Specs Issued for Bid .pdf
PDF 1 MB Posted
- Attached to
- Edna Sunset Lift Station Generator
- Solicitation number
- 2560B
- Issued by
- Jefferson County, Texas
About this file
Summary
This is a Technical Specifications document issued by the City of Edna, Texas for the Sunset Lift Station Generator project, prepared by Lynn Engineering with specifications dated September 2025. The project involves the installation of permanent emergency generators and automatic transfer switches at the Sunset Lift Station in Edna, Jackson County, Texas. The work will be conducted under a single prime contract, with construction to proceed in a sequence required to meet the timeframe specified in the Bid Proposal. The contract documents include comprehensive Division 1 General Requirements covering project coordination, payment procedures, submittal requirements, project meetings, field engineering, and closeout procedures, along with Division 3 specifications for cast-in-place concrete and Division 26 specifications for electrical systems including diesel-fueled engine generators and automatic transfer switches. The specifications emphasize coordination between contractors, protection of existing utilities and vegetation within easements, and compliance with ACI standards for concrete work.
The specifications require extensive administrative and procedural compliance including daily construction reports, materials location reports, and coordination drawings where necessary. Contractors must submit a Schedule of Values with their initial payment application and a Submittal Schedule within ten days following the Pre-Construction Conference. All submittals require transmittal using AIA Document G810 or approved equivalent forms. The contract mandates preconstruction conferences, regular progress meetings, and final closeout procedures including submission of operation and maintenance manuals in five copies, record drawings, warranties, and final project documentation. Concrete work requires design mixes with 3000 psi compressive strength at 28 days, a minimum of five sacks of cement per cubic yard with maximum 20 percent fly ash, and compliance with ACI 301 and ACI 117 standards. The specifications establish strict requirements for forming, reinforcement placement, concrete consolidation, finishing, curing for not less than seven days, and surface repair using materials and methods matching original construction.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
TECHNICAL SPECIFICATIONS
E2560B Technical Specifications - Table of Contents 1 of 1
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 011000 - SUMMARY OF WORK
SECTION 011400 - COORDINATION
SECTION 012900 - PAYMENT PROCEDURES
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
SECTION 013110 - PROJECT MEETINGS
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 017310 - FIELD ENGINEERING
SECTION 017700 - CLOSEOUT PROCEDURES
SECTION 017823 - OPERATION AND MAINTENANCE DATA
SECTION 017839 - PROJECT RECORD DOCUMENTS
DIVISION 3 - CONCRETE
SECTION 033000 - CAST-IN-PLACE-CONCRETE
DIVISION 26 – ELECTRICAL
SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS
SECTION 260519 - BUILDING WIRE AND CABLE
SECTION 260526 - GROUNDING AND BONDING
SECTION 260529 - SUPPORTING DEVICES
SECTION 260530 - CONDUIT
SECTION 260533 - BOXES
SECTION 260553 - ELECTRICAL IDENTIFICATION
SECTION 263214 - DIESEL FUELED ENGINE GENERATORS
SECTION 263600 - AUTOMATIC TRANSFER SWITCH
DIVISION 1 - GENERAL REQUIREMENTS
SUNSET LIFT STATION GENERATOR CITY OF EDNA 4/2025
E2560B SUMMARY OF WORK 011000 - 1
SECTION 011000 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of each prime contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. The Project consists of, but is not limited to, the following items of work:
1. Installation of permanent emergency generators and automatic transfer switches at the following locations:
a. Sunset Lift Station in Edna, Texas
B. The Project is located in Edna, Jackson County, Texas.
C. Contract Documents dated September 2025 were prepared for the Project by Lynn Engineering.
E2560B SUMMARY OF WORK 011000 - 2
1.3 CONTRACTS
A. The Project will be constructed under one prime contract. This contract document is the primary general contract for construction.
1.4 WORK SEQUENCE
A. The Work will be conducted in a sequence as required to complete the project in the time frame given in the Bid Proposal.
1.5 PRIME CONTRACTOR’S USE OF PREMISES
A. General: During the construction period the Contractor for this contract shall have full use of public rights-of-way for construction operations.
B. Use of the Site: Limit use of the premises to work in areas indicated. Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated.
