SPRDL123R0036.pdf

PDF 172 KB Posted

Attached to
Gunner's Display Federal contract opportunity
Solicitation number
SPRDL123R0036
Issued by
Defense Logistics Agency Land and Maritime

About this file

This is a solicitation for a Gunner's Display issued by the Defense Logistics Agency Land and Maritime. The solicitation seeks delivery of 39 Gunner's Display units and one unit for First Article Testing. The delivery schedule requires delivery of the production units within 465 days of award and 210 days for any option units exercised. The solicitation incorporates standard clauses for commercial item acquisition, electronic submission of payment requests, and various socio-economic requirements. Responses are due by the date and time listed on the cover sheet, and the contract will be awarded electronically.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

Offeror To Complete Block 12, 17, 23, 24, & 30

1. Requisition Number Page Of

2. Contract No. 3. Award/Effective Date 4. Order Number 5. Solicitation Number 6. Solicitation Issue Date

7. For Solicitation Information Call:

A. Name B. Telephone Number (No Collect Calls) 8. Offer Due Date/Local Time

9. Issued By Code 10. This Acquisition is Unrestricted OR Set Aside: % For:

Small Business Women-Owned Small Business (WOSB) Eligible Under the Women-Owned Small Business Program

Hubzone Small Business EDWOSB

Service-Disabled Veteran-Owned Small Business NAICS:

Email: 8(A) Size Standard:

11. Delivery For FOB Destination Unless Block Is Marked

12. Discount Terms 13a. This Contract Is A Rated Order Under DPAS (15 CFR 700) 13b. Rating

See Schedule 14. Method Of Solicitation RFQ IFB RFP

15. Deliver To Code 16. Administered By Code

Telephone No.

17a. Contractor/Offeror Code Facility 18a. Payment Will Be Made By Code

Telephone No.

17b. Check If Remittance Is Different And Put Such Address In Offer

18b. Submit Invoices To Address Shown In Block 18a Unless Block Below Is Checked See Addendum

19.

Item No.

20.

Schedule Of Supplies/Services

21.

Quantity

22.

Unit

23.

Unit Price

24.

Amount

(Use Reverse and/or Attach Additional Sheets As Necessary)

25. Accounting And Appropriation Data 26. Total Award Amount (For Govt. Use Only)

27a.Solicitation Incorporates By Reference FAR 52.212-1, 52.212-4. FAR 52.212-3 And 52.212-5 Are Attached. Addenda Are Are Not Attached.

27b.Contract/Purchase Order Incorporates By Reference FAR 52.212-4. FAR 52.212-5 Is Attached. Addenda Are Are Not Attached.

28. Contractor Is Required To Sign This Document And Return _________ 29. Award Of Contract: Ref. Offer Copies to Issuing Office. Contractor Agrees To Furnish And Deliver All Items Set Forth Or Otherwise Identified Above And On Any Additional Sheets Subject To The Terms And Conditions Specified.

Dated . Your Offer On Solicitation (Block 5), Including Any Additions Or Changes Which Are Set Forth Herein, Is Accepted As To Items:

30a. Signature Of Offeror/Contractor 31a. United States Of America (Signature Of Contracting Officer)

30b. Name And Title Of Signer (Type Or Print) 30c. Date Signed 31b. Name Of Contracting Officer (Type Or Print) 31c. Date Signed

Authorized For Local Reproduction Previous Edition Is Not Usable

Standard Form 1449 (Rev. 2/2012) Prescribed By GSA-FAR (48 CFR) 53.212

SPRDL1-23-R-0036 2023OCT11

CARRIE MAHLMEISTER (586)467-1200

CARRIE.MAHLMEISTER@DLA.MIL

2023NOV20 05:00pm

SPRDL1

DLA LAND WARREN

WARREN, MI 48397-5000

334112

X DOA4

X

SEE SCHEDULE

72197

KVH INDUSTRIES, INC.

50 ENTERPRISE CTR

MIDDLETOWN, RI 02842-5268

SEE SCHEDULE

X X

X 1

1 80

19.

Item No.

20.

Schedule Of Supplies/Services

21.

