SPECIFICATIONS.pdf
PDF 1 MB Posted
- Attached to
- Caruthersville Floodwall Replacement Federal contract opportunity
- Solicitation number
- W912EQ21R0015
About this file
This solicitation describes a small business set-aside contract opportunity for the Caruthersville Floodwall Replacement project. The scope of work involves demolishing an existing concrete floodwall, constructing a new inverted T-type continuous concrete floodwall comprised of individual monoliths with a sheet pile cutoff wall, installing seven gated openings including one pedestrian access, constructing an over-the-levee access ramp, installing temporary flood protection, and performing other related work. The project is located in Caruthersville, Missouri and has an estimated value between $10-25 million. The contract duration is 1,100 calendar days with an anticipated start of October 2021. A request for proposal will be issued on August 9th with proposals due September 9th. The award will be a firm-fixed-price contract determined by best value tradeoff.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CONSTRUCTION CONTRACTOR DATA FORMS.pdf | ||
| AMENDMENT 0002.pdf | ||
| PLANS-AMENDMENT0002.pdf | ||
| Amendment 0001.pdf | ||
| PLANS.pdf | ||
| Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CARUTHERSVILLE FLOODWALL REPLACEMENT W912EQ21R0015
FOR SOLICITATION - NOT FOR CONSTRUCTION
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 CONTRACTOR QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 02.00 11 QUALITY CONTROL SYSTEM (QCS)
01 53 00.01 12 TEMPORARY FLOOD PROTECTION
01 57 20.00 11 ENVIRONMENTAL PROTECTION
01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN
01 58 00 PROJECT IDENTIFICATION
01 58 01.00 11 PROJECT SIGNS, BARRICADES, AND TRAFFIC CONTROL SIGNS
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 50 15 CIVIL WORKS FABRICATIONS
05 59 20 FABRICATION OF HYDRAULIC STEEL STRUCTURES
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DIVISION 31 - EARTHWORK
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00.00 11 CLEARING & GRUBBING
31 23 00.00 12 EXCAVATION
31 24 00.00 12 EMBANKMENT AND BACKFILL
31 41 16.00 12 STEEL SHEET PILING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00.00 11 AGGREGATE SURFACE COURSE
32 92 32.01 11 ESTABLISHMENT OF TURF
DIVISION 33 - UTILITIES
PROJECT TABLE OF CONTENTS Page 1
33 28 00.00 11 PIEZOMETERS
33 46 16 SUBDRAINAGE SYSTEM
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 16.59 CLOSURE GATES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
1.2 OCCUPANCY OF PREMISES
1.3 EXISTING WORK
1.4 LOCATION OF UNDERGROUND UTILITIES
1.5 SALVAGE MATERIAL AND EQUIPMENT
1.6 ORDER OF WORK
1.6.1 Survey
1.6.2 Over-the-Levee Ramp
1.6.3 Locate Existing Cut-off Wall
1.6.4 Temporary Flood Protection (TFP)
1.6.5 Demolition
1.6.6 Excavation
1.6.7 Driving Permanent Sheetpiling
1.6.8 Concrete Placement
1.6.9 Swing Gate Fabrication and Installation
1.6.10 Removal of Temporary Flood Protection (TFP)
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 Floodwall Construction Sequencing
3.2 General Requirements
3.3 Specific Requirements
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work consists of demolition of an existing concrete floodwall, roadway, sidewalks, and storm drainage utilities, along with the construction of an over-the-levee access ramp using material from a borrow pit nearby, temporary flood protection, structural excavation and backfill, backfill, steel sheet piling, reinforced concrete floodwall, storm drainage utilities, permanent sidewalk, steel swing gates and other incidental work.
The estimated value of the work is between $10,000,000 and $25,000,000.
1.1.2 Location
The work shall be located within Caruthersville, MO. The exact location will be as indicated on the contract drawings. The Contracting Officer's Representative will be available to show the exact location of the work at the two organized site visits.
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with installation requirements for locating and marking underground utilities.
Contact local utility locating service to mark utilities within sufficient time required prior to excavating. Verify existing utility locations
SECTION 01 11 00 Page 2 indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged (existing swing gates) remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 30 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
1.6 ORDER OF WORK
Construction of the over-the-levee ramp and floodwall shall follow a specific order of work as outlined in this section. Completion of items of work as mentioned in this section will be determined based on the following:
Over-the-Levee Ramp: All fill shall be in place, settlement markers achieved and concrete pavement has been installed and reached at least 75% of its design strength.
Concrete Floodwall: Permenant sheetpiling has been installed, concrete has been poured for base slab and stem and has reached 100% of its design strength, backfill is in place, swing gates have been installed and meet all requirements of Section 35 20 16.59 CLOSURE GATES, Paragraph 3.3, and toe drain has been installed.
The contractor shall complete all items of work stated above, as applicable, in a given phase prior to beginning work in any subsequent phase.
1.6.1 Survey
The contractor shall survey existing conditions as noted on construction documents prior to start of construction. The contractor shall locate all utilities prior to excavation, and coordinate utility relocations with the City of Caruthersville and other local utility companies when required.
