Specifications_1.pdf

PDF 1 MB Posted

Attached to
DEVIL'S ELBOW CHIPSEAL Federal contract opportunity
Solicitation number
140L3625R0013
Issued by
Department of the Interior Bureau of Land Management

About this file

This document is a comprehensive set of standard specifications for construction by the Bureau of Land Management (BLM) Western Montana District, covering various construction and road-related activities. The specifications provide detailed technical requirements for materials, methods, testing, measurement, and payment across multiple sections including aggregate courses, asphalt concrete pavement, chip sealing, crack sealing, and other road and infrastructure construction processes.

The specifications outline precise technical standards for construction materials like aggregates, asphalt, geosynthetics, and traffic signage, with extensive requirements for quality control, testing procedures, and acceptance criteria. Each section includes detailed guidance on material selection, equipment usage, application methods, weather limitations, surface preparation, compaction, and measurement techniques. The document serves as a comprehensive technical reference for contractors performing construction work on federal lands, ensuring consistent quality, performance, and compliance with BLM engineering standards across various project types.

View the file

Other files for this federal contract opportunity

Other files attached to DEVIL'S ELBOW CHIPSEAL, newest first.
File Type Posted
Drawings_1.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEVIL’S ELBOW COMPLEX CHIP SEAL

SPECIFICATION INDEX

PREFACE ………………………………………………………………………………………………………………………………………………

FORMAT, ABBREVIATIONS, AND DEFINITIONS ..................................................................... Section 101

BID, AWARD, AND EXECUTION OF CONTRACT ……………………………………………………………….. Section 102

SCOPE OF WORK ................................................................................................................... Section 103

CONTROL OF WORK .............................................................................................................. Section 104

CONTROL OF MATERIAL ...................................................................................................... Section 105

ACCEPTANCE OF WORK ........................................................................................................ Section 106

LEGAL RELATIONS ................................................................................................................. Section 107

PROSECUTION AND PROGRESS ............................................................................................ Section 108

MEASUREMENT AND PAYMENT ........................................................................................... Section 109

MOBILIZATION ...................................................................................................................... Section 151

CONTRACTOR QUALITY CONTROL ........................................................................................ Section 153

REMOVAL OF STRUCTURES AND OBSTRUCTIONS ................................................................ Section 203

STRUCTURE EXCAVATION AND BACKFILL ............................................................................. Section 209

UNTREATED AGGREGATE COURSES .................................................................................... Section 301

MINOR CRUSHED AGGREGATE ............................................................................................. Section 302

ASPHALT CONCRETE PAVEMENT .......................................................................................... Section 401

ASPHALT CONCRETE ............................................................................................................. Section 403

FOG SEAL .............................................................................................................................. Section 406

CHIP SEAL .............................................................................................................................. Section 407

MICRO SURFACING ............................................................................................................... Section 409

SLURRY SEAL ......................................................................................................................... Section 410

ASPHALT TACK COAT ............................................................................................................ Section 412

ASPHALT PAVEMENT CRACK SEALING AND FILLING ............................................................ Section 414

ASPHALT CONCRETE PAVEMENT PATCHING ........................................................................ Section 418

CURB AND GUTTER ............................................................................................................... Section 609

ASPHALT MATERIAL .............................................................................................................. Section 702

AGGREGATE .......................................................................................................................... Section 703

JOINT MATERIAL ................................................................................................................... Section 712

GEOSYNTHETIC MATERIAL ……………………………………………………………………………………………… Section 714

TRAFFIC SIGNS AND MARKING MATERIAL ............................................................................ Section 718

MISCELLANEOUS MATERIAL ................................................................................................. Section 725

WMD - SPEC Page 1 of 2 Section 4 Revised 2025

Western Montana District

Standard Specifications for Construction

WMD-SPEC

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

WESTERN MONTANA DISTRICT

WMD - SPEC Page 2 of 2 Section 4

PREFACE

These Standard Specifications for the Construction are issued primarily for constructing roads and recreation sites on Federal Lands under the direct administration of the Bureau of Land Management, Western Montana District. These specifications are cited as “WMD-SPEC” indicating “Western Montana District Standard Specifications” for the Bureau of Land Management, Western Montana District, and contain both United States Customary and Metric units of measure.

