SPECIFICATIONS 26 267.pdf
PDF 4 MB Posted
- Solicitation number
- CIZ-DWU-26 267
- Issued by
- Tarrant County, Dallas City, Texas
About this file
This is a specifications and contract document for erosion control improvements projects issued by the City of Dallas Water Utilities. The contract includes construction of gabion walls with varying heights and lengths and rock ripraps along creek banks at five different locations throughout Dallas: 4690 S Counts Boulevard, Pratt Street at Mayrant Drive, 1215 Lansford Avenue, El Cerrito Drive and Hunnicut Road, and Forest Lane. Sealed bids must be submitted electronically via Euna Procurement (formerly Bonfire) at https://dallascityhall.bonfirehub.com/login before 1:00 p.m. on Friday, December 11, 2026, with bid opening at 2:00 p.m. on the same day. A virtual pre-bid conference will be held on Tuesday, November 17, 2026, at 10:00 a.m. via Teams; interested bidders should email DWUCapitalServices@dallas.gov to receive a calendar invite. Project-related questions must be submitted in Euna Procurement no later than Thursday, December 3, 2026, at 1:00 p.m. Plans, specifications, and bid result tabulations will be available in Adobe PDF format on Friday, November 6, 2026. The contract includes multiple bid items such as clearing and grubbing, mobilization, traffic control, erosion control installation and maintenance, riprap placement, flexmat installation, and pavement restoration. Work must commence no later than 60 calendar days after city council award, with liquidated damages of $1,000 per calendar day for failure to meet this milestone. All work and site restoration must be completed within 360 consecutive working days from the Notice to Proceed date, with liquidated damages of $1,000 per working day for delays.
The successful bidder must provide a cashier's check or acceptable bidder's bond of not less than five percent of the total bid amount and will be required to furnish payment and performance bonds each equal to 100 percent of the contract price. Bidders must demonstrate direct experience with construction projects of the same nature and similar magnitude, with at least two completed projects within the last five years. The contractor must perform no less than 25 percent of the work with its own organization and may propose reductions only with written owner approval. All bidders must acknowledge compliance with Texas Government Code Chapters 2270 and 2252 regarding boycotts of Israel and restrictions on contracts with foreign terrorist organizations; failure to sign these acknowledgements may result in bid rejection. The contract requires contractor participation in project partnering, submission of traffic control plans, hot-mix asphalt mix design approvals, pre-construction and post-construction videos, and detailed construction schedules updated monthly. Mobilization costs exceeding 10 percent of the adjusted contract amount will be paid upon project completion. Insurance requirements follow Item 103.4 of the City of Dallas Addendum to North Central Texas Standard Specification for Public Works Construction. No proposal may be withdrawn within 150 days after the bid opening date. Permanent pavement restoration must commence no later than 14 calendar days after paving release, with liquidated damages of $500 per calendar day for non-compliance with City Ordinance 29993.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF DALLAS
SPECIFICATIONS
AND
FORMS OF CONTRACT AND BONDS
FOR
EROSION CONTROL IMPROVEMENTS PROJECTS
AT
VARIOUS LOCATIONS:
PHASE 8
dallas uuater utrt1es city of dallas
CONTRACT NO. 26-267
IMPORTANT NOTICE!
ADVERTISEMENT FOR BIDS
Sealed Bids for “EROSION CONTROL IMPROVEMENTS PROJECTS AT VARIOUS LOCATIONS: PHASE 8, CONTRACT NO. 26-267”, as detailed on Dallas Water Utilities plans and as described in the Contract Specifications, shall be submitted as pdfs in Euna Procurement (formerly Bonfire) at:
https://dallascityhall.bonfirehub.com/login, before 1:00 p.m. on Friday, December 11, 2026. Bid opening will be read ONLY online by the Purchasing Agent at 2:00 p.m. on Friday, December 11, 2026. You may view this bid opening live by going to www.dallascityhall.com, click on watch city meetings online, and it will be live on DCN 95 live.
There will be a virtual Pre-Bid Conference held on Tuesday, November 17, 2026, at 10:00 am via Teams. To receive a calendar invite to the meeting, please email DWUCapitalServices@dallas.gov. A calendar invite will be sent upon receipt of your request.
Project related questions shall be submitted in Euna Procurement (formerly Bonfire) no later than Thursday, December 3, 2026, at 1:00 PM.
An Adobe (pdf) file version of Plans, Specifications, and Bid result tabulations can be found at the City of Dallas Euna Procurement (formerly Bonfire) website:
https://dallascityhall.bonfirehub.com, on Friday, November 6, 2026. Search for DWU Contract CIZ-DWU-26 267.
http://www.dallascityhall.com/ mailto:DWUCapitalServices@dallas.gov https://dallascityhall.bonfirehub.com/
“FAILURE TO SIGN YOUR BID MAY RESULT IN A REJECTION OF YOUR BID.
Bidder’s Acknowledgement of Prohibition on Contracts with Companies Boycotting Israel Effective September 1, 2017, Bidder acknowledges, in accordance with Chapter 2270 of the Texas Government Code, that Bidder does not boycott Israel and will not boycott Israel during the term of any contract with the City of Dallas to provide goods and services to the City. Bidder further acknowledges that this provision is hereby incorporated by reference, as if written word for word, into any subsequent contract entered into between City and Bidder for goods and services.”
“FAILURE TO SIGN YOUR BID MAY RESULT IN A REJECTION OF YOUR BID.
Bidder’s Acknowledgement of Prohibition on Contracts with Foreign Terrorist Organizations Effective September 1, 2017, Bidder acknowledges, in accordance with Chapter 2252 of the Texas Government Code, that (a) Bidder does not engage in business with Iran, Sudan or any foreign terrorist organization and (b) Bidder is not listed by the Texas Comptroller as a terrorist organization as defined by Chapter 2252 of the Texas Government Code. Bidder further acknowledges that this provision is hereby incorporated by reference, as if written word for word, into any subsequent contract entered into between City and Bidder for (1) professional or consulting services subject to the Professional Services Act - Chapter 2254 of the Texas Government Code, (2) general construction, (3) an improvement, (4) a service, (5) a public works project, or (6) for a purchase of supplies, materials or equipment.”