1.6.2 Over-the-Levee Ramp
Prior to any work commencing on the concrete floodwall or sheetpiling for temporary flood protection in the Bunge Phase (refer to paragraph 3.1), the over-the-levee ramp shall be completed. Note that prior to placing concrete pavement for the new ramp the settlement due to the new fill shall be
SECTION 01 11 00 Page 3 monitored and reached tolerable rates. Refer to Section 31 24 00.00 12
EMBANKMENT AND BACKFILL.
1.6.3 Locate Existing Cut-off Wall
Prior to any work commencing on the concrete floodwall, the contractor shall determine the exact location of the existing cut-off wall identified on the contract drawings. Contract drawings identifies the approximate location of the existing cut-off wall based on historical data. Excavation and demolition around the cutoff shall be performed with care as to not disturb the integrity of the feature unless shown on the plans or approved by the Contracting Officer.
1.6.4 Temporary Flood Protection (TFP)
Prior to any work commencing on the concrete floodwall, the contractor shall have the sheet pile portions of the temporary flood protection (TFP) in place for the portion of floodwall being constructed. The minimal cellular barrier portions of the TFP shall be deployed as triggered by either river forecast or season. Note that the sheet pile tie-ins between the floodwall and TFP will require a limited amount of demolition of the existing floodwall. The sheet pile tie-ins shall be performed only once the majority of the TFP is already in place such that lack of complete flood protection is not outside of the river forecast range of 5 days. The temporary flood protection shall be provided in three distinct phases as outlined on the contract drawing and in Part 3 of this specification.
Temporary flood protection shall be placed in accordance with Section
01 53 00.01 12 TEMPORARY FLOOD PROTECTION.
1.6.5 Demolition
Demolition of the concrete floodwall shall not commence prior to the temporary flood protection being in place. No exceptions.
Temporary flood protection shall be placed in accordance with Section
01 53 00.01 12 TEMPORARY FLOOD PROTECTION.
1.6.6 Excavation
Excavate as indicated on the contract drawings and as specified in Section 31 23 00.00 12 EXCAVATION. Replace any weak soils at bottom of excavation with compacted random fill in accordance with Section 31 24 00.00 12
EMBANKMENT AND BACKFILL.
1.6.7 Driving Permanent Sheetpiling
Sheetpiles shall not be driven in place prior to the approval of required shop drawings.
1.6.8 Concrete Placement
The contractor shall notify the Contracting Officer for observation when reinforcing steel, embeds and formwork are in place. Cast concrete only after approval of reinforcing steel and embed placement by the Contracting Officer. Test concrete in accordance with section 03 30 00 CAST-IN-PLACE
CONCRETE.
SECTION 01 11 00 Page 4
1.6.9 Swing Gate Fabrication and Installation
The contractor shall provide submittals in accordance with section 05 59 20 FABRICATION OF HYDRAULIC STEEL STRUCTURES prior to fabrication of steel gates, hinges, and embeds. Fabrication of gates may begin only after approval of all required swing gate submittals.
1.6.10 Removal of Temporary Flood Protection (TFP)
Once the floodwall construction is complete for a given phase, the temporary flood protection can be removed in a phased approach with the approval of the Contracting Officer. Special emphasis is required at the tie-ins between the TFP and the new floodwall. The final monolith(s) constructed during each phase shall be at the the tie-ins because it could require removal of a small segment of TFP that is in the footprint of the new monoliths. Only one tie-in monolith can be constructed at any given time. When removing the TFP for phase tie-ins the river forecasts (long term and short term) shall be favorable for construction (i.e. Mississippi River gage at Caruthersville not exceeding 3 feet below the bottom of the footing excavation). Construction of the tie-in monoliths shall be completed without delay. The Contractor shall keep approximately 1200 linear feet of cellular barriers (4-foot height), plus infill, on site in the event that the river levels rise above the base of the floodwall while the tie-in monolith is being constructed. Sheets for the TFP alignments that run parallel to the permanent floodwall can be pulled and reused in another phase of construction. The TFP sheets at the floodwall tie-ins, the levee tie-ins and within 50 feet of the casino structure are to remain embedded and cutoff at least 3 feet below the finished ground surface or below the floodwall foundation reinforcement. The areas shall be backfilled in accordance with Section 31 41 16.00 12 STEEL SHEET PILING.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 Floodwall Construction Sequencing
Floodwall construction sequencing phases as indicated on contract drawings can be completed in any order. However, recall from Paragraph 1.6.2, the over-the-levee ramp shall be constructed prior to any floodwall or sheetpiling for temporary flood protection construction commencing within the Bunge Phase. The designations given for each phase are for identification purposes only. The concrete floodwall shall be constructed in three distinct phases as indicated on the contract drawings, and as described below:
(1) Bunge Phase: Begins at the northernmost end of the floodwall near Bunge Grain Facility (Monolith 1) and extends to southern side of the gate opening at Ward Avenue (Monolith 21). Traffic that usually utilizes Ward Avenue as primary access to the riverside shall be directed to use the floodwall openings at Walker Avenue or Bushey Avenue during this phase. The contractor shall maintain public access at all other gate openings not within this phase. In order to begin this phase, the ramp over the levee shall be complete with fill and pavement so that access is provided to the grain facility once the Carleton Avenue opening is permanently closed.
