This specifications document outlines the bidding requirements for Harris County, Texas Precinct 3's invitation to bid for the extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District Unit #J109-01-01 (UPIN #20104MF1BG01). The project encompasses approximately 0.77 miles of road extension and includes demolition of existing pavement, excavation, construction of 10-inch reinforced concrete pavement with 8-inch lime-stabilized subgrade, concrete curb installation, driveway and sidewalk construction, ADA-compliant curb ramps, storm drainage infrastructure installation, pavement markings, traffic signage, traffic control implementation, and a new traffic signal. A voluntary pre-bid conference is scheduled for August 11, 2026 at 11:00 a.m. CST via Microsoft Teams. Written questions must be submitted through the Bonfire platform at https://harriscountytx.bonfirehub.com prior to the deadline specified in the Events Schedule. All bidders must complete the Texas Certificate of Interested Parties (Form 1295) prior to submission and are responsible for examining the entire bid package and reviewing their bids for accuracy.
Bid pricing must be submitted on an all-inclusive basis incorporating all labor, material, equipment, and other costs, with unit pricing governing in case of discrepancies between unit and total pricing. Payment terms are Net 30 from the date the invoice is approved by the Harris County Office of the County Engineer. Contractors must comply with Texas Government Code Section 2258 regarding prevailing wage rates and must pay workers the higher of the Harris County Contractor Minimum Wage (currently $21.65 per hour) or applicable prevailing wages. Performance bonds are required for projects exceeding $100,000, and payment bonds are required for projects exceeding $25,000. Certified weekly payroll records, including documentation of compliance with prevailing wage requirements, must be submitted. The County reserves the right to withhold payment for wage discrepancies and assess penalties of $60 per day per person per incident of underpayment. All invoices must route through the Harris County Office of the County Engineer and include certified payroll records and lien waivers. Vendors are responsible for all toll and parking fees incurred during contract performance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev. 10.17.25
SPECIFICATIONS
SCOPE
Harris County is soliciting bids for Extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control District (HCFCD) Unit #J109-01-01 for Harris County Precinct 3.
PRE-BID CONFERENCE
A VOLUNTARY pre-bid conference is scheduled for August 11, 2026 at 11:00 a.m. CST, local time via
Microsoft Teams.
https://teams.microsoft.com/meet/232850399493196?p=yh8K7ou1xEBDQOSAzU
Meeting ID: 232 850 399 493 196
Passcode: JX2uv3Vh
Or call in (audio only)
+ 1 281-985-1862, 612 829 289#
Attendance is not mandatory but encouraged so vendors can gain a better understanding of the requirements listed within this bid. The pre-bid conference will not be rescheduled due to tardiness or any other issues that may arise, no exceptions. Persons with disabilities requiring special accommodations should contact the Purchasing Office at (713) 274- 4400 at least two (2) days prior to the pre-bid conference.
It is the responsibility of each vendor to examine the entire bid package, seek clarification in writing, and review their bid for accuracy before submitting. Questions relating to this bid must be submitted in writing online within Bonfire at https://harriscountytx.bonfirehub.com. The deadline for submission of questions relating to this bid is listed on the Events Schedule within Bonfire. All questions submitted in writing prior to the deadline will be compiled and answered in writing. A copy of all questions and answers will be released as a Public Notice to all firms through Bonfire. The County will not be bound by any information conveyed verbally.
CERTIFICATE OF INTERESTED PARTIES (FORM 1295)
Texas law requires all parties who enter into any contract with the County which must be approved by
Commissioners Court to disclose all interested parties. Form 1295 must be completed in its entirety at the following website: https://www.ethics.state.tx.us/filinginfo/1295/ prior to submitting your response.
Failure to do so may result in disqualification of your response.
SPECIAL REQUIREMENTS
Where these special requirements and information as detailed in the attachment titled General Conditions for Roads, Bridges and Related Work, differ from the attachment titled General Requirements for bids within, the specific requirements and General Conditions for Roads, Bridges and Related Work, supersede where applicable.