Quantity

22.

Unit

23.

Unit Price

24.

Amount

32a. Quantity In Column 21 Has Been

Received Inspected Accepted, And Conforms To The Contract, Except As Noted: _________________________________________________

32b. Signature Of Authorized Government Representative 32c. Date 32d. Printed Name and Title of Authorized Government Representative

32e. Mailing Address of Authorized Government Representative 32f. Telephone Number of Authorized Government Representative

32g. E-Mail of Authorized Government Representative

33. Ship Number 34. Voucher Number 35. Amount Verified 36. Payment 37. Check Number Correct For Partial Final Complete Partial Final

38. S/R Account No. 39. S/R Voucher Number 40. Paid By

41a. I Certify This Account Is Correct And Proper For Payment 42a. Received By (Print) 41b. Signature And Title Of Certifying Officer 41c. Date 42b. Received At (Location)

42c. Date Rec’d (YY/MM/DD) 42d. Total Containers

Standard Form 1449 (Rev. 2/2012) Back

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: CARRIE MAHLMEISTER

Buyer Office Symbol/Telephone Number: ZGAB/(586)467-1200

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

A.4 Acknowledgment of Amendments

Acknowledge all the amendments received from the Contracting Office by identifying the amendment number and its issue date below:

Amendment Number Date

*** END OF NARRATIVE A0001 ***

A.8 Electronic Contracting Provision

(a) All DLA Land Warren solicitations will be publicized on the Contract Opportunities website https://SAM.gov . Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or referenced with instructions in the solicitation.

(b) As directed in Section L of this solicitation, interested vendors shall submit a quote or proposal via email to the Contract

Specialist listed on the solicitation. The email shall include subject header: Proposal Submission SPRDL1-XX-X-XXXX (company name) on the solicitation.

(c) Requirements for tracking solicitations and submitting bid submissions:

1. Vendors must be registered for a sam.gov account through https://login.gov in order to manage searches and track solicitations. Using the Contract Opportunities search function in sam.gov, vendors will be able to view the Solicitation and any modifications or amendments made by the Contract Specialist.

2. Vendors may Request Access to controlled documents such as the Technical Data Package (TDP). Interested vendors must request

TDPs as directed in Section C of this solicitation.

3. All bids and proposals must be submitted via email to the Contract Specialist on record.

(d) Note to offerors:

Please pay close attention to the solicitation closing date and time as stated on the cover page of this solicitation, local time (EST), for DLA Land Warren. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is Offeror's responsibility to ensure the proposal/quote is received by the Contract Specialist by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure by the exact date and time specified on the cover page of this solicitation, it will be determined late.

Proposal/quote is defined to mean that ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

Solicitations may remain posted on sam.gov after the solicitation closing date. If the response deadline has passed for the

2 80

SPRDL1-23-R-0036

KVH INDUSTRIES, INC.

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

solicitation, vendors will need to send any late quotes, if applicable, directly to the Contract Specialist identified on the cover page of this solicitation.

(e) Any awards issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or

Pricing data/information. If you object to such release in the base contract or contract modifications, and you intend to submit an offer, notify the Procuring Contracting Officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(f) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

*** END OF NARRATIVE A0002 ***

A.10 All or None Commercial Product Acquisition

This provision serves as an addendum that modifies paragraph (h) of FAR 52.212-1, entitled INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS.

Paragraph (h) is modified to state offerors must provide the total quantity of the items in this solicitation. ONLY ONE AWARD WILL BE

MADE AS A RESULT OF THIS SOLICITATION. OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL

NOT BE CONSIDERED FOR AWARD.

*** END OF NARRATIVE A0003 ***

3 80

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 DISPLAY UNIT

NSN: 7025-01-621-5510

Mfr CAGE: 19200

Mfr Part Number: 13034156

0001AA PRODUCTION QUANTITY CLIN 39 EA $ $ ________________________ ______________ __________________

COMMODITY NAME: DISPLAY UNIT

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH2C0382EH PRON AMD: 01

AMS CD: SM2B1100000

The Technical Data Package (TDP) is Source Controlled to Contractor: Name KVH Industries, Cage 72197, Part

Number 13034156.

