73066010-01341-LPTDP0019-001-02_14_2018.pdf

PDF 105 KB Posted

Attached to
Level 1 barstock
Solicitation number
SPMYM418Q0340
Issued by

About this file

This is a level 1 material requirement and interested parties should review the attached SF-18 (solicitation) with accompanying technical date package (TDP) and contract Data (DD 1423) requirements.

View the file

Other files

File Type Posted
SPMYM418Q0340.dotx DOTX file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL DATA PACKAGE

NIIN: LPTDP0019 VERSION: 001 PAGE 1

ITEM NAME: ROUND BAR Feb 14, 2018

1. SCOPE1.1 The material covered in this contract/purchase order will be used in a crucial shipboard system. The use of incorrect or defective material would create a high probability of failure resulting in serious personnel injury, loss of life, loss of vital shipboard systems, or loss of the ship itself. Therefore, the material has been designated as SPECIAL EMPHASIS material (Level I, Scope of Certification, or Quality Assured) and special control procedures are invoked to ensure receipt of correct material.

2. APP DOCS2.1 Order of Precedence - In the event of a conflict between the text of this contract/purchase order and the references and/or drawings cited herein, the text of this contract/purchase order shall take precedence. Nothing in this contract/purchase order, however, shall supersede applicable laws and regulations unless a specific exemption has been obtained.

2.2 Applicable Documents - The document(s) listed below form a part of this contract/purchase order including modifications or exclusions.

2.2.1 "Document References" listed below must be obtained by the Contractor. Ordering information is included as an attachment to this contract/purchase order.

2.3

DOCUMENT REFERENCES

SPEC NO. SLASH NO. PART NO. REV DATE DISTR CD AMEND CHD NTC SUPP

ANSI/ASQ Z1.4 0 0 01/01/2008 A

ANSI/NCSL Z540.3 0 0 03/26/2013 A

ASTM-B666 0 0 04/10/2001 A

ISO 9002 0 0 07/01/1994 A

ISO-9001 0 0 07/01/1994 A

ISO/IEC 17025 0 0 05/15/2005 A

ISO10012 0 0 04/15/2003 A

ISO9001 0 0 12/15/2000 A

ISO_9001 0 0 11/15/2008 A

MIL-I-45208 0 0 A 07/24/1981 A 1

MIL-STD-2132 0 0 D 03/10/2008 F 1

MIL-STD-45662 0 0 A 08/01/1988 A

MIL-STD-792 0 0 F 05/19/2006 A

QQ-N-286 0 0 G 12/07/2000 A

SAE AMS 2806 0 0 C 03/01/2008 A

SAE AMS 2807 0 0 A 09/01/2000 A

SAE AMS 2809 0 0 A 08/01/2007 A

SAE AMS-STD-185 0 0 09/01/2000 A

T9074-AS-GIB-010/271 0 0 1 09/11/2014 A

3. REQUIREMENTS3.1 Manufacture and Design - The item furnished under this contract/purchase order shall meet the requirements as specified in QQ-N-286 except as amplified of modified herein.

QQ-N-286 ordering data information is provided below:

a. Nickel-copper-aluminum alloy, wrought (UNS N05500); QQ-N-286.

b. Form - 1 Condition - Annealed (hot finished or cold drawn), unaged.

Surface Finish - As specified in paragraph 4.3.3.1.3 of QQ-N-286.

c. Specification revision levels shall be as specified elsewhere in the contract/purchase order.

d. Forging sketches are not applicable.

e. Size - 1" DIA

f. A product check analysis is NOT required.

g. Forging rings and discs are not applicable.

h. Tolerances shall be as specified in QQ-N-286.

i. Optional ultrasonic inspection is required. Certification is required.

NIIN: LPTDP0019 VERSION: 001 PAGE 2

j. Optional liquid penetrant inspection is required on cold worked material only.

k. Length - Under 5" dia. = 8 feet min / 12 feet max (plus or minus 10%) 5" dia & over = 5 feet min / 12 feet max (plus or minus 10%) OR as specified elsewhere in the contract/purchase order.

l. Paragraph 3.9.1.3.1 of QQ-N-286 applies unless otherwise specified.

m. Edges shall be as specified in paragraph 3.9.1.4 of QQ-N-286.

n. Forging dimensions are not applicable.

o. Marking shall be as specified elsewhere in the contract/purchase order.

p. All unaged barstock shall be supplied in the annealed condition and be subjected to a capability test.

q. Age hardening shall be performed in accordance with paragraph 4.3.2.2.1, unless otherwise specified.

r. The final heat treatment procedure shall be in accordance with QQ-N-286, unless otherwise specified.

s. The slow strain rate tensile test shall be conducted by one of the laboratories identified below.

t. Level of preservation, packaging, and packing shall be as specified elsewhere in the contract/purchase order.

3.2 Bar, Pipe, and Tube Quantities - When this order results in supplying fewer than 5 pieces as defined in the "Length" paragraph above, all material shall be from a single heat of material.

