Specs - Athletic Vestibule.docx
DOCX document 16 KB Posted
- Attached to
- Replacement HS Gym Entry Athletic Vestibule
- Solicitation number
- RFP - HOME - 240000001022
- Issued by
- Calhoun County, Holt CDP, Michigan
About this file
This document contains the technical specifications for the replacement of the athletic vestibule at Homer High School in Homer, Michigan. The project is being managed by Dale Cornstubble, the Project Manager/Coordinator and Owner's Representative for the Homer Community School District. The work includes providing all labor, materials, tools, equipment, and supervision necessary to complete the vestibule replacement. A pre-bid meeting is scheduled for January 31, 2024, and bids must be submitted by February 9, 2024, at 9:00 am EST to the Homer Community School District Superintendent's office. The project specifications detail the temporary facilities and controls required, as well as the safety responsibilities of the contractor. The document also includes a general list of the products required for the project, such as doors, frames, panics, hinges, pull handles, closers, and sealants.
The related state and local contract opportunity is for the Replacement HS Gym Entry Athletic Vestibule project located in Calhoun County and the Holt CDP in Michigan. No additional pricing terms, set asides, incumbents, funding requirements, or other salient information is provided in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP - Athletic Vestibule.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replacement HS Gym Entry Athletic Vestibule – 2024 Technical Specifications
Homer Community Schools is located at 403 S. Hillsdale Street in Homer, MI. Dale Cornstubble, Project Manager/Coordinator, is the Owner’s Representative and may be contacted regarding any questions or for a pre-bid job site inspection, phone 517-568-4463.
EXTENT OF WORK
1. Provide all labor, material, tools, equipment, and supervision necessary to complete the replacement of the vestibule.
2. The contractor shall be fully knowledgeable of all requirements of the contract documents and shall make themselves aware of all job site conditions that will affect their work.
3. The contractor shall confirm all given information and advise the building owner, prior to bid, of any conflicts that will affect their cost proposal.
PRE-CONSTRUCTION CONFERENCE
1. A pre-bid meeting will be held at the job site on Wednesday, January 31, 2024 from 3:00 to 4:00 pm. Contact the owner’s representative, Dale Cornstubble, Director of Operations, at 517-568-4463 if there are any questions.
2. Prior to bid submittal, the contractor should schedule a job site inspection to observe actual conditions and verify all dimensions of the vestibule. The inspection may occur on the day of the pre-bid meeting or prior to such meeting. Should access to the vestibule be necessary before or after the pre-bid meeting, the contractor must contact the owner’s representative, Dale Cornstubble, Director of Operations, at 517-568-4463 if there are any questions.
3. Bids must be forwarded to the following address no later than Friday, February 9, 2024 at 9:00 am, EST.
Michael Leskowich, Superintendent Homer Community School District 403 South Hillsdale Street Homer, MI 49245 “2024 Athletic Vestibule Replacement Bid”
TEMPORARY FACILITIES AND CONTROLS
1. Temporary Utilities:
a. Water, power for construction purposes and lighting are not available at the site and will not be made available to the roofing contractor.
b. Provide all hoses, valves and connections for water from source designated by the owner when made available.
c. When available, electrical power should be extended as required from the source. Provide all trailers, connections and fused disconnects.
2. Temporary Sanitary Facilities
a. Sanitary facilities will not be available at the job site. The roofing contractor shall be responsible for the provision and maintenance of portable toilets or their equal.
3. Building Site:
a. The roofing contractor shall use reasonable care and responsibility to protect the building and site against damages. The contractor shall be responsible for the correction of any damage incurred as a result of the performance of the contract.
b. The roofing contractor shall remove all construction debris from the job site in a timely and legally acceptable manner so as to not detract from the aesthetics or the functions of the building.
4. Security:
a. Obey the owner’s requirements for personnel identification, inspection and other security measures.
b. All employees on site will be required to have a free background check through Homer Community School District. A form will be provided to the contractor once the bid is awarded.
SAFETY
1. The contractor shall be responsible for all means and methods as they relate to safety and shall comply with all applicable local, state and federal requirements that are safety related. Safety shall be the responsibility of the contractor. All related personnel shall be instructed daily to be mindful of the full time requirement to maintain a safe environment for the facility’s occupants including staff, visitors, customers and the occurrence of the general public on or near the site.
GENERAL PRODUCTS LIST
1. 4 pair – Cross Aluminum WS-500 Doors and Frames – dark bronze anodized
2. (1) Von Duprin Electric Panic
3. (3) Von Duprin Rim Panics
4. (4) Continuous Hinges
5. (4) Ives Pull Handles
6. (1) EPT 10 – Power Transfer
7. (4) LCN 4040XP Closers
8. (2) Von Duprin Keyed Removable Mullions
9. (2) Exterior Cylinders
10. Sweeps/Thresholds
11. Joint Sealants – Dow Corning CWS
File details come from the government source that posted it. Updated .