INDEX TO SPECIFICATIONS
ADVERTISEMENT FOR BIDS
PART A - INFORMATION TO BIDDERS
SECTION A
A 1. Time and Place for Receiving Proposals
A 2. Location and Description of Project
A 3. Special Provisions
A 4. Bid Items
A 5. Living Wage Rate and Davis Bacon Wage Schedule
A 6. Legal Holiday and Overtime Pay
A 7. Proposal Tabulation
A 8. Time
A 9. Specifications
A 10. Addenda
A 11. Developing Regional & Inclusive Vendor Enterprises (DRIVE) Policy
A 12. Drug-Free Jobsite on City Construction Projects
A 13. Insurance Requirements
A 14. Cement Use on Public Projects
A 15. Environmental Policy and Occupational Safety and Health Program
PART T - TECHNICAL SPECIFICATIONS
CONTRACT BONDS AND FORMS
Cashier's check or acceptable Bidder's Bond, payable to the City of Dallas in an amount of not less than five percent of total Bid submitted must accompany Bid. City reserves the right to reject any or all Bids.
The successful Bidder will be required to furnish a Payment Bond and a Performance Bond, each in an amount equal to 100 percent of the Contract Price. Insurance shall be furnished according to Item 103.4 of the City of Dallas Addendum to North Central Texas Standard Specification for Public Works Construction, Latest Edition.
No Proposal may be withdrawn within a period of 150 days after the date fixed for opening Proposals.
SPECIFICATIONS
AND
FORMS OF CONTRACT AND BONDS
FOR
EROSION CONTROL IMPROVEMENTS PROJECTS
AT
VARIOUS LOCATIONS:
PHASE 8
CONTRACT NO. 26-267
PART A - INFORMTION TO BIDDERS
A 1. TIME AND PLACE FOR RECEIVING PROPOSALS
Bids will be received electronically via the City of Dallas’ solicitation website at https://dallascityhall.bonfirehub.com/login on Friday, October 2, 2026 by 1:00 P.M. For any questions, please email DWUCapitalServices@dallas.gov.
Bidder Qualifications
• All Bidders shall have direct experience with construction of the same nature and similar magnitude as that of the project for which bids are being received.
• All Bidders (through its technical advisor, project manager, superintendent, or subcontractor) shall have at least two completed projects within last five (5) years of the same nature and similar magnitude.
A 2. LOCATION AND DESCRIPTION OF PROJECT
The proposed contract includes erosion control projects at five (5) different locations in the City of Dallas.
The erosion control projects include construction of gabion walls with varying heights and lengths and rock ripraps along different creek banks.
Detailed project location and information can be found in the contract specifications.
For details of locations and construction, see the following table and maps.
Erosion Control at Various Locations- Phase 8
Construction Contract No. 26-267
Schedule
Location
Limits
Storm Drain Pipe Sizes & Types
LF Storm/Gabion
Wall
Height of
Gabion Wall
LF
Water
Water Main Sizes & Types
LF
Wastewater
Wastewater Main Sizes & Types
Design Sheet Number Existing Proposed Existing Proposed Existing Proposed
A-1 4690 S Counts 4690 S Counts 18" RCP 18" RCP N/A N/A N/A N/A N/A N/A N/A N/A 425D-200
SHEET(S) 1-5
B-1 Pratt at Mayrant Pratt at Mayrant 3-36" RCP 3-36"
RCP 300 21 N/A N/A N/A N/A N/A N/A 425D-201
SHEET(S) 1-23
B-2 1215 Lansford 1215 Lansford N/A N/A 135 27 N/A N/A N/A N/A N/A N/A 425D-203
SHEET(S) 1-21
B-3
2490 El Cerrito & 8181 Hunnicut
2484 El Cerrito Drive and 2504 El Cerrito
Drive
N/A
12 to 15
425D-213
SHEET(S) 1A-16
B-4
9833 Forest Lane
1000 Woodbridge Drive and 9833 Forest Lane
103.79
425D-199
SHEET(S) 01-11
For details of locations and construction see the above referenced maps and the applicable Standard Drawings.
F
Dallas Water Utilities Construction Contract 26-267
Erosion Control Improvements Project at Various Locations - Phase 8
Council District 1
Mapsco 52-G
Counts Blvd 4690
COUNTS BLVD
COUNTS BLVD
CO
UN
TS
B
LV
D
COUNTS BLVD
S COUNTS
BLVD
Dallas Water Utilities Construction Contract 26-267
Erosion Control Improvements Project at Various Locations - Phase 8
Council District 1
Mapsco 54-L
North of Mayrant Drive
PR
AT
T ST
ZA
NG
BL
VD
M O
N
SSEN
D R
ZA
NG
B
LV
D
MAYRANT DR
MAN
US D
R
MONSSEN DR
Council District 1
Council District 4
54-L
Dallas Water Utilities Construction Contract 26-267
Erosion Control Improvements Project at Various Locations - Phase 8
Council District 1
Mapsco 54-K
Lansford Ave 1215 North side of Elmwood Branch
LANSFORD AVE
CL
IN
TO
N
AV
E
ELM
W
O O
D
BLVD
ELMWOOD BLVD
LEBANON AVE
LANSFORD AVE
LANSFORD
AVE
Dallas Water Utilities Construction Contract 26-267
Erosion Control Improvements Project at Various Locations - Phase 8
Council District 7
Mapsco 48-A
El Cerrito Dr 2490 & Hunnicut Rd 8181
RAN
G
EW
AY D
R
HUNNICUT RD
FALL R
IVER
D R
W O
O D
H U
E R D
EL CERRITO DR
Dallas Water Utilities Construction Contract 26-267
Erosion Control Improvements Project at Various Locations - Phase 8
Council District 10
Mapsco 17-Y
Forest Lane 9833
WOOD FOREST DR
AU
D
ELIA R
D
AU
D
ELIA R
D
FOREST LN
FOREST LN
17-Y
JACKSON BRANCH
A 3. GENERAL SPECIAL PROVISIONS
S-1 INQUIRIES
All Pre-Bid inquiries shall be submitted in Euna Procurement (formerly Bonfire). Only inquiries submitted in Euna Procurement (formerly Bonfire) will receive a response.
Responses will be issued to plan holders by Addendum. For deadlines related to Pre- Bid Conferences interested Bidders shall refer to ADVERTISEMENT FOR BIDS.