3.3 Testing Certification - Certifications are required for the following tests on the items listed below. Additional testing (if any) per applicable specifications is still required, but certifications are only required as listed below.

Test - Ultrasonic Inspection on Starting Material Item - Metal Bar Performance - T9074-AS-GIB-010/271 or MIL-STD-2132, and QQ-N-286 Acceptance - QQ-N-286

Test - Macroetch Test (Duplex Grain Structure) Item - Bar, Metal Performance - QQ-N-286 Acceptance - QQ-N-286

3.4 Slow Strain Rate Tensile Test Laboratories - The Slow Strain Rate Tensile Test of QQ-N-286 must be performed by one of the following laboratories:

Huntington Alloys, a Special Metals Company Attn: Frank Veltry huntington, WV 25705 Phone: (304) 526-5759

FAX: (304) 526-5973

Metallurgical Consultants, Inc.

Attn: W. M. Buehler 4820 Caroline PO Box 88046 Houston, TX 77288-0046 Phone: (713) 526-6351

FAX: (713) 526-2964

Naval Surface Warfare Center, Carderock Division Attn: Eric Focht Code 614 9500 Macarthur Blvd West Bethesda, MD 20817-5700 Phone: (301) 227-5032

FAX: (301) 227-5576

Teledyne Allvac Attn: Dr. W. D. Cao 2020 Ashcraft Ave.

Monroe, NC 28110 Phone: (704) 289-4511

FAX: (704) 289-4269

Westmoreland Mechanical Testing and Research Inc.

Attn: Andrew Wisniewski P.O. Box 388 Youngstown, PA 15696-0388

Mannesmann Rohrenwerke Mannesmann Forschungsinstitut (MFI)

NIIN: LPTDP0019 VERSION: 001 PAGE 3

Attn: Dr. Weiss Postfach 251160 47251 Duisburg Germany Phone: 011-49-0203-9993194

FAX: 011-49-0203-9994415

ThyssenKrupp VDM USA, Inc.

Attn: D. C. Agarwal 11210 Steeplecrest Drive, Suite 120 Houston, TX 77065-4939 Phone: (281) 955-6683

3.5 Certificate of Compliance - (SPECIAL EMPHASIS MATERIAL) The Contractor shall prepare and submit a certificate of compliance certifying that the items/components furnished under this contract comply with the requirements of the procurement document, including any/all invoked specifications and drawings.

3.6 Configuration Control - The Contractor shall maintain the total equipment baseline configuration.

For items of proprietary design, Contractor drawings showing the latest assembly configuration shall be provided to the Government in electronic (C4) format. Definitions are provided elsewhere in he Contract/Purchase Order.

3.6.1 Waivers/Deviations - All waivers and deviations, regardless of significance or classification require review and approval by the Contracting Officer. Waivers and Deviations shall be designated as Critical, Major, or minor. The Contractor shall provide a copy of this request to the QAR. Requests shall include the information listed below.

a. A complete description of the contract requirement affected and the nature of the waiver/deviation (non-conformance), including a classification of Critical, Major, or Minor.

b. Number of units (and serial/lot numbers) to be delivered in this configuration.

c. Any impacts to logistics support elements (such as software, manuals, spares, tools, and similar) being utilized by Government personnel or impacts to the operational use of the product.

d. Information about remedial action being taken to prevent reoccurrence of the non-conformance.

3.6.2 All requests for Waivers/Deviations on NAVSUP-WSS Contracts shall be submitted using the ECDS (Electronic Contractor Data Submission) system at https://register.nslc.navy.mil/

3.6.3 ECPs - The Government will maintain configuration control and change authority for all modifications or changes affecting form, fit, function, or interface parameters of the Equipment and its sub-assemblies. The Contractor shall submit an Engineering Change Proposal (ECP) for any Class I or II changes that impact the Equipment covered by this contract. ECPs shall be prepared in Contractor format, and shall include the following information:

a. The change priority, change classification (Class I or Class II), and change justification.

b. A complete description of the change to be made and the need for that change.

c. A complete listing of other Configuration Items impacted by the proposed change and a description of the impact on those CIs.

d. Proposed changes to documents controlled by the Government.

e. Proposed serial/lot number effectivities of units to be produced in, or retrofitted to, the proposed configuration.

f. Recommendations about the way a retrofit should be accomplished.

g. Impacts to any logistics support elements (such as software, manuals, spares, tools, and similar) being utilized by Government personnel in support of the product.

h. Impacts to the operational use of the product.

i. Complete estimated life-cycle cost impact of the proposed change.

j. Milestones relating to the processing and implementation of the engineering change.

3.7 Mercury Free - Mercury and mercury containing compounds shall not be intentionally added or come in direct contact with hardware or supplies furnished under this contract. Mercury contamination of the material will be cause for rejection.

