Specifications.pdf

PDF 4 MB Posted

Attached to
Rehabilitate Highway Lights on Bourne and Sagamore Bridges
Solicitation number
W912WJ20B0013
Issued by

About this file

This solicitation is for a set aside small business contract to rehabilitate highway lights on the Bourne and Sagamore Bridges in Massachusetts. The U.S. Army Corps of Engineers, New England District will award a contract between $1 million to $5 million. The scope of work includes repairing steel supports, replacing hardware and conduit for lights, replacing fixtures on one bridge with LEDs, replacing ladders in abutments on both bridges, and installing a life line system. All lights will be rewired from below. The period of performance is fall 2020 through November 2021. Only certified small businesses meeting the NAICS code size standard of $16.5 million may submit bids by the specified due date.

View the file

Other files

File Type Posted
BidAbstract.pdf PDF
Amendment 0003 W912WJ20B0013.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
W912WJ20B0013.pdf PDF
Plans.pdf PDF
W912WJ20B0013.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number:

W912WJ20B0004

Rehabilitate Highway Lights

Bourne and Sagamore Bridges Cape Cod Canal Bourne and Buzzards Bay, Massachusetts

Construction Solicitation and Specifications

July 2020

Rehab Highway Lights, Bourne & Sagamore Bridges, CCC, MA

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 41 00 BIDDING SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 55 00 TRAFFIC REGULATION

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

DIVISION 05 - METALS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 71 33 FIBERGLASS REINFORCED PLASTIC (FRP) LADDERS

DIVISION 09 - FINISHES

09 97 02 PAINTING

DIVISION 26 - ELECTRICAL

26 20 00 ELECTRICAL DISTRIBUTION SYSTEM

26 56 19 ROADWAY LIGHTING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 SITE PHOTOGRAPHS

1.3 REFERENCES

1.4 SUBMITTALS

1.5 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK

1.5.1 General

1.5.2 Debris Control

1.6 SUPERINTENDENCE BY THE CONTRACTOR

1.7 PROJECT/SITE CONDITIONS

1.7.1 Site Security

1.8 WORK SEQUENCE AND SCHEDULING

1.8.1 Hours of Operations

1.8.2 Work Sequence

1.8.2.1 General

1.8.2.2 Two-Week Schedule of Work Activities

1.8.2.3 Initial Project Schedule

1.8.2.4 Periodic Schedule Updates

1.8.3 Required Sequence of Construction

1.8.4 Schedule of Phases

1.8.5 Organization at the Site

1.8.5.1 General

1.8.5.2 Rate of Progress

1.9 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

1.10 CONTRACTOR USE OF PREMISES

1.10.1 Access to the Site and Storage/Staging Areas

1.10.2 Temporary Facilities and Utilities, and Storage Areas

1.10.3 Work Limits

1.10.4 Protection and Security

1.10.5 Work By Other Contractors

1.10.6 Emergency Contacts

1.10.7 Damaged Property

1.10.8 Contractor's Receipt of Supplies

1.10.9 Daily Clean Up

1.10.10 Government Sanitary Facilities

1.11 QUALITY ASSURANCE

1.12 GENERAL SAFETY REQUIREMENTS

1.12.1 General

1.12.2 Contractor's Project Superintendent

1.13 ENVIRONMENTAL PROTECTION

1.14 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

1.15 PRECONSTRUCTION CONFERENCE

1.16 RECORD DRAWINGS

1.16.1 Preparation of Record Drawings

PART 2 PRODUCTS (Not Applicable)

SECTION 01 11 00 Page 1

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The work of this project includes repair of steel supports of highway light structures at the Bourne and Sagamore Bridges over the Cape Cod Canal in Bourne and Buzzards Bay, Massachusetts. Additional work includes the following:

Both Bridges:

1. Re-wire each fixture from handhole below sidewalk to fixture with government furnished wire, connectors, splices, and terminations (except where noted).

