This is a Scope of Work and Specifications document for custodial services at the Iowa Department of Transportation's Ames Complex Outer Buildings located at 800 Lincoln Way, Ames, Iowa. The contractor must provide all labor, equipment, and supplies necessary to maintain six outbuildings: the Auction Building, District 1 Office Building, Repair Shop Annex, Sign Shop, Trades Building, and Warehouse/Print Building. Cleaning services shall be performed five days per week, Monday through Friday, between 4:30 p.m. and 7:30 a.m. CT, excluding Iowa DOT state holidays. The scope includes three line items: general daily, weekly, semi-weekly, monthly, semi-annual, and annual cleaning tasks; carpet shampooing twice annually in April and October with a minimum 15-day advance notice requirement; and waxing and stripping of terrazzo and VCT floors twice yearly in April and October, also requiring 15-day advance notice. The contractor is responsible for providing cleaning cloths, dusters, brooms, dustpans, vacuums, mop equipment, janitorial carts, and any additional supplies deemed necessary, while the DOT provides toilet bowl cleaner, floor cleaner, trash liners, hand soap, paper products, and other specified items. The contractor must maintain a Lead Worker and backup cleaning crew members, with no more than three missed shifts permitted during the contract term; missing shifts may result in disciplinary action up to contract termination. Contractor personnel must pass background and criminal history checks as deemed necessary by DOT, maintain building security with assigned access badges that cannot be shared, and comply with all DOT policies including no smoking, vaping, sleeping on duty, or unauthorized visitors on premises.

The contract term is one year with five optional one-year renewals for a maximum of six years. Payment terms are Net 60 with zero percent payment discounts, and invoices must be itemized with service dates and locations and submitted only after services are rendered in accordance with Iowa Code 8A.514 and Iowa DOT Standard Terms. The contractor must submit signed documentation confirming staff training on contract requirements and must provide copies of specifications to all employees. The contract is available to other Iowa state agencies, Regent institutions, and political subdivisions at the same prices and terms. The DOT Project Manager will have final approval authority for quality and acceptability of all work performed and will respond to all questions and establish cleaning crew responsibilities. The document specifies detailed cleaning checklists, Safety Data Sheet requirements for all on-site janitorial products, and emergency notification procedures for power outages, vandalism, water system failures, building alarms, hazardous material spills, and emergency service calls, with notification required within one hour of such incidents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work/Specifica�ons Custodial Services for Ames Complex Outer Buildings

Overview Provide all labor, equipment and supplies necessary to perform the du�es as outlined in the Scope of Work and appendices for the Iowa DOT, located at 800 Lincoln Way, Ames, IA 50010. DOT requires con�nuous cleaning service coverage for our Ames Complex out Buildings.

1.0 Defini�ons

DOT Project Manager (“Project Manager”) - The DOT Project Manager and their contact informa�on will be provided to Contractor upon contract execu�on. DOT Project Manager will be responsible for ordering supplies and managing issues or concerns rela�ng to scheduled cleaning visits or other general ques�ons as they relate to the contract.

Contractor (“Contractor”)- Awarded Contractor named on executed DOT contract.

Contractor Cleaning Crew (“Cleaning Crew”) The Cleaning Crew must consist of a “Lead Worker” (the primary cleaning crew member) and addi�onal back up cleaning crew member(s) who will cover any scheduled shi�s missed by the Lead Worker.

DOT — Iowa Department of Transporta�on (“DOT”) DOT Buildings –(“DOT Buildings”) Are iden�fied as the following:

Warehouse Sign Shop Trades Building Repair Shop Annex/ State Maintenance Print Shop Auc�on Bldg.

Dist. 1 Office

1.1 Appendix’s

Appendix A: Cleaning Schedule/Requirements Appendix B: Cleaning Checklist Appendix C: Floor Plans Appendix D: Iowa DOT Policy 020.06 (Smoking, Vaping and Smokeless Tabacco Use Appendix E: DEPARTMENT OF ADMINISTRATIVE SERVICES, 8A.514

2.0 Scope of Work — General Requirements

The Project Manager will respond to all ques�ons, establish the responsibili�es of the Cleaning Crew, and have the final approval for the quality and acceptability of all work performed under this Contract. Contractor will be responsible for janitorial staffing and services for DOT Buildings as defined herein. The name and contact informa�on for the Project Manager shall be provided to the Contractor upon execu�on of the contract.

