Text version

REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of

(This is NOT an Order)

1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating

See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)

See Schedule

7. Delivery

FOB Other Destination

5B. For Information Call: (Name and telephone no.) (No collect calls)

8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)

See Schedule

10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.

Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. Schedule (Include applicable Federal, State, and local taxes)

Item Number (a)

Supplies/Services (b)

Quantity (c)

Unit (d)

Unit Price (e)

Amount (f)

(See Schedule)

12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage

NOTE: Additional provisions and representations are are not attached.

13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation

16. Signer

a. Name (Type or Print) b. Telephone

Area Code

c. Title (Type or Print) Number

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)

X

SPRRA1-18-Q-0052 2016APR26 DOA1

SPRRA1DEFENSE LOGISTICS AGENCY

5201 MARTIN ROAD/DLA-AVN-AH

REDSTONE ARSENAL AL 35898-7340

ERICA ALLEN (256)955-9253

DLA-AVN-AHA

EMAIL: ERICA.ALLEN@DLA.MIL

X

2018MAY31

1 53

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

THE FOLLOWING AMENDMENTS HAVE BEEN INCORPORATED

Buyer Name: ERICA ALLEN

Buyer Office Symbol/Telephone Number: DLA-AVN-AHA/(256)955-9253

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

1. THIS REQUIREMENT IS 100% SMALL BUSINESS SET-ASIDE IN ACCORDANCE WITH FAR 19.502-2. ONLY OFFERS FROM SMALL BUSINESS FIRMS WILL BE

CONSIDERED.

2. THIS REQUIREMENT IS IN SUPPORT OF THE BK CH-47 (CHINOOK) WEAPON SYSTEM.

3. FLIGHT SAFETY/CRITICAL SAFETY ITEM (CSI) IS NOT REQUIRED. ______

4. PRODUCTION LOT TESTING (PLT) IS NOT REQUIRED. ______

5. FIRST ARTICLE (FAT) IS REQUIRED. __

6. FAT UNIT SHALL NOT BE RETAINED AS A MATERIAL STANDARD. TEST ITEM WILL NOT BE DESTROYED AS PART OF TESTING. _________

7. SNRR MARKINGS ARE NOT REQUIRED. _______

8. TAMMS-A MARKINGS ARE NOT REQUIRED. _______

9. IUID MARKINGS ARE NOT REQUIRED. _______

10. RFID MARKINGS ARE NOT REQUIRED. _______

11. ARMS EXPORT CONTROL NOT APPLICABLE. ___

12. SERIAL NUMBERING IS NOT REQUIRED. ______

13. FIT CHECK IS NOT REQUIRED. ______

14. THIS IS A THREE YEAR INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ), FIRM FIXED PRICE EFFORT.

15. CONTRACTOR POINT OF CONTACT INFORMATION:

NAME: ___________________________________

TELEPHONE NUMBER: ___________________________________

E-MAIL ADDRESS: ________________________________________

16. FUNDS WILL BE OBLIGATED/CITED UPON ISSUANCE OF EACH DELIVERY ORDER.

17. ACCELERATED DELIVERY IS ENCOURAGED AND AUTHORIZED AT NO ADDITIONAL COST TO THE GOVERNMENT

18. HISTORY FOR COMPETITIVE BUYS:

SPRRA1-114-D-0081 190 EACH 396.75 U/P 18 APRIL 2011

CONTRACTOR FIRST ARTICLE TEST

FIRST ARTICLE TEST TIME IS 3 DAYS. UNITS TO BE TESTED IS 1 EACH. FIRST ARTICLE TEST SHALL BEGIN ON A MUTUALLY AGREED UPON DATE BETWEEN _ _

THE GOVERNMENT AND THE CONTRACTOR. THE DATE SHALL OCCUR WITH ENOUGH TIME IN ADVANCE TO BEGIN SCHEDULED DELIVERIES 540 DATA. THE ___

CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER IN WRITING 30 DAYS PRIOR TO THE PROPOSED DATE OF FIRST ARTICLE. THE PREFEREED METHOD OF __

TRANSMITTAL IS CD. THE GOVERNMENT HAS 30 DAYS TO APPROVE/DISAPPROVE THE TEST REPORT. __

THE FIRST ARTILCE TEST UNIT WILL NOT BE DESTROYED AS PART OF THE TESTING.

2 53

SPRRA1-18-Q-0052

REPRINT

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

THIS SOLICITATION INCLUDES PROVISION 52.215-9023, REVERSE AUCTION. A REVERSE AUCTION MAY BE CONDUCTED, OFFERORS ARE ENCOURAGED TO ACCESS

THE PROCUREX SYSTEM AND REVIEW THE REVERSE AUCTION HELP TUTORIALS AT: WWW.DLA.PROCUREXINC.COM TO LEARN MORE ABOUT HOW TO PARTICIPATE IN

AN AUCTION.

*** END OF NARRATIVE A0001 ***

THIS AMENDMENT 0001 TO SOLICITATION SPRRA1-18-Q-0052 IS ISSUED TO EFFECT THE FOLLOWING:

A-1. TO CORRECT THE ISSUE DATE OF SOLICITATION

READS AS:

2016 APR 26

SHOULD READ AS:

2018 APR 30

A-2. NO OTHER CORRECTIONS OR CHANGES AT THIS TIME.

