INTRODUCTION
1. The Contractor shall provide and deliver the list of Ground Support
Equipment (GSE) and associated services1 detailed in this document to support flying activities in Mountain Home Air Force Base (MHAFB). All goods and services shall be provisioned in accordance with the requirements as stated within this document and all applicable federal, state, local laws and applicable regulations.
2. The Contractor shall offer the list of GSE and associated services required by the Authority on a rental basis.
REQUIREMENTS
3. Requirement Window.
a. Delivery: not later than 18 Aug 2021 0900H
b. Collection: not earlier than 30 Sep 2021 0900H
4. Delivery Location. The GSE and associated services shall be delivered to drop-off point within Mountain Home Air Force Base (MHAFB) (refer to Figure
2). The GSE shall be collected from the same location by the Contractor.
5. The breakdown of requirements is tabulated in Table 1 below.
Table 1: List of Ground Logistics Support Required
S/N Description Qty
Required Other Operational Requirements
3.1kVA Diesel
Generators
A/C Frequency: 50 Hz
A/C Output Voltage: 220 V
Rated A/C Output: 2.8 kVA
Maximum A/C output: 3.1 kVA
1 Includes the delivery and collection of the equipment, and the 1-to-1 exchange of malfunctioned equipment.
S/N Description Qty
Required Other Operational Requirements
Generator shall be equipped with US domestic power outlets
Generator is required to be portable (i.e. can be towed by a tractor or shifted by a forklift)
15kVA Diesel
Generators
Power Rating: 15kVA
Rated Voltage: 230VAC
Rated Current: 32A
No. of Phases: 1 and 3
No. of Outlets: Minimum one 1-phase outlet and one 3-phase outlet
16kVA Diesel
Generators
Power Rating: 16kVA
Rated Voltage: 230 / 400VAC
Rated Current: 23.8A
No. of Phases: 3
200 kW Diesel
Generators
Power Rating: 200kW
Rated Voltage: 400VAC
No. of Phases: 3 (50Hz)
Requires US 110V domestic electrical outlets
Electrical Power
Cable Extension
Output Rating: 230VAC, 1-Phase, 16A
Length: at least 250ft
Recommended: 3/C 10 AWG (5.26mm) Cable
(refer to Figure 1)
The contractor is required to splice the power cable extension to the generator, and the adapter connector provided by the Authority.
The Contractor shall also terminate the splice at the end of the requirement window.
Electrical Power
Cable Extension
Output Rating: 230VAC, 3-Phase, 32A
Length: at least 250ft
Recommended: 6/4 Type G Cable (refer to
Figure 1)
The contractor is required to splice the power cable extension to the generator, and the adapter connector provided by the Authority.
S/N Description Qty
Required Other Operational Requirements
The Contractor shall also terminate the splice at the end of the requirement window.
Cable Protector
Ramps
As
Required
Length of cable to be protected: approximately
500ft
Diameter of cable to be protected: 4 x ¼ in
Fibre Optic cable
The Contractor shall provide the manpower to lay the cable protector ramps at the predetermined location (refer to Figure 3) under supervision of the Authority’s personnel. The Contractor shall also provide the manpower to collect the cable protector ramps at the end of the requirement window.
Sample:
6. Contractor shall connect all necessary cord ends. The required specialized cord ends will be supplied.
7. Contractor shall connect all required cables to the generators.
8. Contractor shall be responsible for all required maintenance as well as repairs as required.
9. Contractor shall place and connect cable protectors where required.
10. Diesel fuel will be supplied via the requiring agency, Contractor need not provide fuel for generators.
Figure 1: Electrical Power Cable Extension required for Rental Generators (Items 5 & 6)
Require Splicing
Require Splicing
Require Splicing
Require Splicing
Figure 2: Drop-Off & Collection Point for GSE
The Contractor shall provide the manpower to lay the cable protector ramps along the gravel path depicted by the yellow box. The Contractor shall also provide the manpower to collect the cable protector ramps at the end of the requirement window.