1. Driveways and Entrances: Keep driveways and entrances serving private property clear and available to the Property Owner, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
2. Utility Easements: Contractor shall protect private property adjacent to utility easements.
Vegetation existing within utility easements shall be protected from damage where feasible. ENGINEER shall be consulted to determine if damage to existing vegetation is unavoidable.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 011000
E2560B COORDINATION 011400 - 1
SECTION 011400 - COORDINATION
A. Drawings and general provisions of the Contract, including General and Supplementary
1.2 SUMMARY
A. This Section includes administrative and supervisory requirements necessary for coordinating construction operations including, but not necessarily limited to, the following:
1. General project coordination procedures.
2. Conservation.
3. Coordination Drawings.
4. Administrative and supervisory personnel.
5. Cleaning and protection.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 1 Section "Project Meetings" for progress meetings, coordination meetings, and reinstallation conferences.
2. Division 1 Section "Submittal Procedures" for preparing and submitting the Contractor's Construction Schedule.
1.3 COORDINATION
A. Coordinate construction operations included in various Sections of these Specifications to assure efficient and orderly installation of each part of the Work. Coordinate construction operations included under different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in the sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to assure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
B. Where necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.
1. Prepare similar memoranda for the Owner and separate contractors where coordination of their work is required.
E2560B COORDINATION 011400 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and assure orderly progress of the Work. Such administrative activities include, but are not limited to, the
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
D. Conservation: Coordinate construction operations to assure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Salvage materials and equipment involved in performance of, but not actually incorporated in, the Work.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare coordination drawings where careful coordination is needed for installation of products and materials fabricated by separate entities. Prepare coordination drawings where limited space availability necessitates maximum utilization of space for efficient installation of different components.
B. Staff Names: Within 15 days of commencement of construction operations, submit a list of the Contractor's principal staff assignments, including the superintendent and other personnel in attendance at the Project Site. Identify individuals and their duties and responsibilities. List their addresses and telephone numbers.
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
B. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
3.2 CLEANING AND PROTECTION
A. Clean and protect construction in progress and adjoining materials in place, during handling and installation. Apply protective covering where required to assure protection from damage or deterioration at Substantial Completion.
E2560B COORDINATION 011400 - 3
B. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to assure operability without damaging effects.
C. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Special care must be taken to preclude unnecessary exposure from hurricanes. Where applicable, such exposures include, but are not limited to, the following:
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Air contamination or pollution.
7. Water or ice.
8. Solvents.
9. Chemicals.
10. Light.
11. Radiation.
12. Puncture.
13. Abrasion.
14. Heavy traffic.
15. Soiling, staining, and corrosion.
16. Bacteria.
17. Rodent and insect infestation.
18. Combustion.
19. Electrical current.
20. High-speed operation.
21. Improper lubrication.
22. Unusual wear or other misuse.
23. Contact between incompatible materials.
24. Destructive testing.
25. Misalignment.
26. Excessive weathering.
27. Unprotected storage.
28. Improper shipping or handling.
29. Theft.
30. Vandalism.
END OF SECTION 011400
E2560B PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
A. This Section specifies administrative and procedural requirements governing the Contractor's Applications for Payment.
1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Engineer and paid for by the Owner.
B. Payment-Application Times: Unless otherwise modified by agreement, applications for payment for work completed by the last day of the preceding month shall be submitted to the Engineer within five (5) days of the last day of the preceding month. Partial payments for work completed by the last day of the preceding month, based upon engineer’s approval of the Contractor’s estimate, may be approved by the Owner, and payment made as soon as practicable thereafter. Appropriate retainage will be withheld until Final Acceptance of the Work.
C. Payment-Application Forms: Use forms approved by Owner and Engineer for Applications for Payment. Contractor to submit sample format to Engineer for approval prior to first application.
D. Application Preparation: Complete every entry on the form. Applications shall be executed by a person authorized to sign legal documents on behalf of the Contractor.
The Engineer will return incomplete applications without action.
1. Entries shall match data on the Bid Proposal.
2. Include amounts of approved Change Orders issued prior to the last day of the construction period covered by the application.
E. Transmittal: Submit signed digital copies of each Application for Payment to the Project Engineer by a method ensuring receipt within 24 hours. One copy shall be complete, including waivers of lien and similar attachments, when required.
F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment, include the following:
1. Schedule of Values.
2. Contractor's Construction Schedule (preliminary if not final).
E2560B PAYMENT PROCEDURES 012900 - 2
G. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment.