*** END OF NARRATIVE A0002 ***

3 53

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 STEERING BAR, AIRCRAFT

NSN: 1730-01-299-8688

Mfr CAGE: 81996

Mfr Part Number: 1730-CHSE-001-02

THIS IS A THREE YEAR INDEFINITE DELIVERY INDEFINITE

QUANTITY (IDIQ) SOLICITATION.

FUNDS WILL BE OBLIGATED /CITED UPON THE ISSUANCE OF

EACH DELIVERY ORDER.

THE GOVERNMENT WILL ONLY BE OBLIGATED TO ORDER THE

STATED MINIMUM QUANTITY. THE GOVERNMENT IS NOT

OBLIGATED TO ISSUE ANY ADDITIONAL ORDERS AGAINST THIS

CONTRACT; HOWEVER, THE GOVERNMENT RESERVES THE RIGHT

TO ORDER UP TO THE MAXIMUM QUANTITY.

THE GOVERNMENT HAS SEGREGATED THE POTENTIAL QUANTITIES

INTO THREE ORDERING PERIODS. HOWEVER, THIS DOES NOT

PRECLUDE EXERCISING ITS RIGHTS UNDER FAR 52.216-19 BY

ORDERING THE MAXIMUM QUANTITY SPECIFIED IN FAR 52.216-

19(b)(1) AT ANY TIME DURING THE INDEFINITE QUANTITY

PERIOD.

THE GOVERNMENT'S MINIMUM QUANTITY TO BE AWARDED

SIMULTANEOUSLY WITH THE AWARD OF THE BASIC CONTRACT IS

23 EACH.

THE GOVERNMENT'S MAXIMUM QUANTITY DURING THE

INDEFINITE QUANTITY PERIOD IS 63 EACH. THE DELIVERY

ORDER MINIMUM ORDER QUANTITY IS 20 EACH.

PRICES QUOTED FOR EACH ORDERING PERIOD WILL BE VALID

FOR ALL QUANTITIES ORDERED DURING THAT ORDERING

PERIOD. THE SOLICITATION IS FOR THE SUPPLIES AS

DETAILED ON THE FOLLOWING PAGES.

OFFERORS ARE CAUTIONED TO INSURE THAT OFFERS ARE

PROVIDED ON ALL QUANTITIES. FAILURE TO PROPOSE ALL

CLINS, WILL RESULT IN A DETERMINATION OF NON

RESPONSIVENESS.

ORDERING PERIOD 1 WILL BE FROM DATE OF AWARD

THROUGH DAY 365 DAYS AFTER CONTRACT AWARD (DACA).

ORDERING PERIOD 2 WILL BEGIN 366 DACA AND END 730

DACA. ORDERING PERIOD 3 WILL BEGIN 731 DACA AND END

1,095 DACA.

THE CONTRACTOR SHALL PROVIDE UNIT PRICES FOR EACH CLIN

BELOW. ALL REFERENCES TO F.O.B. ORIGIN THROUGHOUT THIS

SOLICITATION APPLY ONLY TO ALL QUANTITIES ORDERED

AFTER THE FIRST ORDERING PERIOD.

THE ESTIMATED (E) QUANTITY LISTED HEREIN DOES NOT

COMMIT THE GOVERNMENT TO ORDER THAT OR ANY QUANTITY

ABOVE THE MINIMUM QUANTITY.

4 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

THE GOVERNMENT INTENDS TO AWARD ONLY ONE BASIC

INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT AS A

RESULT OF THIS SOLICITATION.

(End of narrative A001)

0001AA YEAR 1 (ONE) WITH FIRST ARTICLE TESTING 23 EA $ $ _______________________________________ ______________ __________________

PROGRAM YEAR: 1

COMMODITY NAME: STEERING BAR, AIRCRAFT

CLIN CONTRACT TYPE:

Firm Fixed Price

THE GOVERNMENT WILL AWARD EITHER CLIN 0001AA OR

0001AC.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: STDP 1730CHSE001

REVISION: C

DATE: 02-NOV-2017

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 MARKINGS SHALL APPLY

UNIT PACK: 001 INTERMEDIATE PACK: 000

LEVEL PRESERVATION: Military

LEVEL PACKING: A

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES):

WT [74.0]

LN [105.0]

WD [22.0]

DP [7.0]

ALL WOOD PACKAGING MATERIAL (WPM) MUST BE ISPM-15

COMPLIANT.

MIL-STD-2073-1 CODES, APPENDIX J:

JI/A/MP [10] JII/CD [1] JIII/PM [00] JIV/WM [FA]

JV/CD [LK]

JVI/CT [F] JVII/UC [F2] JVII/IC [00]

JIX/A/PK [F] JX/SM [00] JVIIIA/OPI [M]

SUPPLEMENTAL INFORMATION:

WPM MUST BE ISPM-15 COMPLIANT

5 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Destination

SHIP TO:

(SW3211) DLA DISTRIBUTION DEPOT OKLAHOMA

3301 F AVE CEN REC BLDG 506 DR 22

TINKER AFB OK 73145-8000

TINKER AFB,OK,73145-8000

DELIVERIES SHALL COMMENCE 540 DAYS AFTER RECEIPT OF

ORDER (DARO).