(2) Reynolds Park Phase: Begins at the southern end of the gate closure at
SECTION 01 11 00 Page 5
Ward Avenue (Monolith 22), and extends to southern side of the gate opening at the casino boat ramp (Monolith 43). During construction of this phase, the Ward Avenue gate opening that was newly constructed in the Bunge Phase shall be made available for public use to access the riverside of the floodwall. The contractor shall maintain public access at all other gate openings not within this phase.
(3) Century Casino Phase: Begins at the southern side of the gate opening at the casino boat ramp (Monolith 44) and extends to the southern end of the floodwall (Monolith 69). This phase includes an existing pedestrian walkway that extends from Century Casino, over the existing floodwall. See paragraph 3.3 of this specification for special considerations for this phase of construction.
See contract drawings for approximate locations of the beginning and end of the temporary flood protection tie-ins for each phase described above. The contractor shall submit, with his phasing plan as required by 01 53 00.01 12 TEMPORARY FLOOD PROTECTION, any proposed deviaitons from the phase boundaries as outlined above for approval.
3.2 General Requirements
The contractor shall follow these general requirements:
(1) Work shall be scheduled and accomplished in a manner that maximizes public use of the openings in the floodwall.
(2) When construction is not active at a gate opening, the opening shall be safely secured and made available for public use. The exception to this requirement will be any curing periods required immediately following placement of concrete at the gate monoliths.
(3) Once construction has commenced at the site, the contractor shall schedule work in a manner to complete foundations within a reasonable time to minimize closure time of the gate openings.
3.3 Specific Requirements
The existing pedestrian walkway located at Century Casino shall remain in place during construction. The Contractor shall coordinate with the casino, and provide at least a 30 day notice prior to commencing work on the Century Casino Phase of construction. Care shall be taken to initiate no damage to the existing walkway. Press in methods shall be used for advancing sheet piles within 50 feet of the casino structure. Reference Section 31 41 16.00 12 STEEL SHEET PILING.
-- End of Section --
SECTION 01 11 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Environmental Protection
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Demolition
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Write/Amend and Maintain SWPPP
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Vehicle Washdown Rack
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Traffic Control and Coordination
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Procurement, Delivery, Storage, Protection, and Disposal of Cellular Barriers
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Demolition of Cut-off Concrete Cap
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.2 Silt Fence
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.3 Concrete Washouts
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.4 Construction Vehice Egress
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.5 Compacted Impervious Fill
1.2.5.1 Payment
1.2.5.2 Measurement
1.2.5.3 Unit of Measure
SECTION 01 22 00.00 10 Page 1
1.2.6 Compacted (Random) Fill
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
1.2.7 Establishment of Turf
1.2.7.1 Payment
1.2.7.2 Measurement
1.2.7.3 Unit of Measure
1.2.8 Clearing
1.2.8.1 Payment
1.2.8.2 Measurement
1.2.8.3 Unit of Measure
1.2.9 Grubbing
1.2.9.1 Payment
1.2.9.2 Measurement
1.2.9.3 Unit of Measure
1.2.10 Aggregate Surface Course
1.2.10.1 Payment
1.2.10.2 Measurement
1.2.10.3 Unit of Measure
1.2.11 Asphalt Pavement
1.2.11.1 Payment
1.2.11.2 Measurement
1.2.11.3 Unit of Measure
1.2.12 Temporary Flood Protection PZ 27 Sheet Pile
1.2.12.1 Payment
1.2.12.2 Measurement
1.2.12.3 Unit of Measure
1.2.13 Installation, Maintenance, Repositioning, and Removal of Cellular Barriers
1.2.13.1 Payment
1.2.13.2 Measurement
1.2.13.3 Unit of Measure
1.2.14 Toe Drain System
1.2.14.1 Payment
1.2.14.2 Measurement
1.2.14.3 Unit of Measure
1.2.15 Sheet Pile Cutoff PZ 22
1.2.15.1 Payment
1.2.15.2 Measurement
1.2.15.2.1 Pulled Piles
1.2.15.3 Unit of Measure
1.2.16 Reinforced Concrete Floodwall
1.2.16.1 Payment
1.2.16.2 Measurement
1.2.16.3 Unit of Measure
1.2.17 Swing Gate Closure Structure
1.2.17.1 Payment
1.2.17.2 Measurement
1.2.17.3 Unit of Measure
1.2.18 Pipe Sleeve
1.2.18.1 Payment
1.2.18.2 Measurement
1.2.18.3 Unit of Measure
1.2.19 Geotextile Filter Fabric
1.2.19.1 Payment
1.2.19.2 Measurement
1.2.19.3 Unit of Measure
1.2.20 Miscellaneous Metals
SECTION 01 22 00.00 10 Page 2
1.2.20.1 Payment
1.2.20.2 Measurement
1.2.20.3 Unit of Measure
1.2.21 Concrete Slope Paving
1.2.21.1 Payment
1.2.21.2 Measurement
1.2.21.3 Unit of Measure
1.2.22 Piezometers
1.2.22.1 Payment
1.2.22.2 Measurement
1.2.22.3 Unit of Measure
1.2.23 Bollards
1.2.23.1 Payment
1.2.23.2 Measurement
1.2.23.3 Unit of Measure
1.2.24 Ramp Concrete Pavement
1.2.24.1 Payment
1.2.24.2 Measurement
1.2.24.3 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00.00 10 Page 3
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Contract Clause PAYMENT FOR
MOBILIZATION AND DEMOBILIZATION.