1. Administrative actions and submittals that shall precede or coincide with this application include the following as appropriate:
a. Warranties (guarantees) and maintenance agreements.
b. Test/adjust/balance records.
c. Maintenance instructions.
d. Application for reduction of retainage and consent of surety.
e. List of incomplete Work, recognized as exceptions to Engineer’s Certificate of Substantial Completion.
H. Final Payment Application: Administrative actions and submittals that must precede or coincide with submittal of the final Application for Payment include the following:
1. Completion of Project closeout requirements.
2. Completion of items specified for completion after Substantial Completion.
3. Submit Affidavit of All Bills Paid, or similar document.
4. Transmittal of required Project construction records to the Owner.
5. Removal of temporary facilities and services.
6. Removal of surplus materials, rubbish, and similar elements.
7. Final clean-up.
PART 2 - EXECUTION (Not Applicable)
END OF SECTION 012900
E2560B PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
A. This Section includes administrative and procedural requirements for schedules and reports required for proper performance of the Work, including:
1. Daily construction reports.
2. Special reports.
1. Division 1 Section "Project Meetings" specifies requirements for submittal and distribution of meeting and conference minutes.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of schedules and reports with performance of other construction activities.
1.4 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at the site. Review the daily construction report with the Engineer or his representative within 24 hours of the report date. Revise or correct the report as may be required following review. Report must be signed by Engineer or his representative. Submit duplicate copies to the Engineer at weekly intervals.
1. List of subcontractors at the site.
2. List of separate contractors at the site.
3. Approximate count of personnel at the site.
4. High and low temperatures, general weather conditions.
5. Accidents.
6. Meetings and significant decisions.
7. Unusual events (refer to special reports).
8. Stoppages, delays, shortages, and losses.
9. Meter readings and similar recordings.
10. Emergency procedures.
11. Orders and requests of governing authorities.
12. Change Orders received, implemented.
13. Services connected, disconnected.
E2560B PROJECT MANAGEMENT AND COORDINATION 013100 - 2
14. Equipment or system tests and startups.
15. Partial Completions, occupancies.
16. Substantial Completions authorized.
B. Material Location Reports: When requested by engineer at a minimum when requesting payment for materials on site, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered less materials installed. Include with the list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from the site. Submit materials list with contractor’s application for payment.
C. Field Correction Reports: When the need to take corrective action that requires a departure from the Contract Documents arises, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Submit a copy to the Engineer immediately.
1.5 SPECIAL REPORTS
A. Reporting Unusual Events: When an event of an unusual and significant nature occurs at the site, prepare and submit a special report. List the chain of events, persons participating, response by the Contractor's personnel, an evaluation of the results or effects and similar pertinent information. Advise the Engineer in advance when such events are known or predictable.
END OF SECTION 013100
E2560B PROJECT MEETINGS 013110 - 1
SECTION 013110 - PROJECT MEETINGS
A. This Section specifies administrative and procedural requirements for project meetings, including, but not limited to, the following:
1. Preconstruction conferences.
2. Progress meetings.
3. Coordination meetings.
1. Division 1 Section "Coordination" for procedures for coordinating project meetings with other construction activities.
2. Division 1 Section "Submittals" for submitting the Contractor's Construction Schedule.
1.3 PRECONSTRUCTION CONFERENCE
A. A preconstruction conference will be scheduled by the Engineer before construction starts at a time convenient to the Owner and the Contractor. The conference will be held at the Project Site or another convenient location. The meeting will be held to review responsibilities and personnel assignments.
B. Attendees: Authorized representatives of the Owner, Engineer, and their consultants; the
Contractor and its superintendent; major subcontractors; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
C. Agenda: Items of significance that could affect progress will be discussed, including the
1. Tentative construction schedule.
2. Critical work sequencing.
3. Designation of responsible personnel.
4. Procedures for processing field decisions and Change Orders.
5. Procedures for processing Applications for Payment.
6. Distribution of Contract Documents.
7. Submittal of Shop Drawings, Product Data, and Samples.
8. Preparation of record documents.
E2560B PROJECT MEETINGS 013110 - 2
9. Use of the premises.
10. Parking availability.
11. Office, work, and storage areas.
12. Equipment deliveries and priorities.
13. Safety procedures.
14. First aid.
15. Security.
16. Housekeeping.
17. Working hours.
1.4 PROGRESS MEETINGS
A. The Engineer will conduct progress meetings at the Project Site as necessary. Engineer will notify the Owner and the Contractor of scheduled meeting dates. Dates of meetings will be coordinated with preparation of the payment request.