Approved Sources must meet the requirements of the

TDP.

(End of narrative C001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE SPECIAL PACKAGING CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W52H092103Z329 W562RP J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 39 0465

4 80

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

FOB POINT: Destination

SHIP TO:

(W562RP) SU ARMY GENERAL SUPPLY LMP STOCK RE

DLA DISTRIBUTION ANNISTON

7 FRANKFORD AVE 362

ANNISTON,AL,36201-4199

0001AB FIRST ARTICLE TEST CLIN 1 LO $ ** NSP ** _______________________ __________________

SERVICE REQUESTED: FIRST ARTICTLE TEST CLIN

CLIN CONTRACT TYPE:

Firm Fixed Price

A FIRST ARTICLE TEST REPORT IS REQUIRED IN ACCORDANCE

WITH THE CLAUSE ENTITLED "FIRST ARTICLE APPROVAL--

CONTRACTOR TESTING",

FAR 52.209-3.

THE PRICE FOR FIRST ARTICLE TESTING IN THE TOTAL

AMOUNT OF $_______________ IS INCLUDED IN THE TOTAL

AMOUNT FOR CLIN 0001AA.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0240

0002 DISPALY UNIT

NSN: 7025-01-621-5510

Mfr CAGE: 19200

Mfr Part Number: 1303415

0002AA UNEXERCISED OPTION CLIN 39 EA $ $ _______________________ ______________ __________________

COMMODITY NAME: DISPALY UNIT

CLIN CONTRACT TYPE:

Firm Fixed Price

OPTION QUANTITY,

PURSUANT TO THE NARRATIVE ENTITLED 'SEPARATELY PRICED

OPTION FOR INCREASED QUANTITY' IN SECTION I OF THE

BASIC CONTRACT.

5 80

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

The quantity stated for the option CLIN DOES NOT Form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract IAW option narrative entitled "Separately Priced Options for Increased Quantity", at the discretion of the

Government.

The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the Government, at the basic contract unit price, and the offer will be evaluated for award.

(End of narrative B001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE SPECIAL PACKAGING CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 39 0210

FOB POINT: Destination

SHIP TO:

(SPRDL1) DLA LAND WARREN

ZGA

6501 EAST ELEVEN MILE ROAD

WARREN,MI,48397-5000

6 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.13 Configuration Control Engineering Changes

(a) The Contractor may submit Engineering Change Proposal(s) (ECPs) and Request for Variance(s) (RFVs) for the requirements in the

Government provided Technical Data Package (TDP). If a Value Engineering Change Proposal(s) (VECPs) clause is included on this contract, VECPs shall be submitted in the same manner as ECPs.

(1) ECPs - The Contractor may request a permanent change to the requirements specified in the TDP or any other baseline documentation by submitting an ECP. ECPs shall be submitted to include all Notice of Revisions (NORs) necessary to completely define the requested change. Each ECP shall be accompanied with at least one NOR per affected document. The Contractor shall not present any production items for acceptance that incorporate any change to the TDP or other baseline documentation until notified by the Government the ECP has been approved and incorporated in the contract.

(i) Page 1 of DD Form 1692 (or equivalent) shall be submitted for all ECPs. Pages 2-7 of DD Form 1692 shall be submitted when required to properly explain all the potential logistics and technical impacts of the proposed change. DD Form 1695 NOR or DD Form 1695-1

Tabulated NOR (or equivalents) shall be submitted to completely describe the desired change on each affected document.

(ii) All ECPs submitted by the Contractor will be routine priority unless otherwise justified. If the Contractor considers the ECP to be emergency or urgent, they shall include justification within 48 hours of submittal of the ECP.

(2) RFVs - The Contractor may request to temporarily depart from a requirement specified in the TDP or any other baseline documentation, by submitting an RFV. RFVs may be submitted either pre-production (formerly known as Request for Deviation (RFD)) or post-production and prior to acceptance by the Government (formerly known as Request for Waiver (RFW)). DD Form 1694 (or equivalent) shall be submitted for all RFVs. The Contractor shall not present any production items for acceptance with any nonconformance to the requirements in the TDP or other baseline documentation until notified by the Government the RFV has been approved and incorporated in the contract.

