Attachment 1

W911WN20Q8004

SPECIFICATIONS

REPLACE THE OPERATIONS BUILDING ROOF SYSTEMS

INCLUDING REPLACING THE PENTHOUSE ROOF

ALLEGHENY RIVER LOCK AND DAM #6

Freeport, Armstrong County, Pennsylvania

Table of Contents

SCOPE OF WORK

1. General Requirements

General Labor and materials Existing Roof — Allegheny River Lock and Dam #6

1.3.1. New roof details

1.3.2. Protection of Existing Items

1.3.3. Wooden Penthouse (Cupola) roof replacement

1.3.3.1. Lead abatement

Disposal Inspection

2. Security Requirements-AT/OPSEC

(2.) Access and General Protection and Security Policy and Procedures (2b.) For contractors who do not require Common Access Card (CAC), but require access to a DOD facility or installation (13.) Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas (15.) Pre-screen candidates using E-Verify Program Employee Identification and Background Check

3. Safety Requirements

Accident Prevention Plan (APP) Risk Management Implementation of Safety and Occupational Health (SOH) Program Mishap Reporting Hazardous Material Exclusion Unforeseen Hazardous Material Damage Reports Minimum Personal Protective Equipment Designated Persons

4. Project/Site Conditions

Reference Drawings Verification of Field Conditions Work Areas Time of Performance Period of Performance (PoP) Permits Protection of Government Property Inspections and Acceptance of Work Project Government personnel contacts

Points of Contact (POCs)

SPECIFICATIONS

5. Specified Requirements

References Submittals

5.2.1. Manufacturer's Literature

5.2.2. Required Submittals

All contractor data submissions shall be submitted to:

Quality Assurance

5.4.1. Daily Inspection Report

5.4.2. Pre-roofing Conference

5.4.3. Fire Resistance

Delivery, Storage, and Handling

5.5.1. Delivery

5.5.2. Storage

5.5.3. Handling

Environmental Requirements Sequencing Certificates

5.8.1. Warranty

5.8.1.1. Roofing System Installer Warranty

5.8.1.2. Roof Membrane Manufacturer Warranty

5.8.1.3. Continuance of Warranty

5.8.2. Operations and Maintenance manual/data

5.8.3. Conformance and Compatibility

EPDM Products

5.9.1. Materials

5.9.1.1. EPDM Sheet

5.9.1.2. Energy Performance

5.9.1.3. Seam Tape

5.9.1.4. Lap Splice Adhesive

5.9.1.5. Bonding Adhesive

5.9.1.6. Lap Cleaner, Lap Sealant, and Edge Treatment

5.9.1.7. Water Cutoff Mastic/Water Block

5.9.1.8. Membrane Fasteners and Plates

5.9.1.9. Stress Plates for Fasteners

5.9.1.10. Auxiliary Fasteners

5.9.1.11. Powder-Driven Fasteners

5.9.1.12. Metal Disks

5.9.1.13. Roof Insulation below EPDM Sheet

5.9.1.14. Wood Products

5.9.1.15. Membrane Liner

5.9.1.16. Flashing Cement

5.9.1.17. Roof Joists

5.9.1.18. Uplift Clips

5.9.1.19. Roof Sheathing

5.9.1.20. Continuous Nailer

5.9.1.21. Flashings

5.9.1.22. Roof Drains

EPDM sheet Execution

5.10.1. Examination

5.10.2. Application

5.10.2.1. Special Precautions

5.10.2.2. EPDM Sheet Roofing

5.10.2.3. Application Method

5.10.3. Substrate Preparation

5.10.4. Application of Insulation

5.10.4.1. Protection of Aluminum

5.10.4.2. Connections and Jointing

5.10.4.3. Reglets

5.10.5. Coordination Requirements

5.10.6. Fully Adhered Membrane Application

5.10.6.1. Tape Seams / Lap Splices

5.10.6.2. Adhesive Seams / Lap Splices

5.10.6.3. Perimeter Attachment

5.10.6.4. Securement at Base Tie-In Conditions

5.10.7. Isolated Paver Blocks

5.10.8. Set-On Accessories

5.10.9. Correction of Deficiencies

5.10.10. Clean Up

5.10.11. Protection of Applied Roofing

5.10.11.1. Temporary Flashing for Permanent Roofing

5.10.11.2. Temporary Walkways, Runways, and Platforms

6. Specifications - Asphalt Shingles, Copulas

References Definitions

6.2.1. Top Lap

6.2.2. Head Lap

6.2.3. Exposure

Delivery and Storage Warranties Shingle Manufacturer's Warranty Contractor's Warranty Shingle Products