Project related questions shall be submitted in Euna Procurement (formerly Bonfire) no later than Thursday, December 3, 2026, at 1:00 PM.
S-2 PRE-BID CONFERENCE
There will be a virtual Pre-Bid Conference held on Tuesday, November 17, 2026, Via TEAMS. To receive a calendar invite to the meeting, please email DWUCapitalServices@dallas.gov. A calendar invite will be sent upon receipt of your request.
S-3 BIDDING RESTRICTIONS
No individual, partnership, corporation, holding company, or other business organization shall submit more than one Bid on this project. The submittal of multiple bids in the names of different Contractors by the same individual, partnership, corporation, holding company, or business is specifically prohibited.
S-4 BID PACKET SUBMITTAL
Contractors must provide an electronic copy of their Bid Proposal Spreadsheet in Excel (.xls, .xlsx) and PDF format with their Bid Packet submittal in Bonfire.
S-5 QUANTITIES
The quantities in all Unit Price bid items in the Proposal are approximate and may represent quantities in excess of those actually installed. Payment will be based on the actual quantities installed and paid in accordance with the applicable Specifications.
S-6 CONSTRUCTION SCHEDULE
The Contractor must submit to the Owner a detailed Construction Schedule outlining the major items of work on the project. This schedule must be approved as to form by the Owner prior to Contractor starting work on the project. The schedule must be updated on a monthly basis. Owner will stop work on the project if the Contractor fails to provide an updated schedule as requested. The Owner shall not be responsible for any delay as a result of the Contractor's failure to submit the schedule in a timely manner.
S-7 MILESTONE / LIQUIDATED DAMAGES
Bidder agrees that the work covered by the contract award will be completed in accordance with the following Milestones:
Milestone 1: Effective Start Date shall be no longer than 60 Calendar days after City
Council award of this project. Liquidated Damages shall be $ 1,000 Per Calendar Day.
Milestone 2: All work and site restoration completed within 360 Consecutive Working
Days from Notice to Proceed Date. Liquidated damages shall be $1,000 per Working Day.
S-8 PROJECT SIGN (EROSION CONTROL)
This Contract requires work at more than one geographical location. A Project Sign will be required at each location of work from the period when work has started at that location until all work is complete at that location.
The signs will be provided to the Contractor at no charge, however, delivery to the project site is not included and the Contractor will be required to pick the sign up when notified at Dallas Lite and Barricade, 1607 Fort Worth Avenue, Dallas, Texas, 75208.
The Contractor will also be required to erect the sign at the project site and also to deliver the signs upon completion of the project site for re-use. The Contractor will be required to notify the Project Manager two (2) weeks prior to the placement of the signs.
NO PAY ITEM.
S-9 NOTIFICATION OF CONSTRUCTION OPERATIONS EROSION CONTROL AND
STORM DRAIN IMPROVMENTS
The Contractor shall be responsible for all Construction Staking associated with the
Erosion Control and Storm Drainage Improvements – Part I on this project. No Separate Pay Item, unless otherwise noted. Staking shall be performed by qualified personnel. Typed Cut-Sheets must be submitted to Stormwater Inspection, 2121 Main Street, #500, Dallas, Texas 75201 (Phone - 214-671-9530; Fax - 214-670-3018) no later than 3:00P.M. the day prior to scheduled start of construction. (See example in Part T - Technical Specifications).
The Contractor is responsible for maintaining all staked controls and hubs in the construction area at all times and any costs for re-staking or re-establishing controls required shall be borne by the Contractor.
Inspection of work associated with the Erosion Control and Storm Drain Improvements be done by Dallas Water Utilities (DWU) and shall be requested through the appropriate DWU Construction Superintendent a minimum of ten (10) days prior to the scheduled start of construction for each location. Actual start date is dependent upon approval and issuance of the “Public Relations” letter from the Project manager.
S-10 INSPECTION OVERTIME REIMBURSEMENTS
The following paragraph in Item 105.9.3.COD: Inspection Overtime of the DWU Addendum to North Central Texas Standard Specifications for Public Works Construction shall be revised as follows:
Inspection overtime will be charged to the Contractor at the rate of $50.00 per hour per Inspector with the number of Inspectors to be determined by the Owner under the following overtime conditions:
1. Weekdays between the hours of midnight to 7:30am and 4:30pm to midnight.
2. Saturdays, Sundays and Holidays between the hours of midnight to midnight with a minimum of four (4) hours, at a rate of $50.00 per hour per Inspector and a minimum of $200 per day per Inspector.
S-11 SUBMITTALS
The Contractor is required to furnish written submittals. The following additional information is required with all pay applications.
MONTHLY ESTIMATE:
PAYMENT REQUEST COVER LETTER
DESCRIPTION OF PAY ITEMS/QUANTITY INFORMATION UPDATED PROJECT
SCHEDULE
SCHEDULE OF WORK AND ACTUAL PAYMENT FORM
CONTRACTOR/SUBCONTRACTOR CERTIFIED PAYROLL REPORT
NEIGHBORHOOD JOB OPPORTUNITIES
CERTIFICATE OF LIABILITY INSURANCE
VERIFICATION OF PAYMENT FOR INSPECTORS OVERTIME AFFIDAVIT OF
SUBCONTRACTOR/SUPPLIER PAYMENT BREAKDOWN OF STORED
MATERIALS (IF APPLICABLE) SBE PROPOSED CHANGES
FINAL ESTIMATE:
CONTRACTOR AFFIDAVIT OF SUBCONTRACTOR/SUPPLIER PAYMENT
POST CONSTRUCTION CONTRACTOR EVALUATION (with final application) RELEASE OF CLAIMS (if applicable with final application)
SBE SUBCONTRACTOR/SUPPLIER EVALUATION(S) INSPECTOR'S OVERTIME
FEE PAID
SUBCONTRACTOR EXPLANATION OF VARIANCE FROM PAYMENT SCHEDULE
WARRANTY(S) ORIGINAL(S)
CONSENT OF SURETY TO FINAL PAYMENT NEIGHBORHOOD JOB
OPPORTUNITIES FORM
WEEKLY CERTIFIED PAYROLLS THROUGH COMPLETION OF WORK SWORN
STATEMENT OF ACCOUNTS
DISPOSITION OF EXISTING ASSETS FORM
S-12 APPROVED MATERIALS BY TRADE NAME
The Owner maintains a list of approved materials by trade name as shown in DWU Standard
Technical Specifications for Water and Wastewater Construction, Latest Edition. If applicable Contractor shall use materials specified on Approved Materials List unless otherwise specified in this contract.