When designated in a contract, the WMD-SPEC becomes part of the contract and binding upon all parties to the contract. Construction contracts of the Bureau of Land Management, Western Montanan District, are also governed by the following regulations:

● Federal Acquisition Regulation (FAR), Title 48, Code of Federal Regulations, Chapter 1; and

FAR, Chapter 1 is not included in the WMD-SPEC. A complete copy of the FAR can be found online at:

https://www.acquisition.gov/content/regulations

Standard Forms (SF) are not included in the WMD-SPEC. SF’s can be obtained online at:

https://www.gsa.gov/forms-library/solicitation-offer-and-award-construction-alteration-or-repair

WMD - SPEC Page 1 of 10 Section 101

Section 101. — FORMAT, ABBREVIATIONS, AND DEFINITIONS

101.01 Specifications Format. These specifications are divided into 10 Divisions.

Division 100 consists of general contract requirements for which no direct payment is made. The requirements contained in Division 100 are applicable to all contracts.

Division 150 consists of project contract requirements that are applicable to all contracts. Work under Division 150 is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.

Divisions 200 through 600 consist of construction contract requirements for specific items of work.

Work under these Divisions is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.

Division 700 contains the material requirements for Divisions 150 through 600. No direct payment is made in Division 700. Payment for material is included as part of the work required in Divisions 150 through 600.

The first three digits of the pay item number in the bid schedule identify the Section under which the work is performed.

101.02 Abbreviations. Whenever these abbreviations are used in the contract, they represent the following:

(a) Acronyms.

AASHTO — American Association of State Highway and Transportation Officials

ACI — American Concrete Institute

AGC — Associated General Contractors of America

AISC — American Institute of Steel Construction

AITC — American Institute of Timber Construction

ANSI — American National Standards Institute

APWA — American Public Works Association

ARTBA — American Road and Transportation Builders Association

ASME — American Society of Mechanical Engineers

ASTM — ASTM International

ATSSA — American Traffic Safety Services Association

WMD - SPEC Page 2 of 10 Section 101

AWPA — American Wood Protection Association

AWS — American Welding Society

AWWA — American Water Works Association

BMP — Best Management Practice

CFR — Code of Federal Regulations

CO — Contracting Officer and authorized representatives

CRSI — Concrete Reinforcing Steel Institute

EPA — Environmental Protection Agency

FAR — Federal Acquisition Regulations (48 CFR Chapter 1)

FHWA — Federal Highway Administration

FICA — Federal Insurance Contributions Act

FLH — Federal Lands Highway

FSS — Federal Specifications and Standards

FED-STD — Federal Standards

FUTA — Federal Unemployment Tax Act

ISO — International Organization for Standardization

ISSA — International Slurry Surfacing Association

JMF — Job-Mix Formula

MASH — Manual for Assessing Safety Hardware

MPI — Master Painters Institute

MSDS — Material Safety Data Sheet

MUTCD — Manual on Uniform Traffic Control Devices for Streets and Highways

NCHRP — National Cooperative Highway Research Program

NEMA — National Electrical Manufacturers Association

NIST — National Institute of Standards and Technology

OSHA — Occupational Safety and Health Administration

PCI — Precast/Prestressed Concrete Institute

PVC — Polyvinyl Chloride

PTI — Post-Tensioning Institute

SEP — Sand Equivalent Passing

SF — Standard Form

WMD - SPEC Page 3 of 10 Section 101

SI — International System of Units

SSPC — The Society for Protective Coatings

SWPPP — Storm Water Pollution Prevention Plan

UL — Underwriter's Laboratory

U.S. — United States of America

USC — United States Code

(b) U.S. Customary unit abbreviations and symbols.

°F — degree Fahrenheit temperature ft — feet length ft2 — square feet area ft3 — cubic feet volume in — inches length in2 — square inches area in3 — cubic inches volume lb — pound mass mi — mile length oz — ounces mass psi — pounds per square inch pressure

T — ton (2000 lb) mass yd — yards length yd2 — square yards area yd3 — cubic yards volume s — second time

° — degree plane angle

' — minute plane angle

" — second plane angle

(c) Metric unit abbreviations and symbols.

A — ampere electric current cd — candela luminous intensity

°C — degree Celsius temperature

WMD - SPEC Page 4 of 10 Section 101 d — day time g — gram mass

H — Henry inductance ha — hectare area

Hz — hertz (s-1) frequency

J — joule (N•m) energy

K — kelvin temperature kg — kilogram mass

L — liter volume lx — lux illuminance m — meter length mm — millimeter length m2 — square meter area m3 — cubic meter volume min — minute time

N — newton (kg•m/s2) force

Pa — pascal (N/m2) pressure t — metric ton mass

V — volt (W/A) electric potential

W — watt (J/s) power

Ω — ohm V/A electric resistance

(d) Metric prefix symbols.