B. Attendees: In addition to representatives of the Owner, Engineer and Contractor, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
C. Agenda: Review items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
1. Contractor's Construction Schedule: Review progress since the last meeting.
Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
2. Review the present and future needs of each entity present, including the
a. Interface requirements.
b. Time.
c. Sequences.
d. Status of submittals.
e. Deliveries.
f. Site utilization.
g. Housekeeping.
h. Quality and work standards.
i. Change Orders.
j. Documentation of information for payment requests.
E2560B PROJECT MEETINGS 013110 - 3
1.5 COORDINATION MEETINGS
A. Project coordination meetings will be conducted by the Engineer at regular intervals convenient for all parties involved. Project coordination meetings are in addition to specific meetings held for other purposes, such as regular progress meetings and special pre-installation meetings.
B. Representation at each meeting by every party currently involved in coordination or planning for the construction activities involved will be requested.
C. The Engineer will record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
END OF SECTION 013110
E2560B SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
A. This Section includes administrative and procedural requirements for submittals required for performance of the Work, including the following:
1. Submittal schedule.
2. Shop Drawings.
3. Product Data.
4. Quality assurance submittals.
B. Administrative Submittals: Refer to other Division 1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to, the following:
1. Permits.
2. Applications for Payment.
3. List of subcontractors.
C. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 1 Section "Applications for Payment" specifies requirements for submittal of the Schedule of Values.
2. Division 1 Section "Coordination" specifies requirements governing preparation and submittal of required Coordination Drawings.
3. Division 1 Section "Project Meetings" specifies requirements for submittal and distribution of meeting and conference minutes.
4. Division 1 Section "Contract Closeout" specifies requirements for submittal of Project Record Documents and warranties at project closeout.
D. Digital copies are portable document Files (PDF) that can be transmitted electronically.
1.3 DEFINITIONS
A. Coordination Drawings show the relationship and integration of different construction elements that require careful coordination during fabrication or installation to fit in the space provided or to function as intended.
E2560B SUBMITTAL PROCEDURES 013300 - 2
1. Preparation of Coordination Drawings is specified in Division 1 Section "Coordination" and may include components previously shown in detail on Shop Drawings or Product Data.
B. Field samples are full-size physical examples erected on-site to illustrate finishes, coatings, or finish materials. Field samples are used to establish the standard by which the Work will be judged.
C. Mockups are full-size assemblies for review of construction, coordination, testing, or operation; they are not Samples.
1.4 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay. Allow sufficient time for submittal review, including time for resubmittals.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related elements of the
Work so processing will not be delayed by the need to review submittals concurrently for coordination.
a. The Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until all related submittals are received.
B. Submittal Preparation: Include on transmittal form, as appropriate, the name of the entity that prepared each submittal.
1. Provide a space on the form to record the Contractor's review and approval markings and the action taken.
2. Include the following information on the transmittal form for processing and recording action taken.
a. Project name.
b. Date.
c. Name and address of the Engineer.
d. Name and address of the Contractor.
e. Name and address of the subcontractor.
f. Name and address of the supplier.
g. Name of the manufacturer.
h. Number and title of appropriate Specification Section.
i. Drawing number and detail references, as appropriate.
E2560B SUBMITTAL PROCEDURES 013300 - 3
C. Submittal Transmittal: Package each submittal appropriately for transmittal and handling.
Transmit each submittal from the Contractor to the Engineer using a transmittal form.
The Engineer will not accept submittals received from sources other than the Contractor.
1. On the transmittal form, record relevant information and requests for data. On the form, or a separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor's certification that information complies with Contract Document requirements.
2. Transmittal Form: Use AIA Document G810 or other form as may be approved by the Project Engineer.
1.5 SUBMITTAL SCHEDULE
A. Contractor shall prepare a list of all submittals for materials and equipment to be incorporated into the project. The list must include an approximate date that the submittal will be sent to the Project Engineer for review. Submit the Submittal Schedule within 10 days following the Pre-Construction Conference.
1.6 SHOP DRAWINGS
A. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings. Include the following information:
1. Dimensions.
2. Identification of products and materials included by sheet and detail number.
3. Compliance with specified standards.
4. Notation of coordination requirements.
5. Notation of dimensions established by field measurement.
6. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 22 by 34 inches.
7. Initial Submittal: a digital copy for the Engineer’s review. The Engineer will return the digital copy revised with the appropriate notations.