1.1.1.2 Unit of Measure
Unit of measure, Job: JA
1.1.2 Environmental Protection
1.1.2.1 Payment
Payment will be made for costs associated with operations necessary for "Environmental Protection" as specified in Section 01 57 20.00 11 ENVIRONMENTAL PROTECTION. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for "Environmental Protection." This price and payment does not include those items covered under "Storm Water Pollution Prevention;" however, it does include items incidental thereto. The Contractor shall be responsible for payment of fees associated with environmental permits, SECTION 01 22 00.00 10 Page 4 application, and/or notices obtained by the Contractor. The Contractor shall be responsible for payment of all fines/fees arriving from violation or non-compliance with Federal, State, Regional, and local laws or regulations. The Government will not provide any compensation for payments of fines/fees, in the event that fines/fees are incurred by the Contractor.
1.1.2.2 Unit of Measure
No measurement will be made for Environmental Protection.
Unit of measure, Job: JA
1.1.3 Demolition
1.1.3.1 Payment
Payment will be made for costs associated with "Demolition", which shall be considered full compensation for furnishing all plant, labor, materials, and equipment for the removal of existing floodwall, removal of all structures associated with the floodwall, removal of existing sidewalks and existing pavement, removal of existing lightpoles along sidewalks, removal of all resulting rubbish and debris, disposal of demolished items, final clean up, and all other items incidental thereto as specified in Section 02 41 00 DEMOLITION. Excavation and stockpile of soil for the demolition of the existing floodwall will be included under the line item for Excavation.
1.1.3.2 Unit of Measure
No measurement will be made for Demolition.
Unit of measure, Job: JA
1.1.4 Write/Amend and Maintain SWPPP
1.1.4.1 Payment
Payment for Write/Amend and Maintain SWPPP will be made at the contract job price for "Write/Amend and Maintain SWPPP". Price and payment shall constitute full compensation for Contractor creation, according to Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN, and submittal of the SWPPP to the US Army Corps of Engineers for approval, updating and maintaining of the project SWPPP throughout the duration of the project, conducting stormwater inspections, submitting appropriate reports to the Contracting Officer, and all other operations incidental thereto for the duration of the construction project.
1.1.4.2 Unit of Measure
No measurement will be made for Write/Amend and Maintain SWPP.
Unit of measure, Job: JA
SECTION 01 22 00.00 10 Page 5
1.1.5 Vehicle Washdown Rack
1.1.5.1 Payment
Payment will be made for costs associated with providing a vehicle washdown rack.
1.1.5.2 Unit of Measure
No measurement will be made for Vehicle Washdown Rack.
Unit of measure, Job: JA
1.1.6 Traffic Control and Coordination
1.1.6.1 Payment
Payment will be made at the contract job price for "Traffic Control and Coordination". Price and payment shall constitute full compensation for providing all plant, labor, materials and equipment to complete the traffic control and coordination work; preparation of the Traffic Control Plan (TCP); all as specified herein and as shown on the drawings.
1.1.6.2 Unit of Measure
No measurement will be made for the preparation of a Traffic Control Plan (TCP), nor the maintenance, control or coordination of traffic routing including barricades, temporary pavement markings, warning or detour signs as specified herein.
Unit of measure, Job: JA
1.1.7 Procurement, Delivery, Storage, Protection, and Disposal of Cellular Barriers
1.1.7.1 Payment
Payment will be made at the contract job price for "Procurement, Delivery, Storage, Protection, and Disposal of Temporary Flood Protection Systems".
Price and payment shall constitute full compensation for all equipment, labor and materials required for furnishing, transporting, storing, and disposal of Cellular Barriers as required to complete the work specified in Section 01 53 00.01 12 TEMPORARY FLOOD PROTECTION. Damage to temporary flood protection systems during transport or while stored shall be repaired at no additional expense to the Government.
1.1.7.2 Unit of Measure
Unit of measure, Job: JA
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
SECTION 01 22 00.00 10 Page 6
1.2.1 Demolition of Cut-off Concrete Cap
1.2.1.1 Payment
Payment for Demolition of Cut-off Concrete Cap performed as described on the contract drawings will be made at the contract unit price per linear foot for "Demolition of Cut-off Concrete Cap". Price and payment shall constitute full compensation for furnishing all equipment and performing all labor for demolition and re-establishment of cut-off concrete cap.