(End of narrative F001)

0001AB FIRST ARTICLE TEST REPORT 1 EA $ ** NSP ** $ ** NSP ** _________________________ ______________ __________________

PROGRAM YEAR: 1

COMMODITY NAME: STEERING BAR, AIRCRAFT

CLIN CONTRACT TYPE:

Firm Fixed Price

FIRST ARTICLE TEST TIME IS 3 DAYS. UNITS TO BE TESTED IS 1 EACH. _ _

FIRST ARTICLE TEST SHALL BEGIN ON A MUTUALLY AGREED UPON DATE

BETWEEN THE GOVERNMENT AND THE CONTRACTOR. THE DATE SHALL OCCUR

WITH ENOUGH TIME IN ADVANCE TO BEGINE SCHEDULED DELIVERIES 540 ___

DACA. THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER IN

WRITING 30 DAYS PRIOR TO THE PROPOSED DATE OF FIRST ARTICLE __

TESTING. THE FIRST ARTICLE TEST REPORT IS DUE 15 DAYS AFTER FAT. __

THE PREFERRED METHOD OF TRANSMTTAL IS CD. THE GOVERNMENT HAS

30 DAYS TO APPROVE/DISAPPROVE THE TEST REPORT.__

THE FIRST ARTILCE TEST UNIT WILL NOT BE DETROYED AS

PART OF THE TESTING.

(End of narrative B001)

Packaging and Marking _____________________

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

6 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 3

DEL REL CD QUANTITY DEL DATE __________ ______________ ___________

001 1 AS REQUIRED

FOB POINT: Destination

SHIP TO:

(SPRRA1) DLA AVIATION AT HUNTSVILLE, AL

DLR PROCUREMENT OPERATIONS (AH)

5201 MARTIN ROAD

REDSTONE ARSENAL,AL,35898-7340

0001AC YEAR 1 (ONE) WITHOUT FIRST ARTICLE TESTING 23 EA $ $ __________________________________________ ______________ __________________

PROGRAM YEAR: 1

COMMODITY NAME: STEERING BAR, AIRCRAFT

CLIN CONTRACT TYPE:

Firm Fixed Price

THE GOVERNMENT WILL AWARD EITHER CLIN 0001AA OR

0001AC.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: STDP 1700CHSE001

REVISION: C

DATE: 02-NOV-2017

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 MARKINGS SHALL APPLY

UNIT PACK: 001 INTERMEDIATE PACK: 000

LEVEL PRESERVATION: Military

LEVEL PACKING: A

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES):

WT [74.0]

LN [105.0]

WD [22.0]

DP [7.0]

ALL WOOD PACKAGING MATERIAL (WPM) MUST BE ISPM-15

COMPLIANT.

MIL-STD-2073-1 CODES, APPENDIX J:

JI/A/MP [10] JII/CD [1] JIII/PM [00] JIV/WM [FA]

JV/CD [LK]

JVI/CT [F] JVII/UC [F2] JVII/IC [00]

7 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

JIX/A/PK [F] JX/SM [00] JVIIIA/OPI [M]

SUPPLEMENTAL INFORMATION:

WPM MUST BE ISPM-15 COMPLIANT

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Destination

SHIP TO:

(SW3211) DLA DISTRIBUTION DEPOT OKLAHOMA

3301 F AVE CEN REC BLDG 506 DR 22

TINKER AFB OK 73145-8000

TINKER AFB,OK,73145-8000

DELIVERIES SHALL COMMENCE 360 DAYS AFTER RECEIPT OF

ORDER (DARO).

(End of narrative F001)

0002 STEERING BAR, AIRCRAFT

NSN: 1730-01-299-8688

Mfr CAGE: 81996

Mfr Part Number: 1730-CHSE-001-02

0002AA YEAR 2 (TWO) PRODUCTION QUANTITY 20 EA $ $ ________________________________ ______________ __________________

PROGRAM YEAR: 2

COMMODITY NAME: STEERING BAR, AIRCRAFT

CLIN CONTRACT TYPE:

Firm Fixed Price

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: STDP 1700CHSE001

REVISION: C

DATE: 02-NOV-2017

8 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 MARKINGS SHALL APPLY

UNIT PACK: 001 INTERMEDIATE PACK: 000

LEVEL PRESERVATION: Military

LEVEL PACKING: A

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES):

WT [74.0]

LN [105.0]

WD [22.0]

DP [7.0]

ALL WOOD PACKAGING MATERIAL (WPM) MUST BE ISPM-15

COMPLIANT.

MIL-STD-2073-1 CODES, APPENDIX J:

JI/A/MP [10] JII/CD [1] JIII/PM [00] JIV/WM [FA]

JV/CD [LK]

JVI/CT [F] JVII/UC [F2] JVII/IC [00]

JIX/A/PK [F] JX/SM [00] JVIIIA/OPI [M]

SUPPLEMENTAL INFORMATION:

WPM MUST BE ISPM-15 COMPLIANT

(End of narrative D001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

DELIVERIES SHALL COMMENCE 360 DAYS AFTER RECEIPT OF

ORDER (DARO).