Coordination of the project will be through the Harris County Office of the County Engineer and all invoices must be routed through their department. All invoices shall include submission requirements stated in the specifications including completed certified payroll records and lien waivers. Payment terms are “Net 30” from date the invoice is approved by the Office of the County Engineer; therefore, payment to the vendor may be up to one (1) month from the date the invoice is approved by the Office of the County Engineer. Payment of material shall be in accordance with the attachment titled Policy for Payment.
Extension of Birnam Wood Boulevard from Hickorygate Drive to south of Harris County Flood Control
District (HCFCD) Unit # J109-01-01 for Harris County Precinct 3 - UPIN #20104MF1BG01 https://teams.microsoft.com/meet/232850399493196?p=yh8K7ou1xEBDQOSAzU https://harriscountytx.bonfirehub.com/ https://www.ethics.state.tx.us/filinginfo/1295/
In addition, the vendor must comply with Texas Government Code (GC) 2258, Prevailing Wage Rates, and GC 2253.021, Performance and Payment Bonds. Accordingly, GC 2258 requires the vendor to submit a certified payroll record as detailed in the attachment titled Prevailing Wage Rates, Worker Classification
Definitions and Payroll Submittal Instructions (http://www.eng.hctx.net/Consultants/Construction/Prevailing-Wage-Rates), and compensate any worker employed on a public works project not less than as applicable. As well, GC 2253.021, Performance and
Payment Bonds, requires the vendor to provide a payment bond on all public works jobs that exceed
$25,000, and a performance bond on all public works jobs that exceed $100,000.
The rates quoted on the BidTable (bid pricing sheets) within Bonfire must be all-inclusive. “All-inclusive" shall be construed as costs incorporating all charges for labor, material, equipment and any other cost incurred. No separate line item rates or charges will be accepted. Quantities are estimated. Harris County may require more or less. In case of a discrepancy between unit and total pricing, unit pricing governs.
The Extra Work Items section of the BidTable are to be used only on the instructions of the field engineer on the job. No compensation will be received for any part of these items unless they are actually used on the job under the direction of the field engineer. Any additional items required over and above those listed on the BidTable will have to be secured on a change-in-contract and are not to be used until they have been approved by the Harris County Auditor’s Office and/or Commissioners Court.
It may be required that the vendor submit a sample of specified items on the BidTable for inspection and approval by the Office of the County Engineer prior to order placement.
This bid or Commissioners Court approved award does not obligate Harris County to the eventual purchase of any product/service described, implied or which may be proposed. Progress toward this end is solely at the discretion of Harris County and may be terminated at any time.
NO CONFIDENTIALITY OF BIDS
Once opened, bids are public record. There are no exceptions. When submitting a bid, the vendor must be sure to redact confidential information if the information is needed to address requirements of the bid. If there are any questions concerning confidentiality of information to be submitted, contact Luke Herdrich immediately at Luke.Herdrich@harriscountytx.gov.
ALTERATION OF DOCUMENT
No alterations may be made to this document. Any alterations made may result in the bid being rejected.
The terms and conditions contained within this bid supersede all conflicting terms within any cooperative purchasing contracts associated with this purchase.
TOLL/PARKING FEES
Any and all toll/parking FEES incurred by the vendor during the term of this contract will be the responsibility of the vendor.
DRAWINGS/ADDITIONAL SPECIFICATIONS
Vendors may download the drawings, plans, and/or maps for this project through Bonfire at https://harriscountytx.bonfirehub.com as referenced in the attachments titled General Notices, Notes and Information, and Drawings. Do NOT include the drawings from this bid package with the bid submittal.