1.2.1.2 Measurement
Measurement for Demolition of Cut-off Concrete Cap satisfactorily demolished shall be made by the linear foot.
1.2.1.3 Unit of Measure
Unit of measure, Linear Foot: LF
1.2.2 Silt Fence
No separate measurement or payment will be made for the work "Storm Water Pollution Prevention" required by Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN except as described in the paragraphs 1.2.1.1 and
1.2.1.2 for silt fence below. Any additional costs associated with Storm Water Pollution Prevention, other than these listed, shall be included in the contract price under Environmental Protection. The Government will pay all costs for the "Storm Water Pollution Prevention" at the contract unit price for each sub-item list below as follows:
(1) Sixty percent of the unit price upon completion of the installation.
(2) The remaining 40 percent throughout the contract life, with a maximum of 20 percent being retained until final removal and cleanup of the premises.
The Contracting Officer will require the Contractor to furnish cost data to calculate the exact percentage to be paid upon installation.
1.2.2.1 Payment
Payment for Silt Fence installed as specified in Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN will be made at the contract unit price per linear foot for "Silt Fence" as broken down by the percentages in the "sub-item list" above. Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, including geotextile fabric, and performing all operations necessary for the placement and maintenance of silt fence throughout the contract period, including final dressing and cleanup.
1.2.2.2 Measurement
Measurement for silt fence satisfactorily placed shall be made by the linear foot.
SECTION 01 22 00.00 10 Page 7
1.2.2.3 Unit of Measure
Unit of measure, Linear Foot: LF
1.2.3 Concrete Washouts
1.2.3.1 Payment
Payment for the temporary Construction Washouts, including its maintenance and removal, will be made at the contract unit price for "Construction Washouts" as broken down by the percentages in the "sub-item list" above.
Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as shown on drawings.
1.2.3.2 Measurement
Measurement for Construction Washouts satisfactorily designed, constructed and maintained by the Contractor will be per each placed.
1.2.3.3 Unit of Measure
Unit of measure, Each: EA
1.2.4 Construction Vehice Egress
1.2.4.1 Payment
Payment for the temporary Construction Vehicle Egress, including its maintenance and removal, will be made at the contract unit price for "Construction Vehicle Egress" as broken down by the percentages in the "sub-item list" above. Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as shown on drawings.
1.2.4.2 Measurement
Measurement for Construction Vehicle Egress satisfactorily designed, constructed and maintained by the Contractor will be per each placed.
1.2.4.3 Unit of Measure
Unit of measure, Each: EA
1.2.5 Compacted Impervious Fill
1.2.5.1 Payment
Payment for Compacted Impervious Fill performed as described in Section 31 24 00.00 12 EMBANKMENT AND BACKFILL will be made at the contract unit price per cubic yard for "Compacted Impervious Fill" which price and payment shall constitute full compensation for furnishing all equipment and performing all labor for construction of the completed compacted impervious fill. No separate payment will be made for excavation required for construction of the completed compacted impervious fill. Excavation shall be considered incidental to Compacted Impervious Fill.
SECTION 01 22 00.00 10 Page 8
1.2.5.2 Measurement
Measurement for Compacted Impervious Fill shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in in Paragraph 1.6 "Layout of Work", subparagraph d. "Quantity Surveys". Pre-construction quantity surveys shall be performed before stripping topsoil.
Post-construction quantity surveys shall be performed after the fill has been completed and the stripped topsoil has been spread. Stripping, stockpiling, and re-spreading topsoil will be considered incidental to the compacted fill. The cubic yardage to be paid will be determined by the volumes computed by the average end area method. The basis for the measurement will be cross sections of the excavated areas and the existing levee and a second cross section survey of the same area after the completion of the compacted impervious fill construction. The quantity of compacted impervious fill to be paid for will be computed between the before compacted impervious fill construction surface and the theoretical grades and slope lines shown on the contract drawings. Compacted impervious fill not constructed to specified grade and section including allowable tolerance will not be accepted. No allowance or payment will be made for compacted impervious fill placed outside the required theoretical grade and section. For areas where lines and grades are shown on the drawings, measurement will be limited to those lines and grades.
1.2.5.3 Unit of Measure
Unit of measure, Cubic Yard: CY
1.2.6 Compacted (Random) Fill
1.2.6.1 Payment
Payment for Compacted (Random) Fill performed as described in Section 31 24 00.00 12 EMBANKMENT AND BACKFILL will be made at the contract unit price per cubic yard for "Compacted (Random) Fill" which price and payment shall constitute full compensation for furnishing all equipment and performing all labor for construction of the completed compacted (random) fill. No separate payment will be made for excavation required for construction of the completed compacted (random) fill. Excavation shall be considered incidental to Compacted (Random) Fill.