(b) Submission of requested changes - The submission of an ECP or RFV by the Contractor does not affect the required delivery dates specified within the contract, shall not constitute excusable delay in the performance of this Contract by the Contractor or in any way relieve the Contractor from compliance with the contract delivery schedule. If a delivery date change is needed, it must be negotiated with the Procuring Contracting Officer and documented via modification to the contract. The submission of an ECP and/or RFV by the

Contractor shall not preclude the Government from exercising its rights under any clause of the Contract.

(c) Specifications - Permanent proposed changes to specifications which are part of the TDP or baseline documentation shall be requested with an ECP and NOR (i.e. Specification Change Notices (SCNs) are not required).

(d) Forms If any of the above listed forms are not included with the solicitation or contract, the Contractor may locate forms on the

DOD Forms Website https://www.esd.whs.mil/Directives/forms/dd1500_1999/ or contact the Contract Specialist listed on page 1 of the solicitation or contract for copies of the forms.

*** END OF NARRATIVE C0001 ***

C.14 Acquisition of Source-Controlled Part Number

Acquisition under this contract is restricted to:

(1) The manufacturer's part number or numbers set forth in the Schedule or the Technical Data Package (TDP); and

(2) Other manufacturer's part numbers that are physically, functionally, and mechanically interchangeable with the manufacturer's part number(s) listed in the TDP; provided (i) that these non-listed part numbers have been furnished to one of the approved manufacturers listed in the TDP, which firm has then, without making any changes in the characteristics or properties of the part, redesignated that part with one of the approved part numbers; and (ii) that firms tendering a non-listed part number as described in this paragraph (2) have completed the REPRESENTATION OF INTENT TO SUPPLY A SOURCE CONTROLLED ITEM narrative and has received approval from the Contracting Office.

*** END OF NARRATIVE C0002 ***

C.5 Technical Data Package Information (Contract Opportunities in sam.gov) Version

The following Xd item applies to this solicitation:

[ x ] 1. There is no Technical Data Package (TDP) included with this solicitation.

7 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line-Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN:

TDP Link (URL):

[ ] 3. The TDP for this solicitation resides within sam.gov under the Contract Opportunities search function https://sam.gov , and is associated with this solicitation number and can be accessed via this URL:

a. Log on to the sam.gov website.

b. Select Contract Opportunities in the search bar and search by solicitation number.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and Contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense Logistics Information Service (DLIS). If you are currently certified, your MPIN will be verified and you may proceed to the next step. To obtain certification, login to the Joint Certification Program (JCP) https://www.dla.mil/Logistics-

Operations/Services/JCP/ . Click on documents and follow instructions provided. Processing time is estimated at six (6) to ten (10) weeks after receipt. Contract Opportunities will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.

Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

c. If technical data is otherwise restricted, click the document title to request access. A window will pop-up, select Request Access to controlled documents and enter the Reason for Access. This will generate an email to the Contract Opportunities system administrator at

DLA Warren with all the information needed for them to grant you access. Contract Opportunities will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this Contract

Opportunities-TDP access/approval process through sam.gov.

d. Only one individual in your company can request access to the Technical Data Package (TDP) for a solicitation. That individual must be registered as the Data Custodian, as identified in the JCP, and be granted approval to view the Technical Data Package (TDP) for a solicitation. The Data Custodian MUST be registered for a sam.gov account through https://login.gov . Any individual(s) no longer with the company should be deleted. Questions related to registration in https://login.gov should be directed to https://login.gov/help/ .

Questions related to accounts in sam.gov should be directed to https://sam.gov/content/help . Vendors are responsible for placing correct information in login.gov and sam.gov accounts.

e. It is strongly suggested that you submit an access request and provide the Contract Specialist with the completed Use and Non-

Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by the Data Custodian of your firm, as identified in the JCP, before access is granted to the technical data. The appropriate Agreement is titled , and is:

[ ] available by emailing the Contract Specialist listed on page 1 of this solicitation.