2. Remove Type B light fixtures and replace hardware and conduit.

3. Spot paint Type B light fixtures after removal, and spot paint Type D lights in place on the concrete pylons.

4. Install horizontal lifeline (HLL) along catwalk located beneath the bridge.

5. Optional item - Replace ladders inside of bridge abutments, including fall protection system.

Bourne Bridge Only:

1. Re-place existing light fixtures with government furnished LED light fixtures.

2. Repair ladder at pier 3.

Work on the bridges is limited to one bridge at a time as simultaneous traffic control on both bridges is not allowed. The Contractor shall note that scheduling of this project is critical, as work is not allowed on the bridges from approximately Memorial Day weekend through Labor Day weekend, as well as Columbus Day weekend and Thanksgiving Day weekend. Note work below the bridge deck on the catwalk and inside of the abutments is permitted during the entire period of performance.

1.2 SITE PHOTOGRAPHS

Photographs taken during a site visit by U.S. Army Corps of Engineers personnel showing the existing conditions of lighting and other project features are attached at the end of the specification. The photographs are attached for informational purposes only. The Contractor shall make his own investigations of existing conditions in the field prior to the start of work.

SECTION 01 11 00 Page 1

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule; G, RO

In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.

Two-Week Schedule of Work Activities

In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks).

SD-07 Certificates

Periodic Schedule Updates; G, RO

Request Application; G, RO

Request Application to work outside the hours of operation.

SD-11 Closeout Submittals

Record Drawings; G, DO

Record drawings showing all deviations which have been made from the contract drawings shall be submitted to the Contracting Officer for approval at the completion of work. See paragraph RECORD DRAWINGS for record keeping and submittal requirements.

SECTION 01 11 00 Page 2

1.5 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK

1.5.1 General

The Contractor shall protect the existing bridge structures and all utilities from damage or interruption of service. Damage or any interruption of service resulting from the Contractor's operations shall be repaired or service restored promptly at the expense of the Contractor.

1.5.2 Debris Control

Care shall be taken that no bridge material, pieces of support structures, debris, or any materials whatsoever, fall into the canal or to the ground.

Should debris or construction materials fall from the bridges inadvertently, prompt corrective action shall be taken to prevent further occurrences and the fallen items shall be secured and removed. The Contractor shall take all precautions practicable to prevent items from falling from the bridges. Debris deposited on horizontal surfaces of the superstructure and piers shall be collected and disposed of properly.

Sweeping of debris off the bridge to the land or water below will not be permitted. No falling debris will be tolerated as the Canal is continually open to marine traffic.

1.6 SUPERINTENDENCE BY THE CONTRACTOR

a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

b. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.

c. The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

d. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings.

e. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

f. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or

SECTION 01 11 00 Page 3 part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PROJECT/SITE CONDITIONS

1.7.1 Site Security

The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible. The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.

1.8 WORK SEQUENCE AND SCHEDULING

1.8.1 Hours of Operations

For this contract, the Contractor will be required to work according to the schedule indicated in the Subpart titled "Required Sequence of Construction" of this section. In the spring before Memorial Day weekend, the Contractor will be required to use, as a minimum, 2 shifts per day, 7 days per week. In the fall after the Labor Day weekend, the Contractor will again be required to work 2 shifts per day for 7 days per week. The inclusion of work on Saturday, Sunday and some legal holidays has been considered in computing the performance time of this contract. The following legal holidays and work restrictions will be observed:

January 1st (No work scheduled) Third Monday in January (No work scheduled) Third Monday in February (No work scheduled) Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December (No work scheduled)

When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.

Requests to deviate from the schedule presented in the Article titled "Phasing of Work" shall be made in writing to the Contracting Officer.

Every effort will be made to accommodate such requests that are not detrimental to maintaining the flow of traffic or to the completion of the contract work.

Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals

SECTION 01 11 00 Page 4 who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

1.8.2 Work Sequence

1.8.2.1 General

There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE entitled SCHEDULES FOR CONSTRUCTION CONTRACTS (48 CFR 52.236-15). Variations shall be approved by the Contracting Officer prior to implementation.

1.8.2.2 Two-Week Schedule of Work Activities

In addition to the scheduling and notification requirements specified elsewhere in this section, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Sunday through Saturday for two weeks). The schedule of work activities shall be updated and submitted by the Contractor to the Contracting Officer on a weekly basis, by noon on every Thursday during the prosecution of work period.

1.8.2.3 Initial Project Schedule

The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation pursuant to FAR Clause 52.236-15 "Schedules for Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The scheduling of the entire project is required. Provide a schedule that is a forward planning as well as a project monitoring tool.

The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart.

Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

1. Activity Durations

2. Design and Permit Activities

3. Procurement Activities

4. Mandatory Tasks

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

SECTION 01 11 00 Page 5

b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of installed equipment lists.

h. Submission and approval of test data, and reports

i. Show Government and other agency activities that could impact progress. These activities include, but are not limited to:

approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE), etc.

This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included in the schedule.

Submit the Initial Project Schedule for approval within 30 calendar days after notice to proceed is issued. No payment will be made for work items not fully detailed in the Project Schedule.

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.

The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

1.8.2.4 Periodic Schedule Updates

An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.

1.8.3 Required Sequence of Construction

Within the overall project schedule; commence and complete the work on each bridge in each of the two (2) phases below. Each phase of the work shall be completed before commencing execution of work in the next sequential phase. Based upon the Contractor's submitted and approved progress schedule, specific calender dates will be noted for the commencement and completion of portions of the work within that phase. The following is to be used as the gauge for the length of time to complete the aspects of the

SECTION 01 11 00 Page 6 work that constitutes the total phase. The Contractor shall determine the appropriate sequence of work within each phase listed below.

1. SAGAMORE BRIDGE WORK

PHASE I: Closure of the Curb Side Traffic Lane

PHASE II: Closure of the Sidewalk Side Traffic Lane

2. BOURNE BRIDGE WORK

PHASE I: Closure of the Sidewalk Side Traffic Lane

PHASE II: Closure of the Curb Side Traffic Lane

1.8.4 Schedule of Phases

The following schedule of dates will serve as the Contractor's guide for the completion of the work to be performed under this contract.

1. Repair of Sagamore Bridge Lighting

SCHEDULED START COMPLETION

PHASE DESCRIPTION DAY/DATE DAY/DATE

I Closure of Curb Notice to Proceed Prior to the Start Side Traffic Lane of Phase II

II Closure of Sidewalk After Completion Prior to the start Side Traffic Lane of Phase I of Bourne Bridge work

2. Repair of Bourne Bridge Lighting

SCHEDULED START COMPLETION

PHASE DESCRIPTION DAY/DATE DAY/DATE

I Closure of Sidewalk After Completion Prior to the Start Side Traffic Lane of Sagamore Work of Phase II

II Closure of Curb Side After completion After Completion Traffic Lane of Phase I of Phase II

a. Scheduled Start Date: The date designated as the beginning of a particular phase.

b. Completion Date: The date designated as the end of a given phase and the day the work in that phase must be completed.

c. Schedule: This sequencing/phasing shall be clearly indicated on the Contractor's Project Schedule.

d. For the period 22 May 2021 through 8 September 2021, inclusive, the Contractor and all traffic control devices must be off the bridges.

e. The Contractor and all traffic control devices must be off the bridges on Columbus Day Weekends (9 October 2020 through 12 October 2020, inclusive, and 8 October 2021 through 11 October 2021, inclusive).

SECTION 01 11 00 Page 7

f. The Contractor and all traffic control devices must be off the bridges on Thanksgiving Day Weekends (24 November 2020 through 30 November 2020, inclusive, and 23 November 2021 through 29 November 2021, inclusive).

g. Liquidated damages will be assessed for each day that the Contractor and all traffic control devices are not completely removed from the bridge during the time periods specified in paragraphs d, e, and f, above.

h. The dates listed above which require the bridges to be fully open to traffic will be enforced.

i. The restrictions above do not apply to work on the catwalk under the bridge or inside of abutments.

1.8.5 Organization at the Site

1.8.5.1 General

The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause

COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.

1.8.5.2 Rate of Progress

Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.

1.9 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

The Contractor shall be responsible for the following:

(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.

(3) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.

1.10 CONTRACTOR USE OF PREMISES

1.10.1 Access to the Site and Storage/Staging Areas

Access to the project site is limited to the specified dates scheduled for work and as indicated on the contract drawings. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.

Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS.

SECTION 01 11 00 Page 8

1.10.2 Temporary Facilities and Utilities, and Storage Areas

The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.10.3 Work Limits

Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.

1.10.4 Protection and Security

a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.

b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.

c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

1.10.5 Work By Other Contractors

During the performance period of this contract, no other work is anticipated to occur by other contractors.

1.10.6 Emergency Contacts

The Contractor shall provide a list of emergency contacts to be used in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.10.7 Damaged Property

Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

1.10.8 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

1.10.9 Daily Clean Up

The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be

SECTION 01 11 00 Page 9 removed from the premises daily.