6.7.1. Materials

6.7.1.1. Shingles

6.7.1.2. Mineral-Surfaced Asphalt Roll Roofing

6.7.1.3. Smooth-Surfaced Asphalt Roll Roofing

6.7.1.4. Underlayment

6.7.1.5. Self-Adhering Membrane

6.7.1.6. Nails for Applying Shingles and Asphalt-Saturated Felt

6.7.1.7. Asphalt Roof Cement

6.7.1.8. Asphalt Primer

6.7.1.9. Ventilators

Shingle Execution

6.8.1. Verification of Conditions

6.8.2. Surface Preparation

6.8.3. Application

6.8.3.1. Underlayment

6.8.3.2. Drip Edges

6.8.3.3. Starter Strip

6.8.3.4. Shingle Courses

6.8.3.5. Hips and Ridges

6.8.3.6. Flashing

7. Field Quality Control

Construction Monitoring Certification of Compliance

8. Roof Drain / Leak Test

9. Information Card

10. Final Cleanup

11. Measurement and Payment

12. Attachments

Attachment 2 – Reference Drawings Attachment 3 – Photos Attachment 4 – Accident Prevention Plan Template Attachment 5 – Quality Control Plan Template Attachment 6 – Submittal Register Attachment 7 – Sketch Flash-1 – Parapet Flashing R1 Attachment 8 – Security Background Check Form

SCOPE OF WORK

1. General Requirements

General The contract of this project is to replace the existing roof on the Operations building’s roof at Allegheny River Lock and Dam #6, including replacing the Penthouse roof (or Cupola) with new wood and shingle roof system. This contract shall include replacing the Penthouse roof, from where the roof attaches to the walls. The Contractor shall ensure the roofs are completely leak free, so that no water can enter the building.

This contract is for the complete removal of the existing rubber sheet roof system and replacement with a fully adhered 0.060 inch EPDM membrane roof system. Work will include, but is not limited to, the removal of the rubber sheeting, associated insulation, flashing, and drains; prepping of the existing sub-surface, and installing a new roofing system. The new roof system shall be a single ply, fully adhered, 0.060 inch EPDM system to include associated insulation, flashing, and drains, and any other necessary work to deliver a fully functioning roof system that is in compliance with the manufacturer’s warranty requirements and the National Roofing Contractors Association (NRCA) roofing manual. In addition to the drains, the drain pipes will be replaced from the drain to one (1) foot below the lower floor’s ceiling. Electrical equipment, conduit, and wires shall be removed as indicated in the photos’ captions, and shall be properly terminated and unpowered. See Attachment 3 Photos The building is located on the Land Wall of the Lock in a Restricted Area, secured behind a security fence. All work shall be performed in a professional manner and in accordance with industry standards. The roof system shall provide a watertight seal with no leaks, especially to the lower floors, thru the deck, parapets, Penthouse, chimney, or drainpipes.

Work will include, but is not limited to:

• Remove existing roof system down to the deck, i.e.-membrane, insulation, drains, etc.

• The Contractor will remove the drainpipes to 1 foot below ceiling surface.

• Remove the plaster/insulation (Dryvit) on the entire inside face of the parapet.

• Remove protrusions thru Penthouse roof to 1 foot below Penthouse roof, per attached pictures.

• Electrical equipment, conduit, and wires shall be removed as indicated in the photos’ captions, and shall be properly terminated and unpowered.

• Once the roof materials have been removed and the deck is bare, the Contractor will conduct an inspection of the roof with the Contracting Officer or their designated representative and submit an inspection report.

• Once the Contracting Officer or their designated representative approves the inspection report, remove Penthouse roof.

• The Contractor will fill any cracks as appropriate.

• Prep and level existing sub-surface.

• The Contractor will install new drainpipes from 1 foot below ceiling surface.

• Prepare all parapets per Sketch Flash-1 - Parapet flashing R1. (Attachment 7)

• Install main roofing system to include, but not limited to, insulation, drains, membrane, flashing.

• Install Penthouse roof to include, but not limited to, underlayment, shingles, flashing, per drawing 038-L9-70/3.3.

• The Contractor shall verify all appropriate areas are flashed properly.

• The Contractor shall conduct roof leak test, and verify there are no leaks.

• The Contractor shall remove debris, equipment, and materials from the site.

The Contractor is responsible for transporting materials and equipment to and from the building’s roof. All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Contracting Officer or their designated representative and Lockmaster. All damage to existing government property because of the Contractor’s work shall be repaired or replaced to the satisfaction of the Contracting Officer or their designated representative. No utilities will be made available in execution of this work.

Labor and materials The contractor shall provide all labor and materials necessary to remove and replace the existing roof coating and must furnish all equipment, labor, and layout of work, supervision, and materials necessary to complete the work as shown and as specified.

The Contractor shall be responsible for transport of materials to and from the site and to prevent removed materials from entering the river. All material provided in the performance of this contract shall be unused and meet the requirements of the specifications. Materials are not to be installed in adverse weather conditions. Details of the building construction are shown on the attached reference drawings. All materials are shall be properly stored, handled, and protected from moisture or other damages.