DOT Ames Outbuildings:

• Auc�on Building

• District 1 Office Building

• Repair Shop Annex

• Sign Shop

• Trades Building

• Warehouse/Print Building

The Contractor is required to provide the Cleaning Crew name and contact informa�on including backup crew contact informa�on, to the Project Manager. The Contractor must have employees hired and trained before the start date of the contract.

The Contractor will be provided training by the Project Manager for specific tasks. Contractor is responsible for training their staff. Contractor must provide copies of these specifica�ons to all employees. Contractor must submit a signed document sta�ng they have provided training for their staff. Contractor must also provide a form signed by their employees sta�ng that they understand the requirements and specifica�ons to the Project Manager.

The work performed must be of high quality, maintaining the aesthe�c appearance of the building(s) in a clean and neat manner, as specified herein.

Occasionally addi�onal services may be requested by DOT. These addi�onal services may be required in the DOT Buildings or other buildings located in the Ames Complex. For example, assis�ng with addi�onal cleanup (sewer backup, watermain break, etc. which may require extra hours from the Contractor. Department will compensate Contractor for any approved addi�onal hours beyond the scope defined herein.

Contractor is expected to ensure all DOT Buildings are fully staffed for the en�re scheduled shi�s as per the Hours of Opera�on as defined herein. Contractor must provide backup staff in the event that Cleaning Crew is unable to work their assigned shi�. Contractor is to have no more than three (3) missed shi�s during the term of the contract. The Contractor must immediately no�fy the Project Manager by text, phone (no voicemail) or email if DOT Building (s) will not be fully staffed during any shi� and must inform the Project Manager of plan to fully staff the DOT Building(s). Missing more than three (3) shi�s may result in disciplinary ac�ons, up to and including contract termina�on. The DOT will not pay for days of cleaning that are missed and not remedied within 24 hours.

2.1 Products-Cleaning Supplies

The DOT will provide the following items.

• Toilet Bowl Cleaner

• Floor cleaner

• Trash Can Liners

• Hand Soap

• Toilet Paper

• Paper Towels

• Sanitary Napkin Liners

• Urinal Cakes

• Cleaner for Mirrors (e.g. Windex)

• Cleaner for Stainless Steel (e.g. Water Fountain)

• Cleaner/Disinfectant for services (e.g. Clorox spray cleaner)

Contractor will provide the following.

• Cleaning cloths

• Duster

• Broom

• Dustpan

• Vacuum

• Vacuum Bags

• Janitorial Cart

• Mophandle

• Mophead

• Mop Bucket

• Any addi�onal items the contractor deems necessary to assist their custodial staff with cleaning

DOT paper towels should not be used as cleaning supplies. The Contractor is responsible for supplying all other cleaning supplies, materials, and equipment.

DOT requires a two-week advance no�ce for any supplies that need replenishment. Contract must email the DOT Project Manager when replacements are required.

DOT will provide space in the DOT Buildings to Contractor for janitorial products to be stored onsite.

Space is minimal. Contractor will work with Project Manager to determine adequate shelving needs for cleaning supplies and equipment. The janitorial closets have electrical outlets.

2.2 Logs and Repor�ng

Cleaning supplies stored on site require a Safety Data Sheet (“SDS”). Contractor must supply a list of all applicable SDS sheets in a binder to be stored in each building’s custodial closets

Cleaning Checklist Contractor will maintain a daily checklist at each building. Checklist will be provided by DOT and adhered to doors and/or walls in each cleaning area or Custodial Closet. Project Manager will review checklist and loca�on of list with Contractor and Contractor must review list and loca�ons with their staff.

2.3 Rules & Regula�ons:

All personnel or agents of Contractor must observe all rules and regula�ons in effect at Iowa DOT. These include but are not limited to:

• There is no smoking or vaping allowed on DOT sites including buildings or grounds per Policy 020.06 as shown on Appendix C.

• Collec�ng cans is prohibited.

• Sleeping is not allowed while on duty, including when Contractor Staff are on break.

• Only Contractor employees are allowed on the premises. No Contractor employee visitors are allowed on the premises.

• Animals of any kind are not allowed on the premises unless they are a ‘Service

Animal’ as defined and in compliance with Iowa Code Chapter 216C (Rights of Persons with Disabili�es).

ALL BULLETS LISTED ABOVE ARE CONSIDERED CONTRACT VIOLATIONS AND MAY RESULT IN

DISCIPLINARY ACTION UP TO AND INCLUDING CONTRACT TERMINATION.

