JA_Urgent_ATLASIIFL_SPRDL1-16-C-0178_REDACTED.pdf

PDF 121 KB Posted

Attached to
Redacted J&A
Solicitation number
SPRDL1-16-R-0206
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Urgent Justification & Approval SPRDL1-16-R-0206

DEFENSE LOGISTICS AGENCY

JUSTIFICATION FOR OTHER THAN

FULL AND OPEN COMPETITION

SPRDL1-16-R-0206

The Defense Logistics Agency (DLA) - Warren is the procuring activity for this action. The statutory authority permitting other than full and open competition is 10 U.S.C. 2304(c)(2), as implemented by FAR 6.302-2, "Unusual and Compelling Urgency."

PART I - Description of Items Required

NSN 2530-01-572-2281;

PRON EH67E452EH

NSN 2530-01-572-4923;

PRON EH67E453EH

NOUN: Wheel, Pneumatic Tire

(Wheel/Tire Assembly)

Wheel, Pneumatic Tire

(Wheel/Tire Assembly)

Basic Quantity: 57 ea. 37 ea.

MPN: 4520679 4520678

Cage: 1YHH8, JLG Industries 1YHH8, JLG Industries

Vehicle System: ATLAS II Forklift ATLAS II Forklift

Estimated Unit Price: $2,541.68 $2,545.48

Estimated Total Value: $144,875.76 $94,182.76

Type of Funds: C-AWCF C-AWCF

Type of Contract: Firm-Fixed Price Firm-Fixed Price

TOTAL ESTIMATED VALUE: $239,058.52

PART II - Statement of Urgency

1. TACOM has an urgent need for the items described above. They must be procured by the quickest means possible since full and open competition and/or normal acquisition procedures will not achieve the required delivery date. The rationale for citing urgency follows:

a. Description of Urgent Requirement:

These parts are required for the ATLAS II Forklift in support of dead-lined vehicles, deployments, and programs that include ATLAS II RESET. In CY15, there were 02-priority requisitions for a total of 57 each, 01-572-2281 Wheel/Tire Assemblies, and the Government currently has no issuable Depot stock. These items transferred from

DLA management to TACOM management in October 2015 with no advance notice and insufficient due-in, and all DLA stock transferred to TACOM has been exhausted due to an unforeseen increase in demands. These Wheel/Tire Assemblies are an

Essentiality Code C item, which will dead-line the vehicle if unserviceable. Delivery of these items is crucial to unit readiness and requires expedited delivery. These items are repairable, but there are no unserviceables on-hand for a repair program, nor are unserviceables expected to arrive through FY16.

Unserviceable returns from the field are expected to be very low for the next few years until the Army Material Command (AMC) adds the unserviceable credit to this item to incentivize unit turn-ins. The process for adding the unserviceable credit typically takes two years so no repair programs are expected in the near future;

therefore, the Government is restricted to procurement only for now.

b. Justification of proposed delivery schedule:

Units require delivery of these items to ensure unit readiness and to perform the units’ daily mission. These PRONs are the bare minimum requirement to fill backorders and an aggressive delivery schedule is necessary.

c. Description of the extent and nature of the harm to the Government if the proposed delivery date is not met:

1. What is the serious injury (dollars, harm to soldier, etc.) to the Government if the required delivery dates are not met?

Lack of these items will adversely affect unit readiness. These items are coded essential and will render the machine/vehicle Non-Mission Capable (NMC). This will prevent supplies, cargo, and essential items from being transported into combat zones.

2. What impact would this have on the Army’s mission?

If these parts are not received promptly, units will be unable to perform their mission and Letterkenny Army Depot RESET programs will be adversely affected.

The ATLAS II Forklift performs material handling functions at all echelons of the

Army, to include beach, port, and air terminal operations, material holding areas, and marshalling yards. All of these mission areas would be adversely impacted without the proper Material Handling Equipment available. Additionally, contingency operations in theater will not be able to move forward.

3. What financial impact would this have on the Government and how was this dollar value assigned?

No financial impact anticipated.

4. Consider and address whether or not any other items that we currently have in stock could fill this requirement and alleviate the immediate need.

N/A –These Wheel/Tire Assemblies are only valid for the left and right sides of

ATLAS II forklifts. There are no substitutes for these items. A long term contract

(LTC) is in process, but deliveries will not begin in time to meet the requirements for backorders. Therefore, this urgent buy represents the minimum urgent quantity needed to provide these items until the LTC begins deliveries.

d. Urgent circumstances requiring the inclusion of an option:

None

e. Net Requirement:

NSN 2530-01-572-

2281;

PRON EH67E452EH

NSN 2530-01-572-

4923;

PRON EH67E453EH

Number of existing high priority (1-3) backorders:

0 0

Number of anticipated high priority (1-3) demands from the current date through the anticipated award date (ALT) if normal acquisition methods are used:

33 26

Number of anticipated high priority (1-3) demands expected from the end of the

ALT through production lead time (PLT) if normal acquisition methods are used:

24 18

Total Requirement (sum of 1-3): 57 44

4 Current serviceable stock on hand: 0 7

Expected receipts from procurement from current date through the end of

PLT:

0 0

Expected receipts from repair from current date through the end of PLT:

0 0

Total Available Assets (sum of 4-6): 0 7

If high priority requirements are greater than assets this figure represents current and anticipated high priority backorders:

57 37

NET REQUIREMENT (Total

Requirements -Total Assets):

57 37

2. The POC for this action is Michael Angelo, DSN 330-6115 and Amy Gilley, DSN 330-6115

3. Requirements Certification - I certify that my supporting data included in this document are accurate and complete to the best of my knowledge and belief.

Name: Michael Angelo

Title: GS-12 Weapon System Manager, MHE Group

Date: 03/18/2016

Signature: //s// Michael Angelo

Name: Amy Gilley

Title: GS-13 Team Leader, MHE Supply

Date: 03/21/2016

Signature: /s/ Amy Gilley

PART III - Contracting Information

1. Description of Action: Offers to provide the required item will be solicited under Request for

Proposals SPRDL1-16-R-0206. DLA Land Warren proposes to negotiate a firm-fixed-price contract with JLG Industries for part numbers 4520679 and 4520678.

2. Extent of Competition: Due to the urgency of this buy, no further action will be taken to increase competition on this buy. No market survey will be conducted. Further, the procurement will not be synopsized due to the urgency of the requirement.

Future buys of this item will be competed based on the commercial nature of these items and the competitive TDP.

3. The POC for this action is Patty Roussin, OFFICE SYMBOL: ZGBD, EXT. 282-3225.

4. Fair and Reasonable Determination: I hereby determine that the anticipated cost to the

Government for this contract action will be fair and reasonable based on price analysis. Certified cost or price data will not be required based on the exception stated in FAR Part 15.403-1(b)(3) commercial item.

5. Contracting Officer Certification: I certify that this J&A is accurate and complete to the best of my knowledge and belief.

Signature: //s// LCB

Name: Leah C. Bourdeau

Title: Contracting Officer

Office: ZGBD

Date: 21 March 2016

PART IV - Legal Concurrence:

Concur: // Darin R. Morency //

Date: 03/22/2016

File details come from the government source that posted it. Updated .