3.8 Vendor Acknowledgement of K-Monel Heat Review

1. Recent investigations into mechanical property failures of fasteners manufactured from NiCuAl (KMonel) material that was produced by Special Metals Corporation (formerly INCO Alloys) of Huntington, West Virginia has found eighty (80) heats of material which may not meet the mechanical property requirements of QQ-N-286 throughout the heat. In 1994, Special Metals Corporation implemented a process change that eliminated the addition of extra aluminum at the toe of each NiCuAl (K-Monel) ingot resulting in the toe portion of the heat being non-homogeneous in comparison to the rest of the heat. Due to cropping practices at Special Metals Corporation, material from the toe of the ingot with non-homogeneous aluminum content was not cropped from production material prior to shipment. A recent study has shown that the aluminum concentration in the toe portion of the ingot could be as low as

NIIN: LPTDP0019 VERSION: 001 PAGE 4

approximately 2.0% with corresponding yield strength as low as approximately 40,000 PSI. QQ-N-286 specifies an aluminum content of 2.3% minimum and a yield strength of 90,000 PSI minimum or 85,000 PSI minimum for material = l". As a result of the investigation, the eighty (80) heats listed in Table I are considered suspect of having problems with insufficient aluminum content and an inability to consistently attain the requited minimum yield strength.

2. You are requested to review your records of in stock in process K-Monel material from the Special Metals Corporation for the sect heat numbers listed in Table I below. You are prohibited from providing raw stock or finished products made from the suspect K-monel heats. If suspect heats are intended to be used, contact the PHNS & IMF contracting officer for adjudication the material.

Table I - List of Suspect Special Metals Corporation K-Monel Heat Numbers

M00J6KG M02J9KG M00J7KG M03J8KG

M01J1KG M04J2KG M02J8KG M04J6KG

M04J7KG M11J3KG M17J2KG M19J7KG

M06J5KG Ml1J4KG M17J3KG M21J2KG M06J8KG Ml1J5KG M17J4KG M22J7KG Ml1J2KG M15J6KG M18J7KG M22J8KG

M23J2KG M24J5KG M26J8KG M26J9KG

M27J9KG M33J7KG M28J4KG M34H4KG

M30J9KG M35H0KG M31J9KG M35J0KG

M35J7KG M35H8KG M36H7KG M36J2KG

M36J3KG M37J4KG M39J3KG M41J1KG

M41J2KG M41H3KG M41J3KG M41J7KG

M41J8KG M44J4KG M44J6KG M45J2KG

M45J8KG M45J9KG M46J7KG M52H9KG

M61J8KG M61J9KG M62J5KG M64J4KG

M64J5KG M64J6KG M67H2KG M67J4KG

M69J1KG M70J6KG M73J4KG M76H6KG

M80H2KG M80H3KG M84H9KG M85H0KG

M88H6KG M88H7KG M89H5KG M89H6KG

M92H0KG M95H7KG M97H8KG M99H3KG

* QUALITY ASSURANCE REQUIREMENTS *

3.9 See CDRL DI-MISC-80678 (Test Certification) - A statement of tests performed, listing the pieces tested, shall be furnished along with a copy of the test results. Certification shall include the contractor's name, address, and date, quantity inspected, identified to the contract/purchase order and item number, and the Contractor's or authorized personnel's signature. Test certifications must reference the standard/specification, including the revision, to which the testing was performed and the acceptance criteria used. Test procedure numbers may also be referenced on test reports. Test reports on weldments shall be identified to weld joint and layer.

3.10 Quality System Requirements - The Contractor furnishing items under this contract/purchase order shall provide and maintain a quality system in accordance with ISO-9001 as amplified or modified herein, with the calibration system requirements of ISO-10012 or ANSI-Z540.3 with ISO-17025. A Quality System in accordance with MIL-I-45208, with the calibration system requirements of MIL-STD- 45662, is acceptable as an alternate.

3.10.1 The Contractor's quality system and products supplied under the system are subject to evaluation, verification inspection, and acceptance/non-acceptance by the Government to determine the system's effectiveness in meeting the quality requirements established in the Contract/Purchase Order.

3.10.2 The Contractor's quality system shall be documented and shall be available for review by the Contracting Officer prior to initiation of production and throughout the life of the contract. The Prime Contractor shall, upon notification, make his facilities available for audit by the Contracting Officer or his authorized representative.

3.10.3 See CDRL DI-QCIC-81110 (Inspection System Procedures) - All suppliers of Level I/SUBSAFE (LI/SS) material are required to submit a copy of their current documented quality system procedures to the Procurement Contracting Officer (PCO) prior to award of any contract/purchase order. Suppliers that have a copy of their current quality system procedures on file at the Procuring Activity may request the PCO waive this requirement.