SPECIFICATION
The project will consist of furnishing all labor, supervision, equipment, materials, and incidentals necessary for the extension of Birnam Wood Boulevard from Hickorygate Drive to south of HCFCD Unit #J109-01- 01 for Harris County Precinct 3.
http://www.eng.hctx.net/Consultants/Construction/Prevailing-Wage-Rates mailto:Luke.Herdrich@harriscountytx.gov https://harriscountytx.bonfirehub.com/
This project consists of furnishing all labor, materials, equipment, tools, supervision, transportation, and incidentals necessary to complete the improvements for the project, which is approximately 0.77 miles in length. The Work includes, but is not limited to, demolition of portions of the existing pavement;
preparation of portions of the right-of-way; excavation; construction of 10-inch reinforced concrete pavement with 8-inch lime-stabilized subgrade and concrete curb; construction and reconstruction of driveways, sidewalks, and ADA-compliant curb ramps; installation of storm drainage infrastructure, including inlets and storm sewer pipe; installation of pavement markings and traffic signage;
implementation and maintenance of traffic control; and installation of a new traffic signal. All work shall be performed in accordance with the Contract Documents, plans, specifications, and all applicable federal, state, and local requirements.
For bidding purposes and to get a better understanding of the requirements of this bid, please refer to the attachment titled General Notices, Notes and Information, Report File and Drawings under Supporting Documents inside Bonfire.
PREVAILING WAGES
In accordance with Section 2258 of the Texas Government Code, contractor and any subcontractor hired by contractor for the construction of any project, shall not pay less than the rates set forth in the Schedule of Prevailing Wages attached and incorporated by reference in each Project Manual. Contractor warrants that it and its subcontractors shall comply with all requirements and worker ratios per the applicable Schedule of Prevailing Wages and Texas state law.
In addition to these wage rates, Contractors must separately comply with Harris County's Minimum Wage Policy [see link] and pay all workers on county projects at least Harris County's Contractor Minimum Wage (currently $21.65/hour). Every worker on a Harris County construction project will make at least the higher of the Harris County Minimum Wage or their applicable Prevailing Wage.
Contractor shall submit certified payroll of contractor and all subcontractors on a weekly basis. At County’s request, contractor shall make available and shall require its subcontractors to make available, copies of cancelled checks and check stubs for comparisons by the County or its agents.
County reserves the right for its agents to visit the project site and to interview contractor, its subcontractors and employees of each on any date or time, as often as desired during the construction period, without prior notification.
County will ascertain if proper wage rates are being paid to the employees as required by the Project Manual. In the event of a discrepancy between the work performed and the wages paid, County will document same and notify contractor. All initial determinations of the classification of workers or the appropriate prevailing wage shall be made by the Harris County Contract Compliance Officer. Her determinations shall be binding.
If, for any length of time and as determined by the Harris County Contract Compliance Officer, discrepancies appear between the certified payrolls and the actual wage paid, County shall require check stubs to be attached to each weekly certified payroll.
Pursuant to TEX. GOV’T CODE ANN. §2258.051, the County reserves the right to withhold any monies due contractor until such discrepancy is resolved and the necessary adjustment made. Contractor shall also pay a penalty in accordance with TEX. GOV’T CODE ANN. § 2258.023(b), of Sixty and No/Dollars ($60.00) per day per person per incident that such person is underpaid. Contractor shall impose these same obligations upon its Subcontractors. Contractor understands that with monthly certified payrolls, contractor is responsible for any and all penalties that shall accrue during the month, regardless of the fact that any error could not be discovered by the Contract Compliance Officer until the following certified payroll.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fpurchasing.harriscountytx.gov%2FServices%2FProcurement-Data-Information&data=05%7C02%7CTiffany.Harris%40pur.hctx.net%7C4fe71ed2f4a5421bf7be08de0d8176b2%7C0d9bc79c581b4477acf78d70dd3e555a%7C0%7C0%7C638963046867576022%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=lwI6PxZW90ZmX35G2IjJYVFCBCACu%2F2ocLH%2FheC3Gu8%3D&reserved=0
| SPECIFICATIONS |
| PRE-BID CONFERENCE |
| CERTIFICATE OF INTERESTED PARTIES (FORM 1295) |
| SPECIAL REQUIREMENTS |
| NO CONFIDENTIALITY OF BIDS |
| ALTERATION OF DOCUMENT |
| TOLL/PARKING FEES |
| DRAWINGS/ADDITIONAL SPECIFICATIONS |
| SPECIFICATION |
| PREVAILING WAGES |