U.S. Fish & Wildlife Service Kirtland Landing Pre-Cast Boat Ramp CT Route 145 - Westbrook, CT
SPECIFICATIONS
This procurement is being solicited as a firm-fixed price contract. Evaluation Factors:
· Lowest Price, Technically Acceptable
· Schedule availability, see deliverables schedule within specifications
Specifications:
Stewart B McKinney National Wildlife Refuge in Partnership with the Town of Westbrook Connecticut are looking to purchase a 13 foot wide by 42 foot pre-cast public access boat ramp. The ramp will support primarily non-motorized watercraft and small powered watercraft.
The contractor will provide the design and fabrication of a pre-cast ramp that will be shipped unassembled to Westbrook, CT; to be off-loaded and assembled on-site by others.
Shop drawings will be provided by the contractor indicating structure layout, steel reinforcing sizing and placement, geometry, design assumptions, material specifications, assembly notes and requirements for backfill material and placement signed and stamped by a State Licensed Professional Engineer. The design shall be submitted to USFWS Engineers for approval prior to manufacturing.
Variations from provided documentation will have to be verified with the design engineer prior to award. Please submit all questions to the contracting officer.
The boat ramp must meet the following specifications:
· Overall Width: 13’0”
· Inside Curb Width: 12’0”
· Overall Length: 42’0”
· Pre-cast Panel Length: ~6’0”
· Thickness: 10”
· Curb Height: 6”
· Traction Pattern: Grooved – TBD by manufacture
· Panel Connection Type: Corrosion resistant connectors – TBD by manufacture
· Loading: HS20
· Type of Material: Precast and reinforced concrete, 5,000 PSI (certified)
· Additional Materials: Include all gaskets, seals, bolts, and hardware directly related to the install
· Technical Assistance: Include 1 day of field technician on-site to aid in setting of precast items
Bid Schedule:
Bid must include the following:
1. Lead Time for Design Drawings after receipt of award
2. Lead Time for Fabrication and Delivery once approvals are received
3. Specifications and Materials
Deliverables Schedule and Location:
Design to be provided for review no more than 2 weeks after contract award. Design approval from USFWS Engineers will be granted or rejected in no more than 7 business days upon receipt of design.
Delivery of culvert shall be on or before 4/1/2022 to:
Kirtland Landing Near: CT RT 145 – Westbrook, CT Geo Location: 41.28810, -72.49217
USFWS – KIRTLAND LANDING BOAT RAMP
U.S. Fish & Wildlife Service
CT Route 145 - Westbrook, CT
Deadlines:
· Questions must be emailed to technical contact at darren_stover@fws.gov no later than 12:00pm, EST, 12/31/2021
· Quotes must be emailed tostephanie_long@fws.gov no later than 12:00pm, EST, 01/06/2022
CT Route 145 - Westbrook, CT
Attachments: Site Plans
CT Route 145 - Westbrook, CT
QUOTE SCHEDULE
BOAT RAMP DESIGN AND FABRICATION
BEFORE SUBMITTING A QUOTE, quoters shall carefully review the Contract Documents including Government Standard Forms, Contract Clauses and General Provisions, Additional General Provisions, Labor Standards, Wage Rates, Technical Specifications and Drawings, and Safety Requirements.
BASE BID ITEM:
1. Boat ramp design, fabrications and delivery as specified in solicitation above. as specified herein, the sum of:
DESIGN LEAD TIME:
FABRICATION LEAD TIME:
ON-SITE DELIVERY DATE:
LUMP SUM QUOTE:
COMPANY NAME
QUOTE PREPARED BY
TITLE
SIGNATURE
ADDRESS
DATE
TELEPHONE
FAX
image1.png image2.png image3.jpeg
File details come from the government source that posted it. Updated .