Liquid components are to be properly mixed prior to application.

Existing Roof — Allegheny River Lock and Dam #6 The project is located at 1258 River Road, Freeport, PA 16229-2023. The main roof is approximately 65 feet by 25 feet, or 1625 square feet, and shall be replaced with EPDM sheeting. The small peaked wooden Penthouse roof, 8 feet by 9 feet, which shall be completely removed and replaced with new wood and asphalt shingles roof system.

Project personnel will designate a laydown area next to the worksite that can be used to store materials. The area shall be cleaned up of debris daily.

1.3.1. New roof details

New flashing, vent covers, and caps shall be installed on all pipe vents protruding from roof surface. All existing roof ventilator shall be removed and reinstalled. Drain covers shall be removed and replaced. The antennas shall be supported in place and remain functional during the roof replacement. The EPDM shall have a proper waterproof seal around all existing items that protrude thru or from the roof.

1.3.2. Protection of Existing Items

The antennas shall be cribbed so the contractor can work underneath, removing roofing material and installing the new roofing. The antennas, and any other surface bearing items, shall have paver blocks on a layer of reinforced membrane or walk-pad applied over the completed roof membrane to protect the new roof, as discussed in Isolated Paver Blocks. Electric or communication lines will stay in place and should not be disturbed.

1.3.3. Wooden Penthouse (Cupola) roof replacement

The Penthouse roof is approximately 8 feet by 9 feet. The existing wooden Penthouse Roof shall be removed and replaced per similar to as existing, see Attachment 2 Reference Drawings-AR6 Powerhouse.pdf, marked Penthouse. Exception: The roof shall be covered with Shingles, per Specifications - Asphalt Shingles, Copulas. Repair or replacement of the walls of the Penthouse is not a part of this contract.

The contractor shall provide all appropriate flashing to create a watertight seal around the perimeter where the Penthouse meets the main roof and chimney, as well as any protrusions. The contractor shall provide a new chimney cap over the top of the chimney. The rubber membrane at this vertical transition shall be kept taught. Tapered insulation or cant strips shall be used for transitioning the rubber membrane from the Penthouse to the main roof and chimney. The Contractor shall provide flashing details for the Penthouse roof and chimney prior to beginning work, per Section Submittals.

The Contractor shall provide details on the chimney cap and ensure its proper dimensions. Once the copula is completed, the Contractor shall test and verify the Penthouse to be leak-free.

1.3.3.1. Lead abatement

It is suspected that the underside of the existing wooden joists and sheeting boards of the Penthouse are coated with lead-based paint (LBP). The wood of the Penthouse Roof shall be tested for lead-based paint prior to the commencement of demolition activities. Based upon these results, a written lead compliance plan shall be submitted prior to commencement of demolition activities and include an appendix of the Contractor’s APP. The Contractor shall use methods to remove and/or abate the materials in accordance with the requirements set forth in EM 385-1-1 06.C and 29 CFR 1926.62.

Disposal All materials removed in the performance of this contract and not reused shall become the property of the contractor and be disposed of offsite in accordance with Federal, State, and Local regulations.

Inspection Once the roof materials have been removed and the deck is bare, the Contractor will conduct an inspection of the entire roof and verify the integrity of the drain lines to ensure they do not leak. This could be as simple as visual inspection (with Contracting Officer or their designated representative present) of the interior of the roof drain pipe.

This should occur as soon as possible once the roof drain strainer is removed. If visual inspection is not possible or if there is still some question, the contractor shall plug the line from below, and fill it with water to ensure there is no interior leakage. The Contractor shall submit an inspection report with the Contractor’s Recommendations with detail sketches, as needed, to the Contracting Officer or their designated representative for review within 24 hours. The Contracting Officer or their designated representative shall then determine whether to continue with the installation or whether modification of the Contract is necessary per the Contractor’s recommendations.

2. Security Requirements-AT/OPSEC

(2.) Access and General Protection and Security Policy and Procedures The contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative).

The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the USACE Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The contractor must submit the full name, Social Security Number/or a valid driver’s license number with state of issue, Date of Birth, and Place of Birth/Citizenship for all associated contractor or subcontractor employees to the USACE Security Office, Joseph M. Bali, 412-395-7162, joseph.m.bali@usace.army.mil. Attachment 8, Security Background Check Form, is to be completed in its entirety and submitted to the USACE Security Office. To protect employee PII, the submission of the completed form through a secure fax is preferred; however, a secured email is acceptable. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.

(2b.) For contractors who do not require Common Access Card (CAC), but require access to a DOD facility or installation

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

(13.) Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

(15.) Pre-screen candidates using E-Verify Program The Contractor must pre‐screen Candidates using the E‐verify Program (https://www.e-mailto:joseph.m.bali@usace.army.mil https://www.e-verify.gov/ verify.gov/) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E‐verify system.