(End of narrative F001)

9 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0003 STEERING BAR, AIRCRAFT

NSN: 1730-01-299-8688

Mfr CAGE: 81996

Mfr Part Number: 1730-CHSE-001-02

0003AA YEAR 3 (THREE) PRODUCTION QUANTITY 20 EA $ $ __________________________________ ______________ __________________

PROGRAM YEAR: 3

COMMODITY NAME: STEERING BAR, AIRCRAFT

CLIN CONTRACT TYPE:

Firm Fixed Price

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: STDP 1700CHSE001

REVISION: C

DATE: 02-NOV-2017

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

MIL-STD-129 MARKINGS SHALL APPLY

UNIT PACK: 001 INTERMEDIATE PACK: 000

LEVEL PRESERVATION: Military

LEVEL PACKING: A

ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND

SIZE (INCHES):

WT [74.0]

LN [105.0]

WD [22.0]

DP [7.0]

ALL WOOD PACKAGING MATERIAL (WPM) MUST BE ISPM-15

COMPLIANT.

MIL-STD-2073-1 CODES, APPENDIX J:

JI/A/MP [10] JII/CD [1] JIII/PM [00] JIV/WM [FA]

JV/CD [LK]

JVI/CT [F] JVII/UC [F2] JVII/IC [00]

JIX/A/PK [F] JX/SM [00] JVIIIA/OPI [M]

SUPPLEMENTAL INFORMATION:

WPM MUST BE ISPM-15 COMPLIANT

(End of narrative D001)

10 53

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

DELIVERIES SHALL COMMENCE 360 DAYS AFTER RECEIPT OF

ORDER (DARO).

(End of narrative F001)

11 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C02 Manufacturing Phase-Out or Discontinuation of Production, Diminishing Sources, and Obsolete Materials or Components (DEC 2016)

The contractor shall notify the contracting officer immediately upon determining the unavailability of obsolete materials or components.

The contractor may recommend a solution to include the impact on the contract price and delivery. The contractor shall not initiate any item redesign or incur any additional costs without the express, written authorization of the contracting officer.

In the event that manufacturing phase-out or discontinuance of production of such items is contemplated, the contractor is required to notify the contracting officer and publish the discontinuance in the Government-Industry

Data Exchange Program (GIDEP), where feasible; and to provide immediate advance notice of production phase-out to DLA DMSMS at dscc.dmsms@dla.mil.

C03 Contractor Retention of Supply Chain Traceability Documentation (SEP 2016)

(1) By submitting a quotation or offer, the contractor agrees that, when the contractor is not the manufacturer of the item, it is confirming that it currently has or will obtain before delivery and shall retain documented evidence

(supply chain traceability documentation) that the item is from the approved manufacturer and conforms to the technical requirements.

The retention period is five years after final payment under this contract.

(2) At a minimum, the supply chain traceability documentation for the item shall include: basic item description, part number and/or national stock number, manufacturing source, manufacturing sources Commercial and Government Entity

(CAGE) code, and clear identification of the name and location of all supply chain intermediaries between the manufacturer to the contractor to item(s) acceptance by the Government. The documentation should also include, where available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers.

(3) Examples of acceptable supply chain traceability documentation can be found at:

http://www.dla.mil/LandandMaritime/Business/Selling/Counterfeit-Detection-Avoidance-Program/

(4) The contractor shall immediately make available documentation upon request of the contracting officer. The contracting officer determines the acceptability and sufficiency of documentation. If the contractor fails to retain or provide the documentation or the contracting officer finds the documentation to be unacceptable, corrective action may be taken including, but not limited to, cancellation of undelivered orders or rejection of delivered supplies.

*** END OF NARRATIVE C0001 ***

PACKAGING AND MARKING

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

1 52.208-4700 WOOD PACKING MATERIALS REQUIREMENTS JUL/2007

A. Wood packaging material (WPM) means wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. The definition excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSD).

B. All Wood Packaging Material (WPM)) acquired by DOD must meet requirements of International Standards for Phytosanitary Measures

(ISPM) 15, "Guidelines for Regulating Wood Packaging Materials International Trade." DOD shipments inside and ouside of the United

States must meet ISPM 15 whenever WPM is used to ship DOD cargo.

(1) All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KD

HT) in accordance with American Lumber Standard Committee, incorporated (ALSC) Wood Packaging Material Program and WPM Enforcement

Regulations (see http://www.alsc.org/).

(2) All WPM shall include certification/quality markings in accordance with the ALSC standard. Marking shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.

C. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment at entry. The Agency reserves the right to recoup from the Contractor any remediation costs incurred by the Government.

D. Replacement Preservative for Pentachlorophenol

If packaging requirements of this contract specify the use of wood products and a preservative is required, Pentachlorophenol, commonly referred to as "Penta" or "PCP" is prohibited. Replacement preservatives are 2 percent copper naphthenate, 3 percent zinc naphthenate or

1.8 percent copper 8 quinolinolate.