S-13 OFF-SITE CONSTRUCTION AREA, SITE ACCESS AND ACCESS RAMP
The Contractor is not permitted to use any public right-of-way as a staging area, yard, office, storage, access, access ramp, etc., unless permitted by the Project Manager.
Should the Contractor require the use of private property as a staging area, yard, office, storage, access, or access ramp, etc. then he will submit that location along with a copy of the agreement from the Property Owner/Owners to the Project Manager.
Staging area, yard, office, storage, access, and access ramp shall be incidental to contract bid items unless otherwise noted. NO SEPARATE PAY ITEM.
S-14 TRAFFIC RESTRICTIONS
The following traffic restrictions shall be enforced during construction.
1. Two-way traffic shall be maintained on all streets at all times. Flagmen should be used to maintain two-way traffic.
2. The Contractor will be responsible for barricading all projects. All barricades, warning signs, and traffic control devices shall conform as a minimum to the standards in the City of Dallas Traffic Barricade Manual and TxDOT Texas Manual on Uniform Traffic Control Devices 2006 (Texas MUTCD).
3. When closing side streets, four working days notification is required for Fire and Police Departments. Contact Traffic Safety Coordinators Beth Adams at (214) 670-5896 or Gary Hughes at (214) 670-5662.
S-15 TRANSPORTATION/TRAFFIC CONTROL
The Contractor shall provide a Traffic Control Plan to assure two- w a y traffic and uninterrupted access to properties at all times.
S-16 STORM DRAIN MANHOLES CORROSION PROTECTION
All proposed Storm Drain Manholes coating shall conform to Public Works Construction Standards Fifth Edition, unless otherwise specified in the plans. NO SEPARATE PAY
ITEM.
S-17 TEMPORARY PAVING
Temporary Paving will be placed over the compacted, backfilled ditch in paved areas.
The Temporary Paving shall consist of 6” minimum thickness flexible base and High- Performance mix asphalt at the width and 2” minimum thickness as specified for payment in the bid items.
The Contractor may exceed these limits of measure for payment; however, all cost associated with this increase will be at the Contractor's expense. If the Contractor concludes the Temporary Pavement is not adequate in thickness or width for the conditions, this should be taken into account when preparing the bid.
Temporary surface shall be adequately compacted and sealed to prevent degradation of the repair during the temporary period. Any temporary surface shall be repaired or removed and replaced, as directed by the Engineer, at the Contractor's expense.
If an alternate route is required, the placement and removal of Flex Base and Asphalt
Paving as approved by the Construction Engineer will be entirely at the Contractor's expense.
S-18 POST CONSTRUCTION CONTRACTOR AND SUBCONTRACTOR/ SUPPLIER
EVALUATION
The Contractor will be evaluated by the Owner. The completed form will be submitted for the Contractor's signature prior to final payment.
The Contractor shall evaluate each Subcontractor and Supplier. The evaluation(s) will be furnished to the Owner prior to payment of the final estimate.
Examples of the evaluation forms are available at 2121 Main Street, Suite 400, Dallas, Texas 75201.
S-19 CONTRACTOR ENVIRONMENTAL PACKET
Contractor shall read and understand 107.28 of the City of Dallas NCTCOG Addendum, Latest Edition, and provide a signed “Environmental Record Affidavit” prior to start construction.
S-20 PRIORITY CONSTRUCTION LOCATIONS
Owner reserves the right to prioritize locations not identified at this time prior to the “Notice To Proceed” letter being issued for this Contract.
S-21 DENSITIES
Densities shall be taken at the amount of three (3) per one hundred (100) feet of open cut trench excavation, equally spaced.
The density tests are to be conducted by DWU’s approved soil density labs. The depths of the samples and the approximate locations are to be coordinated and approved by the DWU Stormwater Field Inspector.
All densities shall meet the requirements set forth in the pavement Cut and Repair
Standards Manual issued by the Department of Public Works and Transportation as applicable.
Payment for these services related to DWU’s Stormwater Project Manager’s Projects shall be borne by DWU’s Stormwater program.
S-22 CONSTRUCTION ADJACENT TO SCHOOLS
The Contractor is instructed to carefully control his operations when nearby schools, particularly during the morning and afternoon drop-off and pick-up hours, to assure continuous safety of schoolchildren and adults.
The Contractor shall install water and wastewater mains in such a way as to minimize disruption to the school operations. The Contractor shall coordinate construction activities through the Construction Engineer. The Contractor shall notify the School Principals at least ten (10) working days prior to beginning construction adjacent to the school. All work including paving operations and clean-up shall be completed immediately after the water line is tested.
S-23 PERFORMANCE OF WORK BY THE CONTRACTOR
Contractor Participation. Except as otherwise provided, the Contractor shall perform no less than 25 percent (25%) of the work with his own organization. The on-site production of materials produced by other than the Contractor's forces shall be considered as being subcontracted. If, during the progress of work hereunder, the Contractor requests a reduction in such participation percentage and the OWNER determines that it would be to the OWNER'S advantage, the percentage of work required to be performed by the Contractor may be reduced; provided, written approval of such reduction is obtained by the Contractor from the OWNER.
The organization of the Specifications into divisions, sections, and articles, and the arrangement and titles of project drawings shall not control the Contractor in dividing the work among subcontractors or in establishing the extent of work to be performed by any trade.
S-24 DAMAGE TO EXISTING STRUCTURES AND OTHER UTILITIES
Contractor shall take care to protect, and to not cause damage to, existing structures and other utilities as specified in 107.23, 203.1, and all Addenda thereto. If any utility structure, line, service, or any other structure or utility is damaged, contractor shall notify the structure or utility Owner or Operator immediately upon causing the damage incident as per local, state, and federal laws and regulations. Contractor shall notify DWU Inspector or Superintendent within one hour from the time of the damage incident. In case of service disruption to an individual or in case of an emergency, contractor shall also attempt to notify adjacent property owner of the damage incident.