1.2.6.2 Measurement
Measurement for Compacted (Random) Fill shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in in Paragraph 1.6 "Layout of Work", subparagraph d. "Quantity Surveys". Pre-construction quantity surveys shall be performed before stripping topsoil. Post-construction quantity surveys shall be performed after the fill has been completed and the stripped topsoil has been spread. Stripping, stockpiling, and re-spreading topsoil will be considered incidental to the compacted fill.
The cubic yardage to be paid will be determined by the volumes computed by the average end area method. The basis for the measurement will be cross sections of the excavated areas and the existing levee and a second cross section survey of the same area after the completion of the compacted fill construction. The quantity of compacted (random) fill to be paid for will be computed between the before compacted (random) fill construction surface and the theoretical grades and slope lines shown on the contract drawings.
Compacted (random) fill not constructed to specified grade and section including allowable tolerance will not be accepted. No allowance or payment will be made for compacted (random) fill placed outside the required
SECTION 01 22 00.00 10 Page 9 theoretical grade and section. For areas where lines and grades are shown on the drawings, measurement will be limited to those lines and grades.
1.2.6.3 Unit of Measure
Unit of measure, Cubic Yard: CY
1.2.7 Establishment of Turf
1.2.7.1 Payment
Payment for Establishment of Turf will be made at the contract unit price per acre for "Establishment of Turf", which price and payment shall constitute full compensation for furnishing all plant, labor, equipment, materials, and performing all operations necessary for Establishment of Turf as specified in Section 32 92 32.01 11 ESTABLISHMENT OF TURF.
1.2.7.2 Measurement
Measurement for Establishment of Turf shall be by the acre, measured along the areas turfed within the construction limits and computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
Measurement for Establishment of Turf shall be limited to the areas specified in the drawings and as indicated in the field by the Contracting Officer.
1.2.7.3 Unit of Measure
Unit of measure, Acre: AC
1.2.8 Clearing
1.2.8.1 Payment
Payment for Clearing as specified in this section will be made at the contract unit price per acre for "Clearing," which price and payment shall constitute full compensation for furnishing all plant, labor, material, equipment, and performing all operations necessary for "Clearing" as specified in SECTION 31 11 00.00 11 - CLEARING AND GRUBBING. If regrowth of vegetation or trees occurs after Clearing and before placement of embankment, the Contractor is required to clear again prior to embankment construction, no payment will be made for this additional clearing.
1.2.8.2 Measurement
Measurement for Clearing shall be made by the acre, measured along the areas of work for embankment, excavation, and/or any other areas requiring clearing as indicated on the plans. For measurement purposes, the acreage will be computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
1.2.8.3 Unit of Measure
Unit of measure, Acre: AC.
SECTION 01 22 00.00 10 Page 10
1.2.9 Grubbing
1.2.9.1 Payment
Payment for Grubbing will be made at the contract unit price per acre for "Grubbing," which price and payment shall constitute full compensation for furnishing all plant, labor, material, equipment, and performing all operations necessary for "Grubbing" as specified in SECTION 31 11 00.00 11
- CLEARING AND GRUBBING. If regrowth of vegetation or trees occurs after Grubbing and before placement of embankment, the Contractor is required to grub again prior to embankment construction, no payment will be made for this additional grubbing.
1.2.9.2 Measurement
Measurement for Grubbing shall be made by the acre, measured along the areas of work for embankment, excavation, and/or any other areas requiring Grubbing as indicated on the plans. For measurement purposes the acreage will be computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
1.2.9.3 Unit of Measure
Unit of measure, Acre: AC
1.2.10 Aggregate Surface Course
1.2.10.1 Payment
Payment for Aggregate Surface Course will be made at the contract unit price per ton for "Aggregate Surface Course", which price and payment shall include all costs of furnishing, hauling, handling, placing and maintaining the Aggregate Surface Course as specified in the contract drawings.
1.2.10.2 Measurement
Measurement for Aggregate Surface Course shall be by the ton (2,000 pounds), measured by weighing each truckload to the nearest 1/10 ton, and the final quantity of the whole sum for Aggregate Surface Course rounded to the nearest whole ton. When Aggregate Surface Course is delivered by truck, the material shall be measured for payment, in the presence of a Government Inspector, unless the Contracting Officer waives such right, by weighing on approved, accurately calibrated scales furnished by and at the expense of the Contractor. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be inspected, tested, and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. Scales shall be checked and certified before any material hauling;
also, rechecked and re-certified whenever a variance is suspected.
Individual weight tickets for each truckload of Aggregate Surface Course shall be furnished to the Government Inspector at the time of delivery. At a minimum, all weight tickets shall have the contract number or project name, the gross weight, the vehicle identity and empty weight, and the net load weight. Scales that produce this information printed on the weight tickets are preferred. Weight certificates furnished by a Public Weighmaster, where available, will be acceptable, when authorized by the Contracting Officer. The Contractor has the option to use certified, and otherwise acceptable, scales that are Contractor furnished, quarry/supplier furnished, or commercial/public facilities.