12 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) Heat Treatment: Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated.

All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure traceability to the original source of heat treatment.

(2) Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention

Standard. The quality mark shall be placed on both ends of the outter packaging, between the end cleats or end battens: on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood proces verified in accordance with their

National Plant Protection Organization's compliance program. In addition, wood used as dunnage for blocking and bracing shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.

(End of Clause)

2 52.247-4700 BAR CODE MARKINGS (USAAMCOM) MAY/2014

Bar Code Markings are required in accordance with the latest revision of MIL-STD-129 and ISO/IEC 16388 - Information Technology -

Automatic Identification and Data Capture Techniques - Bar Code Symbology Specification - Code 39.

(End of Clause)

INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/ or https://www.acquisition.gov/

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

3 52.246-1 CONTRACTOR INSPECTION REQUIREMENTS APR/1984

4 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

5 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

6 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014

(a) The contractor shall comply with the higher-level quality standard(s) listed below.

ANSI/ISO/ASQ 9001:2008, AS 9100 OR EQUIVALENT, TAILORING: ALL PARAGRAPHS UNDER 7.3 (DESIGN AND DEVELOPMENT) DO NOT APPLY

(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

E05 Product Verification Testing (SEP 2016)

(1) When PVT is invoked, the QAR will notify the contractor that testing will be performed. The product verification testing (PVT) will be performed at a Government-designated testing laboratory.

(a) The contractor shall not ship or deliver any material unless directed to do so in writing by the contracting officer or until notified of acceptable PVT results.

(b) PVT results will be provided in 20 working days after receipt at the Government testing facility.

(2) The QAR will select a random sample from the contractors production lot. Selected PVT samples are to be shipped by the contractor at

Government expense with a copy of the Department of Defense DD Form 250 and a DD Form 1222. The packaging will be marked Product

Verification Test Samples, Contract Number __________, Lot/Item Number_________."

13 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(3) Test results will indicate one of the following:

(a) Samples that pass testing and are not destroyed during evaluation will be returned to the contractor at the Government's expense and will be included as part of the total contract quantity. The contractor and Government may agree to dispose of samples not destroyed when the cost of the item does not justify the shipping expense. These samples will be considered part of the contract quantity. Samples that pass testing and are not returned to the contractor will be considered part of the contract quantity for payment and delivery. The contractor will deliver the remaining lot quantity minus sample units.

(b) If samples fail testing, such failure will result in rejection of the entire contract lot from which the samples were taken. At the

Governments discretion, parts failing any test criteria may be retained and not be returned to the contractor.

E06 Inspection and Acceptance at Origin (SEP 2016)

The contractor shall indicate the location where supplies will be inspected:

Commercial and Government Entity (CAGE) code:__________________________________

Address_________________________________________________________________

Applicable to contract line-item numbers(s) (CLIN(s)):_______________________________

The contractor shall indicate the location where packaging will be inspected:

( ) Same as for supplies OR

CAGE code:______________________________________________________________

Address:_________________________________________________________________

Applicable to CLIN(s):_______________________________________________________

E07 Evaluation Factor for Origin Inspection (JAN 2018)

This solicitation contemplates an award based on destination inspection. If an offeror proposes inspection and acceptance at origin, the

Government will add an evaluation factor of $2,500 to the offerors quoted/offered price for each origin inspection required. If phased deliveries are required or offered, the Government will consider each phase of delivery to result in one inspection for evaluation purposes.

*** END OF NARRATIVE E0001 ***

DELIVERIES OR PERFORMANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/ or https://www.acquisition.gov/

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

7 52.211-17 DELIVERY OF EXCESS QUANTITIES SEP/1989

8 52.242-15 STOP-WORK ORDER AUG/1989

9 52.242-17 GOVERNMENT DELAY OF WORK APR/1984

10 52.247-29 F.O.B. ORIGIN FEB/2006

11 52.247-34 F.O.B. DESTINATION NOV/1991

12 52.247-48 F.O.B. DESTINATION--EVIDENCE OF SHIPMENT FEB/1999

13 52.247-58 LOADING, BLOCKING, AND BRACING OF FREIGHT CAR SHIPMENTS APR/1984

14 52.247-59 F.O.B. ORIGIN--CARLOAD AND TRUCKLOAD SHIPMENTS APR/1984

15 52.247-65 F.O.B. ORIGIN, PREPAID FREIGHT--SMALL PACKAGE SHIPMENTS JAN/1991

16 52.211-8 TIME OF DELIVERY JUN/1997

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER DATE OF

CONTRACT

14 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

0001AA 23 540 DACA

0001AB 1 AS REQUIRED

0001AC 23 360 DACA

0002AA 20 360 DACA

0003AA 20 360 DACA

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFERORS PROPOSED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS

AFTER DATE OF

CONTRACT

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the

Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the

Contractors date of receipt of the contract or notice of award by adding

(1) five calendar days for delivery of the award through the ordinary mails, or

(2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of Clause)

RQ009: INSPECTION AND ACCEPTANCE AT ORIGIN

1. The Governments Quality Assurance Representative (QAR) will inspect supplies described by manufacturer's name/code and part number at origin location(s):

a. The QAR may require that objective evidence be furnished establishing the name and address of the plant that manufactures the supplies to ensure that a domestic product is being supplied.

b. Objective evidence of performance must be present for all quality assurance requirements specified in the contract. The QAR may require additional examinations and tests to determine:

i. Completeness of item

ii. Material is new and unused

iii. Absence of rust

iv. Contamination, or deterioration

v. Correct identification/item marking

vi. Correct packaging

vii. Absence of any damage

viii. Compliance with preparation for delivery

15 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

2. If the supplier is not the manufacturer of the supplies, objective evidence must be furnished to establish that the supplies were produced by the approved manufacturer.