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement and email it to the Contract Specialist at N/A. The Contract Specialist will notify the

Contract Opportunities administrator upon receiving the NDA. The Administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the

TDP. If you have any questions/problems viewing the TDP contact the Contract Specialist.

8 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

*** END OF NARRATIVE C0003 ***

C.18 Use of Class 1 Ozone Depleting Substances (CIODS)

(a) Definitions.

(1) Class I and Class II Ozone-Depleting Substances (CIODS) refers to the class of substances identified in Section 602(a) of the Clean Air Act, (42 U.S.C. 7671a(a)), complete list provided at: https://www.epa.gov/clean-air-act-overview/clean-air-act-title-vi-stratospheric-ozone-protection

(2) Directly requires the use of CIODS means that the Government's specification or technical data package, at any tier, explicitly requires the use of any Class I Ozone-Depleting Substance (CIODS) in performance of the contract.

(3) Indirectly requires the use of CIODS means that the Government's specification or technical data package, while not explicitly requiring the use of any CIODS, does require a feature that you can meet or produce only by the use of CIODS.

(b) No CIODS shall be used in meeting the requirements of this contract. If the use of CIODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.

(c) No Class II Ozone Depleting Substances shall be required in the performance of this contract without Government approval. If the use of Class II ODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.

*** END OF NARRATIVE C0004 ***

C.23 Contractor Retention of Supply Chain Traceability Documentation

1) By submitting a quotation or offer, the Contractor, is confirming it currently has, or will obtain before delivery, and shall retain supply chain traceability documentation, as described in paragraph (2) below, demonstrating the item conforms to the technical requirements, and for part numbered items, is from an approved manufacturer.

2) Supply Chain Traceability Documentation

i. Supply chain traceability documentation shall include: basic item description, part number; drawing or specification;

national stock number, manufacturing source, manufacturing sources Commercial and Government Entity (CAGE) code, and clear identification of the name and location of all supply chain intermediaries between the manufacturer to the contractor to Government acceptance. The documentation should also include, if available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers.

ii. Supply chain traceability documentation shall also include, if available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers. For part numbered items, contractors can find examples of acceptable supply chain traceability documentation at the Counterfeit Detection and Avoidance Program (CDAP) website http://www.dla.mil/LandandMaritime/Business/Selling/Counterfeit-Detection-Avoidance-Program/ .

iii. In addition, the contractor will obtain, retain, and provide to the contracting officer written documentation of all inspections and tests necessary to substantiate that the supplies furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers parts. Such records shall include, without limitation, test reports, test data, material certification, and manufacturing process sheets, in addition to any other information identified in the technical specifications applicable to the item.

3) The contractor shall make supply chain traceability documentation available to the contracting officer within three business days upon the contracting officers request. The contracting officer determines the acceptability and sufficiency of documentation. The contractor shall retain supply chain traceability documentation for ten years after final payment under this contract for audit and other valid government purposes. If the contractor fails to retain or provide the documentation, or the contracting officer finds the documentation to be unacceptable, the contracting officer may take corrective action, including, but not limited to, cancellation of undelivered orders or rejection of delivered supplies.

*** END OF NARRATIVE C0005 ***

9 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

PACKAGING AND MARKING

D.2 Packaging Requirements (Special Packaging Instructions)

A. Military preservation, packing, and marking for the item identified above shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1 and the Special Packaging Instruction (SPI) contained in the TDP.

PRESERVATION: MILITARY

LEVEL OF PACKING: -1-

QUANTITY PER UNIT PACKAGE: -2-

SPI NUMBER: -3-

B. Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The pallet shall be a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

C. Marking: In addition to any special markings called out on the SPI;

C.1. All unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129 including bar coding and a MSL label. The Contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel. Passive RFID tagging is required in all contracts that contain DFARS clause

252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see http://www.acq.osd.mil/log/sci/ait.html for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation Plan.

If the item has Unique Item Identifier (UII) markings then the concatenated UII needs to be 2D bar coded and applied on the unit package, intermediate and exterior containers, and the palletized unit load.

D. Heat Treatment and Marking of Wood Packaging Materials: All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure tractability to the original source of heat treatment. Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard.

Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens; on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood products verified in accordance with their National Plant Protection Organizations compliance program. In addition, wood used as dunnage for blocking and bracing, to include ISO containers, shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.

E. This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided Contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

F. Hazardous Materials (as applicable):

F.1. Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated. (This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

F.2. Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements for the mode of transport and the applicable performance packaging contained in the following documents:

--International Air Transport Association (IATA) Dangerous Goods Regulations

--International Maritime Dangerous Goods Code (IMDG)

--Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

--Joint Service Regulation AFJMAN24-204/TM38-250/NAVSUPPUB 505/MCO

P4030.19/DLAM 4145.3 (for military air shipments).

10 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

F.3. If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United

Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

F.4. When applicable, a Product Safety Data Sheet (SDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

G. SUPPLEMENTAL INSTRUCTIONS: -4-

*** END OF NARRATIVE D0001 ***

D.2 Packaging Requirements (Special Packaging Instructions)

A. Military preservation, packing, and marking for the item identified above shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1 and the Special Packaging Instruction (SPI) contained in the TDP.

PRESERVATION: MILITARY

LEVEL OF PACKING: B

QUANTITY PER UNIT PACKAGE: 001

SPI NUMBER: 13034156

B. Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The pallet shall be a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

C. Marking: In addition to any special markings called out on the SPI;

C.1. All unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129 including bar coding and a MSL label. The Contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel. Passive RFID tagging is required in all contracts that contain DFARS clause

252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see http://www.acq.osd.mil/log/sci/ait.html for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation Plan.

If the item has Unique Item Identifier (UII) markings then the concatenated UII needs to be 2D bar coded and applied on the unit package, intermediate and exterior containers, and the palletized unit load.

D. Heat Treatment and Marking of Wood Packaging Materials: All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure tractability to the original source of heat treatment. Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard.

Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens; on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood products verified in accordance with their National Plant Protection Organizations compliance program. In addition, wood used as dunnage for blocking and bracing, to include ISO containers, shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.

E. This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided Contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

F. Hazardous Materials (as applicable):

11 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

F.1. Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated. (This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

F.2. Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements for the mode of transport and the applicable performance packaging contained in the following documents:

--International Air Transport Association (IATA) Dangerous Goods Regulations

--International Maritime Dangerous Goods Code (IMDG)

--Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

--Joint Service Regulation AFJMAN24-204/TM38-250/NAVSUPPUB 505/MCO

P4030.19/DLAM 4145.3 (for military air shipments).

F.3. If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United

Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

F.4. When applicable, a Product Safety Data Sheet (SDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

G. SUPPLEMENTAL INSTRUCTIONS: N/A

*** END OF NARRATIVE D0002 ***

12 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

INSPECTION AND ACCEPTANCE

E.18 Inspection and Acceptance Points - Origin

The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT:

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT:

(Name) (CAGE)

Address) (City) (State) (Zip)

*** END OF NARRATIVE E0001 ***

E.4 First Article Test (Contractor Testing)

a. The first article shall be examined and tested in accordance with contract requirements, the item specification(s), Quality Assurance

Provisions (QAPs) and all drawings listed in the Technical Data Package.

b. The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.

c. The first article shall be inspected and tested by the Contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:

(1) Inspections and tests contained in material specifications provided that the required inspection and tests have been performed previously and certificates of conformance are submitted with the First Article Test Report.

(2) Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.

(3) Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the

First Article Test Report.

(4) Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the

First Article Test Report.

(5) Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the Contractor's facility and certifications are submitted with the First Article Test Report.

d. Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.

e. A First Article Test Report shall be compiled by the Contractor documenting the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The First Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, 13 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. Evidence of the QAR's verification will be provided. One copy of the First Article Test Report will be copy furnished to the PCO, Eric Tucker at eric.tucker@dla.mil, Contract Specialist, Carrie Mahlmeister at carrie.mahlmeister@dla.mil and usarmy.ria.devcom.ac.mbx.rdar-qep@army.mil.

f. Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Procuring Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of one year, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Procuring Contracting Officer so that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the additional first article testing resulting from any of the causes listed herein that were instituted by the Contractor and not due to changes directed by the Government shall be borne by the Contractor.