E — exa 1018

P — peta 1015

T — tera 1012

G — giga 109

M — mega 106 k — kilo 103 c — centi 10-2 m — milli 10-3 µ — micro 10-6

WMD - SPEC Page 5 of 10 Section 101 n — nano 10-9 p — pico 10-12 f — femto 10-15 a — atto 10-18

(e) Slope notation (vertical : horizontal). For slopes flatter than 1V:1H, express the slope as the ratio of one unit vertical to a number of units horizontal. For slopes steeper than 1V:1H, express the slope as the ratio of a number of units vertical to one unit horizontal.

101.03 Definitions. The following definitions apply to this contract:

Award — The written acceptance of a bid by the CO.

Backfill — Material used to replace or the act of replacing material removed during construction.

Material placed or the act of placing material adjacent to structures.

Base — The layer or layers of material placed on a subbase or subgrade to support a surface course.

Bid — A written offer by a bidder to perform work at a quoted price.

Bidder — An individual or legal entity submitting a bid.

Bid Guarantee — A form of security assuring that the bidder will not withdraw a bid within the period specified for acceptance and will execute a written contract and furnish required bonds.

Bid Schedule — The prepared schedule included with the bid forms, containing the estimated quantities of pay items for which unit bid prices are invited.

Bridge — A structure more than 20 feet (6 meters) long, including supports, spanning and providing passage over a depression, waterway, railroad, highway, or other obstruction.

Clear Zone — The portion of the roadside, including the shoulder, available for the safe use by an errant vehicle in which the driver may regain control of the vehicle.

Commercial Certification — See Subsection 106.03.

Construction Limits — The limits on each side of the project that establish the area disturbed by construction operations and beyond which no disturbance is permitted. Typically, the construction limits are the same as the clearing limits, except when additional clearing is required.

Contract — The written agreement between the Government and the Contractor setting forth the obligations of the parties for the performance of and payment for the prescribed work.

Contracting Officer (CO) — An official of the Government with the authority to enter into, administer, and terminate contracts and make related determinations and findings. The term

WMD - SPEC Page 6 of 10 Section 101 includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO.

Contract Modification — A written change in the terms of the contract. Contract modifications are of the following forms:

(a) Administrative change. A unilateral contract change, in writing, that does not affect the substantive rights of the parties (such as a change in the paying office or the appropriation data).

(b) Change order. A written order, signed by the CO, directing the Contractor to make a change that FAR Clause 52.243-4 Changes authorizes the CO to order without the Contractor's consent.

(c) Supplemental agreement. A contract modification that is accomplished by the signature of the CO (unilateral contract modification) or by the signature of the CO and the Contractor (bilateral contract modification).

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work.

Contract Time — The specified time allowed for completion of contract work.

Crashworthy — A highway feature that has been successfully crash tested under MASH or the NCHRP Report 350, Recommended Procedures for the Safety Performance Evaluation of Highway Features.

Cross-Section — A vertical section of the ground or structure at right angles to the centerline or baseline of the roadway or other work.

Culvert — A structure, not classified as a bridge, that provides an opening under the roadway.

Day — A calendar day beginning and ending at midnight.

Density — Mass per unit volume of material. Specific gravity multiplied by the density of water.

Detour — A temporary rerouting of public traffic onto alternate existing roadways to avoid the work or part of the work.

Diversion — Defined as follows:

(a) A temporary rerouting of public traffic onto a temporary alignment within the project limits to bypass the work or a portion of the work.

(b) A temporary rerouting of water into a temporary channel or through a system of structures within the project limits to maintain water flow through or around the project.

WMD - SPEC Page 7 of 10 Section 101

Drawings — Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Federal Land Management Agencies — Federal agencies including the National Park Service, U.S.

Forest Service, U.S. Fish & Wildlife Service, U.S. Army Corps of Engineers, Bureau of Land Management, and Bureau of Reclamation.

Government — The Government of the United States of America.

Highway, Street, or Road — A general term denoting a public way for purposes of vehicular travel, including the entire area within the right-of-way.

Lane Mile (Lane Kilometer) — An area of pavement one mile (kilometer) long and one lane wide;

not including turn lanes, turnouts, parking area lanes, or other auxiliary lanes.

Layer — See "lift".

Lift — Defined as follows:

(a) When placing and compacting soils, aggregates, or pavement; a lift is a single, continuous layer of material that receives the same compaction effort throughout during a single work operation.

(b) When installing culvert pipe less than or equal to 48 inches (1200 millimeter) in diameter;

the backfill material placed on both sides of the pipe is considered to be contained in the same lift when the material is placed to the same elevation on both sides of the culvert, the compaction effort applied to one side of the culvert is the same as that applied to the other, and the compaction effort is applied to both sides of the pipe in a continuous operation.

Material — Substances specified or necessary to satisfactorily complete the contract work.

Measurement — The process of identifying the dimensions, quantity, or capacity of a pay item. See Section 109 for measurement methods, terms, and definitions.

