52.209-1 QUALIFICATION REQUIREMENTS.docx

DOCX document 14 KB Posted

Attached to
5556 TIG WIRE
Solicitation number
SPMYM4-24-Q-0635
Issued by

About this file

This document is the clause 52.209-1 QUALIFICATION REQUIREMENTS from the Federal Acquisition Regulation (FAR). It defines the qualification requirements that apply to the supplies or services covered by the contract. Offerors must demonstrate that they or their products, manufacturers, or sources meet the specified qualification standards before award of the contract, even if they are not yet on a qualified products or bidders list. Any changes in location or ownership of a qualified product, manufacturer, or source requires reevaluation of the qualification prior to contract award. The clause outlines the information offerors should provide regarding their qualification status and the process for obtaining qualification.

The related federal contract opportunity is a Request for Quote (RFQ) from the Defense Logistics Agency Land and Maritime for 5556 TIG WIRE, Solicitation Number SPMYM4-24-Q-0635. The solicitation closes on July 31, 2024 at 12:00 PM Hawaii Standard Time. Offerors must provide pricing, FOB destination, contact information, tax ID, unique entity ID, CAGE code, GSA contract number (if applicable), business size, and payment terms. Offerors must clearly indicate their capability to meet all specifications and requirements.

View the file

Other files

File Type Posted
BRAND NAME.pdf PDF
S1. SPMYM4-24-Q-0635.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

52.209-1 QUALIFICATION REQUIREMENTS (FEB 1995)

(a) Definition: "Qualification requirement," as used in this clause, means a Government requirement for testing or other quality assurance demonstration that must be completed before award.

(b) One or more qualification requirements apply to the supplies or services covered by this contract. For those supplies or services requiring qualification, whether the covered product or service is an end item under this contract or simply a component of an end item, the product, manufacturer, or source must have demonstrated that it meets the standards prescribed for qualification before award of this contract. The product, manufacturer, or source must be qualified at the time of award whether or not the name of the product, manufacturer, or source is actually included on a qualified products list, qualified manufacturers list, or qualified bidders list. Offerors should contact the agency activity designated below to obtain all requirements that they or their products or services, or their subcontractors or their products or services, must satisfy to become qualified and to arrange for an opportunity to demonstrate their abilities to meet the standards specified for qualification.

(Name) (Address)

(c) If an offeror, manufacturer, source, product or service covered by a qualification requirement has already met the standards specified, the relevant information noted below should be provided.

Offeror's Name Manufacturer's Name Source's Name Item Name Service Identification Test Number (to the extent known)

(d) Even though a product or service subject to a qualification requirement is not in itself an end item under this contract, the product, manufacturer, or source must nevertheless be qualified at the time of award of this contract. This is necessary whether the Contractor or a subcontractor will ultimately provide the product or service in question. If, after award, the Contracting Officer discovers that an applicable qualification requirement was not in fact met at the time of award, the Contracting Officer may either terminate the contract for default or allow performance to continue if adequate consideration is offered and the action is determined to be otherwise in the Government's best interests.

(e) If an offeror, manufacturer, source, product, or service has met the qualification requirement but is not yet on a qualified products list, qualified manufacturers list, or qualified bidders list, the offeror must submit evidence of qualification prior to award of this contract. Unless determined to be in the Government's interests, award of this contract shall not be delayed to permit an offeror to submit evidence of qualification.

(f) Any change in location or ownership of the plant where a previously qualified product or service was manufactured or performed requires reevaluation of the qualification. Similarly, any change in location or ownership of a previously qualified manufacturer or source requires reevaluation of the qualification. The reevaluation must be accomplished before the date of award.

(End of clause)