Contractor shall not provide maintenance on any areas in the DOT Building(s) unless approved by the DOT Project Manager. Cleaning Crew must no�fy Project Manager of any maintenance issues that require aten�on, including but not limited to, anything broken or needing aten�on in the bathrooms or breakrooms, lights that need lightbulbs…

If any of the following problems occur while the Cleaning Crew is on duty the Project Manager is to be no�fied within one (1) hour and correc�ve ac�on should be taken. List of Emergency Contact Informa�on will be posted in the Custodial Closets.

• Power Outages

• Major Vandalism

• Well or Booster System Failure or major water leak

• Any building alarm in alarm state, including HVAC, generator or li� sta�on

• Hazardous material spills

• Emergency service calls to site

2.4 Invoicing

Contractor shall submit an invoice for Deliverables rendered in accordance with the Contract. Compliant Invoices are paid only a�er services are rendered and as defined in accordance with Iowa Code 8A.514 and the Iowa DOT Standard Terms Formal Rev 08-14-26. Invoices must be itemized with a list of services, the date of service and the service loca�on.

Non-compliant invoices will be returned to the Contractor to be corrected and resubmited within five (5) business days. Electronic invoices are recommended; a DOT email address will be provided upon Contract execu�on.

2.5 Hours of Opera�on

DOT Hours of Opera�on are Monday- Friday 8:00 a.m.-4:30 p.m. Cleaning services shall be performed five (5) days a week., Monday through Friday. Cleaning services shall be conducted a�er business hours, between 4:30 pm and 7:30 am CT. Cleaning services will not be required on DOT Holidays. Any changes to the established cleaning schedule require prior approval from the Project Manager.

Iowa DOT State Holiday Schedule:

New Years Day Dr. Mar�n Luther King, Jr Day Memorial Day

Independence Day Labor Day Veterans Day

Day Before Thanksgiving and Thanksgiving Day

Day a�er Thanksgiving Christmas Day

2.6 Security

Building security For security purposes, only Contractor employees with badge access are permited to be in the DOT Buildings during hours of cleaning.

DOT Buildings must remain locked and secured at all �mes. Contractor staff must not prop open doors when they are not atending the building. If Contract Staff leaves a DOT Building(s) unsecured it may result in disciplinary ac�on, up to and including Contract termina�on.

The�/Vandalism

Any vandalism to the DOT building(s), premises or property caused by Contractor employees and/or any the�, atempted the�, or unauthorized removal of property by the Contractor's staff from any DOT building, premises, or property shall result in the immediate suspension of the involved employee's access card(s) pending inves�ga�on and may result in termina�on of the Contract.

Criminal History and Background Inves�ga�ons:

The DOT reserves the right to conduct criminal history checks, background checks, or both, on Contractor personnel when deemed necessary by the DOT. The Contractor shall cooperate with any such review and ensure its personnel comply with all applicable DOT security requirements.

Building Access Cards

The DOT will provide building access badges to designated Contractor personnel as approved by the DOT Project Manager. Access is granted only to the individual Contractor employee to whom the badge is issued and may not be shared, transferred, or used by any other person, including other Contractor employees.

Visitors are not permited in DOT buildings during cleaning opera�ons. For purposes of this Contract, "visitors" include any individual who is not authorized Contractor personnel, including, but not limited to, spouses, children, friends, or non-service animals.

The Contractor shall immediately no�fy the DOT Project Manager of any lost, stolen, damaged, or unreturned access badge, access card, or key. The Contractor shall cooperate with the DOT in taking any necessary security measures related to lost or compromised access creden�als. All badges, access cards and keys must be returned to the Project Manager when contract is complete. DOT will withhold final payment un�l all keys, badges and Access Cards are returned. If it becomes necessary to change the locks at a building because of failure to return keys or Contractor Staff problems all costs associated with the process will be deducted from Contractor’s final payment. Contractor is responsible for cost of keys that need to be replaced because they are missing or broken. Contractor will be alloted a specific number of keys for each building.

The DOT Project Manager will work with the Contractor and its employees to arrange appointments for access cards this includes all Cleaning Crew and backup members.

2.7 Staffing Expecta�ons: Contractor personnel are employees of the Contractor and not employees of the DOT. The Contractor shall exercise complete supervision over all Cleaning Crew Personnel and shall be solely responsible for their conduct, performance, compensa�on and benefits. The Contractor shall pay all wages, benefits and all applicable federal, state, and local taxes, unemployment taxes, workers’ compensa�on costs and any other required employment-related taxes or assessments.