Notice to Proceed — Written notice to the Contractor to begin the contract work.

Pavement Structure — The combination of subbase, base, paving geotextiles, and surface courses placed on a subgrade to support and distribute the traffic load to the roadbed.

Pay Item — A specific item of work for which a unit and price is provided in the contract.

Payment Bond — The security executed by the Contractor and surety or sureties and furnished to the CO to ensure payments as required by law to persons supplying labor or material according to the contract.

WMD - SPEC Page 8 of 10 Section 101

Performance Bond — The security executed by the Contractor and surety or sureties furnished to the CO to guarantee completion of the contract work.

Plans — The contract plans furnished by the Government showing the location, type, dimensions, and details of the work.

Production Certification — See Subsection 106.03.

Professional Engineer — Engineers holding valid state licenses permitting them to offer engineering services directly to the public. Engineers that are experienced in the work for which they are responsible, take legal responsibility for their engineering designs, and are bound by a code of ethics to protect the public health.

Profile Grade — The trace of a vertical plane intersecting a particular surface of the proposed road construction located according to the plans, usually along the longitudinal centerline of the roadbed.

Profile grade means either elevation or gradient of the trace according to the context.

Project — The specific section of the highway or other property on which construction is to be performed under the contract.

Right-of-Way — Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Roadbed — The graded portion of a highway prepared as a foundation for the pavement structure and shoulders.

Roadside — The area between the outside shoulder edge and the right-of-way limits. The area between roadways of a divided highway may also be considered roadside.

Roadway — In general, the portion of a highway, including shoulders, for vehicular use. A divided highway has two or more roadways. In construction specifications, the portion of a highway within the construction limits.

Roadway Prism — The volume defined by the area between the original terrain cross-section and the final design cross-section multiplied by the horizontal distance along the centerline of the roadway.

Roller Pass— One trip of a roller in one direction over one spot.

Shoulder — A portion of the roadway contiguous with the traveled way that accommodates pedestrians, bicycles, stopped vehicles, and emergency use; as well as for lateral support of the subbase, base, and surface courses.

Sieve — See AASHTO M 92.

WMD - SPEC Page 9 of 10 Section 101

Solicitation — The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Special Contract Requirements (SCR) — Additions and revisions to the standard specifications applicable to an individual project.

Specifications — The written requirements for performing work.

Standard Forms (SF) — Numbered forms issued by the General Services Administration for use as contract documents.

Standard Specifications — The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects approved for general application and repetitive use.

Station — A precise location along a survey line.

Structures — Bridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, end walls, buildings, sewers, service pipes, underdrains, foundation drains, and other constructed features that may be encountered in the work.

Subbase — The layer or layers of material placed on a subgrade to support a base.

Subcontract — The written agreement between the Contractor and an individual or legal entity prescribing the performance of a specific portion of the work.

Subcontractor — An individual or legal entity with which the Contractor sublets part of the work.

This includes subcontractors in all tiers.

Subgrade — The top surface of a roadbed upon which the pavement structure, shoulders, and curbs are constructed.

Substantial Completion — The point at which the project is complete such that it can be safely and effectively used by the public without further delays, disruption, or other impediments. For conventional bridge and highway work, the point at which bridge deck, parapet, pavement structure, shoulder, drainage, sidewalk, major demolition, roadway obliteration, permanent signing and markings, traffic barrier, safety appurtenance, utility, and lighting work is complete.

Substructure — Components of a bridge below the bearings of simple and continuous spans, skewbacks of arches, and tops of footings of rigid frames including backwalls, wingwalls, and wing protection railings.

Suitable Material — Rock or earth material that will provide stable foundations, embankments, or roadbeds, and is free of organic matter, muck, frozen lumps, roots, sod, or other deleterious material. Suitable material may require drying or adding water, root picking, and other methods of manipulation before use. Suitable material includes the classifications of material for which the project was designed.

WMD - SPEC Page 10 of 10 Section 101

Superintendent — The Contractor's onsite representative who has authority to act for the Contractor and is responsible for directing and supervising construction operations on behalf of the Contractor.

Superstructure — The entire bridge, except the substructure.

Surety — An individual or corporation legally liable for the debt, default, or failure of a Contractor to satisfy a contract obligation.

Surface Course — The top layer or layers of a pavement structure designed to accommodate the traffic load and resist skidding, traffic abrasion, and weathering.

Target Value — A number established as a center for operating a given process. Once established, adjustments should be made in the process as necessary to maintain a central tendency about the target value. Test results obtained from a well-controlled process should cluster closely around the established target value and the mean of the test results should be equal to or nearly equal to the established target value.

Traveled Way — The portion of the roadway designated for the movement of vehicles, exclusive of shoulders.