3.10.4 This contract provides for the performance of Government Quality Assurance at source. The place or places of performance may not be changed without the authorization of the Procurement Contracting Officer. Upon receipt of this order, promptly notify the Government representative who normally services your plant so that appropriate planning for Government inspection can be accomplished. If you do not have an assigned Government representative, notify the nearest Defense

NIIN: LPTDP0019 VERSION: 001 PAGE 5

Contract Management Agency (DCMA) Office. In the event that a local Government representative or DCMA Office cannot be located, our purchasing agent should be notified immediately.

3.10.5 Any changes made by the Contractor to a qualified quality system will require re-submittal to the PCO.

3.11 Contractor Inspection Requirements - The Contractor shall maintain adequate records of all inspections and tests. The records shall indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected and the nature of corrective action taken as appropriate. Inspection records shall be traceable to the material inspected.

3.11.1 The supplier's gauges, measuring and test equipment shall be made available for use by the Government when required to determine conformance with Contract requirements. When conditions warrant, the supplier's personnel shall be made available for operations of such devices and for verification of their accuracy and condition.

3.11.2 All documents and reference data applicable to this contract shall be available for review by the Government. Copies of documents required for Government inspection purposes shall be furnished in accordance with the instructions provided by the Government.

3.12 Subcontractor Inspection Requirements - The Government has the right to inspect at source, any supplies or services that were not manufactured or performed within the contractor's facility. Any purchasing documents to a subcontractor must cite the applicable portions of the contractually invoked quality system (e.g. calibration requirements), plus any product requirements that apply to the supplies being purchased. When the Government elects to perform source inspection at the subcontractor's facility, applicable purchase documents shall be annotated with the following statement: "A Government inspection is required prior to shipment from your plant. Upon receipt of this order, promptly notify the Prime Contractor who will notify the PCO so that appropriate planning for Government inspection can be accomplished.

3.12.1 The prime contractor's program shall include procedures to assess the capability of the prospective suppliers to produce the products or supply the services in accordance with the contract, prior to the issuance of any purchase document.

3.12.2 Each sub-tier supplier of material or services for items in Section 3 of this contract shall be subjected to a periodic review or audit by the Prime to determine the continued capability of the supplier to control the quality of the products or services specified in the purchase order or contract.

3.12.3 The prime contractor shall ensure that the purchased product conforms to specified purchase requirements and this contract. The type and extent of control applied to the supplier and the purchased product shall be dependent upon the effect of the purchased product on the end item represented by this contract.

3.12.4 The prime contractor shall evaluate the requirements of the contract and select suppliers based on their ability to supply the product in accordance with the prime contractor's requirements and the contract. Criteria for selection and evaluation shall be established. Records of this effort shall be available for review by the government.

3.12.5 The prime contractor's supplier quality assurance program shall provide for a review of purchase documents to assure applicable quality requirements are included or referenced in the documentation for compliance by the supplier.

3.13 Government Furnished Material and/or Equipment (GFM/GFE) - When material or equipment is furnished by the Government, the Contractor shall develop documented control procedures that require at least the following:

3.13.1 Visual examination upon receipt to detect damage during transit.

3.13.2 Inspection for completeness and proper type.

3.13.3 Verification of material quality received.

3.13.4 Periodic inspection and precautions to assure adequate storage conditions and to guard against damage from handling and deterioration during storage.

3.13.5 Functional testing, either prior to or after installation, or both, as required by the Contract to determine satisfactory operation.

3.13.6 Identification and protection from improper use or disposition.

3.13.7 Reporting to the Government, any GFM or GFE property found damaged, malfunctioning, or

NIIN: LPTDP0019 VERSION: 001 PAGE 6

otherwise unsuitable for use. In the event of damage or malfunction during or after installation, the supplier shall determine and record probable cause and necessity for withholding the material from use.

3.13.8 For GFE material, and as required by the terms of the bailment agreement, the supplier must establish procedures for adequate storage, maintenance, and inspection of bailed Government material.

Records of all inspection and maintenance performed on bailed property shall be maintained.

3.13.9 Material returned to the contractor shall be handled as GFM.

3.14 Traceability and Certification Requirements - To assure that correct materials are installed in Level I/SUBSAFE systems, it is imperative that traceability be maintained from the material to the material certification test report and other required Objective Quality Evidence (OQE). The material certification report must completely and accurately reflect that the material supplied meets the specified requirements. Materials requiring Traceability and Certification Data are identified within Paragraph 3, Section C of this contract/purchase order.

3.14.1 The following provides the minimum requirements for maintaining material traceability and supplements the requirements specified in DI-MISC-81020 and elsewhere in the contract/purchase order.

The Contractor shall develop written procedures that implement the material control requirements stated herein.

3.15 Material Traceability - The certification data report shall be identified through a unique traceability number, heat-lot number, or heat-treat number, as applicable, which shall also be marked on the material. This traceability marking on the material shall provide direct traceability to the material's chemical composition and mechanical properties certification data. For material produced by batch, continuous cast, or continuous pour processes, samples shall be taken no less than once in every eight hours of operation for the purpose of validating proper chemical composition and mechanical properties. Traceability shall be maintained through all process operations including any subcontracted operations, to the finished component.