8. Final Submittal: If necessary (ie. Shop drawing noted revise and resubmit), submit PDF of revised shop drawing for review and approval.
9. Do not use Shop Drawings without an appropriate final stamp indicating action taken.
1.7 PRODUCT DATA
A. Collect Product Data into a single submittal for each element of construction or system.
Product Data includes printed information, such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams, and performance curves.
1. Mark each copy to show applicable choices and options. Where printed Product
Data includes information on several products that are not required, mark copies to indicate the applicable information. Include the following information:
E2560B SUBMITTAL PROCEDURES 013300 - 4
a. Manufacturer's printed recommendations.
b. Compliance with trade association standards.
c. Compliance with recognized testing agency standards.
d. Application of testing agency labels and seals.
e. Notation of dimensions verified by field measurement.
f. Notation of coordination requirements.
2. Do not submit Product Data until compliance with requirements of the Contract
Documents has been confirmed by the contractor.
3. Submittals: Submit a digital copy of each required submittal. The Engineer will mark with action to be taken and/or corrections or modifications required prior to returning to Contractor.
a. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
4. Distribution: Furnish copies of final submittal to installers, subcontractors, suppliers, manufacturers, fabricators, and others required for performance of construction activities.
Show distribution on transmittal forms.
a. Do not proceed with installation until a copy of Product Data is in the Installer's possession.
b. Do not permit use of unmarked copies of Product Data in connection with construction.
1.8 QUALITY ASSURANCE SUBMITTALS
A. Submit quality-control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other Sections of the Specifications.
B. Certifications: Where other Sections of the Specifications require certification that a product, material, or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with specified requirements.
1. Signature: Certification shall be signed by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.
C. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies are specified in Division 1 Section "Quality Control."
1.9 PROJECT MANAGER’S/ENGINEER’S ACTION
A. Except for submittals for the record or information, where action and return is required, the Engineer will review each submittal, mark to indicate action taken, and return promptly.
E2560B SUBMITTAL PROCEDURES 013300 - 5
1. Compliance with specified characteristics is the Contractor's responsibility.
B. Action Stamp: The Engineer will stamp each submittal with a uniform, action stamp. The Engineer will mark the stamp appropriately to indicate the action taken, as follows:
1. Approved as Submitted: When the Engineer marks a submittal "Approved," the
Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents. Final payment depends on that compliance.
2. Approved as Noted: When the Engineer marks a submittal "Approved as Noted," the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents. Final payment depends on that compliance.
3. Revise and Resubmit: When the Engineer marks a submittal "Not Approved, Revise and Resubmit," do not proceed with Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal according to the notations; resubmit without delay. Repeat if necessary to obtain different action mark.
a. Do not use, or allow others to use, submittals marked "Not Approved, Revise and Resubmit" at the Project Site or elsewhere where Work is in progress.
4. Other Action: Where a submittal is for information or record purposes or special processing or other activity, the Engineer will return the submittal marked "Action Not Required."
END OF SECTION 013300
E2560B FIELD ENGINEERING 017310 - 1
SECTION 017310 - FIELD ENGINEERING
A. General: This Section specifies administrative and procedural requirements for field-engineering services including, but not limited to, the following:
1. Civil-engineering services.
1. Division 1 Section "Coordination" for procedures for coordinating field engineering with other construction activities.
2. Division 1 Section "Submittals" for submitting Project record surveys.
3. Division 1 Section "Contract Closeout" for submitting final Project Record
Documents and recording of Owner-accepted deviations from indicated lines and levels.
1.3 SUBMITTALS
A. Project Record Documents: Submit a record of Work performed and record survey data as required under provisions of "Submittals" and "Project Closeout" Sections.
1.4 QUALITY ASSURANCE
A. Engage a qualified surveyor or surveying technician to perform layout of the various construction activities and to record as built locations of finished installations.
3.1 EXAMINATION
A. Identification: The Owner will identify existing control points.
B. Verify layout information shown on the Drawings, in relation to the control points and existing benchmarks, before proceeding to lay out the Work. Locate and protect existing benchmarks and control points. Preserve permanent reference points during construction.
1. Do not change or relocate benchmarks or control points without prior written approval. Promptly report lost or destroyed reference points or requirements to relocate reference points because of necessary changes in grades or locations.