Unsuitable Material — Material not capable of creating stable foundations, embankments, or roadbeds. Unsuitable material includes muck, sod, or soils with high organic contents.

Work — The furnishing of labor, material, equipment, and other incidentals necessary to complete the project according to the contract.

WMD - SPEC Page 1 of 3 Section 102

Section 102. — BID, AWARD, AND

EXECUTION OF CONTRACT

102.01 Acquisition Regulations. Bid, award, and execution of the contract is governed by the FAR.

102.02 Preparation of Bids. Follow the requirements of FAR Clause 52.214-18 Preparation of Bids - Construction.

Execute and submit required standard forms, bid schedules, and solicitation provisions contained in the solicitation as part of the bid.

Insert a numeric unit bid price for each pay item for which a quantity appears in the bid schedule (WMD Form 102). Multiply the unit bid price by the quantity for each pay item and show the amount bid. When mathematical checks made by the Government show a mistake in the amount bid, the corrected unit price extension governs.

When the words "lump sum" appear as a unit bid price, insert an amount bid for each lump sum pay item.

When the words "contingent sum" or "fixed rate" appears as a unit bid price, include the Government inserted amount bid for the pay item in the total bid amount.

Total the amounts bid for each pay item and show the total bid amount.

The quantities listed in the bid schedule are approximate, unless designated as a contract quantity, and are used for the comparison of bids. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. The scheduled quantities may be increased, decreased, or deleted. Bid schedule quantities are considered the original contract quantities.

102.03 Bid Guarantee. Follow the requirements of FAR Clause 52.228-1 Bid Guarantee.

(a) General. Submit the bid guarantee on SF 24, Bid Bond. If the bid guarantee is other than a corporate or individual surety, sign the SF 24 as the principal and make a statement on the form pledging the security. Make checks or money orders payable to the agency issuing the solicitation.

(b) Power of attorney. A corporate surety shall submit a current power of attorney for the signing agent or attorney-in-fact with each SF 24.

(c) Evidence of guarantee assistance. A surety that has a guarantee of assistance from the Small Business Administration (SBA) shall submit a copy of SBA Form 990, Surety Bond Guarantee Agreement with each SF 24. In addition, submit a power of attorney for the surety representative identified in the agreement.

WMD - SPEC Page 2 of 3 Section 102

102.04 Individual Surety. Follow the requirements of FAR Clause 52.228-11 Pledges of Assets.

Complete and date the SF 28, Affidavit of Individual Surety after the solicitation date. The individual surety shall personally sign the SF 28. Bidders cannot serve as their own surety. See FAR 28.203 Acceptability of Individual Sureties.

After reviewing the SF 28, the surety may be requested to submit further documentation with respect to its assets, debts, or encumbrances. The information may be required to be furnished under oath. Failure of the surety to respond with the requested documentation within 7 days of receipt of the request is cause for rejection of the surety.

Any material misstatement by the surety, overstatement of assets (either as to ownership or value), or understatement of liabilities is cause for rejection of the surety. Substitution of individual sureties to support a bid bond after the bid opening will not be permitted.

Furnish documentary evidence as to the ownership and value of the assets pledged in support of the bond and details of the security interest in the assets by the individual sureties for the apparent low bidder within 14 days after the opening of bids. Failure to submit evidence within the time required will be grounds for declaring the surety unacceptable.

In addition, the CO may, after reviewing the SF 28 and documentary information on the security interest and the assets pledged; request the surety to submit further information and documents with respect to the documents submitted. The CO may require such information to be furnished under oath. Failure of the surety to accept such mail or failure of the surety to respond with the requested information or documents within 7 days of receipt of the request; will be cause for rejection of the surety.

These requirements are in addition to the requirements in FAR Subpart 28.203, except where in conflict with the requirements in the FAR, in which case the FAR controls.

102.05 Public Opening of Bids. Bids will be publicly opened at the time specified in the SF 1442, Solicitation, Offer, and Award. Their contents will be made public information. The Government reserves the right to reject bids as set forth in the FAR, Part 14.

102.06 Performance and Payment Bonds. Follow the requirements of FAR Clause 52.228-15 Performance and Payment Bonds – Construction.

Use SF 25, Performance Bond and SF 25A, Payment Bond for submitting the bonds.

The requirements contained in Subsections 102.03 and 102.04 relating to power of attorney, evidence of guarantee assistance, and individual sureties also apply to performance and payment bonds.

Submit the documentary evidence for individual sureties at the same time as the Affidavit of Individual Surety and security interest in assets pledged. A Contractor submitting an unacceptable individual surety in satisfaction of a performance or payment bond before the issuance of the

WMD - SPEC Page 3 of 3 Section 102

Notice to Proceed will be permitted one opportunity to substitute an acceptable surety or sureties within 7 days of receipt of notification that the surety is unacceptable.