Contractor crew which caused the damage incident shall incur a one day mandatory shut-down for each occurrence of a failure to notify DWU Inspector or Superintendent within one hour of a damage incident. Contractor crews shut down as provided will not be prohibited from performing site cleanup or general maintenance on any mandatory shut down day. Contractor shall be responsible for all costs and delays incurred. NO
SEPARATE PAY ITEM.
S-25 PRE-CONSTRUCTION VIDEO
The Contractor is required to furnish a pre-construction video of the segments prior to moving any equipment, material, or personnel to that location as stipulated in the DWU Standard Technical Specifications for Water and Wastewater Construction, Latest Edition. NO SEPARATE PAY ITEM.
S-26 POST-CONSTRUCTION VIDEO
The Contractor is required to furnish a post-construction video of the segments after all
Storm Drainage and Erosion Control work and site restoration is complete as stipulated in the DWU Standard Technical Specifications for Water and Wastewater Construction, Latest edition. NO SEPARATE PAY ITEM.
S-27 ENVIRONMENTALLY CONTAMINATED SOIL
In the possible event where environmentally, contaminated soil is encountered at any project site; the City of Dallas will hire a third-party environmental consultant who will determine the extent of environmental contamination through laboratory testing and environmental analysis. The third-party consultant will be responsible for:
• Site reconnaissance and environmental study,
• Soil borings and evaluation,
• Determination of site-specific chemicals,
• Development of environmental soil and ground water management plan,
• On-site environmental inspection of waterline installation,
• Loading, transport and disposal of environmentally contaminated soil to appropriate landfill.
The cost associated with the items above will be paid by the City.
Contractor is instructed to immediately contact the Owner Representative when environmental issues arise so that arrangements can be made. Contractor will coordinate with the third-party environmental consultant as necessary for the compliance of environmental requirements.
Any delay of the project due to environmentally contaminated soil will be adjusted in contract milestones. City will not provide any additional compensation to the contractor due to the delay caused by encountering environmentally contaminated soil.
S-28 HOT MIX ASPHALTIC CONCRETE PAVING
Contractor shall provide Hot Mix Asphaltic Concrete mix design submittal for review and approval prior to commencement of work. Mix design must have been previously approved for use by Texas Department of Transportation (TxDOT) and be performing satisfactorily. Submittal shall include a list of TxDOT projects where the mix was installed. Submittal shall include source of asphaltic materials, laboratory test results as specified in 302 of these Specifications and Addenda thereto, and equipment listing for spreaders, finishers and rollers to be used. Contractor shall submit a separate mix design, complete as specified hereto, for each permanent asphalt type required for the project. Owner shall, at owner’s discretion, perform materials testing to ensure control of materials and installation. Contractor shall notify Inspector no less than 24-hours prior to asphalt placement. These requirements shall be considered inclusive to the permanent paving pay items.
S-27 MACHINE FINISH PERMANENT PAVING
Unless otherwise specified or approved by owner, permanent paving restoration of cuts greater than eight (8) feet width in asphalt requires machine spreading and machine finishing, and greater than eight (8) feet width in concrete requires machine finishing, per 302.9.6.6 and 303.5.6, of these specifications, respectively and addenda thereto.
These requirements shall be considered inclusive to the permanent paving pay items.
S-28 PERMANENT PAVEMENT RESTORATION COMMENCEMENT
As a condition of the street cut permit, issued on behalf of Contractor and per Dallas
City Code Chapter 43 by Ordinance 24495, amended by Ordinance 25409 and then amended by Ordinance 29993: Contractor is notified that permanent paving restoration shall commence no later than 14 calendar days after paving release is issued.
Liquidated Damages shall be $500.00 per calendar day.
S-29 CITY OF DALLAS ORDINANCE 29993
Ordinance 29993, amending the street cut permit conditions and requirements of the
City Code, went into effect as a result of Council action on 1/27/2016 by Resolution 16-0193, and is made part of this contract as per 107.16 of these specifications and addenda thereto.
S-30 PERMANENT PAVING REPAIR LIMITS
City of Dallas Pavement Cut and Repair Standards establish the minimum repair standard required and rules for determining actual extent necessary. Some project locations require the extent of paving repairs in excess of the minimum repair extent, up to and including the full width of the street. Quantities for these locations have been calculated and included in the contract. Final determination of paving limits will be made by the City of Dallas at these locations prior to release to contractor for final paving repairs. All paving repairs are considered Contract Work. Compensation will be at the bid unit rates established for the bid items, as applicable. Repairs necessitated as a result of contractor’s inadequate construction means and methods, or due to contractor damage to adjacent property are non-compensatory repairs.
S-31 UNCLASSIFIED CHANNEL EXCAVATION FOR EROSION CONTROL
IMPROVEMENT
All authorized excavation; dewatering; undercutting subgrade and reworking or replacing the undercut material; hauling; disposal of material not used elsewhere on the project; scarification and compaction; and equipment, labor, materials, tools, and incidentals are subsidiary to Erosion Control Improvement including, but not limited to Gabion Structure, Concrete Retaining Wall, or Flexmat.
Excavation shall not exceed five (5) feet around the perimeter of or behind the structure unless otherwise noted in the plans or if authorized by project manager.
Existing appurtenances and materials determined by the Owner to be salvageable shall be protected. Material removed that is not deemed to be salvageable is the property of the Contractor. Dispose of removed material off the site in accordance with federal, state, and local regulations. This item shall adhere to NCTCOG ITEM 203.5
UNCLASSIFIED CHANNEL EXCAVATION.
Unclassified channel excavation for Erosion Control Improvement is a NO SEPARATE PAY ITEM, unless otherwise specified.
S-32 TEMPORARY WATER CONTROL
Contractor is responsible for temporary water control during construction, if required.
NO SEPARATE PAY ITEM.
S-33 ROCK FILTER DAM
The purpose of a rock filter dam is to reduce the velocity of small concentrated flows, provide a limited barrier for sediment and help disperse concentrated flows, reducing potential erosion. Rock filter dams are typically used early in construction in swales for long linear projects such as roadways. They can also be used in short swales with a steep slope to reduce unacceptable velocities. Rock Filter dams shall not be used in live stream channels. Rock filter dams shall be placed in accordance with NCTCOG
201.9. CHECK DAM (ROCK).
All items including labor and materials associated with installation, maintenance and removal of rock f ilter dam as required or as shown in the construction plans and SWPPP are the Contractor’s responsibility and are included in the construction of every project, if required. NO SEPARATE PAY ITEM.