1.10.10 Government Sanitary Facilities

Toilet facilities are not available on site for the Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION

FACILITIES AND CONTROLS.

1.11 QUALITY ASSURANCE

a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.

Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.

f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

1.12 GENERAL SAFETY REQUIREMENTS

1.12.1 General

The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.

1.12.2 Contractor's Project Superintendent

The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of

SECTION 01 11 00 Page 10 violations, etc., and including that of any subcontractor's work.

1.13 ENVIRONMENTAL PROTECTION

To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.

1.14 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to "FAR 52.245-2, Government Property (Fixed Price Contracts)," the Government will furnish the following materials and equipment for installation by the Contractor: LED Light Fixtures and appurtenances required for installation on this project. The LED light fixtures are available at the U.S. Army Corps of Engineers Cape Cod Canal Administrative facility.

Notify the Contracting Officer in writing at least 10 calendar days in advance of the date on which the materials and equipment are required.

1.15 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.

1.16 RECORD DRAWINGS

Maintain at the jobsite one set of full-size contract drawings marked to show all deviations which have been made from the contract drawings, including buried or concealed construction and utility features revealed during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings.

These drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, submit the original marked set of prints to the Contracting Officer for approval. Requests for partial payments will not be approved if the marked prints are not current, and request for final payment will not be approved until the marked prints are submitted to and approved by the Contracting Officer.

1.16.1 Preparation of Record Drawings

The entries shall be made in the jobsite set of prints at the time field changes are made, pertinent information collected, or need for corrections established, as a continuing process during the life of the contract. As revised drawings are issued by the Contracting Officer, revised prints shall be introduced into the set to replace the superseded drawings and all applicable notations previously made on the superseded drawings transferred to the current prints. Carefully prepared sketches, not less than 8-1/2" x 11", may be used to depict changes or added information in lieu of

SECTION 01 11 00 Page 11 notations on the actual prints. Staple sketches to the prints affected by the change. All plan views, sections, elevations, profiles, diagrams, details, or schedules affected by a change shall be marked up as required to reflect the change. All notations or changes made on the prints shall be in sufficient detail to clearly depict the change. Colored pens or pencils shall be used to make notations on the record prints as follows:

Red pen or pencil shall be employed to indicate added or corrected work or information.

Green pen or pencil shall be used to show the deleted or incorrectly depicted work or information.

Blue or black pen or pencil shall be used to show information not to be recorded on the drawings but included on the marked-up prints for explanatory or clarification purposes for the benefit of the Contracting Officer.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 11 00 Page 12

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.2 BIDDING SCHEDULE - PAYMENT ITEMS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2 BIDDING SCHEDULE - PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job payment item shall be included in the listed item most closely associated with the work involved.

Base Bid Items

A. Item Number 0001, "Sagamore Bridge Lighting Rehabilitation".

All costs for labor, equipment, and materials for the Sagamore Bridge lighting rehabilitation, as shown on the contract drawings and in accordance with Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS, Section 26 20 00 ELECTRICAL DISTRIBUTION SYSTEM, Section 26 56 19 ROADWAY LIGHTING, Section 09 97 02 PAINTING, and other appropriate sections of the specifications.

Unit of Measure: Job.

B. Item Number 0002, "Bourne Bridge Lighting Rehabilitation".

All costs for labor, equipment, and materials for the Bourne Bridge lighting rehabilitation, as shown on the contract drawings and in accordance with Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS, Section 26 20 00 ELECTRICAL DISTRIBUTION SYSTEM, Section 26 56 19 ROADWAY LIGHTING, Section 09 97 02 PAINTING, and other appropriate sections of the specifications.

Unit of Measure: Job.

C. Item Number 0003, "Sagamore Bridge Horizontal Lifeline System".

All costs for labor, equipment, and materials for the Sagamore Bridge horizontal lifeline system, as shown on the contract drawings and in accordance with Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS and

SECTION 01 22 00 Page 2 other appropriate sections of the specifications.

Unit of Measure: Job.

D. Item Number 0004, "Bourne Bridge Horizontal Lifeline System Installation and Ladder Repair".

All costs for labor, equipment, and materials for the Bourne Bridge horizontal lifeline system installation and ladder repair, as shown on the contract drawings and in accordance with Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS and other appropriate sections of the specifications. This item also includes ladder repair at Pier 3.

