Specifications 23IFB8867.pdf
PDF 62 KB Posted
- Attached to
- Base Course Gravel, CSP
- Solicitation number
- 23IFB8867
- Issued by
- Harding County, South Dakota
About this file
This document is a Specification for a state and local contract opportunity to purchase and deliver base course gravel to Custer State Park in South Dakota. The work consists of furnishing labor, tools, equipment, and materials to construct gravel surfacing at designated locations. The gravel must conform to specific gradation requirements. Delivery is required between June 26th and July 7th, with two tonnage options of 2,000 tons or 2,500 tons requested. Custer State Park will choose the final tonnage amount.
The accepted quantities of gravel surfacing will be paid for at the contract price per ton. Tonnage weight tickets will be required. No further details are provided regarding pricing terms, set asides, incumbents, funding, or other salient information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SDVendorManual_20211221.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02510
BASE COURSE GRAVEL SURFACING
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work shall consist of furnishing all labor, tools, equipment and materials necessary to construct the gravel surfacing at the locations shown on the plans.
PART 2 - MATERIALS
2.1 The aggregate for gravel surfacing shall consist of sound durable particles of gravel and sand, which may include limited amounts of fine soil particles. The gravel surfacing shall conform to the following gradation requirements:
Sieve Size Percent Passing by Weight
1" 100 3/4" 80-100 1/2” 68-91
No. 4 42-70 No. 8 29-58
No. 40 10-35 No. 200 3.0–20.0
Plasticity Index: 0-6
PART 3 - EXECUTION
3.1 Gravel will be hauled to the CSP gravel pit near the corrals, and to the intersection of Fishermans Flats Road and Swint Road. CSP will provide all necessary permits and haul agreements. CSP will provide a loader and operator to push up gravel into a pile. Delivery will be June 26th through July 7th.
Gravel needs to be bid in two tonnage amounts for each location.
2,000 ton
2,500 ton CSP will choose which tonnage will work best for the project.
Contact Jayme Severyn at (605)280-1811
PART 4 - METHOD OF PAYMENT
4.1 The accepted quantities of gravel surfacing shall be paid for at the contract price per ton complete in place.
4.2 Tonnage weight tickets for gravel surfacing will be required on this project.
END OF SECTION