E2560B FIELD ENGINEERING 017310 - 2
2. Promptly replace lost or destroyed Project control points. Base replacements on the original survey control points.
C. Establish and maintain a minimum of 2 permanent benchmarks on the site, referenced to data established by survey control points.
1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.
D. Existing Utilities and Equipment: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning site work, investigate and verify the existence and location of underground utilities and other
1. Prior to construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, gas, water-service piping, and underground communications and electric cables.
3.2 PERFORMANCE
A. Work from lines and levels established by the control survey. Establish benchmarks and markers to set lines and levels as needed to locate each element of the Project. Calculate and measure required dimensions within indicated or recognized tolerances. Do not scale Drawings to determine dimensions.
1. Advise entities engaged in construction activities of marked lines and levels provided for their use.
2. As construction proceeds, check every major element for line, level, and plumb.
B. Surveyor's Log: Maintain a log of control and other survey work. Make this log available for reference.
1. Record deviations from required lines and levels, and advise the Engineer when deviations that exceed indicated or recognized tolerances are detected. On Project Record Drawings, record deviations that are accepted and not corrected.
2. On completion of major site improvements, and other work requiring field-engineering services, prepare a survey showing dimensions, locations, angles, and elevations of construction and site work.
C. Site Improvements: Locate and lay out site improvements, including pavements, stakes for grading, utility slopes, and invert elevations.
D. Existing Utilities: Furnish information necessary to adjust, move, or relocate existing structures, utility poles, lines, services, or other appurtenances located in or affected by construction. Coordinate with local authorities having jurisdiction.
END OF SECTION 017310
E2560B CLOSEOUT PROCEDURES 017700 - 1
SECTION 017700 - CLOSEOUT PROCEDURES
A. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:
1. Inspection procedures.
2. Project record document submittal.
3. Operation and maintenance manual submittal.
4. Submittal of warranties.
5. Final cleaning.
B. Closeout requirements for specific construction activities are included in the appropriate Sections in Divisions 2 through 31.
1.3 SUBSTANTIAL COMPLETION
A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request.
1. In the Application for Payment that coincides with, or first follows, the date
Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete.
a. Include supporting documentation for completion as indicated in these
Contract Documents and a statement showing an accounting of changes to the Contract Sum.
b. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete.
2. Advise the Owner of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents.
4. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
5. Submit record drawings, maintenance manuals, and similar final record information.
6. Deliver tools, spare parts, extra stock, and similar items.
E2560B CLOSEOUT PROCEDURES 017700 - 2
7. Make final changeover of permanent locks and transmit keys to the Owner.
Advise the Owner's personnel of changeover in security provisions.
8. Complete startup testing of systems and instruction of the Owner's operation and maintenance personnel. Discontinue and remove temporary facilities from the site, construction tools, and similar elements.
9. Complete final cleanup requirements, including touch up painting.
10. Touch up and otherwise repair and restore marred, exposed finishes.
B. Inspection Procedures: On receipt of a request for inspection, the Engineer will either proceed with inspection or advise the Contractor of unfilled requirements. The Engineer will prepare the Certificate of Substantial Completion following inspection or advise the Contractor of construction that must be completed or corrected before the certificate will be issued.
1. The Engineer will repeat inspection when requested and assured that the Work is substantially complete.
2. Results of the completed inspection will form the basis of requirements for final acceptance.
1.4 FINAL ACCEPTANCE
A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request.
1. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required.
2. Submit an updated final statement, accounting for final additional changes to the Contract Sum.
3. Submit a certified copy of the Engineer’s final inspection list of items to be completed or corrected, endorsed and dated by the Engineer. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance and shall be endorsed and dated by the Engineer.
4. Submit consent of surety to final payment.
5. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
B. Reinspection Procedure: The Engineer will reinspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to the Engineer.
1. Upon completion of reinspection, the Engineer will prepare a certificate of final acceptance. If the Work is incomplete, the Engineer will advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance.
2. If necessary, reinspection will be repeated.
E2560B CLOSEOUT PROCEDURES 017700 - 3
1.5 RECORD DOCUMENT SUBMITTALS
A. General: Do not use record documents for construction purposes. Protect record documents from deterioration and loss in a secure, fire-resistant location. Provide access to record documents for the Engineer’s reference during normal working hours.
B. Record Drawings: Maintain a clean, undamaged set of blue or black line white-prints of
Contract Drawings and Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from the Work as originally shown. Mark which drawing is most capable of showing conditions fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and record at a later date.
1. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in separate categories of the Work.
2. Mark new information that is important to the Owner but was not shown on
Contract Drawings or Shop Drawings.
3. Note related change-order numbers where applicable.
4. Organize record drawing sheets into manageable sets. Bind sets with durable-paper cover sheets; print suitable titles, dates, and other identification on the cover of each set.
C. Record Specifications: Maintain one complete copy of the Project Manual, including addenda. Include with the Project Manual one copy of other written construction documents, such as Change Orders and modifications issued in printed form during
1. Mark these documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications.
2. Give particular attention to substitutions and selection of options and information on concealed construction that cannot otherwise be readily discerned later by direct observation.
3. Note related record drawing information and Product Data.
4. Upon completion of the Work, submit record Specifications to the Engineer for the Owner's records.
D. Record Product Data: Maintain one copy of each Product Data submittal. Note related Change Orders and markup of record drawings and Specifications.
1. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site and from the manufacturer's installation instructions and recommendations.
2. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily discerned later by direct observation.
3. Upon completion of markup, submit complete set of record Product Data to the Engineer for the Owner's records.
E2560B CLOSEOUT PROCEDURES 017700 - 4
E. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of the Work. Immediately prior to the date or dates of Substantial Completion, complete miscellaneous records and place in good order. Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit to the Engineer for the Owner's records.
F. Maintenance Manuals: Organize operation and maintenance data into suitable sets of manageable size. Bind properly indexed data in individual, heavy-duty, 2-inch, 3-ring, vinyl-covered binders, with pocket folders for folded sheet information. Mark appropriate identification on front and spine of each binder. Include the following types of information:
1. Emergency instructions.
2. Spare parts list.
3. Copies of warranties.
4. Wiring diagrams.
5. Recommended "turn-around" cycles.
6. Inspection procedures.
7. Shop Drawings and Product Data.
8. Fixture lamping schedule.
PART 2 - PRODUCTS (Not Applicable)
3.1 CLOSEOUT PROCEDURES
A. Operation and Maintenance Instructions: Arrange for each Installer of equipment that requires regular maintenance to meet with the Owner's personnel to provide instruction in proper operation and maintenance. Provide instruction by manufacturer's representatives if installers are not experienced in operation and maintenance procedures. Include a detailed review of the following items:
1. Maintenance manuals.
2. Record documents.
3. Spare parts and materials.
4. Tools.
5. Lubricants
6. Fuels.
7. Identification systems.
8. Control sequences.
9. Hazards.
10. Cleaning.
11. Warranties and bonds.
12. Maintenance agreements and similar continuing commitments.
E2560B CLOSEOUT PROCEDURES 017700 - 5
B. As part of instruction for operating equipment, demonstrate the following procedures:
1. Startup.
2. Shutdown.
3. Emergency operations.
4. Noise and vibration adjustments.
5. Safety procedures.
6. Economy and efficiency adjustments.
7. Effective energy utilization.
3.2 FINAL CLEANING
A. General: The General Conditions require general cleaning during construction. Regular site cleaning is included in Division 1 Section "Construction Facilities and Temporary Controls."
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to the condition expected in a normal, commercial building cleaning and maintenance program. Comply with manufacturer's instructions.
1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion.
a. Remove labels that are not permanent labels.
b. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other substances that are noticeable vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials.
c. Clean exposed exterior and interior hard-surfaced finishes to a dust-free condition, free of stains, films, and similar foreign substances. Restore reflective surfaces to their original condition. Leave concrete floors broom clean. Vacuum carpeted surfaces.
d. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances. Clean plumbing fixtures to a sanitary condition. Clean light fixtures and lamps.
e. Clean the site, including landscape development areas, of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits. Rake grounds that are neither paved nor planted to a smooth, even-textured surface.
C. Removal of Protection: Remove temporary protection and facilities installed for protection of the Work during construction.
D. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the site and dispose of lawfully.
E2560B CLOSEOUT PROCEDURES 017700 - 6
1. Where extra materials of value remain after completion of associated Work, they become the Owner's property. Dispose of these materials as directed by the Owner.
END OF SECTION 017700
E2560B OPERATION AND MAINTENANCE DATA 017823 - 1
SECTION 017823 - OPERATION AND MAINTENANCE DATA
Conditions and other Division 01 Specification Sections, apply to this Section.