The Government's right to direct the substitution of sureties to ensure the continuing acceptability of the bonds during the performance of the Contract according to FAR Clause 52.228-2 Additional Bond Security is not restricted.

These requirements are in addition to the requirements in FAR Subpart 28.203, except where in conflict with the requirements in the FAR, in which case the FAR controls.

WMD - SPEC Page 1 of 2 Section 103

Section 103. — SCOPE OF WORK

103.01 Intent of Contract. The intent of the contract is to provide for the construction and completion of the work described. The precise details of performing the work are not described, except as considered essential for the successful completion of the work. Furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

103.02 Disputes. Follow the requirements of FAR Clause 52.233-1 Disputes (Alternate I).

When requesting a CO's decision on an interpretation of contract terms for the recovery of increased costs; quantify the amount and certify the amount if required by FAR Clause 52.233-1 Disputes (Alternate I). Include an explanation of the interpretation of contract terms, the contract clause under which the claim is made, supporting documentation, and adequate cost data to support the amount claimed.

103.03 Value Engineering. Follow the requirements of FAR Clause 52.248-3 Value Engineering - Construction.

Before undertaking significant expenditures, submit a written description of the value engineering change proposal (VECP) concept. Within 14 days the CO will inform the Contractor as to whether the concept appears to be viable or if the concept is unacceptable. If the CO indicates that the concept appears to be viable, prepare and submit the formal VECP proposal.

103.04 Contractor Records. Upon request, provide records related to the contract to the Government for up to 3 years after final payment or for longer periods as provided by law.

Include a provision in subcontracts at all tiers giving the Government the same rights as provided above with respect to the subcontractor's records.

103.05 Partnering. To facilitate this contract, the CO offers to participate in a formal partnership with the Contractor. This partnership draws on the strengths of each organization to identify and achieve reciprocal goals. Partnering strives to resolve problems in a timely, professional, and non-adversarial manner. If problems result in disputes, partnering encourages, but does not require, alternative dispute resolution instead of the formal claim process. The objective is effective and efficient contract performance to achieve a quality project within budget and on schedule.

Acceptance of this partnering offer by the Contractor is optional, and the partnership is bilateral.

If the partnering offer is accepted, mutually agree with the CO on the level of organizational involvement and the need for a professional to facilitate the partnering process. Engage the facilitator and other resources for key Contractor representatives and the CO to attend a partnership development and team-building workshop usually between the time of award and the Notice to Proceed. Hold additional progress meetings upon mutual agreement.

WMD - SPEC Page 2 of 2 Section 103

The direct cost of partnering facilities, professional facilitation, copying fees, and other miscellaneous costs directly related to partnering meetings will be shared by the Contractor and Government. Secure and pay for facilities, professional fees, and miscellaneous requirements.

Submit invoices to the CO. The Government will reimburse the Contractor for 50 percent of the agreed costs incurred for the partnering process. The Government’s share will not exceed $5,000.

Each party is responsible for making and paying for its own travel, lodging, and meal arrangements.

No time extension for the completion of the project will be made for the use of partnering.

WMD - SPEC Page 1 of 7 Section 104

Section 104. — CONTROL OF WORK

104.01 Authority of the Contracting Officer (CO). The CO may delegate authority to Contracting Officer Representatives (COR) to decide on acceptability of work, progress of work, suspension of work, interpretation of the contract, and acceptable fulfillment of the contract. The term "CO" includes authorized representatives of the CO, including inspectors, acting within the limits of their authority as delegated by the CO.

104.02 Authority of Inspectors. Project Inspectors (PI) are authorized to inspect work including the preparation, fabrication, or manufacture of material for the project. The inspector is not authorized to alter or waive contract requirements, issue instruction contrary to the contract, act as foreman for the Contractor, or direct the Contractor's operations. The inspector has authority to identify non-conforming work until the issue can be referred to and decided by the CO. The inspector may take necessary action to prevent imminent and substantial risk of death or injury including stopping work.

104.03 Specifications, Drawings, and Submittals. Follow the requirements of FAR Clause 52.236-21 Specifications and Drawings for Construction.

(a) General. Review and submit documents required to construct the work for accuracy, completeness, and compliance with the contract for approval by the CO. Documents submitted without evidence of Contractor approval may be returned for resubmission. Time for approval starts over when documents are returned for revision or if additional information is requested by the CO. Do not perform work related to submitted documents or drawings before approval of the CO. Obtain written approval before changing or deviating from the approved drawings.

