIREMENTS (AVN & MSL)

A. Wood packaging material (WPM) means wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. The definition excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSD).

B. All Wood Packaging Material (WPM)) acquired by DOD must meet requirements of

International Standards for Phytosanitary Measures (ISPM) 15, "Guidelines for Regulating

Wood Packaging Materials International Trade." DOD shipments inside and outside of the

United States must meet ISPM 15 whenever WPM is used to ship DOD cargo.

12 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KD HT) in accordance with American Lumber Standard Committee, incorporated (ALSC) Wood Packaging Material Program and WPM Enforcement Regulations

(see http://www.alsc.org/).

(2) All WPM shall include certification/quality markings in accordance with the ALSC standard.

Marking shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.

C. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment at entry. The Agency reserves the right to recoup from the Contractor any remediation costs incurred by the Government.

D. Replacement Preservative for Pentachlorophenol

If packaging requirements of this contract specify the use of wood products and a preservative is required, Pentachlorophenol, commonly referred to as "Penta" or "PCP" is prohibited.

Replacement preservatives are 2 percent copper naphthenate, 3 percent zinc naphthenate or 1.8 percent copper 8 quinolinolate.

(1) Heat Treatment: Boxes/pallets and any wood used as inner packaging made of nonmanufactured wood shall be heat-treated. All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard

Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure traceability to the original source of heat treatment.

(2) Marking: Each box/pallet shall be marked to show the conformance to the International Plant

Protection Convention Standard. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens: on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood process verified in accordance with their National Plant Protection Organization's compliance program. In addition, wood used as dunnage for blocking and bracing shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.

*** END OF NARRATIVE H0001 ***

13 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

*** END OF NARRATIVE L0001 ***

14 15

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION M - EVALUATION FACTORS FOR AWARD

Section MEvaluation

Evaluation Criteria

Minimum technical requirements. To be technically acceptable and thus, eligible for award, a proposal must conform to ALL solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements provided within all sections of this solicitation and/or within its attached addenda. Proposals receiving a technical rating of "Unacceptable" will be ineligible for award.

Price. In addition to meeting the solicitation's technical and quantity increment or range requirements above and cost and pricing requirements below, the Government will evaluate a proposal's pricing for reasonableness. Evaluation of a proposal's pricing will not obligate the Government to order the estimated quantities or to distribute orders in the manner evaluated. The Government may reject a proposal as "Unacceptable", if its pricing is determined to be materially unbalanced.

Cost and Pricing Data. Offerors must provide all cost or pricing information required by FAR 15.4. Failure of a proposal to provide cost or pricing information required by FAR 15.4 will result in said proposal being deemed Unacceptable, and thus, ineligible for award.

Basis of Award

Lowest Priced Technically Acceptable (LPTA). In acquisitions in which more than one proposal is received, proposals will be evaluated using the Lowest Priced Technically Acceptable (LPTA) evaluation procedure to make a best value award decision. In these situations, the

Government will award to the offeror which submits a technically acceptable proposal, with the lowest overall price. Because the

Government intends to make an award based on the initial proposals, offerors are encouraged to make their best offers, initially;

however, if the deemed necessary, the Government reserves the right to enter discussions.

Technical Acceptability. To be technically acceptable, a proposal must conform to ALL solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements provided within the solicitation or within its attached addenda. Proposals receiving a technical rating of "Unacceptable" will be ineligible for award.

*** END OF NARRATIVE M0001 ***