3.15.1 Material Marking for Traceability and Identification - The following are the minimum marking requirements. In addition to the marking requirements on applicable specifications, marking for traceability is required. Pipe, Tube, and Metal Bar shall have both permanent marking and temporary marking applied as specified below.

3.15.2 Permanent marking - Permanent traceability marking shall be marked on each end of each pipe, tube, and metal bar. (MONEL and K-MONEL bar: 3/4 inch to 1 inch rods, and 7/8 inch hex bar may be marked on the surface near the end of bar/rod, and rod less than 3/4 inch and hex bar less than 7/8 inch may be bundled and tagged or boxed with the traceability marking on the tag or box.) All traceability marking shall be permanently applied in accordance with MIL-STD-792. An alternate marking method is permissible provided it is an available option in the contractually invoked specification, except in instances where the material has been modified by this contract/purchase order, and differs from that specified in the specification. Electric arc marking or impression marking is strictly prohibited on thin wall tubing. (wall thickness of less than 0.125 inch).

3.15.3 Temporary Marking - Temporary Marking shall consist of: Name or Trademark of Manufacturer, specification and grade (as applicable), size, contract number, and the traceability marking. Pipe and tube marking shall also include SML (for seamless). Marking shall be in accordance with the material specification and SAE-AMS-2806, SAE-AMS-2807, SAE-AMS-2809, Table I of SAE-AMS-STD-185, or ASTM-B666 as applicable. Application shall be in accordance with MIL-STD-792, type A (temporary ink stenciling). An alternate method is permissible for MONEL and K-MONEL bar provided it is an available option (temporary marking only) in the applicable material specification, except that hot finished rod with rough ground surface 3/4 inch and under may be bundled and tagged or boxed with the traceability marking on the bag or box. Contamination levels for ink stenciling shall be as outlined in paragraph

5.2 of MIL-STD-792.

3.16 See CDRL DI-MISC-81020 (Chemical and Mechanical) - Material Certification - In addition to the certification data requirements specified in DI-MISC-81020, the following material certification requirements apply:

3.16.1 Quantitative chemical and mechanical analysis of material traceable to traceability markings is required. Material certification test reports shall include the class, form, condition, grade, type, finish, and/or composition, as applicable, of the material supplied.

3.16.2 Re-identification and re-certification of material is required when the material is subjected to a process which alters it's properties. If the starting material or raw stock is processed in a manner that will not affect its chemical composition or mechanical properties, the original certifications for the chemical composition and mechanical properties, as required by the material specification, are acceptable. Re-certification of the chemical or mechanical properties is required if a process is used during fabrication that alters the original properties of the material (e.g.

alloying, heat treating, or forming). In these instances, the properties of the material must be re-determined and documented to reflect the altered condition. The altered material shall be uniquely

NIIN: LPTDP0019 VERSION: 001 PAGE 7

re-identified. The properties thus determined and documented, are required for final certification and shall conform to the material specification or the contract/purchase order requirements. When only the mechanical properties are altered, the original certification for chemical composition shall be overstamped and/or annotated with the unique traceability marking used with the altered material and at a minimum contain the information below.

TRACEABILITY MARKING ________________________________________________

(marking on finished item)

IS FABRICATED FROM RAW MATAERIAL IDENTIFIED TO

HEAT/LOT NUMBER ________________ AND HEAT TREAT NUMBER ________________________

(when applicable)

_________________________________________ DATE _____________________

(name and signature of auth. co. rep.)

3.16.3 Material certification data forwarded by the manufacturer shall contain a signed certification that the report results represent the actual attributes of the material furnished and indicate full compliance with all applicable specification and contract requirements. Transcription of certification data is prohibited.

3.16.4 Statements on material certification documents must be positive and unqualified. Disclaimers such as "to the best of our knowledge" or "we believe the information contained herein is true" are not acceptable.

3.17 See CDRL DI-MISC-80678 (Special Emphasis C of C) - The certificate of compliance must show traceability to the marking applied on each individual item, and shall contain the following information:

1. Contractor's name, address and date.

2. The contract/purchase order number (for example: N00104-11-P-FA12)

3. The Local Stock Number (LSN). The 18 character Local Stock Number for Special Emphasis Material includes the two digit COG, the four digit FSC, the 9 digit Local Item Control Number (LICN), and the two digit SMIC (for example: 1H 4820 PSTDP0000 L1).

4. Lubricants, sealants, anti-seize, and/or thread locking compounds ("N/A" when Not Applicable).

5. Certification that O-rings, packing, gaskets, or other elastomeric products were installed in a compressed state within an assembly or sub-assembly, prior to expiration of the shelf life ("N/A" when Not Applicable).