3. For supplies designated as former Government surplus (whether described by manufacturers name/code and part number, or by Military or

Federal specification or drawing), the original package markings of each item shall be verified to previous Government contract number and part number. Any deviation shall be cause for rejection of the item. The Procuring Activity may add additional inspection requirements based on the evaluation of the surplus offer. Such additional requirements will be identified before the award.

(End of TQ Requirement)

*** END OF NARRATIVE F0001 ***

F-12 52.211-9020 TIME OF DELIVERY ACCELERATED (JUN 2008)

Unless otherwise authorized in the award, accelerated delivery is acceptable only if there is no additional cost or obligation to the

Government for accelerated delivery.

*** END OF NARRATIVE F0002 ***

16 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

CONTRACT ADMINISTRATION DATA

17 252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS MAY/2013

(a) Definitions. As used in this clause--

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall--

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this

Web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice

Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the

WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer

Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

THE CONTRACTOR IS ENCOURAGED TO USE THE COMBINATION INVOICE AND RECEIVING REPORT (COMBO) FOR SUBMITTING INVOICES FOR SUPPLIES. THIS

ELIMINATES THE NEED TO SEPERATELY PROCESS A RECEIVING REPORT AND INVOICE.

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

INSPECTION LOCATION: AS DETAILED IN DELIVERY ORDER

ACCEPTANCE LOCATION: AS DETAILED IN DELIVERY ORDER

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in

WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC TBD

Issue By DoDAAC SPRRA1

Admin DoDAAC TBD

Inspect By DoDAAC TBD

Ship To Code TBD

Ship From Code TBD

Mark For Code NOT APPLICABLE

Service Approver (DoDAAC) NOT APPLICABLE

Service Acceptor (DoDAAC) NOT APPLICABLE

Accept at Other DoDAAC NOT APPLICABLE

LPO DoDAAC NOT APPLICABLE

DCAA Auditor DoDAAC TBD

Other DoDAAC(s) NOT APPLICABLE

17 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the email address identified below in the "Send Additional Email

Notifications" field of WAWF once a document is submitted in the system.

TBD

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

TBD

(2) For technical WAWF help, contact the WAWF helpdesk at 866-

618-5988.

(End of clause)

G01 Additional Wide Area Workflow (WAWF) Information (AUG 2017)

Contractors shall include the Transportation Control Number (TCN) and carrier shipment tracking information when submitting the DD250/iRAPT Receiving Report in Wide Area Workflow (WAWF) inorder to assist with material inspection and acceptance.

*** END OF NARRATIVE G0001 ***

18 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SPECIAL CONTRACT REQUIREMENTS

18 52.243-4000 ENG CHG PROPOSAL, VALUE ENG CHG PROPOSAL, REQUEST FOR DEVIATION, MAR/2011

REQUEST FOR VARIANCE, ENG RELEASE RECORDS, NOTICE OF REVISION, &

SPECIFICATION CHG NOTICE PREPARATION AND SUBMISSION INSTRUCTIONS

1. Contractor initiated Engineering Change Proposals (ECPs), Value Engineering Change Proposals (VECPs), Request for Deviations (RFDs), and Request for Variance (RFVs), collectively referred to as "proposals", shall be prepared, submitted and distributed in accordance with paragraphs 2, 3 and 4 below except as specified in paragraph 5 below.

2. Format.

a. Class 1 ECPs require the "Long Form Procedure" for documenting the change and describing the effects of the change on the suitability and supportability of the Configuration Item (CI). Class I ECPs should be limited to those that are necessary or offer significant benefit to the Government. Class I ECPs are those that affect the performance, reliability, maintainability, survivability, weight, balance, moment of inertia, interface characteristics, electromagnetic characteristics, or other technical requirements in the specifications and drawings. Class I ECPs also include those changes that affect Government Furnished Equipment, safety, compatibility, retrofit, operation and maintenance manuals, interchangeability, substitutability, replaceability, source control specifications and drawings, costs, guarantees or warranties, deliveries, or schedules. Class II ECPs are those that do not affect form, fit and function, cost, or schedule of the system CI and do not meet the other criteria described above for Class I ECPs.

b. Long Form Procedure: Class I changes to the CI require that RDMR Form 523, pages 1 through 7 (as applicable), be prepared. Use of this procedure assures that all effects of the change on the CI are properly addressed and documented to the necessary detail to allow proper evaluation of the proposed change.

c. Short Form Procedure: ECPs and VECPs , which meet the requirements of Class II ECPs, shall be prepared using RDMR Form