S-34 BID EVALUATION
An award will be made to the lowest responsive Bidder subject to Bid Proposal Tabulation and Contractor Experience Record review.
Owner will award a contract based on the Total Base Bid amount. The Owner may choose to add the additive bid items: The Base Bid and Additive Bids consist of the following schedules:
• Base Bid consists of all bid items in schedule A-1, B-1, B-2, B-3 and B-4
The City will review and evaluate the proposals submitted to determine if submitted proposals demonstrate the required experience and qualifications to fulfill the obligations of the services identified in this Request for Bid (RFB).
The City may conduct all necessary inquiries or investigations, including but not limited to, contacting references to verify the statements, documents, and information submitted in connection with the Proposal. The City may also seek clarification from the referenced proposers about any financial and experience issues.
Please be aware that the City of Dallas may use sources of information not supplied by the proposer concerning the abilities to perform this work. Such sources may include current or past customers of the organization; current or past suppliers; articles from industry newsletters or other publications or from non-published sources made available to the City of Dallas.
Upon completing a thorough review and/or investigation, if inaccurate information is found, the vendor may be disqualified from submitting bid or proposal for the solicitation.
S-39 TEMPORARY PAVING
Temporary Paving will be placed over the compacted, backfilled ditch in paved areas. The Temporary Paving shall consist of 6” minimum thickness flexible base and High-Performance mix asphalt at the width and 2” minimum thickness as specified for payment in the bid items.
The Contractor may exceed these limits of measure for payment; however, all cost associated with this increase will be at the Contractor's expense. If the Contractor concludes the Temporary Pavement is not adequate in thickness or width for the conditions, this should be taken into account when preparing the bid.
Temporary surface shall be adequately compacted and sealed to prevent degradation of the repair during the temporary period. Any temporary surface shall be repaired or removed and replaced, as directed by the Engineer, at the Contractor's expense.
If an alternate route is required, the placement and removal of Flex Base and Asphalt Paving as approved by the Construction Engineer will be entirely at the Contractor's expense.
S-40 EQUAL EMPLOYMENT OPPORTUNITY/NONDISCRIMINATION
The selected Bidder shall not discriminate against any employee or applicant for employment because of race, age, color, national origin, religion, marital status, sex, sexual orientation, military or veteran status, political opinions or affiliations, genetic characteristics, or disability, consistent with applicable laws.
The selected Bidder shall prohibit discrimination regarding, but not limited to, the following: employment, upgrading, demotion or transfer, recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection of training, including apprenticeship. The selected Bidder shall also comply with all applicable requirements of the Americans with Disabilities Act, 42 U.S.C.A. §§12301-12233, as amended. The selected Bidder agrees to post in conspicuous places, available to employees and applicants, notices setting forth the provisions of this nondiscrimination clause.
S-41 PRATT AND MAYRANT
Contractors’ mobilization will begin at Pratt and Mayrant location. This location needs to be completed first.
S-42 STEEL PLATE USAGE FOR PAVEMENT CUTS
City Ordinance 33394, amending Chapter 43 - Streets and Sidewalks of the City Code, was adopted by City Council on April 22, 2026, by Resolution 26-0719 and officially published on April 25, 2026. Amendment Section 5 for Ordinance Section 43-139, paragraph (7) of Subsection (d) covers use of steel plates to cover street pavement cuts and provides guidance on steel plate dimensions, usage fee, and maximum days for placement.
A 4 BID ITEMS
EROSION CONTROL
IMPROVEMENTS PROJECTS AT
VARIOUS LOCATIONS: PHASE 8
A 4. SCHEDULE A-1 – COUNTS BLVD S 4690 BID ITEMS
ITEM 11003 CLEARING AND GRUBBING FOR STORMWATER
PROJECTS
This item consists of required Clearing and Grubbing from the beginning to the end of the project. This item shall be in accordance with NCTCOG Item 201.1: Removal, Protection, and Replacement of Trees, Shrubbery, Plants, Sod, and Other Vegetation and NCTCOG ITEM 203.COD: Site Preparation. It includes the removal of all-natural material/soil, trees (less than 6 inches in diameter), snag trees/fallen trees (no size limits), brush, road material, and ancillary components such as trimming and mowing in order to begin construction and equipment access to the site. The Contractor is responsible for the protection of any item that is to remain. The City of Dallas Traffic Barricade Manual shall be utilized when directed to by the City of Dallas representative.
Payment will be Lump Sum at contract bid price. Partial Payment will be measured by 100-foot stations, regardless of the Right of Way width.
Payment will be made by the station at the prorated unit bid price per station for Clearing and Grubbing.
ITEM 11009 STORMWATER PROJECT MOBILIZATION
Mobilization includes the movement of all labor, equipment and supplies, establishment of facilities, and construction site access necessary for work, and other work and operations which must be performed and cost no directly attributable to other pay items, excluding bidding costs, which must be incurred in order to enable the Contractor to begin work on other contract items.
This item shall be measured as a Lump Sum. If the Lump Sum amount bid for Mobilization exceeds 10% of the Adjusted Contract Amount, the City will pay the excess (the amount that exceeds 10%) upon completion of the Project.
The adjusted contract amount is defined as the sum of all bid prices excluding water and wastewater main items minus the Lump Sum bid for Mobilization. When work begins on the other contract items, the Adjusted Contract Amount shall be used throughout for determining the amount earned under Mobilization.
The Lump Sum bid for this item shall not include any cost or sum for mobilization for work related to Dallas Water Utilities.
Partial Payments of the Lump Sum bid for Mobilization shall be limited as follows:
1. When 1% of the adjusted contract amount is earned, 50% of the Mobilization Lump Sum or 5% of the Public Works total contract amount shall be paid, whichever is less. Previous payments under this item will be deducted from this amount.
2. When 5% of the adjusted contract amount is earned, 75% of the Mobilization Lump Sum or 10% of the Public Works total contract amount
3. When 10% of the adjusted contract amount is earned, 90% of the
4. When all work under the contract is completed by the Contractor and accepted by the City, 100% of the Mobilization Lump Sum will be paid.