*** END OF NARRATIVE E0002 ***

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

For FAR clauses: https://www.acquisition.gov/

For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

2 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014

(a) The contractor shall comply with the higher-level quality standard(s) listed below.

The Contractor shall comply with the higher level quality standard (s) listed below:

ISO 9001: 2015 (21 Oct 2015) or equivalent

(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

14 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DELIVERIES OR PERFORMANCE

F.1 Delivery Schedule

(a) Delivery under this contract must conform to the required schedule specified below, unless acceleration is acceptable.

(b) DEFINITIONS:

(1) DAYS means the number of days after the date of contract award when you must deliver the stated quantity (QTY) of supplies.

(2) DELIVERY is defined as follows:

FOB Origin - Contractor is required to deliver its shipment as provided in FAR 52.247-29(a)(1)-(4) by the time specified in the individual contract; or

FOB Destination - Contractor is required to deliver its shipment as provided in FAR 52.247-34(a)(1)-(2) by the time specified in the individual contract. The Contractor must take into consideration the length of time necessary to deliver its shipment to the destination designated in the contract, to ensure that the item reaches its destination by the time reflected in the contract.

(c) The Government requires delivery to be made according to the following schedule:

(1) GOVERNMENT REQUIRED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)

ITEM NO. QTY WITHIN DAYS AFTER DATE OF

CONTRACT AWARD

0001AA 39 465 days after contract award and FAT approval

0001AB 1 240 days after contract award

00012AA 39 210 days after option exercised

(2) GOVERNMENT REQUIRED DELIVERY SCHEDULE IF THERE IS NO FIRST ARTICLE TEST (FAT), OR IF FAT IS WAIVED

ITEM NO. QTY WITHIN DAYS AFTER DATE OF

CONTRACT AWARD

(d) Accelerated delivery schedule is acceptable.

(e) If an accelerated delivery schedule is not acceptable, the required delivery schedule above will apply. If it is acceptable, you may propose an accelerated delivery schedule at no additional cost; fill in the appropriate information here:

(1) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)

ITEM NO. QTY WITHIN DAYS AFTER DATE OF

CONTRACT AWARD

(2) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITHOUT FIRST ARTICLE TEST (FAT), or IF FAT IS WAIVED

ITEM NO. QTY WITHIN DAYS AFTER DATE OF

CONTRACT AWARD

*** END OF NARRATIVE F0001 ***

F.5 Depot Address for the Applicable Mode of Shipments: In-The-Clear Addresses

Rail/ Motor SPLC*: 206721 and 209405

MILSTRIP Address Code: W2561U

Rail Ship to: Transportation Officer

Defense Dist. Depot

15 80

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Susquehanna

New Cumberland, PA

Motor Ship to: Transportation Officer

Defense Dist. Depot

Susquehanna

New Cumberland, PA

Parcel Post Mail to: Transportation Officer

Defense Dist. Depot

Susquehanna

New Cumberland, PA 17070-5001

NOTE: All deliveries to New Cumberland MUST be scheduled at least 10 days prior to the delivery date. The carrier or Contractor must call the New Cumberland DDSP customer service number, 800-307-8496 and provide the following information: contract number, item name, National Stock Number, total weight and cube, and vendor. All shipments to this MILSTRIP address code (W25G1U) are for mission stock and they will need to know that as well, but if you have instructions from the Procuring Contracting Officer (PCO) to use MILSTRIP address code W25N14 instead, you must inform the appointment-taker that the delivery is for Consolidation and Containerization Point (CCP) stock.

Appointments for FOB Origin shipments should be coordinated with DCMA Transportation.

For FOB Origin shipments, or for FOB Destination shipments outside of the Continental United States, Contractors performing under DCMA

Administered contracts may request support with shipment and labeling via the Shipping Instructions Request (SIR) Module found at https://www.dcma.mil . This module is available under the eTools tab and can be used by suppliers to send requests for shipping instructions to the DCMA Transportation Office.

This is the start of the file's text. The full file is on GovTribe.