SECTION 01 22 00.00 10 Page 11
1.2.10.3 Unit of Measure
Unit of measure, Ton: TN
1.2.11 Asphalt Pavement
1.2.11.1 Payment
Payment for Asphalt Pavement as described on the contract drawings will be made at the contract unit price per square foot for "Asphalt Pavement" which price and payment shall constitute full compensation for placing all features of the asphalt pavement.
1.2.11.2 Measurement
Measurement for Asphalt Pavement shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in in Paragraph 1.6 "Layout of Work", subparagraph d. "Quantity Surveys".
1.2.11.3 Unit of Measure
Unit of measure, Square Foot: SF
1.2.12 Temporary Flood Protection PZ 27 Sheet Pile
1.2.12.1 Payment
Payment for Temporary Flood Protection performed as described in Section 01 53 00.01 12 TEMPORARY FLOOD PROTECTION will be made at the contract unit price per square foot for "Temporary Flood Protection PZ 27 Sheet Pile".
Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and equipment required for the installation, maintenance, splicing,cutting, cross sheeting, tie-ins and removal of the temporary flood protection; and all other work which is incidental thereto.
Payment applies for sheet pile temporary flood protection and the deployment of cellular barriers at the phase tie-ins (if required). The Government will pay costs for the "Temporary Flood Protection PZ 27 Sheet Pile" at the contract unit price as follows:
(1) Sixty percent of the unit price upon completion of the installation.
(2) The remaining 40 percent throughout the contract life, with a maximum of 20 percent being retained until final removal and cleanup of the premises.
The Contracting Officer will require the Contractor to furnish cost data to calculate the exact percentage to be paid upon installation.
Cut-offs and/or splices which are not required under the original terms of this contract but become necessary to construct the sheet pile structures as shown on the drawings and as specified herein, and which are necessitated due to Contractor negligence in any procedure required to install such structures shall be provided at no additional cost to the Government. Cut-offs and/or splices of this type which are required through no fault of the Contractor shall be paid for by lump sum payments of $10.00 per cut-off and $25.00 per splice. Additionally, the portion of a Contractor furnished pile which is cut off when the Contractor is deemed to be not at fault, shall be paid for at 75 percent of the applicable
SECTION 01 22 00.00 10 Page 12 contract unit price for the amount measured in accordance with below paragraph 1.2.12.2 "Measurement".
Piles, which are directed to be pulled and found to be in good condition, will be paid for at the contract price for furnishing and driving the pile in its original position. The cost of pulling will be paid for at 25 percent of the contract unit price and when such piles are redriven, the cost of redriving will be paid for at 25 percent of the contract unit price for that portion of the pile acceptably redriven below the cut-off elevation. When piles are pulled and found to be defective and/or damaged due to Contractor negligence, no payment will be made for originally furnishing and driving such piles, nor for the operation for pulling.
Piles replacing defective or damaged piles will be paid for at the applicable contract unit price. Piles which are pulled and found to be damaged through no fault of the Contractor, will be paid for at the applicable contract unit price for originally installing the damaged pile plus 25% of the applicable contract unit price for the cost of pulling.
Subsequently, when a new pile is furnished and driven, it shall be paid for at the applicable contract unit price.
1.2.12.2 Measurement
Measurement of driven steel sheet piling, except for fabricated piles (special corners, transitions, tee sections, etc.) and rolled corners, will be by the square foot of piling acceptably installed. The length of each pile driven will be measured to the nearest tenth of a linear foot and converted to square feet for payment purposes. The square footage will be determined by multiplying the number of piles times the measured length acceptably driven below the cut-off elevation shown on the drawings times the theoretical driving width of the pile. The number of piles paid for will be based on the number of floodwall sheet piles shown on the Contractor's approved shop drawings submitted after demolition of the existing floodwall. When driven piles are directed to be cut off before reaching the penetration depth shown on the drawings, that portion cut off will be measured for payment on the basis of its total length, provided that the length is not greater than the difference between the total length of piles shown on the plans for that location and the length of piles driven below the cut-off elevation. No deduction will be made for holes cut for drains and utilities in computing the area of steel sheet pile structures. The portion of any pile driven below the tip elevation shown on the drawings will not be measured for payment unless overdriving is directed by the Contracting Officer. No separate measurement will be made for the fabricated piles and rolled corners, or sheet piling void backfill.
1.2.12.3 Unit of Measure
Unit of measure, Square Foot: SF
1.2.13 Installation, Maintenance, Repositioning, and Removal of Cellular Barriers
1.2.13.1 Payment
Payment will be made at the contract unit price per linear foot for "Installation, Maintenance, Repositioning, and Removal of Cellular Barriers". Price and payment shall constitute full compensation for all equipment, labor and materials required for assembling, setting, adjusting, maintaining, repositioning, disassembling, and stowing of Cellular Barriers as required to complete the work specified in Section 01 53 00.01 12
SECTION 01 22 00.00 10 Page 13
TEMPORARY FLOOD PROTECTION. Damage to deployed temporary flood protection systems resulting from the Contractor's operations shall be repaired at no additional expense to the Government.
1.2.13.2 Measurement
Measurement for temporary flood protection systems satisfactorily deployed shall be made by the linear foot.