6. Manufacturer's compound number ("N/A" when Not Applicable).

7. When weld procedure submittal is required by the contract, a statement that the approval date of the qualification data precedes any production or repair welding performed on this Contract. ("N/A" when Not Applicable).

8. A statement to the effect that all items furnished on this contract are in full compliance with the specifications and requirements and list each contractually invoked conformance/compliance test performed by name and that it was performed satisfactorily.

9. Contractor's or authorized personnel's signature.

4. QA PROV4.1 Notes to DCMA QAR and the Contractor -

4.1.1 DCMA QAR and the Contractor for proprietary designs - Departures from Contractor imposed requirements, not specifically covered by the contract, must be judged individually on the basis of the effect, if any, on contractual requirements. When there is a disagreement between the Contractor and the Government representative as to the effect on contractual requirements, the departure shall be considered a nonconformance and be submitted to the PCO for disposition.

4.1.2 DCMA QAR and the Contractor for proprietary designs - All records of departures from Contractor imposed requirements shall be maintained and available for review at the Contractor's facility. A copy shall be given to the local Government representative. A record of these departures, traceable to the applicable part number and contract number shall be submitted to the PCO.

4.1.3 DCMA QAR and the Contractor for proprietary designs - For proprietary designs, the contractor's part numbers are acceptable for reference only. The delivered material must conform to all drawings, specifications, and other contractual requirements.

4.1.4 DCMA QAR - It is the responsibility of DCMA QAR to review Non-Destructive Testing (NDT) procedures for NAVSUP Contracts/Purchase Orders.

4.1.5 DCMA QAR and the Contractor - The ECDS (Electronic Contractor Data Submission) system is

NIIN: LPTDP0019 VERSION: 001 PAGE 8

available for certain data submissions and to submit questions and clarifications, and waiver requests on Contracts and Solicitations. ECDS can be found at: https://register.nslc.navy.mil/

5. PACKAGING5.1 Preservation, Packaging, Packing and Marking - Preservation, Packaging, Packing and Marking shall be in accordance with the Contract/Purchase Order Schedule and as specified below.

6. NOTES6.1 Several definitions of terms that apply to LI/SOC items are listed below. All terms may not apply to every item.

6.1.1 The ECDS (Electronic Contractor Data Submission) system is at: https://register.nslc.navy.mil/ This application will require advance registration using a PKI Digital Certificate.

Information on initiating a PKI can be found at: http://iase.disa.mil/pki/eca/Pages/index.aspx A Vendor User Guide is available as CSD001 in the CSD (Contract Support Document) Library within ECDS.

6.1.2 Critical Safety Item (CSI) - Any ship part, assembly, or support equipment containing a critical characteristic whose failure, malfunction, or absence of which could cause a catastrophic or critical failure resulting in loss of, or serious damage to the ship, or unacceptable risk of personal injury or loss of life.

6.1.3 Critical Process - As determined by the TWH, any process, operation or action performed on a Ship CSI that serves to establish a critical characteristic (such as welding, soldering, machining, polishing, cleaning, or assembling) or confirm that a critical characteristic is within drawing or specification compliance (such as, testing, measurement, or non-destructive evaluation).

6.1.4 First Article - Pre-production models, initial product samples, test samples produced to ensure a manufacturer's capability to meet full specification requirements.

6.1.5 First Article Test (FAT) - Contractually required testing and inspection of a supplier's pre-production, production, or "production representative" specimens to evaluate a manufacturer's ability to produce conforming product prior to the Government's commitment to receive subsequent production items. First Article Testing is product specific and does not assess manufacturing process controls nor does it assure the effectiveness of the manufacturer's quality program.

6.1.6 Objective Quality Evidence (OQE) - The quantitative and qualitative data of all mechanical, chemical, and performance tests performed (as required by the applicable specification, drawing, or purchase document) to prove that the material supplied conforms to the specified requirements.

6.1.7 Surface Discontinuity - Any surface irregularity, marking, or localized change in physical character of the surface, other than dimensional, that exists infrequently at one or several places.

(Examples: burrs, dents, nicks, scratches, gouges, pits, center-punches, scribes, and tool marks) Surface discontinuities less than 0.005-inch in depth are acceptable provided they do not violate any other design requirements specified in this Contract/Purchase Order.

6.1.8 Traceability Code - A code or number providing traceability to the actual chemical and mechanical properties of the specified heat, batch, or form from which the material originated.

6.1.9 Verification - An examination performed to determine compliance with a specific requirement.

6.1.10 Nonconformance - Defined as affecting or violating the following:

- The requirements of this contract/purchase order.

- Contractually invoked drawings (i.e. envelope dimensions, interface dimensions with mating parts/equipment, center of gravity, weights, piece part identification, material, etc.).

- Contractually invoked federal, military, or commercial specifications and/or standards.

- Form, fit, function, performance to contract requirements, reliability, maintainability, interchangeability, safety of personnel or equipment, or additional cost to the Government.