A. This Section includes administrative and procedural requirements for preparing and submitting operations and maintenance manuals for all of the equipment and materials incorporated into the completed project.
B. Related Sections include the following:
1. Division 1 Section “Submittal Procedures” for submitting copies of submittals for operation and maintenance manuals.
2. Division 1 Section “Closeout Procedures” for submitting operation and maintenance manuals.
1.3 SUBMITTALS
A. Initial Submittal: Submit 2 draft copies of each manual at least 15 days before requesting inspection for Substantial Completion. Include a complete operation and maintenance directory. Engineer will return one copy of draft and mark whether general scope and content of manual is acceptable.
1. Correct or modify draft manual to comply with Engineer’s comments.
B. Final Submittal: Submit five (5) copies of corrected draft manual in final form at least 15 days before final inspection.
PART 2 - PRODUCTS
2.1 MANUALS, GENERAL
A. Organization: Organize the manual as follows:
1. Title page
2. Table of contents
3. Manual contents
B. Title Page: Include the following information in the Title Page:
1. Name and address of Project
2. Name and address of Owner
E2560B OPERATION AND MAINTENANCE DATA 017823 - 2
3. Name and address of Engineer
4. Name and address of Contractor
5. Date of Submittal
C. Table of Contents: Provide the following sections in the Manual.
1. Generator
2. Automatic Transfer Switch
3. Misc. electrical components
D. Manual Assembly: Assemble the manual as follows:
1. Binders: Heavy-duty, 3 ring, vinyl-covered, loose-leaf binders, in thickness necessary to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
a. If two or more binders are necessary to accommodate complete operation and maintenance data of a system, organize data in each binder into groupings by major plant system and related components.
Cross-reference other binders if necessary to provide essential information for proper operation or maintenance of equipment or system.
b. Identify each binder on front and spine, with printed title “OPERATION AND MAINTENANCE MANUAL,” Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.
2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.
3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software diskette for computerized electronic equipment.
4. Supplementary Text: Prepared on 8-1/2-by-11-inch white bond paper.
5. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.
a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.
b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert type written pages indicating drawing titles, descriptions of contents and drawing locations.
2.2 EMERGENCY OPERATION
A. Content: When appropriate, include for each items of equipment, procedures for emergency operation and attach the following:
E2560B OPERATION AND MAINTENANCE DATA 017823 - 3
B. Type of emergency
1. Emergency instructions
2. Emergency procedures
C. Type of Emergency: For each type of emergency indicated below, include instructions and procedures, as applicable, for each system, piece of equipment and component:
1. Fire
2. Flood
3. Water leak
4. Power failure
5. Water outage
6. Equipment failure
7. Chemical release or spill
D. Emergency Instructions: Describe and explain warnings, trouble indications, error messages, and similar codes and signals. Include responsibilities of Owner’s operating personnel for notification of Installer, supplier and manufacturer to maintain warranties.
E. Emergency Procedures: Include the following, as applicable:
1. Instructions on stopping
2. Shutdown instructions for each type of emergency
3. Operating instructions for conditions outside normal operating limits.
4. Required sequences for electric or electronic systems
5. Special operating instructions and procedures.
2.3 STANDARD OPERATION
A. Content: For each plant component or item of equipment provide the following:
1. System and equipment descriptions
2. Operating standards
3. Operating procedures
4. Wiring diagrams
5. Control diagrams
6. Precautions against improper use
7. License requirements including inspection and renewal date
B. Descriptions: Include the following:
1. Product name and model number
2. Manufacturer’s name
3. Equipment identification with serial number of each component
4. Equipment function
5. Operating characteristics
6. Limiting conditions
E2560B OPERATION AND MAINTENANCE DATA 017823 - 4
7. Performance curves
8. Engineering data and tests
9. Complete nomenclature and number of replacement parts
C. Operating Procedures: Include the following, as applicable:
1. Startup procedures
2. Equipment or system break-in procedures
3. Routine and normal operating instructions
4. Regulation and control procedures
5. Instructions on stopping
6. Normal shutdown instructions
7. Seasonal and weekend operating instructions
8. Required sequences for electric or electronic systems
9. Special operating instructions and procedures
D. Systems and Equipment Controls: Describe the sequence of operation and diagram controls as installed.
2.4 MAINTENANCE REQUIREMENTS
A. Content: Organize manual into a separate section for each product, material and finish.
Include source information, product…
This is the start of the file's text. The full file is on GovTribe.