523 (page 1 only). Supplemental pages may be used with the form as necessary. The responsible Contract Management Office (CMO) will enter the appropriate data in Block 5 "Class of ECP", Block 6 "Justification Codes", and Block 7 "Priority."

d. The Contractor shall not manufacture items for acceptance by the Government that incorporate a known departure from requirements, unless the Government has approved an RFD. RFDs shall be prepared using RDMR Form 527 or RDMR Form 530 (Type I, see block

5 of the form.)

e. The Contractor shall not submit items for acceptance by the Government that include a known departure from the requirements, unless the Government has approved a RFV. RFVs shall be prepared using RDMR Form 528.

f. Each ECP, RFD or RFV shall be accompanied by a written and signed evaluation prepared by the responsible Defense Contract

Management Agency (DCMA) technical representative. The DCMA written evaluation shall be considered part of the ECP/RFD/RFV proposal.

g. Classification of RFDs/RFVs.

(1) Major RFDs/RFVs. RFDs/RFVs written against CIs shall be designated as major when the RFD/RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation involving health; performance;

interchangeability; reliability; survivability; maintainability; effective use or operation; weight; appearance (when a factor); or when there is a departure from a requirement classified as major in the contractual documentation.

(2) Critical RFDs/RFVs. RFDs/RFVs written against CIs shall be designated as critical when the RFD/RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation involving safety or when there is a departure from a requirement classified as critical in the contractual documentation.

(3) Minor RFDs/RFVs. RFDs/RFVs written against CIs shall be designated as minor when the RFD/RFV consists of acceptance of an item having a nonconformance with contract or configuration documentation which does not involve any of the factors listed above in paragraphs g(1) or g(2), or when there is a departure from a requirement classified as minor in the contractual documentation.

h. Proposals shall include sufficient technical data to describe all changes from existing contract requirements.

i. Proposals shall include sufficient justification for making the change, including a statement of contract impact, if the change is not authorized.

j. Proposals for ECPs shall set forth a "not to exceed" price and delivery adjustment acceptable to the Contractor if the

Government subsequently approves the proposal. If approved, the equitable increase shall not exceed this amount.

k. Times allowed for technical decisions for ECP and RFD/RFV proposals will be worked out via mutual agreement between the

Contractor and the Government.

19 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

l. The Contractor shall submit, concurrent with the ECP, a separate AMSAM-RD Form 525, "Specification Change Notice" (SCN), for each specification that would require revision if the ECP were approved.

m. Proposals for VECPs shall set forth a "not less than" price and delivery adjustment acceptable to the Contractor if the

Government subsequently approves the proposal. If approved, the savings shall not be less than this amount.

n. The Contractor shall utilize RDMR Form 526, "Engineering Release Record" (ERR) to release new or revised configuration documentation to the Government for approval.

o. The Contractor shall utilize RDMR Form 524, "Notice of Revision" (NOR) to describe the exact change(s) to configuration documentation specified as a data requirement in the contract. The Contractor shall describe the change using sub-sections entitled

"WAS" to describe the current contractual technical requirement and "IS" to describe the proposed new requirement.

3. Submittal. The Contractor shall submit two (2) copies of each proposal to the responsible Administrative Contracting Officer (ACO).

One (1) copy of each proposal shall be returned to the Contractor within (5) working days after receipt by the ACO, stating whether or not the proposal is in compliance with this provision. Any unresolved differences between the ACO and the Contractor concerning ECPs, VECPs, RFVs or RFDs will be submitted to the PCO for resolution. Submittals may be made by electronic means by scanning the appropriate completed forms into a computer or preparing the forms electronically.

4. Distribution.

a. Electronic Distribution. The preferred method of distribution is through the Internet E-mail System to the PCO. Microsoft

Word is required for use with the transmittal letter (E-mail). Required forms will be attached to the E-mail. All forms may be obtained from the Army Contracting Command - Redstone Website (https://wwwproc.redstone.army.mil/acquisition/forms_check.html) by ______________________________________________________________ clicking on "Forms/Checksheets." The forms are in both "Adobe Acrobat" and "Form Flow" formats. In order to access and use the forms, the user must have the "Adobe Acrobat" or "Form Flow" software installed on their computer. Drawings may be scanned into the computer and sent as an attachment. In some cases, because of size, drawings may have to be sent as hard copies or sent under special electronic instructions provided by the PCO. Contractors who do not have access to the Army Contracting Command - Redstone website will need to contact the PCO, the appropriate Project Office Configuration Management Office, or the Technical Data Management Division (RDMR-SET) to have the forms sent to their facility.

b. Hard Copy Distribution of Class I or II ECPs and RFD/RFVs, For each Class I or II ECP, or each RFD/RFV that the ACO determines to be in compliance with this provision, the Contractor shall submit the original plus five copies to the PCO and one copy to the ACO. Upon receipt of any type of change proposal that is submitted to the PCO, the ACO shall immediately submit DCMA's written evaluation pertaining to the proposed engineering change action to the PCO. Assistance in preparing any of these proposals may be obtained from the ACO or AMCOM Change Control Point at:

Aviation and Missile Research, Development, and Engineering Center

ATTN: RDMR-SET

Redstone Arsenal, Al 35898-5000

Telephone: 256-876-1335

c. Hard Copy Distribution of VECPs. For each VECP that the ACO determines to be in compliance with this provision, the

Contractor shall submit the original plus five copies to the PCO and one copy to the ACO. Upon receipt of any VECP that is submitted to the PCO, the ACO shall immediately submit DCMA's written evaluation to the PCO. The Contractor shall also submit one copy of the VECP to the Value Engineering Program Manager (VEPM) whose address is below. Assistance in preparing VECPs may be obtained from the VEPM.