6.1.11 Waiver - A written authorization to accept an item, which during manufacture, or after having been submitted for Government inspection or acceptance, is found to depart from specified requirements, but nevertheless is considered suitable for use as is or after repair by an approved method.

6.1.12 Deviation - A specific written authorization (granted prior t0 the manufacture of an item) to depart from a particular requirement(s) of an item's current approved configuration documentation for a specific number of units or a specified period of time, and to accept an item which is found to depart from specified requirements, but nevertheless is considered suitable for use "as is" or after repair by an approved method.

6.1.13 Critical Waiver/Deviation - This waiver/deviation consists of a departure involving safety.

6.1.14 Major Waiver/Deviation - This waiver/deviation consists of a departure involving:

- Performance

NIIN: LPTDP0019 VERSION: 001 PAGE 9

- Interchangeability, Reliability, Survivability, Maintainability, or Durability of the item or its repair parts

- Health or Safety

- Effective Use or Operation

- Weight, Stability, or Structural Integrity

- System design parameters as schematics, flows, pressures or temperatures

- Compartment arrangements or assigned function

6.1.15 Minor Waiver/Deviation - This waiver/deviation consists of a departure which does not involve any of the factors listed as critical or major

6.1.16 Engineering Change (EC) - A change to the current approved configuration documentation of a configuration item at any point in the life cycle of the item.

6.1.17 Engineering Change Proposal (ECP) - A proposed Engineering Change and the documentation by which the change is described, justified, and submitted to the Government for approval or disapproval.

6.2 In accordance with OPNAVINST 5510.1 all documents and drawings provided by the U.S. Navy to perspective Contractors must include a "Distribution Statement" to inform the contractor of the limits of distribution, and the safeguarding of the information contained on those documents and drawings.

6.2.1 There are 7 (seven) seperate distribution statement codes used for non-classified documents and drawings. The definition for each is as follows:

A... approved for public release; distribution is unlimited.

B... distribution authorized to US Governments agencies only.

C... distribution authorized to US Government agencies and their contractors.

D... distribution authorized to DoD and DoD contractors only.

E... distribution authorized to DoD Components only.

F... further distribution only as directed by Commander, Naval Sea Systems Command, code 09T.

X... distribution is authorized to US Government agencies and private individuals or enterprises eligible to obtain export controlled technical data in accordance with OPNAVINST 5510.161.

6.3 Ordering Information for Document References - The Department of Defense Single Stock Point (DODSSP), Website http://www.dsp.dla.mil/, provides product information for the Department Of Defense Index Of Specifications and Standards (DODISS) (i.e.Military/Federal Specifications and Standards), Data Item Descriptions (DIDs), and other DODSSP Products. Most Specifications can obtained directly from http://quicksearch.dla.mil/

A. Availability of Cancelled Documents - The DODSSP offers cancelled documents that are required by private industry in fulfillment of contractual obligations in paper format. Documents can be requested by phoning the Subscription Services Desk.

B. Commercial Specifications, Standards, and Descriptions - These specifications, standards and descriptions are not available from Government sources. They may be obtained from the publishers of the applicable societies.

C. Ordnance Standards (OS), Weapons Specifications (WS), and NAVORD OSTD 600 Pages - These type publications may be obtained by submitting a request to:

Commander, Indian Head Division, Naval Surface Warfare Center Code 8410P, 101 Strauss Avenue Indian Head, MD 20640-5035

D. On post-award actions, requests for "Official Use Only" and "NOFORN" (Not Releasable To Foreign Nationals) documents must identify the Government Contract Number, and must be submitted via the cognizant Defense Contract Management Command (DCMC) for certification of need for the document. On pre-award actions such requests must be submitted to the PCO for certification of need for the document.

E. NOFORN Military Specifications and Standards (including Amendments, Change Notices and Supplements, but NOT interim Changes) to be ordered from:

Contracting Officer

NAVSUP-WSS

Code 87321 5450 Carlisle Pike P.O. Box 2020 Mechanicsburg, Pa. 17055-0788

F. Nuclear Reactor Publications Assigned NAVSEA Documents and Identification Numbers (i.e. NAVSEA Welding Standard, NAVSEA 250-1500-1) are to be ordered from:

NIIN: LPTDP0019 VERSION: 001 PAGE 10

Commanding Officer

NAVSUP-WSS

Code 009 5450 Carlisle Pike P.O. Box 2020 Mechanicsburg, Pa. 17055-0788

G. Technical Manuals Assigned NAVSEA Identification Numbers (i.e. NAVSEA Welding And Brazing Procedure, NAVSEA S9074-AQ-GIB-010/248) are to be ordered from:

Commanding Officer

NAVSUP-WSS

Code 1 Support Branch 700 Robbins Avenue Phildelphia, Pa. 19111-5094

H. Interim Changes and Classified Specifications shall be obtained by submitting a request on DD Form 1425 to NAVSUP-WSS.