Contractor shall provide Personnel who are able to fulfill the du�es required and are always neat and clean when they are on duty. Staff must be able to li� 50lbs. Personnel must be able to communicate with the public and Department staff and follow writen and oral instruc�ons and document daily ac�vi�es. At least one employee per building must be fluent in speaking and wri�ng in English.

It is the Contractor's responsibility to ensure there is a backup Cleaning Crew Member(s) in place to cover any extended absences greater than a 24-hour period.

If any Cleaning Crew Member(s) is permanently replaced, the Contractor must no�fy the DOT Project Manager by email. The email must include the new crew member(s) name and 1st date of employment with Contractor on the DOT premises. The Contractor is responsible for working with the DOT Project Manager to ensure that an access card is issued to the new Cleaning Crew Member(s). If a Cleaning Crew Member is no longer employed by the Cnntractor, all access cards must be returned to the DOT immediately.

TASK Daily Weekly Semi-

Weekly Monthly Annually Semi-

Annually

Dus�ng:

DO NOT USE FURNITURE POLISH ON COMPUTER

EQUIPMENT OR COPIERS

Dust all exposed tables, chairs, desks, filing cabinets, bookcases, shelves, moldings, frames, baseboards, and HVAC items.

Detail elevators, stairs, handrails, and baseboard

X

Computer Equipment-dry dust only X

All blinds/window shades. X

Windowsills X

Remove dust and cobwebs from baseboards, ceiling areas, corners, were possible.

X

General Cleaning:

Clean and sani�ze drinking fountains and Elevator controls.

X

Wash glass on all par��ons, dividers, and protec�ve glass.

X

APPENDIX A

CLEANING SCHEDULE/REQUIREMENTS

Wash glass on all interior and exterior entrance/exit doors X

Wipe down & sani�ze employee and customer worksta�on surfaces

X

Clean, sani�ze and polish all restroom fixtures including toilet bowls (Inside & out), urinals and hand basins.

X

Clean all glass, mirrors, stainless steel covers, handrails and metal towel dispensers.

X

Wipe down, clean and sani�ze, restroom walls and doors.

X

Clean all surfaces in break room including counters, tables and chair seats. Clean microwaves in breakrooms

X

Clean refrigerators in break rooms X

TASK Daily Weekly Semi-

Weekly Monthly Annually Semi-

Annually

Fill dispensers in all restrooms and break rooms, (paper towels, soap, and bath �ssue).

Cleaning Crew is NOT responsible for emptying hazardous waste containers, including famine hygiene containers and Sharps containers.

Clean and sani�ze door handles/ plates, light switches

Empty wastebaskets, trash containers and transport to larger trash bins and dispose trash in dumpsters. Re-line containers with plas�c liners.

EXCEPTION: Contractor shall NOT remove DOT employee personal trash or recycling bins located at their employee cubicles.

Spot clean all walls, doors and par��ons.

Clean and sani�ze handrails

Vacuum all upholstered office chairs.

Spot clean office chairs when needed. (As needed)

Floors:

Restroom Sanita�on: Damp mop and sani�ze restroom floors daily using an approved germicide cleaner, paying special aten�on to grout lines and corners

X

Entrances & Mats: Vacuum and sweep entrance door mats and foyer areas daily, extending maintenance ranges during winter months for ice melt and sand.

X

Sweep, dust mop all hard surface floors and baseboards.

Sweep, damp mop all hard surface floors and baseboards.

Vacuum all carpet and runners (move chairs, wastebaskets, and tables as necessary for access).

Strip/wax hard floors (To be coordinated with Project Manager). Waxing and stripping of the Terrazzo and VCT floors in Outbuildings will be conducted two �mes per year during the months of April and October as per the atached Specifica�ons. Services must be completed between 4:30 p.m. and 7:30 am CT, to avoid interrup�ng DOT opera�ons. The vendor is required to provide a minimum fi�een (15) day advance no�ce to the DOT Facili�es Manager prior to conduc�ng carpet cleaning.

X

Shampoo Carpets (To be coordinated with Project Manager). Carpet shampooing will be performed twice annually during the months of April and October as per the atached Specifica�ons. Services must be completed between 4:30 p.m. and 7:30 am CT, or at any �me on a weekend, to avoid interrup�ng DOT opera�ons. The vendor is required to provide a minimum fi�een (15) day advance no�ce to the DOT Facili�es Manager prior to conduc�ng carpet cleaning.

X

Windows:

Wash all interior windows (Spring and/or Fall to be coordinated with Project Manager)

X

Wash all exterior windows (Spring and/or Fall to be coordinated with Project Manager)