ITEM 11013 STORMWATER PROJECT PARTNERING
This item is intended for compensating the Contractor for all costs to implement Project Partnering as detailed in the DWU Standard Technical Specifications for Water & Wastewater Construction, Latest Edition.
This item to include hiring a third-party facilitator, travel and lodging expenses, meeting room rental, program materials, reproduction costs and all costs associated with Contractor's own personnel, Subcontractors and Suppliers participating in partnering.
This is a Contingent Item and payment will be made, as directed by the Project Manager to apply the entire contract. Payment for this item shall be Lump Sum.
ITEM 11027 BLOCK SODDING FOR STORMWATER PROJECT
This item consists of furnishing and placing approximately 100
Square Yards of Block Sodding in accordance with Item 204.5.1. Description, Item
204.5.2. Materials, and Item 204.5.3.2. Solid Sodding of these specifications and addenda thereto.
This is a Contingent Item and payment will be made, if placement is directed by the Project Manager.
This item consists of providing and installing grass sod as shown on the plans or as directed. The payment is made according to the unit bid price for block sodding of the species of grass specified on the plans. Payment will be in accordance with Item Item 204.5.4.COD: Measurement and Payment (Plugging and Solid Sodding) of these Specifications. This price is full compensation for securing a source, excavation, loading, hauling, placing, rolling, finishing, furnishing materials, equipment, labor, tools, supplies, and incidentals. Water used to maintain and prepare the sod before planting shall be subsidiary to this item. This is for use with Bermuda, St.
Augustine, or Buffalo grass.
Measurement and payment will be per Square Yard of completed and accepted work.
ITEM 11029 GRASS SEEDING BY HYDRO MULCHING FOR
STORMWATER PROJECT
This item consists of furnishing and placing approximately 100 Square Yards of Seed by Hydromulch in accordance with these specifications and addenda thereto. Hydromulch shall be in accord with Item 204.4. Fertilizer, Item
204.6.4.1. General, Item 204.6.4.4. Hydraulic Mulching And, Item 204.6.4.6.
Watering, Maintaining, and Finishing Seeded Areas of these specifications.
This item shall include all labor, tools, transportation, materials, (including topsoil, seed and fertilizer), equipment, supervision, and incidentals required to establish a grass turf.
Measurement and payment will be Square Yard in accordance with Item 204.6.5. Measurement and Payment of these specifications and addenda thereto.
ITEM 11035 LOCATE UNDERGROUND UTILITY NOT UNDER
PAVEMENT
This item provides for the location 1 Each underground utilities not under pavement. This item consists of excavating specific infrastructure(s) to determine type, size, location, elevation, and/or condition as determined by the Owner.
The disturbed area will be replaced with compacted backfill in accordance with NCTCOG ITEM 504. Open Cut – Backfill.
This item includes all equipment, materials and labor, saw-cut, pavement, base, and sub-base removal, excavation, backfill, compaction, disposal of excess materials, all temporary and permanent paving, and paving related items, sidewalk, curb and/or gutter, driveways, sod, costs for barricading, trench safety and support, support for existing utilities, and all other work associated with this item.
Payment will not be made under this item if the infrastructure is to be adjusted, abandoned, or replaced prior to the placement of backfill. If the investigation is for more than one infrastructure in the same excavation, payment shall be made for only one investigation.
Measurement and payment will be per Each complete in place. Payment will not be paid for unless approved by the Owner prior to the probing.
ITEM 11111 FURNISHING AND PLACING TOP SOIL
This item provides for the furnishing of 100 Square Yards of
Top Soil. This item is only to be utilized there is insufficient top soil on the project. All disturbed areas to be re-vegetated are required to have a minimum of six (6) inches of topsoil. The topsoil shall be able to support the growth of planting seeding, sodding and native grassland seeding and planting. This ITEM should adhere to NCTCOG Item
204.2. Topsoil
This is a Contingent Item and payment will be made as directed by the Project Manager. Measurement and payment for furnishing and placing topsoil shall be per Square Yard. Topsoil obtained on-site shall not be paid for separately.
ITEM 11113 SELECT BORROW MATERIAL FOR SUBGRADE
This item provides for the furnishing of 18 Cubic Yards of Borrow Material for Subgrade. Borrow material for subgrade consists of suitable granular material with a plasticity index (PI) less than 20, free from trash or other objectionable matter and reasonably free from lumps of earth. This item shall adhere to NCTCOG ITEM
203.4. This item is paid according to the contract bid price.
Measurement and payment for borrow materials is per Cubic Yard, finished in place. The price includes all material, labor, and other incidental expenses.
ITEM 11119 MODIFIED FLOWABLE BACKFILL FOR STORMWATER
PROJECT
This item consists of furnishing and placing 30 Cubic Yards Modified Flowable Backfill as per NCTCOG ITEM COD:504.2.3.5. This item is complete and includes all equipment, materials and labor to furnish flowable fill.
Measurement and payment will be per Cubic Yard, complete in place.
ITEM 11121C2 DRY RIPRAP 24 INCH RIPRAP WITH 18 INCH STONE
This item provides for the furnishing of 30 Cubic Yards of Dry
Riprap. This section shall cover work consisting of dry riprap, all complete ·in place in conformity with the lines, grades and details shown on the plans and in accordance with these specifications. Riprap shall be used for slope, bank and ditch bottom protection, for erosion control at the ends of pipes and structures, and at other designated locations in accordance with ITEM 11601 Grouted Riprap. The type of stone and the weight shall be as shown on the plans and adhere to NCTCOG ITEM 803.3.2.2.1 Types and ITEM
803.3.2.2.3 Weight for the type shown on the plans.
The contract unit price shall be the total compensation for preparing the subgrade, including excavation; for furnishing and placing all materials; for furnishing, placing, shaping and tamping backfill; for proper disposal of all surplus materials; and for all labor, tools, equipment, and incidentals necessary to complete the work, all in accordance with the plans and these specifications.
This item will be measured and paid for per Cubic Yard, based on the dimensions shown on the plans.
ITEM 11203 EROSION CONTROL FOR STORMWATER PROJECT
This item is to reimburse the Contractor for costs to install, maintain, and remove the pollution control devices per NCTCOG ITEM 202. Temporary Erosion, Sedimentation, and Water Pollution Prevention and Control to prevent sediment from entering the storm water system or waterway. Modifications or additions to the control measures used as directed by the Engineer will be at no additional cost.