7. DD FORM 1423 COMMENTS

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

C. CATEGORY

TDP

D. SYSTEM/ITEM

Metal Bar

E. CONTRACT/PR NO.

F. CONTRACTOR

1. DATA ITEM NO.

A00001

2. TITLE OF DATA ITEM

INSPECTION AND TEST PLAN

3. SUBTITLE

INSPECTION SYSTEM PROCEDURES

4. AUTHORITY (Data Acqisition Document No.)

DI-QCIC-81110 (SE)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

9. DIST STATEMENT

REQUIRED

B

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

Draft Final

Reg Repro

16. REMARKS

Paragraph 10.4 of DI-QCIC-81110 does not apply.

PCO 0 1 0

15. Total 0 1 0

G. PREPARED BY

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

2018-01-24

DD Form 1423-1, JUN 90 Page 1 of 4 Page(s)

S/N 0102-LF-010-5600

Form Approved

D. SYSTEM/ITEM

A00002

2. TITLE OF DATA ITEM

CERT DATA FOR SPECIAL EMPHASIS MATL

3. SUBTITLE

CHEMICAL AND MECHANICAL

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-81020 (DD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253 and eMail notification field: PEARL_PHNSY_WAWF_Notification@navy.mil

No material is to be shipped prior to the receipt of Acceptance.>

N32253 0 1 0

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

DD Form 1423-1, JUN 90 Page 2 of 4 Page(s)

Form Approved

D. SYSTEM/ITEM

A00003

2. TITLE OF DATA ITEM

CERTIFICATION/DATA REPORT

3. SUBTITLE

SPECIAL EMPHASIS C OF C

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-80678 (CCDD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

Block 4 - Paragraphs 10.2.1, 10.2.2, 10.2.3, 10.3, and 10.4 of DI-MISC-80678 do not apply.

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253 and eMail notification field: PEARL_PHNSY_WAWF_Notification@navy.mil

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

DD Form 1423-1, JUN 90 Page 3 of 4 Page(s)

Form Approved

D. SYSTEM/ITEM

A00004

2. TITLE OF DATA ITEM

CERTIFICATION/DATA REPORT

3. SUBTITLE

TEST CERTIFICATIONS

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-80678 (DD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253 and eMail notification field: PEARL_PHNSY_WAWF_Notification@navy.mil

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

DD Form 1423-1, JUN 90 Page 4 of 4 Page(s)

(2 Data Items)

Form Approved

D. SYSTEM/ITEM

A0001

2. TITLE OF DATA ITEM

INSPECTION AND TEST PLAN

3. SUBTITLE

INSPECTION SYSTEM PROCEDURES

4. AUTHORITY (Data Acqisition Document No.)

DI-QCIC-81110 (SE)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

9. DIST STATEMENT

REQUIRED

B

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

N/A

Draft Final

Reg Repro

16. REMARKS

Paragraph 10.4 of DI-QCIC-81110 does not apply.

PCO 0 1 0

A0002

2. TITLE OF DATA ITEM

CERT DATA FOR SPECIAL EMPHASIS MATL

3. SUBTITLE

CHEMICAL AND MECHANICAL

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-81020 (DD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253 and eMail notification field: PEARL_PHNSY_WAWF_Notification@navy.mil

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

2018-01-24

DD Form 1423-2, JUN 90 Page 1 of 2 Page(s)

(2 Data Items)

Form Approved

D. SYSTEM/ITEM

A0003

2. TITLE OF DATA ITEM

CERTIFICATION/DATA REPORT

3. SUBTITLE

SPECIAL EMPHASIS C OF C

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-80678 (CCDD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

Block 4 - Paragraphs 10.2.1, 10.2.2, 10.2.3, 10.3, and 10.4 of DI-MISC-80678 do not apply.

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253

A0004

2. TITLE OF DATA ITEM

CERTIFICATION/DATA REPORT

3. SUBTITLE

TEST CERTIFICATIONS

4. AUTHORITY (Data Acqisition Document No.)

DI-MISC-80678 (DD)

5. CONTRACT REFERENCE

TDP: PARA 3

6. REQUIRING OFFICE

PURCHASING ACTIVITY

7. DD 250 REQ

DD

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft Final

Reg Repro

16. REMARKS

Block 4 - Paragraphs 10.2.2, 10.2.3, 10.2.4, and 10.3 of DI-MISC-80678 do not apply.

<Block 12 - Certification data shall be submitted to Pearl Harbor Naval Shipyard for review and acceptance prior to each shipment of material. Certification documentation shall be submitted via WAWF (Wide Area Work Flow).

Enter in WAWF as follows:

"Ship to" N32253 "Inspect by" N32253 "Accept by" N32253

83SYPH14

H. DATE

2018-01-24

I. APPROVED BY

Stacie Hamada

J. DATE

2018-01-24

DD Form 1423-2, JUN 90 Page 2 of 2 Page(s)

File details come from the government source that posted it.