Aviation and Missile Research, Development, and Engineering Center

ATTN: RDMR-SEI

Redstone Arsenal, Al 35898-5000

Telephone: 256-876-8163

5. Alternate Format, Submittal or Distribution Process. Proposals may be prepared in a different format, submitted using a different submittal process or distributed in a different manner than specified in paragraphs 2, 3 and 4 above, so long as the alternate approach is in accordance with a Government approved configuration management plan governed by this contract or the PCO authorizes the alternate format, submittal, or distribution process.

6. Government Acceptance. Acceptance of a proposal by the Government shall be affected by the issuance of a change order or execution of a supplemental agreement incorporating the proposal into the contract unless the PCO authorizes another method of acceptance. The Government will notify the Contractor in writing if a proposal is determined to be unacceptable.

(End of clause)

H03 Supplemental First Article Testing Requirements (OCT 2016)

20 53

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) If there is not a separate contract line item number (CLIN) for FAT, production CLIN pricing shall include all costs and risk associated with completion of the FAT requirement.

(2) If there is a separate FAT CLIN, the FAT CLIN pricing shall include all costs and risk associated with completion of the FAT requirement; if no FAT CLIN pricing is proposed, no payment will be made for any costs associated with FAT. Unit pricing shall be based solely on all costs associated with completion of the production units and shall exclude all FAT-related costs.

(3) The total award price will be used in selecting the best value offer from among all eligible offerors. However, to be eligible for award, the FAT CLIN (unless waived) and unit price CLIN(s) must each be determined to be a fair and reasonable price and, if set-aside under FAR part 19, a fair market price. Additionally, the FAT CLIN (and if separately priced, any CLIN(s) for first articles) shall not be materially unbalanced in relation to unit price CLIN(s) for production quantities. In the event that an offeror receives a waiver of the FAT requirement, the FAT CLIN price for the waived source shall be deducted in determining the total award price.

(4) Waivers. The contractor may submit a request for FAT waiver to the contracting officer. The

Government reserves the right to waive the FAT requirement when all the following criteria are met:

(a) Source has manufactured and delivered the product or similar product within the last five (5)years, or within the last three

(3) years for critical safety items. The contractor shall provide the following supportable information:

(i) Contract Number(s), Date(s), and Issuing Government Agency or Agencies.

(ii) Item previously furnished, identified by part number, type, model number, etc.

(iii) Engineering control document/change number of item previously furnished.

(iv) There have been no changes to manufacturing processes, tooling, or locations.

(b) There have been no changes to manufacturing data (e.g., drawing revisions that change materials, dimensions, processes, inspection or testing requirements; or subcontractors used to manufacture the items successfully in the past).

(c) Item supplied will be of same design and manufactured by same method at same facilities as product or similar product previously furnished and accepted under subparagraph (4)(a). (5) For test report preparation and delivery of contractor FAT, utilize data item description INDTI80809B report format. Mark the test report with the following: First article test report Contract number:

[insert contract number] and lot/item number: [insert lot/item number]. Present the test report to the QAR for review. Forward the QAR signed FAT Report, accompanied by the DD Form 250 and a contractor certification that the same process and facilities used to manufacture the first article units will be used to manufacture the production units, to the contracting officer at the applicable address shown below:

(a) For awards issued by DLA Aviation; or DLA Troop Support Clothing and Textile (C&T), Construction and Equipment, Medical Materiel, or Subsistence, submit the report to the procuring activity in Block 6 of the DD Form

1155, Block 7 of Standard Form (SF) 33, or Block 9 of SF 1449 award.

(b) For awards issued by DLA Land (SPE7L), submit the report to the following address: DLA Land FLSEB, ATTN: FAT Monitor, P O Box

3990, Columbus, OH 43218-3990, or email to:

Land.FAT.Monitor@dla.mil.

(c) For awards issued by DLA Maritime (SPE7M), submit the report to the following address: DLA Maritime FMSE, ATTN: FAT Monitor, P

O Box 3990, Columbus, OH 43218-3990, or email to:

maritime.fat.monitor@dla.mil.

(d) For awards issued by DLA Troop Support Industrial Hardware, submit the report to the following address: DLA Troop Support, Attention: First Article Testing Monitor, Building 3, 700 Robbins Avenue, Philadelphia, Pennsylvania 19111. Preferred electronic submissions: Hardware FAT Monitor at DLAHardwareFATMonitor@dla.mil.

(6) When Government testing is required, provide written notice to the contracting officer and the QAR at least fourteen (14) calendar days (or as otherwise specified in the contract) prior to shipment to Government for FAT, to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.