This item to include all pollution control devices, such as hay bales, rock filter dam, silt fences, inlet protection, or even stabilized construction entrance and this also to include all equipment, materials, labor, and maintenance necessary to control storm water pollution.
Payment will be Lump Sum for complete, in place, maintained, removed, and accepted work.
ITEM 11301 TRAFFIC CONTROL
This item shall include the installation, maintenance, relocation, and removal of all traffic signs (street name, directional, informational or regulatory), barricades, temporary signs, temporary pavement markings (except those identified in the plans as another bid item), and all other traffic control measures necessary to provide for the safe travel of vehicles and pedestrians through, along, or around the construction site and for the protection of the work on the project. This item shall also include all labor, materials, supplies, equipment, and incidentals necessary to complete the work as specified
All barricades and warning signs will conform to those sections of the Texas Manual on Uniform Traffic Control Devices, latest edition, as amended by the Texas Department of Transportation.
Partial payment of the Lump Sum bid shall be limited as follows:
1. When 5% of the *adjusted contract amount is earned, 25% of the Lump Sum bid shall be paid.
2. When 25% of the *adjusted contract amount is earned, 50% of the Lump Sum bid shall be paid. Previous payments under this item will be deducted from this amount.
3. When 50% of the *adjusted contract amount is earned, 75% of the Lump Sum bid shall be paid. Previous payments under this item will be deducted from this amount.
4. When all work under the contract is completed by the Contractor and accepted by the
City, 100% of the Lump Sum bid shall be paid.
5. An overrun of the contract quantity will not be allowed under any circumstances unless the quantity is added by an approved change order.
6. If the Contractor fails to provide properly maintain barricades, signs, and traffic control devices in compliance with the specifications, the Contractor will be considered in non-compliance with this item and payment may be delayed for this item.
*The Adjusted Contract Amount is defined as the total contract amount less the lump sum bid for this item.
The Contractor shall submit the Traffic Control Plan prior to the Pre-Construction conference. If the Owner has revisions to the Traffic Control Plan, the Contractor shall make the revisions for the Pre-Construction conference.
ITEM 11309 REMOVE ASPHALT PAVEMENT
This item provides for breaking, removal, and disposal of 30 Square Yards of existing asphalt pavement and stabilized base materials, if removal of base material is shown on the plans. It includes all associated hauling charges and disposal fees; and all labor, materials, tools, equipment and incidentals to complete the work. All asphaltic material shall be disposed of at a landfill site that is certified to accept asphaltic material. A copy of the disposal ticket shall be furnished to the Owner. This Item shall adhere to ITEM 701.COD: General Structures.
Measurement and payment of this item is per Square Yard regardless of the depth.
ITEM 11373 ASPHALT CONCRETE GRADE “C” SURFACE
This item consists of constructing 4 Tons of hot-mix asphalt
(HMA) pavement layer composed of a compacted, dense-graded mixture of aggregate and asphalt binder mixed hot in a mixing plant as Type “C” Coarse Surface. Type “C” Surface shall adhere to all the requirements as stated in TxDOT ITEM 340 Dense Graded Hot-Mix Asphalt (Small Quantity) and NCTCOG ITEM 302 Asphalt Pavement.
Measurement and payment shall be by the Ton of composite hot-mix, which includes asphalt, aggregate, and additives. The work performed, and materials furnished in accordance with this ITEM and measured will be paid for at the unit bid price for “Dense Graded Hot-Mix Asphalt” of the mixture type, SAC, and binder specified. These prices are full compensation for surface preparation, materials including tack coat, placement, equipment, labor, tools, and incidentals.
ITEM 11401R 18” CLASS III RCP STORM DRAIN
This item consists of furnishing and placing approximately 20 Linear Feet of 18" CLASS III RCP STORM DRAIN in accordance with NCTCOG ITEM
501.6.1 Reinforced Concrete Culvert, Storm Drain, and Pipe and 251D-1, page 2006.
This item will be measured for payment by the linear foot. This is a plans quantity measurement item. Measurement will be made between the ends of the pipe barrel along the flow line. Measurement of spurs, branches, or new connecting pipe will be made from the intersection of the flow line with the outside surface of the pipe into which it connects. Where inlets, headwalls, catch basins, manholes, junction chambers, or other structures are included in lines of pipe, the length of pipe tying into the structure wall will be included for measurement, but no other portion of the structure length or width will be included. For multiple pipes, the measured length will be the sum of the lengths of the barrels.
This item shall be paid for at the contract unit price per Linear Foot. This price is full compensation for constructing, furnishing, transporting, placing, and joining pipes; shaping the bed; cutting pipes on skew or slope; connecting to new structures; concrete collars and reinforcing, breaking back, removing, and disposing of portions of the existing structure; replacing portions of the existing structure; cutting pipe ends on skew or slope; and equipment, labor, tools, and incidentals.
ITEM 11415 REINFORCED CONCRETE FOR PIPE HEADWALL AND
WINGWALLS
This item consists of approximately 5 Cubic Yards of reinforced concrete for furnishing, constructing, and installing concrete headwalls and wing walls for drainage structures and underpasses in accordance with City of Dallas Standard Details, File 251D-1, Page No. 2007. Use 3600 psi compressive strength concrete for cast-in-place and precast concrete units unless otherwise shown on the plans. Furnish cast-in-place or precast headwalls and wing walls unless otherwise shown on the plans.
This item includes full compensation for constructing, furnishing, transporting, and installing the headwalls or wing walls; connecting to existing structure; breaking back, removing and disposing of portions of the existing structure, and replacing portions of the existing structure as required to make connections; excavation and backfill; and concrete, reinforcing steel, corrugated metal pipe or RCP Storm Drain, equipment, labor, tools, and incidentals.
This item will be measured and paid per Cubic Yard. The quantity to be paid is the quantity shown in the proposal unless indicated otherwise in the plans. Additional measurements or calculations will be made if adjustments of quantities are required. For payment purposes, the wing wall height will be rounded to the nearest foot.
ITEM 11425 RCP WYE CONNECTION
This item consists of 1 Each furnishing and connecting new RCP Storm Drain to new…