Unit of Measure: Job.

Optional Items

E. Item Number 0005, "Sagamore Bridge Ladder Replacement".

All costs for labor, equipment, and materials for the Sagamore Bridge ladder replacement, as shown on the contract drawings and in accordance with Section 06 71 33 FIBERGLASS REINFORCED PLASTIC (FRP) LADDERS and other appropriate sections of the specifications.

Unit of Measure: Job.

F. Item Number 0006, "Bourne Bridge Ladder Replacement".

All costs for labor, equipment, and materials for the Bourne Bridge ladder replacement, as shown on the contract drawings and in accordance with Section 06 71 33 FIBERGLASS REINFORCED PLASTIC (FRP) LADDERS and other appropriate sections of the specifications.

Unit of Measure: Job.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 MINIMUM INSURANCE REQUIREMENTS

1.2 SUPERVISION

1.3 PRECONSTRUCTION CONFERENCE

1.4 PARTNERING

1.4.1 Informal Partnering

1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.2 SUPERVISION

See Section 01 11 00 SUMMARY OF WORK, Subpart SUPERINTENDENCE BY THE

CONTRACTOR.

1.3 PRECONSTRUCTION CONFERENCE

See Section 01 11 00 SUMMARY OF WORK, Subpart PRECONSTRUCTION CONFERENCE.

1.4 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.4.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than three to six month intervals.

1.5 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, SECTION 01 30 00 Page 2 and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.

Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

1.1.2 Project Type

1.1.3 Submission of Submittals

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 For Information Only

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

1.5.2.2 Format for SD-02 Shop Drawings

1.5.2.2.1 Drawing Identification

1.5.2.3 Format of SD-03 Product Data

1.5.2.3.1 Product Information

1.5.2.3.2 Standards

1.5.2.3.3 Data Submission

1.5.2.4 Format of SD-04 Samples

1.5.2.4.1 Sample Characteristics

1.5.2.4.2 Sample Incorporation

1.5.2.4.3 Comparison Sample

1.5.2.5 Format of SD-05 Design Data

1.5.2.6 Format of SD-06 Test Reports

1.5.2.7 Format of SD-07 Certificates

1.5.2.8 Format of SD-08 Manufacturer's Instructions

1.5.2.8.1 Standards

1.5.2.9 Format of SD-09 Manufacturer's Field Reports

1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

1.5.2.11 Format of SD-11 Closeout Submittals

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

1.5.3.2 Terms and Conditions

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of SD-04 Samples

1.7 INFORMATION ONLY SUBMITTALS

1.8 PROJECT SUBMITTAL REGISTER

1.8.1 Submittal Management

1.8.2 Preconstruction Use of Submittal Register

SECTION 01 33 00 Page 1

1.8.3 Contractor Use of Submittal Register

1.8.4 Approving Authority Use of Submittal Register

1.8.5 Action Codes

1.8.5.1 Contractor Action Codes

1.8.6 Delivery of Copies

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting that Variations are Compatible

1.9.4 Review Schedule Extension

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

SD-01 Preconstruction Submittals

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

SECTION 01 33 00 Page 3

Certificates Of Insurance

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after

SECTION 01 33 00 Page 4 installation.

Investigation reports

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted operating instructions

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.

SECTION 01 33 00 Page 5

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G, RO

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Government approval is required for any variations from the Solicitation or the Accepted Proposal and for other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.1.1 Approval Codes

a. Construction Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction Division. Send all such submittals to the project Resident or Area Engineer, as applicable.

b. Engineering Division {"DO" (District Office) Reviewer): A "DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.

c. Architect-Engineer Firm {"AE" reviewer): An "AE" on the attached submittal register, column "f" indicates that the submittal review action is by the Architect-Engineer firm asscociated with the project.

d. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

e. Government acceptance is required for submittals with a "G, A" designation.

1.4.2 For Information Only

Submittals not requiring Government approval will be for information only.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."

SECTION 01 33 00 Page 6

1.5 PREPARATION

1.5.1 Transmittal Form

Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are attached at the end of this section and are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.2.2 Format for SD-02 Shop Drawings

Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.

Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.

a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.

b. Dimension drawings, except diagrams and schematic drawings.

This is the start of the file's text. The full file is on GovTribe.