An initial list of verified/eligible Candidates must be provided to the Contracting Officer or their designated representative no later than three (3) business days after the initial contract award.

Employee Identification and Background Check The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working on-site and for requiring each employee engaged on the work to display identification. Identification shall consist of nametags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government-issued photo identification card is required for positive identification. Each employee shall be subject to a background check in accordance with "Homeland Security Presidential Directive (HSPD) 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD- 12).

Only those individual employees that were specifically identified and approved shall be cleared to work on Government property.

3. Safety Requirements In addition to the detailed requirements included in the provisions of this contract, all work shall comply with the most recent edition of the USACE Engineering Manual (EM) 385-1-1, “Safety and Health Requirements Manual”, and all applicable federal, state, and local laws, ordinances, criteria, rules, and regulations. If there are any standards that require interpretation, submit matters to the appropriate administrative agency for resolution before the commencement of work. Where the requirements herein, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.

The Superintendent, QC Manager, and SSHO are subject to dismissal if any of the required regulatory requirements are not being effectively carried out. If dismissal occurs, project work will be stopped and no work shall proceed until a suitable replacement is approved and the appropriate requirements are assured to be effectively carried out.

The latest version of the EM 385-1-1 is available online at:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_ 385-1-1.pdf

Accident Prevention Plan (APP) An Accident Prevention Plan (APP) is a safety and health policy and program document that shall be contract- and/or job-specific. The APP shall be developed by the Contractor and shall interface with the Contractor's overall Safety and Health Program, such that any portions of the Contractor's overall program referenced in the APP shall be included as appropriate.

The Contractor shall develop the APP in accordance with EM 385-1-1, Appendix A, and shall address each of the elements/sub-elements in the outline contained in the appendix in the order that they are provided in the manual, and as supplemented https://www.e-verify.gov/ https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf herein. If an item is not applicable because of the nature of the work to be performed, the Contractor shall state this exception and provide a justification. The APP shall be written in English by the Prime Contractor and shall articulate the specific work, work processes, equipment to be used, and hazards pertaining to the contract. The non-mandatory APP Checklist, Form A-2 of the EM 385-1-1, may be used to ensure each area of required information has been provided as part of the APP to the Contracting Officer.

The Contractor's APP shall be job-specific and must include work to be performed by subcontractors. It is understood that the APP is submitted prior to work starting and some of the project-specific information is not yet known. If sub-contractors and/or suppliers are not known at the time of initial APP submission, the Contractor shall include the following statement in their APP: "The subcontractors for the following defined features of work (DFOW)/activities are not known at this time, but additional information will be submitted to the APP for acceptance prior to the start of any activities listed." All known information shall be provided and additional information submitted to the Contracting Officer for acceptance, as it becomes known.

Once accepted by the Contracting Officer, the APP and all attachments will be enforced as part of the contract. Disregarding provisions of this contract or the accepted APP is a cause for stopping of that portion of the work at the direction of the Contracting Officer until the matter has been rectified.

Each sub-contractor shall be provided a copy of the accepted APP and a copy shall be available on the worksite at all times. A signature log shall be completed by each sub-contractor supervisor attesting that they have read and understand the APP. All sub-contractors shall comply with the APP.

The Contractor shall provide on-going evaluations of the APP throughout the life of the project. Changes, revisions, and updates to the APP shall be reviewed and accepted by the Contracting Officer, project superintendent, SSHO, and Quality Control Manger. An APP template is provided in Attachment 4.

Risk Management Risk management is a business process that includes the identification, assessment, and prioritization of risks, followed by coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of unfortunate events to an acceptable level. A risk management assessment tool, such as activity hazard analysis (AHA), job safety analysis (JSA), or job hazard analysis (JHA) shall be developed by the contractor performing the work for each activity, task, or defined feature of work (DFOW). The assessment shall identify the work sequence, specific anticipated hazards, site conditions, equipment, materials, personnel, and the control measures to be implemented to control the hazards. A Risk Assessment Code (RAC) shall be assigned to each job step based on the residual risk remaining after controls are implemented. A RAC shall then be assigned to the overall activity consistent with the highest RAC identified for the job steps. If developed by a subcontractor, the Prime Contractor shall review and approve the assessment before submission to the Contracting Officer. The Risk Assessment shall be signed by the SSHO, Superintendent, QC Manager, and any subcontracting Foreman performing the work. If

Qualified or Competent Persons are required for a particular activity, they shall be identified and included in the assessment, and their competency/qualification identified.

Work shall not begin until the assessment has been accepted by the Contracting Officer and discussed with all engaged in the activity.

These risk assessment tools are considered living documents and shall be updated as needed. If the RAC increases from what was originally accepted by the Contracting Officer, the assessment shall be re-submitted for acceptance prior to work proceeding.

Changes that do not increase the RAC are not required to be resubmitted for acceptance.

The risk assessment shall be developed in accordance with EM 385-1-1 Section 1, or as specified by the Contracting Officer. Risk assessments shall be submitted for review at least 15 working days prior to the start of the activity, task, or defined feature of work is set to begin. The Government reserves the right to require the Contractor to revise and resubmit any documents if they fail to effectively identify the work sequence, specific anticipated hazards, site conditions, equipment, materials, personnel, and the control measures to be implemented.

Each employee performing work as part of an activity, task, or defined feature of work shall review the risk assessment for the activity and sign the signature log designated for the assessment prior to beginning work. A signature log shall be maintained for each risk assessment.

Completed risk assessments need not be submitted at the time of the APP submission, but the Contractor shall identify each activity, task, or DFOW that will require a risk assessment to be completed at the time of submission.

Implementation of Safety and Occupational Health (SOH) Program The Contractor shall employ a minimum of one Competent Person at each project site to function as the primary Site Safety and Health Officer (SSHO) to implement and administer the Contractor’s safety program and the Government-accepted Accident Prevention Plan (APP). The SSHO is a full-time responsibility and shall be an employee other than the supervisor [unless specified differently in the contract and coordinated with the local SOH Office], that reports directly to a senior project, or corporate, official.

The SSHO shall be present at the project site and be located so they have full mobility and reasonable access to all major work operations during the shift. The SSHO shall meet all training and experience qualifications as outlined in EM 385-1-1 Section 01, Paragraph A.17.

For projects with multiple shifts, or in instances where the SSHO is off-site for a period longer than 24 hours, an Alternate SSHO shall be assigned to ensure coverage for the project at all times work activities are conducted. The alternate SSHO shall meet the same requirements and assume the responsibilities of the primary SSHO. The alternate SSHO shall be identified in the applicable AHAs for the activities they are responsible for overseeing.

When the primary SSHO is temporarily, up to 24 hours, off-site, a Designated Representative (DR) may be used in lieu of an Alternate SSHO. The DR shall be on the project site at all times when work is being performed in the absence of the primary

SSHO. DRs can be collateral duty safety personnel, with safety duties assigned in addition to their full-time occupation. DRs shall perform safety program tasks as designated by the SSHO, and report all findings to the SSHO. DRs shall also be appointed when activities, tasks, or DFOWs contain multiple sites and are more than 45 minutes travel time from the primary SSHO's duty location. The DR shall be identified in the applicable AHAs for the activities they are responsible for overseeing.

Note: DRs may not be assigned to projects or activities that have a risk assessment code (RAC), as identified on the AHA for the activity, level of high or extremely high.

The SSHO may also serve as the Quality Control Manager. The SSHO may not serve as the Superintendent.

SSHOs shall attend the pre-construction conference, pre-work meetings, including preparatory and periodic in-progress meetings.

Mishap Reporting A mishap is any unplanned, undesired event that occurs during the course of work being performed, to include, accidents, incidents, and near misses. All mishaps shall be reported to the Contracting Officer within 24-hours after notification from the affected employee(s). Contractors are responsible for maintaining an OSHA Log of Work- Related Injuries and Illnesses (Form 300) and complying with all reporting and recordkeeping requirements specified in 29 Code of Federal Regulations (CFR) 1904.

Hazardous Material Exclusion Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with EM 385-1-1 such as, nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury, polychlorinated biphenyls (PCBs), Diisocyanates, lead, lead-based paint (LBP), and hexavalent chromium, are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. Low mercury lamps used within fluorescent lighting fixtures are allowed as an exception without further Contracting Officer approval. Notify the Radiation Safety Officer (RSO), Safety Office, and the Contracting Officer prior to excepted items of radioactive material and devices being brought on site.

Unforeseen Hazardous Material USACE shall identify and communicate all known hazardous materials such as Polychlorinated biphenyls (PCBs), lead paint, asbestos, and other OSHA regulated chemicals (i.e. 29 CFR 1910.1000) in which the Contractor may come into contact during the course of activities. If material is encountered that was not indicated, but may be hazardous to human health upon disturbance, that portion of the work shall stop and the Contracting Officer immediately notified. The Government will determine within 14 days of notification if the material is or is not considered hazardous. If the material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If the material is determined to be hazardous or dangerous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4, Changes and FAR 52.236-2, Differing Site Conditions.

Damage Reports All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Contracting Officer and Lockmaster.

Minimum Personal Protective Equipment Personal Protective Equipment (PPE) is governed in all areas by the nature of work personnel are performing based on conducted hazard evaluations. AHAs shall detail the PPE to be used that will provide appropriate protection for the work to be performed when required. All PPE shall be provided by the Contractor, used, and maintained in a sanitary and reliable condition whenever the hazard dictates use.

Mandatory PPE, at minimum, shall include hardhat (construction sites), long pants, short sleeve shirts, and leather or protective work shoes or boots. Personal Floatation Devices (PFDs) shall be worn at all times when working above or near water in which other fall protection methods do not provide the appropriate protection

Designated Persons The Contractor shall provide Qualified and/or Competent Persons in accordance with EM 385-1-1, OSHA, ANSI, and where specified herein. All Qualified and Competent Persons shall be designated in writing and shall meet the requirements for the specific activity for which they are designated.

Competent Persons identified in the Contractor’s Safety and Health Program and Government-accepted APP shall be onsite at all times when the work that presents the hazards associated with the competency is being performed.

Certificates of Qualification/Competency shall be provided to the Contracting Officer for review and provided as part of the applicable AHAs and appendices of the APP.

4. Project/Site Conditions

Reference Drawings Reference Drawings provided in Attachment 2 show existing conditions to the best knowledge of the Government. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on reference drawings, and it shall be the responsibility of the Contractor, whenever necessary, to verify all elevations and the dimensions by measurements in the field. All elevations are referenced to the local datum used for the original construction of the structure. The Contractor shall verify elevations and dimensions before laying out the work. The Contracting Officer shall be notified of any discrepancies prior to commencing work.

Verification of Field Conditions The Contractor shall verify all dimensions and conditions in the field and shall advise the Contracting Officer of any discrepancy before performing any work.

Work Areas Transport of materials and equipment shall be the responsibility of the Contractor. The

Contractor shall be fully responsible for determining the methods used to transport materials and equipment to and from the areas as well as the removal of waste materials from such spaces. The Contractor shall ensure that his operations will not interfere with the operation of the project or the duties of project personnel. Work area will be coordinated and agreed on with the Lockmaster, dependent on other contracts being carried out at the time. (See POCs)

Time of Performance The Contractor shall notify the Points of Contact (See POCs) prior to start of work. The Contractor shall schedule work through the POCs. The Contractor shall coordinate work with the POCs NLT 3 days before starting work. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work. The Contractor shall confine all operations at the work site between the hours of 7:30 AM and 4:00 PM, Monday through Friday, unless otherwise approved. Work will not be permitted on weekends or Federal holidays unless otherwise approved. A list of Federal holidays, can be found at https://www.opm.gov/policy-data-oversight/pay-leave/pay-administration/fact-sheets/holidays-work-schedules-and-pay.

Period of Performance (PoP) The Contractor shall complete all work within 365 calendar days after receipt of Notice to Proceed.

Permits The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required federally and by the State of Pennsylvania.

Protection of Government Property The contractor shall protect all government property during the performance of this contract. All damage to existing government property because of the Contractor’s work shall be repaired or replaced to the satisfaction of the Contracting Officer. Building interior shall be protected at all times. Work area shall be cleaned by the contractor after construction is complete.

Inspections and Acceptance of Work Notwithstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer. The Contracting Officer shall be the individuals solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.

Project Government personnel contacts A pre-quote site visit can be arranged by contacting the Lockmaster. Participation is highly encouraged. Pre-work notifications are required. Coordination with the projects for early planning and tentative schedule compilation purposes and schedule submission is expected. Advance notice to the Lock and Dam personnel at least 30 days prior to the inspection visits is required. The appropriate Government contact is listed by location, along with their telephone number, as shown in section POCs.

Points of Contact (POCs) Prior to commencement of any work being performed on site, the contractor shall participate in a Pre-work Meeting with the Contracting Officer or their designated representative and the Lockmaster on-site.

• Upper Allegheny Locks and Dams Lockmaster – Jeff Dudley, 724-224-2666, Jeffery.C.Dudley@usace.army.mil

• Administrative Contracting Officer (ACO) – Kevin Cannon, 412-395-7658, Kevin.P.Cannon@usace.army.mil

SPECIFICATIONS

5. Specified Requirements

References The publications listed below form a part of this specification to the extent referenced.

The publications are referred to within the text by the basic designation only. Latest reference version should always be used.

• American Society of Civil Engineers (ASCE)

• ASCE 7 - Minimum Design Loads for Buildings and Other Structures

• ASTM International (ASTM)

• ASTM D4637/D4637M - EPDM Sheet Used in Single-Ply Roof Membrane

• ASTM D4811/D4811M - Standard Specification for Non-vulcanized (Uncured)

Rubber Sheet Used as Roof Flashing

• ASTM D6369 - Design of Standard Flashing Details for EPDM Roof Membranes

• ASTM E108 - Fire Tests of Roof Coverings

• FM GLOBAL (FM)

• FM 4470 - Single-Ply, Polymer-Modified Bitumen Sheet, Built-up Roof (BUR), and Liquid Applied Roof Assemblies for Use in Class 1 and Noncombustible Roof Deck Construction

• FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

• National Roofing Contractors Association (NRCA)

• NRCA Roof Man - The NRCA Roofing Manual Single Ply Roofing Industry

(SPRI)

• ANSI/SPRI RD-1 - Performance Standard for Retrofit Drains

• U.S. Department of Energy (DOE)

• Energy Star - Energy Star Energy Efficiency Labeling System (FEMP)

• Underwriters Laboratories (UL)

• UL 790 - Standard Test Methods for Fire Tests of Roof Coverings

• UL RMSD - Roofing Materials and Systems Directory

• International Building Code (IBC) mailto:Kevin.P.Cannon@usace.army.mil http://www.approvalguide.com/

Submittals The Contractor shall provide submittals for Government Approval. All items that will be incorporated into the work shall meet the Buy American Act, FAR 52.225-11. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications. It will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work. The Government has the right to reject defective supplies or services within a reasonable time after delivery by written notification to the Contractor.

The Contractor shall, in such event, promptly replace, correct, or repair the rejected supplies or services at the Contractor’s expense. The bidder shall submit for approval marked manufacturer literature or cut sheets with materials selection, including required product specifications clearly identified on the submittal.

5.2.1. Manufacturer's Literature

For all proposed materials to be furnished under this contract, the Contractor shall furnish manufacturer’s descriptive literature or catalog cuts, illustrations, specifications, and other data to show the proposed materials meet the specified requirements.

5.2.2. Required Submittals

• SD-01 Preconstruction Submittals o For all proposed materials to be furnished under this contract the Contractor shall furnish manufacturer’s descriptive literature or catalog cuts, illustrations, specifications, and other data to show the proposed materials meet the specified requirements.

o Quality Control Plan (QCP) The contractor shall complete and submit a Quality Control Plan. A QCP template is provided in Attachment 5. There shall be one qualified Superintendent and one qualified Quality Control inspector. The Safety person and the Quality Control inspector may be the same person and may be the DR. The quality control system shall consist of plans, procedures, and organization necessary to produce a product that complies with the contract requirements. Cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer.

The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications. Superintendent and QC shall be on site at all times work is being done.

o Accident Prevention Plan (APP) Fall Protection Plan Lead Compliance Plan Demo Plan o Project Schedule Project Schedule must be provided in MS Project or Excel formats. Schedule must be submitted 2 weeks after Notice to Proceed (NTP), at least 2 weeks prior to the proposed start date, and updated at least weekly.

o Work Plan Submit schedule to complete work within approximately twelve (12) consecutive days.

Submit a written plan describing in detail all phases of roofing operations. Address work sequencing, surface preparation, roofing system application, time projections, as well as how each step will be controlled, tested, and evaluated. Address safety measures; work scheduling around weather, how the roof will be protected from weather while being worked on, and record keeping. Assign one supervisor to the job who is to remain at the site throughout all phases of work and who is to act as the contractor's primary point of contact. Identify this person in the submitted schedule. The Contractor shall submit wood materials, types, sizes, nailing, and anchorage details.

• SD-03 Product Data

For evaluation purposes, the bidder shall submit for approval product literature for the materials to be used. Product data shall include catalog cuts, specifications, or other descriptive data for materials proposed for use, including copies of Manufacturer’s warranties. All appropriate descriptive data shall be clearly indicated on the submittal.

o Safety Data Sheets (SDS) for materials If any hazardous chemicals are to be used and/or brought onto the project site, the Contractor shall submit a written Hazard Communication Program and submit it as an appendix to their overall APP. In addition to the written program, the Contractor shall provide Safety Data Sheets (SDSs) for the applicable hazardous chemicals.

o Energy Star Label for Asphalt Shingles

• SD-05 Design Data o Contractor shall provide details for:

Flashing around Penthouse perimeters, roof, and around chimneys Cap flashing on top of Dryvit Replace drain inserts and new pipe to 1 foot below ceiling surface New chimney caps and their installation

• SD-06 Test Reports o Inspection Report Once the roof is bare, the Contractor shall provide an Inspection Report. This Inspection Report shall give the condition of the roof and any recommendations of the Contractor.

• SD-07 Certificates o Warranty Certificates Must include Manufacturer’s warranties and Installer’s warranties.

o Qualifications of Installer System installer shall be approved, authorized, or licensed in writing by the system manufacturer and shall have at least the minimum years’ experience required by the manufacturer as an approved, authorized, or licensed installer with that manufacturer and be approved at a level capable of providing the specified warranty.

o Credentials of Designated Persons to Include: SSHO, DR, CP, Fall Protection o Manufacturer’s Certificate

• SD-08 Manufacturer's Instructions Application o Application Method, including pattern and frequency of application Include detailed application instructions and standard manufacturer drawings altered as required by these specifications. Explicitly identify in writing, differences between manufacturer's printed instructions and the specified requirements.

o Activity Hazard Analyses (AHAs) o Application-Shingles o Standard details for the system

Contractor submit standard details for their system of how their roof materials are to be applied. This submittal shall include how various roof penetrations are to be constructed, how flashing is to be installed along parapet walls and along gravel stops, and how roof ventilators are to be flashed, etc.

• SD-11 Closeout Submittals Warranty o Contractor's Warranty o Warranty information and Contact information o Instructions to Government Personnel

All contractor data submissions shall be submitted to:

U.S. Army Corps of Engineers Pittsburgh District

Attention: ECC-O (Kevin Cannon) 3510 Grand Ave Main Building

Pittsburgh, PA 15225 Phone: 412-395-7658

Quality Assurance

5.4.1. Daily Inspection Report

Submit one copy of the daily inspection report to the Contracting Officer within 24 hours of the date recorded.

5.4.2. Pre-roofing Conference

After approval of submittals and before performing roofing system installation work, hold a Pre-roofing conference to review the following:

• Drawings, specifications, and submittals related to the roof work;

• Roof system components installation;

• Contractor's plan for coordination of the work of the various trades involved in providing the roofing system and other components secured to the roofing;

• Quality control plan (QCP) for the roof system installation;

• Safety requirements; and

• Proposed schedule.

Coordinate pre-roofing conference scheduling with the Contracting Officer. The conference must be attended by the Contractor, the Contracting Officer's designated personnel, personnel directly responsible for the installation of roofing and sheet metal work, mechanical and electrical work, and other trades interfacing with the roof work.

Before beginning roofing work, provide a copy of meeting notes and action items to all attending parties. Note action items requiring resolution prior to start of roof work.

5.4.3. Fire Resistance

Complete roof covering assembly must:

• Be Class A rated in accordance with ASTM E108, FM 4470, or UL 790; and be listed as part of Fire-Classified roof deck construction in the UL RMSD or Class I roof deck construction in the FM APP GUIDE.

FM or UL approved components of the roof covering assembly must bear the appropriate FM or UL label.

Delivery, Storage, and Handling

5.5.1. Delivery

Deliver materials in their original, unopened containers or wrappings with labels intact and legible. Where materials are covered by a referenced specification number, the labels must bear the specification number, type, class, and shelf life expiration date where applicable. Deliver materials in sufficient quantity to allow continuity of work.

5.5.2. Storage

Store and protect materials from damage and weather in accordance with manufacturer's printed instructions, except as specified otherwise. Keep materials clean and dry. Store and maintain adhesives, sealants, primers and other liquid materials in accordance with manufacturers’ recommendations. Utilize insulated hot boxes or other enclosed warming devices in cold weather. Mark and remove damaged materials from the site. Use pallets to support and canvas tarps to completely cover material materials stored outdoors. Do not use polyethylene as a covering. Storage of materials on the roof will not be permitted. Locate materials temporarily in approved areas. Remove unused materials from the roof at the end of each day’s work.

5.5.3. Handling

Prevent damage to edges and ends of roll materials. Do not install damaged materials in the work. Select and operate material handling equipment so as not to damage materials or applied roofing. Do not use materials contaminated by exposure or moisture. Remove contaminated materials from the site. When hazardous materials are involved, adhere to the special precautions of the manufacturer. Adhesives may contain petroleum distillates and may be extremely flammable; prevent personnel from breathing vapors, and do not use near sparks or open flame.

Environmental Requirements The temperature of the roofing materials shall be as required by the manufacturer. Do not install EPDM sheet roofing during high winds or inclement weather, or when there is ice, frost, moisture, or visible dampness on the substrate surface, or when condensation develops on surfaces during application.

Unless recommended otherwise by the EPDM sheet manufacturer and approved by the Contracting Officer, do not install EPDM sheet when air temperature is below 40 degrees F or within 5 degrees F of the dew point. Follow manufacturer's printed instructions for installation during cold weather conditions.

Wind conditions shall be suitable for installation of insulation: Wind chill may affect the proper application temperatures of materials; hot materials may be blown about, creating safety dangers; insulation boards may become difficult and hazardous to handle; wrappers, coverings, and other debris may become airborne, and possibly contaminate laps and seams.

Sequencing Coordinate the work with other trades to ensure that components that are to be secured to or stripped into the roofing system are available and that permanent flashing and counter-flashing are installed as the work progresses. Ensure temporary protection measures are in place to preclude moisture intrusion or damage to installed materials.

Certificates

5.8.1. Warranty

Submit sample certificates for approval.

Provide roof system material and workmanship warranties meeting specified requirements. Provide revision or amendment to standard membrane manufacturer warranty as required to comply with the specified requirements.

5.8.1.1. Roofing System Installer Warranty

The roof system installer must warrant for a period of two years, the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, attachments, and sheet metal installation integral to a complete watertight roof system assembly. Write the warranty directly to the Government.