1.2.13.3 Unit of Measure
Unit of measure, Linear Foot: LF
1.2.14 Toe Drain System
1.2.14.1 Payment
Payment for Toe Drain System performed as described in Section 33 46 16 SUBDRAINAGE SYSTEM will be made at the contract unit price per linear foot for "Toe Drain System". Price and payment shall constitute full compensation for furnishing all equipment and performing all labor for construction of the completed toe drain system. Outlets and manholes as specified on the contract drawings are incidental to the "Toe Drain System". No separate measurement or payment will be made for outlets or manholes.
1.2.14.2 Measurement
Measurement for Toe Drain System satsifactorily installed shall be made made by the linear foot.
1.2.14.3 Unit of Measure
Unit of measure, Linear Foot: LF
1.2.15 Sheet Pile Cutoff PZ 22
1.2.15.1 Payment
Payment for steel sheet piling acceptably installed and measured in accordance with Section 31 41 16.00 12 STEEL SHEET PILING will be made at the contract unit price per square foot for "Sheet Pile Cutoff PZ 22".
Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and equipment required to complete the work as specified in Section 31 41 16.00 12 STEEL SHEET PILING, and as shown on the drawings, including fabricating, adding cover plates, furnishing, painting, handling, driving, cutting holes, backfilling voids, splicing, and all other work incidental to acceptably installing the steel sheet piling. No separate payment will be made for the transition piles or the rolled corners and all costs associated with fabricating, furnishing, delivering, and installing them shall be included in the contract unit cost for "Sheet Pile Cutoff PZ 22".
Cut-offs and/or splices which are not required under the original terms of this contract but become necessary to construct the sheet pile structures as shown on the drawings and as specified herein, and which are necessitated due to Contractor negligence in any procedure required to install such structures shall be provided at no additional cost to the Government. Cut-offs and/or splices of this type which are required
SECTION 01 22 00.00 10 Page 14 through no fault of the Contractor shall be paid for by lump sum payments of $10.00 per cut-off and $25.00 per splice. Additionally, the portion of a Contractor furnished pile which is cut off when the Contractor is deemed to be not at fault, shall be paid for at 75 percent of the applicable contract unit price for the amount measured in accordance with below paragraph 1.2.14.2 "Measurement".
Piles, which are directed to be pulled and found to be in good condition, will be paid for at the contract price for furnishing and driving the pile in its original position. The cost of pulling will be paid for at 25 percent of the contract unit price and when such piles are redriven, the cost of redriving will be paid for at 25 percent of the contract unit price for that portion of the pile acceptably redriven below the cut-off elevation. When piles are pulled and found to be defective and/or damaged due to Contractor negligence, no payment will be made for originally furnishing and driving such piles, nor for the operation for pulling.
Piles replacing defective or damaged piles will be paid for at the applicable contract unit price. Piles which are pulled and found to be damaged through no fault of the Contractor, will be paid for at the applicable contract unit price for originally installing the damaged pile plus 25% of the applicable contract unit price for the cost of pulling.
Subsequently, when a new pile is furnished and driven, it shall be paid for at the applicable contract unit price.
1.2.15.2 Measurement
Measurement of driven steel sheet piling, except for fabricated piles (special corners, transitions, tee sections, etc.) and rolled corners, will be by the square foot of piling acceptably installed. The length of each pile driven will be measured to the nearest tenth of a linear foot and converted to square feet for payment purposes. The square footage will be determined by multiplying the number of piles times the measured length acceptably driven below the cut-off elevation shown on the drawings times the theoretical driving width of the pile. The number of piles paid for will be based on the number of floodwall sheet piles shown on the Contractor's approved shop drawings submitted after demolition of the existing floodwall. When driven piles are directed to be cut off before reaching the penetration depth shown on the drawings, that portion cut off will be measured for payment on the basis of its total length, provided that the length is not greater than the difference between the total length of piles shown on the plans for that location and the length of piles driven below the cut-off elevation. No deduction will be made for holes cut for drains and utilities in computing the area of steel sheet pile structures. The portion of any pile driven below the tip elevation shown on the drawings will not be measured for payment unless overdriving is directed by the Contracting Officer. No separate measurement will be made for the fabricated piles and rolled corners, or sheet piling void backfill.
1.2.15.2.1 Pulled Piles
Piles ordered pulled will be measured for payment by the square foot.
Square footage will be determined by multiplying the theoretical driving width of the pile by the length pulled above the cut-off elevation shown on the drawings. Redriving of such piles, when required, shall be measured for payment by the square foot, which shall be determined by multiplying the theoretical driving width of the pile by the length redriven below the cut-off elevation shown on the drawings.
SECTION 01 22 00.00 10 Page 15
1.2.15.3 Unit of Measure
Unit of measure, Square Foot: SF
1.2.16 Reinforced Concrete Floodwall
1.2.16.1 Payment
Payment will be made at the contract unit price for "Reinforced Concrete Floodwall". Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and the use of all equipment and tools required to complete the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .