This Specifications and Contract document pertains to Project No. 32205, Concrete Pavement Repair 2026, managed by the Jefferson City Department of Public Works in Missouri. The project involves the furnishing of all material, labor, and equipment to remove and replace existing concrete pavement, curbing, and sidewalk ramps, along with providing associated traffic control. Sealed bids were due on Thursday, July 23, 2026, at 1:30 P.M., with bids to be opened and read aloud in the Council Chambers on the same date. A pre-bid conference was scheduled for 10:00 A.M. on Thursday, July 16, 2026, in the Thomas Jefferson Conference Room at City Hall, 320 E. McCarty Street, Jefferson City, MO 65101. Plans were available electronically at no cost through https://jeffersoncitymo.bonfirehub.com or as paper copies for a non-refundable deposit of $20.00. The contract duration is specified as 60 working days from the date the contractor receives the order to proceed. The itemized bid form includes 12 line items, including mobilization, traffic control, inlet protection, subgrade stabilization, curbing, concrete pavement (various configurations), detectable warning panels, street light relocation, and seeding and mulching.
Bidders were required to submit a certified check or bid bond equal to five percent (5%) of the total bid amount, along with a one-year Performance and Payment Bond equivalent to 100 percent (100%) of the contract price. Prevailing wage rates established by the Missouri Division of Labor Standards apply to all work, with specific hourly rates detailed in Annual Wage Order No. 33, Section 026, for Cole County. Liquidated damages are assessed at $500.00 per calendar day if the project is not completed within the contract time. The City reserves the right to reject any and all bids and to waive informalities. Contractors are required to comply with multiple requirements, including provision of Worker's Compensation Insurance, Comprehensive General Liability Insurance with minimum coverage of $500,000 per occurrence, Federal Work Authorization Program participation, OSHA construction safety training, and a Minority Business Enterprise utilization goal of 2.12 percent of the contract amount. The City's sales tax exemption is available for purchases exceeding $500 from individual suppliers.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jefferson City Department of Public Works
July, 2026
SPECIFICATIONS AND CONTRACT DOCUMENTS
PROJECT NO. 32205
Concrete Pavement Repair 2026
TABLE OF CONTENTS
Advertisement for Bids
Notice to Bidders
Information for Bidders
Bid Form *
Bid Bond *
Anti-Collusion Statement *
Contractor's Affidavit *
Minority Business Enterprise Statement
Minority Business Utilization Agreement *
Affidavit of Compliance with Prevailing Wage Law
Prevailing Wage Determination
Affidavit of Compliance Public Works Contracts Law
Federal Work Authorization Program Affidavit
Construction Contract
Performance, Payment, and Guarantee Bond
General Provisions
Special Provisions
Attachments
Addendums ( If Any )
(* INDICATES THIS ITEM INCLUDED IN BID PACKET FOR SUBMISSION OF BID)
ADVERTISEMENT FOR BIDS
Sealed bids will be received at the office of the Purchasing Agent, 320 East McCarty Street, Jefferson City, Missouri 65101, until 1:30 P.M., on Thursday, July 23, 2026. The bids will be opened and read aloud in the Council Chambers at 1:30 P.M.
on that same day.
The proposed work for the project entitled "Project No. 32205, Concrete Pavement Repair 2026" will include the furnishing of all material, labor, and equipment to remove and replace existing concrete pavement, curbing, and sidewalk ramps and to provide associated traffic control.
A pre-bid conference will be held at 10:00 A.M., on Thursday, July 16, 2026 in the Thomas Jefferson Conference Room of City Hall, 320 E, McCarty Street, Jefferson City, MO 65101. All prospective bidders are urged to attend.
Plans may be obtained electronically, at no cost, at the following site:
https://jeffersoncitymo.bonfirehub.com. Alternatively, paper copies of the plans and specifications may be obtained for a non-refundable deposit of Twenty Dollars ($20.00) from the Director of Public Works, 320 East McCarty Street, Jefferson City, Missouri.
The contract will require compliance with the wage and labor requirements and the payment of minimum wages in accordance with the Schedule of Wage Rates established by the Missouri Division of Labor Standards.
The City reserves the right to reject any and all bids and to waive informalities therein, to determine which is the lowest and best bid and to approve the bond.
Any questions that arise as a result of this advertisement should be directed to the City of Jefferson Department of Public Works at (573) 634-6410.
Individuals should contact the ADA Coordinator at (573) 634-6570 to request accommodations or alternative formats as required under the Americans with Disabilities Act. Please allow 3 business days to process the request.
CITY OF JEFFERSON
Megan Stephenson Purchasing Agent
Publication Date Wednesday, July 8, 2026
NOTICE TO BIDDERS
Sealed bids will be received at the Office of the Purchasing Agent, City Hall, 320 East McCarty Street, Jefferson City, Missouri, until 1:30 P.M. on Thursday, July 23, 2026. The bids will be opened and read aloud in the Council Chambers at 1:30 P.M.
on that same day.
The proposed work for the project entitled "Project No. 32205, Concrete Pavement Repair 2026" will include the furnishing of all material, labor, and equipment to remove and replace existing concrete pavement, curbing, and sidewalk ramps and to provide associated traffic control.
A pre-bid conference will be held at 10:00 A.M., on Thursday, July 16, 2026 in the Thomas Jefferson Conference Room of City Hall, 320 E. McCarty Street, Jefferson City, MO 65101. All prospective bidders are urged to attend.
All equipment, material, and workmanship must be in accordance with the plans, specifications, and contract documents on file with the Director of Public Works, Jefferson City, Missouri.
Plans may be obtained electronically, at no cost, at the following site:
https://jeffersoncitymo.bonfirehub.com. Alternatively, paper copies of the plans and specifications may be obtained for a non-refundable deposit of Twenty Dollars ($20.00) from the Director of Public Works, 320 East McCarty Street, Jefferson City, Missouri.
A certified check on a solvent bank or a bid bond by a satisfactory surety in an amount equal to five (5) percent of the total amount of the bid must accompany each proposal.
A one-year Performance and Guarantee Bond is required.
The owner reserves the right to reject any or all bids and to waive informalities therein to determine which is the lowest and best bid and to approve the bond.
CITY OF JEFFERSON, MISSOURI
Kyle Bruemmer, P. E.
Director of Public Works
INFORMATION FOR BIDDERS
IB-1 SCOPE OF WORK
The work to be done under this contract includes the furnishing of all technical personnel, labor, materials, and equipment required to perform the work included in the project entitled "Project No. 32205, Concrete Pavement Repair 2026" in accordance with the plans and specifications on file with the Department of Public Works.
The proposed work for this project will include the furnishing of all material, labor, and equipment to remove and replace existing concrete pavement, curbing, and sidewalk ramps and to provide associated traffic control.
IB-2 INSPECTION OF PLANS, SPECIFICATIONS, AND SITE OF WORK
The bidder is required to examine carefully the site of the proposed work, the bid, plans, specifications, supplemental specifications, special provisions, and contract documents before submitting a bid. Failure to do so will not relieve a successful bidder of the obligation to furnish all materials and labor necessary to carry out the provisions of the contract.
IB-3 INTERPRETATION OF CONTRACT DOCUMENTS
If the bidder has any questions which arise concerning the true meaning or intent of the Plans, Specifications or any part thereof, which affect the cost, quality, quantity, or character of the project, he shall request in writing, at least five (5) days prior to the date fixed for the bid opening, that an interpretation be made and an addendum be issued by the City, which shall then be delivered to all bidders to whom Plans and Specifications have been issued.
All addenda issued shall become part of the contract documents. Failure to have requested an addendum covering any questions affecting the interpretation of the Plans and Specifications shall not relieve the Contractor from delivering the completed project in accordance with the intent of the Plans and Specifications to provide a workable project.
IB-4 QUALIFICATIONS OF BIDDERS
The City of Jefferson may make such investigations as deemed necessary to determine the ability of the bidder to perform the work and the bidder shall furnish to the City all such information and data for this purpose as the City may request. The City reserves the right to reject any bid if the evidence submitted by the bidder or investigation of such bidder fails to satisfy the City that such bidder is properly qualified to carry out the obligations of the Contract and to complete the work contemplated therein.
IB-5 EQUIVALENT MATERIAL
Wherever definite reference is made in these Specifications to the use of any particular material or equipment, it is to be understood that any equivalent material or equipment may be used which will perform adequately the duties imposed by the general design, subject to the approval of the City.
IB-6 BID SECURITY
Each bid must be accompanied by a certified check or bid bond made payable to the City of Jefferson for five percent (5%) of the amount of the bid. Bid securities will be returned after award of the contract except to the successful bidder.
Should the successful bidder fail or refuse to execute the bond and the contract required within seven (7) days after he has received notice of acceptance of his bid, he shall forfeit to the City as liquidated damages for such failure or refusal, the security deposited with his bid.
IB-7 PREPARATION OF BIDS
Bids must be made upon the prescribed forms attached in these Contract Documents. Only sealed bids will be considered, all bids otherwise submitted will be rejected as irregular.
All blank spaces in the bid must be filled in and no change shall be made in the phraseology of the bid, or addition to the items mentioned therein. Any conditions, limitations or provisions attached to bids will render them informal and may be considered cause for their rejection.
Extensions of quantities and unit prices shall be carried out to the penny.
IB-8 PRICES
The price submitted for each item of the work shall include all costs of whatever nature involved in its construction, complete in place, as described in the Plans and Specifications.
Section 144.062 RSMo provides that the City's sales tax exemption may be used for the purchase of goods and materials for this project. The contract for the project will authorize and direct the Contractor to utilize the City's sales tax exemption in the purchase of goods and materials for the project. This provision shall apply to only those purchases totaling over $500 from an individual supplier.
All sales taxes on those items which do not qualify for the use of the City's sales tax exemption and for which sales tax might lawfully be assessed against the City are to be paid by the Contractor from the monies obtained in satisfaction of the Contract. It being understood by the bidder, that the bid prices submitted for those items shall include the cost of such taxes.
IB-9 APPROXIMATE QUANTITIES
In cases where any part or all of the bidding is to be received on a unit price basis, the quantities stated in the bid will not be used in establishing final payment due the successful Contractor. The quantities stated on which unit prices are so invited are approximate only and each bidder shall make his own estimate from the plans of the quantities required on each item and calculate his unit price bid for each item accordingly. Bids will be compared on the basis of number of units stated in the bid. Such estimated quantities, while made from the best information available, are approximate only. Payment of the Contract will be based on actual number of units installed on the complete work.
IB-10 LUMP SUM ITEMS
Payment for each lump sum item shall be at the lump sum bid for the item, complete in place, and shall include the costs of all labor, materials, tools and equipment to construct the item as described herein and to the limits shown on the Plans.
IB-11 SUBMISSION OF BIDS
The Bid and the Bid Security guaranteeing the same shall be placed in a sealed envelope and marked "Project No. 32205, Concrete Pavement Repair 2026", or bids may be submitted electronically through the Bonfirehub site.
IB-12 ALTERNATE BIDS
In making the award, if alternate bids have been requested, the alternate bid which will be in the best interest of the City will be used.
IB-13 WITHDRAWAL OF BIDS
If a bidder wishes to withdraw his bid, he may do so before the time fixed for the opening, without prejudice to himself. No bidder may withdraw his bid for a period of ninety (90) days after the scheduled closing time for the receipt of bids.
No bids received after the time set for opening for bids will be considered.
IB-14 RIGHT TO REJECT BIDS
The City reserves the right to reject any or all bids, to waive any informality in the bids received, or to accept the bid or bids that in its judgement will be in the best interests of the City of Jefferson.
IB-15 AWARD OF CONTRACT
If, within seven (7) days after he has received notice of acceptance of his bid, the successful bidder or bidders shall refuse or neglect to come to the office of the Director of Public Works and to execute the Contract and to furnish the required Performance and Payment Bonds and Insurance, properly signed by the Contractor and the Surety and Sureties satisfactory to the City of Jefferson as hereinafter provided, the bidder or bidders shall be deemed to be in default and shall forfeit the deposit.
IB-16 PERFORMANCE AND PAYMENT BOND
A Performance and Payment Bond in an amount equivalent to one hundred percent (100%) of the Contract price, must be furnished and executed by the successful bidder or bidders.
A form for the bidders use is contained in these Contract Documents.
The issuing Surety shall be a corporate Surety Company or companies of recognized standing licensed to do business in the State of Missouri and acceptable to the City of Jefferson.
IB-17 INDEMNIFICATION AND INSURANCE
The Contractor agrees to defend, indemnify and hold harmless the City from all claims and suits for loss of or damage to property, including loss of all judgments recovered therefore, and from all expense in defending said claims, or suits, including court costs, attorney fees and other expense caused by any act or omission of the Contractor and/or his subcontractors, their respective agents, servants or employees.
The Contractor shall be required to provide the City of Jefferson with a Certificate of Insurance outlining the coverage provided.
IB-18 BID SECURITY RETURNED TO SUCCESSFUL BIDDER
Upon the execution of the Contract and approval of Bond, the Bid Security will be returned to the bidder unless the same shall have been presented for collection prior to such time, in which case the amount of the deposit will be refunded by the City.
IB-19 NONDISCRIMINATION IN EMPLOYMENT
Contracts for work under this bid will obligate the Contractor and subcontractors not to discriminate in employment practices.
IB-20 PREVAILING WAGE LAW
The principal contractor and all subcontractors shall pay not less than the prevailing wage hourly rate for each craft or type of workman required to execute this contract as determined by the Department of Labor and Industrial Relations of Missouri, pursuant to Sections
290.210 through 290.340 inclusive of the Revised Statutes of Missouri, 1994 as amended.
(See Determination included herewith.)
IB-21 GUARANTEE
The Contractor shall guarantee that the equipment, materials and workmanship furnished under this contract will be as specified and will be free from defects for a period of one year from the date of final acceptance. In addition, the equipment furnished by the Contractor shall be guaranteed to be free from defects in design.
Within the guarantee period and upon notification of the Contractor by the City, the Contractor shall promptly make all needed adjustments, repairs or replacements arising out of defects which, in the judgment of the City become necessary during such period.
The cost of all materials, parts, labor, transportation, supervision, special tools, and supplies required for replacement of parts, repair of parts or correction of abnormalities shall be paid by the Contractor or by his surety under the terms of the Bond.
The Contractor also extends the terms of this guarantee to cover repaired parts and all replacement parts furnished under the guarantee provisions for a period of one year from the date of installation thereof.
If within ten days after the City gives the Contractor notice of defect, failure, or abnormality of the work, the Contractor neglects to make, or undertake with due diligence to make, the necessary repairs or adjustments, the City is hereby authorized to make the repairs or adjustments itself or order the work to be done by a third party, the costs of the work to be paid by the Contractor.
In the event of an emergency where, in the judgment of the City delays would cause serious loss or damage, repairs or adjustments may be made by the City or a third party chosen by the City without giving notice to the Contractor, and the cost of the work shall be paid by the Contractor or by his surety under the terms of the Bond.
IB-22 WORK SCHEDULE
To insure that the work will proceed continuously through the succeeding operations to its completion with the least possible interference to traffic and inconvenience to the public, the Contractor shall, at the request of the City, submit for approval a complete schedule of his proposed construction procedure, stating the sequence in which various operations of work are to be performed.
IB-23 CONTRACT TIME
The contract time shall be 60 working days.
IB-24 LIQUIDATED DAMAGES
Liquidated damages shall be assessed at the rate of Five Hundred Dollars ($500.00) per calendar day until the work is complete, should the project not be completed within the contract time.
IB-25 POWER OF ATTORNEY
Attorneys-in-fact who sign bid bonds or contract bonds must file with each bond a certified and effectively dated copy of their power of attorney.
IB-26 QUESTION PERIOD
All questions concerning the project must be submitted five days prior to the bid opening.
Answers to the submitted questions, minutes from the Pre-Bid Meeting, and other relevant information or corrections will then be issued as an addendum to this agreement.
IB-27 BID PACKET
Each bid must be submitted on the prescribed forms and contain certain certifications and documentation.
Each bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, the bidder's address, and the name of the project for which the bid is being submitted. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as follows:
Purchasing Agent City of Jefferson, MO 320 E. McCarty Street Jefferson City, MO 65101
For the convenience of bidding this project, a "BID PACKET" has been included with the project manual. This packet contains the necessary forms to be submitted with the bid proposal. The contents of this packet include the following:
1) BID FORM
2) BID BOND
3) ANTI-COLLUSION STATEMENT
4) CONTRACTOR'S AFFIDAVIT
5) MINORITY BUSINESS UTILIZATION AGREEMENT
END OF INFORMATION FOR BIDDERS
BID FORM
Name of Bidder______________________________________________________________
Address of Bidder_____________________________________________________
To: CITY OF JEFFERSON 320 East McCarty Street Jefferson City, Missouri 65101
THE UNDERSIGNED BIDDER, having examined the plans, specifications, regulations of the Contract, Special Conditions, other proposed contract documents and all addenda thereto; and being acquainted with and fully understanding (a) the extent and character of the work covered by this Bid; (b) the location, arrangement, and specified requirements for the proposed work; (c) the location, character, and condition of existing streets, roads, highways, railroads, pavements, surfacing, walks, driveways, curbs, gutters, trees, sewers, utilities, drainage courses, structures, and other installations, both surface and underground which may affect or be affected by the proposed work; (d) the nature and extent of the excavations to be made and the type, character, and general condition of materials to be excavated; (e) the necessary handling and rehandling of excavated materials; (f) the location and extent of necessary or probable dewatering requirements; (g) the difficulties and hazards to the work which might be caused by storm and flood water; (h) local conditions relative to labor, transportation, hauling, and rail delivery facilities; and (i) all other factors and conditions affecting or which may be affected by the work.
HEREBY PROPOSED to furnish all required materials, supplies, equipment, tools, and plant; to perform all necessary labor and supervision; and to construct, install, erect, and complete all work stipulated, required by, and in accordance with the proposed contract documents and the drawings, specifications, and other documents referred to therein (as altered, amended, or modified by addenda) in the manner and time prescribed and that he will accept in full payment sums determined by applying to the quantities of the following items, the following unit prices and/or any lump sum payments provided, plus or minus any special payments and adjustments provided in the specifications and he understands that the estimated quantities herein given are not guaranteed to be the exact or total quantities required for the completion of the work shown on the drawings and described in the specifications, and that increases or decreases may be made over or under the Contract estimated quantities to provide for needs that are determined during progress of the work and that prices bid shall apply to such increased or decreased quantities as follows:
ITEMIZED BID FORM
ITEM
NO. DESCRIPTION UNIT
APPROX.
QUANTITY
UNIT
PRICE AMOUNT
1 Mobilization LS 1
2 Traffic Control LS 1
3 Inlet Protection EA 8
4 Subgrade Stabilization TON 50
5 Type A Curb & Gutter LF 1051
6 6" Concrete Pavement SY 1773
7 6" Concrete Residential Approach SY 30
8 6" Concrete Sidewalk Ramp SY 41
9 4" Concrete Sidewalk SY 97
10 Detectable Warning Panels SF 60
11 Relocate Street Light EA 1
12 Seeding and Mulching LS 1
TOTAL BASE BID $0.00
Signature of Bidder Date
CONCRETE PAVEMENT REPAIR 2026
PROJECT NO. 32205
SUBCONTRACTORS
If the Bidder intends to use any subcontractors in the course of the construction, he shall list them.
TIME OF COMPLETION
The undersigned hereby agrees to complete the project within 60 working days, subject to the stipulations of the regulations of the Contract and the Special Provisions.
It is understood and agreed that if this bid is accepted, the prices quoted above include all applicable state taxes and that said taxes shall be paid by the Contractor.
The undersigned, as Bidder, hereby declares that the only persons or firms interested in the bid as principal or principals is or are named herein and that no other persons or firms than herein mentioned have any interest in this bid or in the Contract to be entered into; and this bid is made without connection with any other person, company, or parties making a bid; and that it is in all respects fair and in good faith, without collusion or fraud.
The undersigned agrees that the accompanying bid deposit shall become the property of the Owner, should he fail or refuse to execute the Contract or furnish Bond as called for in the specifications within the time provided.
If written notice of the acceptance of this bid is mailed, telegraphed, or delivered to the undersigned within sixty (60) days after the date of opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will, within ten (10) days after the date of such mailing, telegraphing, or delivering of such notice, execute and deliver a Contract in the form of Contract attached.
The undersigned hereby designates as his office to which such notice of acceptance may be mailed, telegraphed, or delivered:
It is understood and agreed that this bid may be withdrawn at any time prior to the scheduled time for the opening of bids or any authorized postponement thereof.
Attached hereto is a Bid Bond for the sum of ____________________________ Dollars (cashier's check), make payable to the City of Jefferson.
Signature of Bidder:
If an individual,________________________________________, doing business as_______________________________________________.
If a partnership,_______________________________________, member of firm.
by_______________________________________________.
If corporation,________________________________________________________ by ______________________________________________.
Title ______________________________________________
SEAL
Business Address of Bidder_____________________________________________
If Bidder is a corporation, supply the following information:
State in which incorporated_____________________________________
Name and Address of its:
President ___________________________________________
Secretary ____________________________________________
Date_______________________________
BID BOND
KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned,__________________________________________________as Principal, and______________________________________________as Surety, are hereby held and firmly bound unto the CITY OF JEFFERSON, MISSOURI , as owner, in the penal sum of____________________________________________for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns, this______day of___________, 20 ____.
The condition of the above obligation is such that whereas the Principal has submitted to the CITY OF JEFFERSON, MISSOURI a certain Bid, attached hereto and hereby made a part hereof to enter into a contract in writing, for the project entitled:
"Project No. 32205, Concrete Pavement Repair 2026"
NOW, THEREFORE,
(a) If said Bid shall be rejected, or in the alternate,
(b) If said Bid shall be accepted and the Principal shall execute and deliver a contract in the Form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a bond for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, shall in all other respects perform the agreement created by the acceptance of said Bid, then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by the extension of the time within which the Owner may accept such Bid; and said Surety does hereby waive notice of any such extension.
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals, and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above.
_________________________________(L.S.)
Principal
By:_________________________________
SEAL
Surety
By: _________________________________
ANTI-COLLUSION STATEMENT
STATE OF _______________________________)
COUNTY OF _____________________________)
___________________________________________________ being first duly sworn, deposes and says that he is ________________________________ of
TITLE OF PERSON SIGNING
NAME OF BIDDER
that all statements made and facts set out in the bid for the above project are true and correct; and that the bidder (the person, firm, association, or corporation making said bid) has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such bid or any contract which result from its acceptance.
Affiant further certifies that bidder is not financially interested in, or financially affiliated with, any other bidder for the above project.
(BY)___________________________________
(BY)___________________________________
Sworn to before me this _______day of ___________________, 20 ___.
NOTARY PUBLIC
My commission expires:________________________________
CONTRACTOR'S AFFIDAVIT
This affidavit is hereby made a part of the Bid, and an executed copy thereof shall accompany each Bid submitted.
STATE OF _________________________)
) ss
COUNTY OF _______________________)
The undersigned, _______________________________________________, of lawful age, being first duly sworn states upon oath that he is
______________________________________________________________ of the contractor submitting the attached bid, that he knows of his own knowledge and states it to be a fact that neither said bid nor the computation upon which it is based include any amount of monies, estimate or allowance representing wages, moneys or expenses, however designated, proposed to be paid to persons who are not required to furnish material or actually perform services upon or as a part of the proposed project.
AFFIANT
Subscribed and sworn to before me, a Notary Public, in and for the County and State aforesaid, this _____ day of ___________________, 20____.
My Commission Expires:________________________________
MINORITY BUSINESS ENTERPRISE STATEMENT
Contractors bidding on City contracts shall take the following affirmative steps to assure that small, women owned, and minority business are utilized when possible as sources of suppliers, services, and construction items.
1. Contractor's will submit the names and other information if any, about their
MBE sub-contractors along with their bid submissions.
2. Sufficient and reasonable efforts will be made to use qualified MBE sub-contractors when possible on City contracts.
3. Qualified small, women owned, and minority business will be included on solicitation lists as sub-contractors for City supplies, services, and construction.
4. Qualified small, women owned, and minority business will be solicited whenever they are potential sources.
5. When economically feasible, Contractors will divide total requirements into smaller tasks or quantities so as to permit maximum small, women owned, and minority business participation.
6. Where the requirement permits, Contractor will establish delivery schedules which will encourage participation by small, women owned and minority businesses.
7. Contractor will use the services and assistance of the Small Business
Administration, the Office of Minority Business Enterprise, and the Community Services Administration.
8. Forms for determining Minority Business Enterprise eligibility may be obtained from the Department of Public Works.
MINORITY BUSINESS UTILIZATION AGREEMENT
A. The bidder agrees to attempt to expend at least two and twelve hundredths percent (2.12)% of the contract, if awarded, for Minority Business Enterprise (MBE). For purposes of this goal, the term "Minority Business Enterprise" shall mean a business:
1. Which is at least 51 percent owned by one or more minorities or women, or, in the case of a publicly owned business, at least 51 percent of the stock of which is owned by one or more minorities or women; and
2. Whose management and daily business operations are controlled by one or more such individuals.
"Minority Group Member" or "Minority" means a person who is a citizen or lawful permanent resident of the United States, and who is:
1. Black (a person having origins in any of the black racial groups of Africa);
2. Hispanic (a person of Spanish or Portuguese culture with origins in Mexico, South or Central America, or the Caribbean Island, regardless of race);
3. Asian American (a person having origins in any of the original peoples of the Far East, Southeast Asia, the Indian sub-continent, or the Pacific Islands);
4. American Indians and Alaskan Native (a person having origins in any of the original peoples of North America);
5. Member of other groups, or other individuals, found to be economically and socially disadvantaged by the Small Business Administration under Section 8(a) of the Small Business Act, as amended [15 U.S.C. 637(a)].
6. A female person who requests to be considered as an MBE, and who "owns" and "controls" a business as defined herein.
Minority Business Enterprises may be employed as contractors, subcontractors, or suppliers.
B. The bidder must indicate the Minority Business Enterprise(s) proposed for utilization as part of this contract as follows:
Name and Addresses Nature of Dollar Value of of Minority Firms Participation Participation
Total Bid Amount:_______________________ Total: _____________
Percentage of Minority Enterprise Participation:___________%
C. The bidder agrees to certify that the minority firm(s) engaged to provide materials or services in the completion of this project: (a) is a bona fide Minority Business Enterprise; and (b) has executed a binding contract to provide specific materials or services for a specific dollar amount.
A roster of bona fide Minority Business Enterprise firms will be furnished by the City of Jefferson. The bidder will provide written notice to the Liaison Officer of the City of Jefferson indicating the Minority Business Enterprise(s) it intends to use in conjunction with this contract. This written notice is due five days after notification to the lowest bidder.
Certification that the Minority Business Enterprise(s) has executed a binding contract with the bidder for materials or services should be provided to the MBE Coordinator at the time the bidder's contract is submitted to the MBE Coordinator.
D. The undersigned hereby certified that he or she has read the terms of this agreement and is authorized to bind the bidder to the agreement herein set forth.
NAME OF AUTHORIZED OFFICER
DATE ____________ _______________________________________
SIGNATURE OF AUTHORIZED OFFICER
AFFIDAVIT
COMPLIANCE WITH PREVAILING
WAGE LAW
Before me, the undersigned Notary Public, in and for the County of _____________, State of _______________, personally came and appeared
NAME POSITION
of the______________________________________________________________
NAME OF COMPANY
(A corporation) ( a partnership) (a proprietorship) and after being duly sworn did depose and say that all provisions and requirements set out in Chapter 290, Section
290.210 through and including 290.340, Missouri Revised Statutes, pertaining to the payment of wages to workmen employed on public works projects have been fully satisfied and there has been no exception to the full and complete compliance with said provisions and requirements and with Annual Wage Order No. 33, Section 026, Cole County in carrying out the contract and work in connection with Project No. 32205, Concrete Pavement Repair 2026 located at Jefferson City in Cole County, Missouri, and completed on the ______ day of ____________, 20___.
SIGNATURE
Subscribed and sworn to me this _____ day of ____________, 20___.
My commission expires: ____________________________________
STATE OF MISSOURI )
COUNTY OF__________ )
Division of Labor Standards
WAGE AND HOUR SECTION
MIKE KEHOE, Governor
Annual Wage Order No. 33 Section 026
COLE COUNTY
In accordance with Section 290.262 RSMo 2000, within thirty (30) days after a certified copy of this Annual Wage Order has been filed with the Secretary of State as indicated below, any person who may be affected by this Annual Wage Order may object by filing an objection in triplicate with the Labor and Industrial Relations Commission, P.O. Box 599, Jefferson City, MO 65102- 0599. Such objections must set forth in writing the specific grounds of objection. Each objection shall certify that a copy has been furnished to the Division of Labor Standards, P.O. Box 449, Jefferson City, MO 65102-0449 pursuant to 8 CSR 20-5.010(1). A certified copy of the Annual Wage Order has been filed with the Secretary of State of Missouri.
Original Signed by Logan Hobbs, Director Division of Labor Standards
Filed With Secretary of State: March 10, 2026
Last Date Objections May Be Filed: April 9, 2026
Prepared by Missouri Department of Labor and Industrial Relations
Missouri
ANNUAL WAGE ORDER NO. 33 03/26
Building Construction Rates For Section 026
COLE COUNTY
OCCUPATIONAL TITLE **Prevailing Hourly Rate
Asbestos Worker $61.67
Boilermaker $33.76*
Bricklayer - Stone Mason $56.40
Carpenter $58.06
Lather
Linoleum Layers & Cutter
Millwright
Pile Driver
Cement Mason $51.32
Plasterer
Communication Technician $64.69
Electrician (Inside Wireman) $64.92
Electrician (Outside Lineman) $33.76*
Outside - Groundman
Outside - Groundman Tree Trimmer
Outside - Lineman Operator
Outside - Lineman Tree Trimmer
Elevator Constructor $33.76*
Glazier $33.76*
Iron Worker $74.57
Laborer $46.86
Laborer - First Semi-Skilled
Laborer - General
Laborer - Second Semi-Skilled
Laborer - Skilled
Mason $60.77
Marble Finisher
Marble Mason
Terrazzo Finisher
Terrazzo Worker
Tile Finisher
Tile Setter
Operating Engineer $70.55
Operating Engineer - Group I
Operating Engineer - Group II
Operating Engineer - Group III
Operating Engineer - Group III - A
Operating Engineer - Group IV
Operating Engineer - Group V
Painter $45.79
Plumber $75.59
Pipe Fitter
Roofer/WaterProofer $57.87
Sheet Metal Worker $62.18
Sprinkler Fitter - Fire Protection $72.88
Truck Driver $33.76*
Truck Control Service Driver
Truck Driver, Teamsters Group I
Truck Driver, Teamsters Group II
Truck Driver, Teamsters Group III
Truck Driver, Teamsters Group IV
* The Division of Labor Standards received fewer than 1,000 reportable hours for this occupational title. The public works contracting minimum wage is established for this occupational title using data provided by Missouri Economic Research and Information Center.
**The Prevailing Hourly Rate includes any applicable fringe benefit amounts for each occupational title as defined in RSMo Section 290.210.
ANNUAL WAGE ORDER NO. 33 03/26
Heavy Construction Rates For Section 026
COLE COUNTY
OCCUPATIONAL TITLE **Prevailing Hourly Rate
Carpenter $64.42 Millwright Pile Driver
Electrician (Outside Lineman)
$87.78
Outside - Groundman Outside - Groundman Tree Trimmer Outside - Lineman Operator Outside - Lineman Tree Trimmer
Laborer $55.27 Laborer - General Laborer - Skilled
Operating Engineer $70.85 Operating Engineer - Group I Operating Engineer - Group II Operating Engineer - Group III Operating Engineer - Group IV
Truck Driver $33.76* Truck Control Service Driver Truck Driver, Teamsters Group I Truck Driver, Teamsters Group II Truck Driver, Teamsters Group III Truck Driver, Teamsters Group IV
Use Heavy Construction Rates on Highway and Heavy construction in accordance iwth the classifications of construction work established in 8 CSR 30-3.040(3).
Use Building Construction Rates on Building construction in accordance with the classifications of construction work established in 8 CSR 30-3.040(2).
If a worker is performing work on a heavy construction project within an occupational title that is not listed on the Heavy Construction Rate Sheet, use the rate for that occupational title shown on the Building Construction Rate Sheet.
*The Division of Labor Standards received fewer than 1,000 reportable hours for this occupational title. Public works contracting minimum wage is established for this occupational title using data provided by Missouri Economic Research and Information Center.
**The Prevailing Hourly Rate includes any applicable fringe benefit amounts for each occupational title.
OVERTIME
and
HOLIDAYS
ANNUAL WAGE ORDER NO. 33 3/26
OVERTIME
For all work performed on a Sunday or a holiday, not less than twice (2x) the prevailing hourly rate of wages for work of a similar character in the locality in which the work is performed or the public works contracting minimum wage, whichever is applicable, shall be paid to all workers employed by or on behalf of any public body engaged in the construction of public works, exclusive of maintenance work.
For all overtime work performed, not less than one and one-half (1½) the prevailing hourly rate of wages for work of a similar character in the locality in which the work is performed or the public works contracting minimum wage, whichever is applicable, shall be paid to all workers employed by or on behalf of any public body engaged in the construction of public works, exclusive of maintenance work or contractual obligation.
For purposes of this subdivision, "overtime work" shall include work that exceeds ten hours in one day and work in excess of forty hours in one calendar week; and
A thirty-minute lunch period on each calendar day shall be allowed for each worker on a public works project, provided that such time shall not be considered as time worked.
HOLIDAYS
January first;
The last Monday in May;
July fourth;
The first Monday in September;
November eleventh;
The fourth Thursday in November; and December twenty-fifth;
If any holiday falls on a Sunday, the following Monday shall be considered a holiday.
AFFIDAVIT OF COMPLIANCE PUBLIC WORKS CONTRACTS LAW
I, the undersigned, ______________________________, of lawful age, first being duly sworn, state to the best of my information and belief as follows:
1. That I am employed as
______________________________________, by
2. That _____________________________ was awarded a public works contract for Project No. 32205, Concrete Pavement Repair
2026.
3. That I have read and am familiar with Section 290.290 RSMo
(1994 as amended) an act relating to public works contracts, which impose certain requirements upon contractors and subcontractors engaged in a public works construction project in the State of Missouri.
4. That _______________________________ has fully complied with the provisions and requirements of Section 290.290 RSMo (1994 as amended)
FURTHER AFFIANT SAYETH NAUGHT.
AFFIANT
Subscribed and sworn to before me this ____ day of ________________, 20____.
My Commission Expires: ___________________________________
STATE OF MISSOURI )
COUNTY OF__________ )
FEDERAL WORK AUTHORIZATION PROGRAM AFFIDAVIT
State of Missouri ) County of Cole )
The undersigned affiant, ____________________________, being first duly sworn, hereby deposes and says:
1. I am over the age of eighteen, suffer no legal disabilities, have personal knowledge of the facts set forth below, and am competent to testify.
2. I am authorized to make this affidavit on behalf of
3. I hereby affirm that the company identified in section 2 of this affidavit is enrolled and participates in a federal work authorization program with respect to the employees working in connection with the contracted services. The name of said Federal Work Authorization program is
4. I hereby affirm that the company identified in section 2 of this affidavit does not knowingly employ any person who is an unauthorized alien in connection with the contracted services.
This the ______ day of ______________________________, 20___.
Name
Title
Sworn and Subscribed before me this the _______ day of ___________________________, 20___.
Notary Public
My Commission expires:_____________________
[attach documentation of enrollment/participation in a federal work authorization program]
CONSTRUCTION CONTRACT
THIS CONTRACT made and entered into the date last executed by a party as indicated below, by and between _______________________________________ hereinafter referred to as "Contractor", and the City of Jefferson, Missouri, a municipal corporation of the State of Missouri, hereinafter referred to as "City".
WITNESSETH: That Whereas, the Contractor has become the lowest responsible bidder for furnishing the supervision, labor, tools, equipment, materials and supplies and for constructing the following City improvements:
Project No. 32205, Concrete Pavement Repair 2026.
NOW THEREFORE, the parties to this contract agree to the following:
1. Scope of Services.
Contractor agrees to provide all labor, equipment, hardware and supplies to perform the work included in the project entitled "Concrete Pavement Repair 2026" in accordance with the plans and specifications on file with the Department of Public Works.
2. Payment.
The City hereby agrees to pay the Contractor for the work done pursuant to this contract according to the payment schedule set forth in the Contract Documents upon acceptance of said work by the Director of Public Works and in accordance with the rates and/or amounts stated in the bid of Contractor dated ___________________which are by reference made a part hereof. No partial payment to the Contractor shall operate as approval or acceptance of work done or materials furnished hereunder. The total amount of this contract shall not exceed _______________ Dollars.
3. Manner and time for Completion.
Contractor agrees with the City to furnish all supervision, labor, tools, equipment, materials and supplies necessary to perform said work at Contractor's own expense in accordance with the contract documents and any applicable City ordinances and state and federal laws, within 60 working days from the date Contractor is ordered to proceed, which order shall be issued by the Director of Public Works within ten (10) days after the date of this contract.
4. Prevailing Wages.
To the extent that the work performed by Contractor is subject to prevailing wage law, Contractor shall pay a wage of no less than the "prevailing hourly rate of wages" for work of a similar character in this locality, as established by Department of Labor and Industrial Relations of the State of Missouri, and as established by the Federal Employment Standards of the Department of Labor. Contractor acknowledges that
Contractor knows the prevailing hourly rate of wages for this project because Contractor has obtained the prevailing hourly rate of wages from the contents of the current Annual Wage Order No. 33, Section 026, Cole County rates as set forth.
The Contractor further agrees that Contractor will keep an accurate record showing the names and occupations of all workmen employed in connection with the work to be performed under the terms of this contract. The record shall show the actual wages paid to the workmen in connection with the work to be performed under the terms of this contract. A copy of the record shall be delivered to the Purchasing Agent of the Jefferson City Finance Department each week. In accordance with Section 290.250 RSMo, Contractor shall forfeit to the City One Hundred Dollars ($100.00) for each workman employed, for each calendar day or portion thereof that the workman is paid less than the stipulated rates for any work done under this contract, by the Contractor or any subcontractor under the Contractor.
5. Insurance.
(a) The Contractor shall obtain and maintain during the term of the Project and this Contract the insurance coverages at least equal to the coverages set forth in this paragraph 7, and as further provided in the General Conditions, but no event less than the individual and combined sovereign immunity limits established by Section
537.610 R.S.Mo. Insurance policies providing required coverages shall be with companies licensed to do business in the State of Missouri and rated no less than AA by Best or equivalent. All costs of obtaining and maintaining insurance coverages are included in the Bid Amount and no additional payment will be made therefor by the City.
Comprehensive General Liability Insurance (including coverage for Bodily Injury and Property Damage)
$500,000 per occurrence $3,500,000 aggregate
Comprehensive Automobile Liability Insurance (including coverage for Bodily Injury and Property Damage)
$500,000 per occurrence $3,500,000 aggregate
Employer’s Liability $3,500,000 bodily injury by accident (each accident) $3,500,000 bodily injury by disease (each employee) $3,500,000 bodily injury policy limit
(b) Worker’s Compensation - In addition, the Contractor and all subcontractors shall provide Worker’s Compensation Insurance in at least statutory amounts for all workers employed at the Project site.
(c) Builder’s Risk - The Contractor shall also provide a policy of Builder’s Risk Insurance in the amount of 100% of the complete insurable value of the Project, which policy shall protect the Contractor and the City, as their respective interests shall appear.
(d) Owner's Protective Liability Insurance - The Contractor shall also obtain at its own expense and deliver to the City an Owner's Protective Liability Insurance Policy naming the City of Jefferson as the insured, in an amount not less than the individual and combined sovereign immunity limits established by Section 537.610 R.S.Mo., except for those claims governed by the provisions of the Missouri Workmen's Compensation Law, Chapter 287, RSMo. No policy will be accepted which excludes liability for damage to underground structures or by reason of blasting, explosion or collapse.
(e) Before commencing any work, the Contractor shall provide to the City certificates of insurance evidencing the issuance and maintenance in force of the coverages required by this paragraph 4. Each such certificate shall show the City, and such other governmental agencies as may be required by the City to be insured by underlying grant or contract relating to the Project, as an additional insured, and shall bear an endorsement precluding cancellation of or change in coverage without at least thirty (30) days written notice to the City. The City may waive any insurance coverages or amounts required by this paragraph 4 when the City deems such waiver to be in the interest of the public health, safety, and general welfare.
(f) Subcontracts - In case any or all of this work is sublet, the Contractor shall require the Subcontractor to procure and maintain all insurance required in Subparagraphs (a), (b), and (c) hereof and in like amounts.
(g) Scope of Insurance and Special Hazard. The insurance required under Sub-paragraphs (b) and (c) hereof shall provide adequate protection for the Contractor and its subcontractors, respectively, against damage claims which may arise from operations under this contract, whether such operations be by the insured or by anyone directly or indirectly employed by it, and also against any special hazards which may be encountered in the performance of this contract.
NOTE: Paragraph (f) is construed to require the procurement of Contractor's protective insurance (or contingent public liability and contingent property damage policies) by a general contractor whose subcontractor has employees working on the project, unless the general public liability and property damage policy (or rider attached thereto) of the general contractor provides adequate protection against claims arising from operations by anyone directly or indirectly employed by the Contractor.
6. Contractor's Responsibility for Subcontractors.
It is further agreed that Contractor shall be as fully responsible to the City for the acts and omissions of its subcontractors, and of persons either directly or indirectly employed by them, as Contractor is for the acts and omissions of persons it directly employs. Contractor shall cause appropriate provisions to be inserted in all subcontracts relating to this work, to bind all subcontractors to Contractor by all the terms herein set forth, insofar as applicable to the work of subcontractors and to give Contractor the same power regarding termination of any subcontract as the City may exercise over Contractor under any provisions of this contract. Nothing contained in this contract shall create any contractual relations between any subcontractor and the City or between any subcontractors.
7. Liquidated Damages.
The Contractor agrees and acknowledges that time is of…