(1) Documents other than drawings. Documents other than drawings include descriptive literature, illustrations, schedules, performance and test data, and similar material submitted by the Contractor to certify or explain, in detail, specific portions of the work required by the contract. Unless otherwise indicated in the contract, submit 3 paper copies and an electronic copy for review. Allow 14 days for approval by the CO unless otherwise specified.

(2) Drawings. Drawings include:

(a) Layouts that show the relative position (vertical and horizontal as appropriate) of work to be performed;

(b) Fabrication details for manufactured items and assemblies;

(c) Installation and erection procedures;

(d) Details of post-tensioning and other systems;

(e) Detailed trench and excavation procedures that conform to OSHA requirements;

(f) Traffic control implementation drawings; and

WMD - SPEC Page 2 of 7 Section 104

(g) Methods for performing work near existing structures or other areas to be protected.

Show drawing dimensions in the same units as shown in the plans. Limit drawings to a maximum size of 24 by 36 inches (610 by 920 millimeters). Include on each drawing and calculation sheet, the project number, name, and other identification as shown in the contract.

Submit 3 paper sets of drawings, an electronic set of the drawings, and supporting calculations. Drawings will be reviewed in the order they are received. Allow 40 days for CO approval of railroad structure drawings and 30 days for approval of other drawings. Submit additional specific drawings for unique situations to clarify layout, construction details, or method when requested by the CO.

(b) Specific requirements for concrete and miscellaneous structures.

(1) Submit drawings for the following:

(a) Site-specific layouts for all wall types and gabion installations;

(b) Gabion and revet mattress details and installation procedures;

(c) Forms and falsework for cast-in-place non-bridge concrete structures and retaining walls less than or equal to 6 feet (1.8 meters) in height;

(d) Fabrication drawings for bridge railings and parapets;

(e) Fabrication drawings for prestressed members;

(f) Fabrication and installation drawings for expansion joint assemblies;

(g) Fabrication drawings for bearing assemblies;

(h) Construction joint location and concrete deck placement sequences not according to the plans;

(i) Erection diagrams for Soil-Corrugated Metal Structure interaction systems (multi-plate structures);

(j) Structural steel fabrication drawings;

(k) Utility hangar details;

(l) Fabrication and installation drawings for precast items; and

(m) Site-specific layouts for rockeries.

(2) Submit drawings that bear the seal and signature of a professional engineer proficient in the pertinent design field for the following:

(a) Forms and falsework for cast-in-place concrete structures greater than 6 feet (1.8 meters) in height;

(b) Shoring systems and cofferdams greater than 6 feet (1.8 meters) in height;

WMD - SPEC Page 3 of 7 Section 104

(c) Shoring systems that support traffic loadings;

(d) Bridge concrete forms, including deck forms; except for railings, parapets, and components less than 6 feet (1.8 meters) in height;

(e) Containment structures for bridge work;

(f) Girder erection plans;

(g) Partial demolition of structural bridge elements;

(h) Post-tensioning systems;

(i) Concrete box culvert and headwall details;

(j) Reinforced soil slopes details;

(k) Ground anchors, soil nail, rock bolt, driven pile, drilled shaft, and micropile assembly details, layout, and installation and testing procedures;

(l) MSE and tie back wall details;

(m) Alternate retaining wall details; and

(n) Details and installation procedures for proprietary wall systems.

(3) Submit drawings that bear the seal and signature of a professional engineer who is proficient in forms and falsework design and licensed in the state where the project will be constructed for the following:

(a) Falsework for structures with spans exceeding 16 feet (4.8 meters);

(b) Falsework for structures with heights exceeding 14 feet (4.3 meters);

(c) Falsework for structures where traffic, other than workers involved in constructing the structure, will travel under the structure; and

(d) Temporary bridge structures for public use.

(c) As-built drawings. Use one set of Government approved plans exclusively for as-built drawings. Use the color "red" to identify changes. Use approved methods to accurately and neatly record changes. Include details and notes on additional information discovered during construction. Note additions or revisions to the location, character, and dimensions of work.

Strikeout details shown that are not applicable to the completed work.

As work progresses, continuously update plan sheets to reflect the as-built details. Check and initial plan sheets that were incorporated into the completed work without change. Include the following:

(1) Title sheet.

(a) "AS-BUILT DRAWINGS" (bold text);

WMD - SPEC Page 4 of 7 Section 104

(b) Name of Contractor;

(c) Name of CO’s on-site representative;

(d) Project completion date;

(e) Revisions to project length;

(f) Revisions to begin and end stations of project;

(h) Revisions to index to sheets;

(i) Revisions to curve widening table;

(j) Strikeout schedules or options not awarded;

(k) A note stating "Work was constructed as designed unless otherwise noted."; and

(l) Plan notes.

(2)Typical section sheets.

(a) Revisions in dimensions;

(b) Revisions in material;

(c) Revisions in station range;

(d) Revisions to begin and end stations of project; and

(e) Strikeout schedules or options not awarded.

(3) Summary of Quantities and tabulation sheets.

(a) Revisions to quantities, locations, notes/remarks, including totals;

(b) Strikeout unused pay items;

(c) Revisions to application rates; and

(d) Revisions to location, type, end treatments, riprap, and skew on the drainage summary.

(4) Plan and profile sheets. Note additions or revisions to the location, character, and dimensions of the following items:

(a) Plan.

(1) Alignment and curve and spiral information;

(2) Construction limits;

(3) Right-of-way;

(4) Road approaches;

WMD - SPEC Page 5 of 7 Section 104

(5) Sub-excavation and roadway obliteration;

(6) Underdrains;

(7) Trenches and drains;

(8) Channels and ditches;

(9) Monuments and permanent references;

(10) Constructed, relocated, or encountered utilities; and

(11) Walls.

(b) Profile.

(1) Grades, elevations, and stationing of points of intersection;

(2) Equations;

(3) Culvert diameter, length, type, and stationing;

(4) Culvert extension and length of existing culvert;

(5) Walls; and

(6) Guardrail, guardwall, and end treatment.

(5) Bridge sheets. Note additions or revisions to the location, character, and dimensions of the following items:

(a) Stationing of bridge ends;

(b) Elevations including footing, bearing pads, deck, and top of walls;

(c) Pile driving record with pile length, size, type, and tip elevation;

(d) Modifications or repairs to drilled shafts or micropiles;

(e) Micropile installation records with drilling duration and observations, drill log, final location and inclination, final tip elevation, cut-off elevation, modification or repairs, grout pressures and quantities, and test records;

(f) Post-tensioning records including stressing sequence, jacking force, and duct size and layout;

(g) Construction and concrete placement sequences;

(h) Bearing details with orientation;

(i) Expansion joints including actual clearance with atmospheric temperature at time of setting joints; and

(j) Changes in plan or dimensions including changes in reinforcing.

WMD - SPEC Page 6 of 7 Section 104

(6) Miscellaneous sheets. Note additions or revisions to the location, character, and dimensions of the following items:

(a) Parking areas and turnouts;

(b) Curbs and sidewalks;

(c) Fencing;

(d) Landscaping and planting;

(e) Pavement markings;

(f) Signs;

(g) Permanent erosion control measures; and

(h) Plan notes.

(7) Standard and detail sheets. Note the additions or revisions to the character and dimensions of details.

Retain the drawings at the project site.

Keep the as-built drawings current and maintain a revision log of changes made. Meet with the CO to jointly review the as-built drawings and log for accuracy, completeness, and legibility before submission of each monthly invoice.

Submit the final as-built drawings and revision logs before the final inspection. Correct errors and omissions found during the final inspection and resubmit the final as-built drawings for approval within 7 days after the final inspection.

When the final as-built drawings are approved, submit the finalized set of as-built drawings and a single file, electronic color copy of the drawings. Submit the electronic copy in an approved format on a CD-R, DVD-R, or other approved electronic media. Include the latest version of the approved reader on the electronic media. Provide a resolution quality where color, text, and lines are clearly discernible.

(d) Submittals. The Contractor shall submit, for review, a proposed schedule of shop drawings, product data, and material data submittals. This schedule will include concrete and asphalt concrete mix designs unless they are previously approved supplier’s mix design.

The schedule will show the proposed submittal date to the CO and the needed response date for each submittal and will indicate the relationship of the submittal to the project construction schedule. The submittal date and response date shall give the CO a minimum of 5 business days for review and response.

104.04 Coordination of Contract Documents. The FAR, special contract requirements, plans, and standard specifications are contract documents. A requirement in one document is binding as

WMD - SPEC Page 7 of 7 Section 104 though occurring in all the contract documents. The contract documents are intended to be complementary and to describe and provide for a complete contract. In case of discrepancy, calculated and shown dimensions govern over scaled dimensions. The contract documents govern in the following order:

(a) Federal Acquisition Regulations;

(b) Special contract requirements;

(c) Plans; and

(d) Standard specifications.

104.05 Load Restrictions. Follow the requirements of FAR Clause 52.236-10 Operations and Storage Areas.

Comply with legal load restrictions when hauling material and equipment on public roads and bridges to and from the project. A special permit does not relieve the Contractor of liability for damage resulting from the moving of material or equipment.

Unless otherwise permitted, do not operate equipment or vehicles that exceed the legal load limits over new or existing structures, or pavements within the project; except those pavements to be removed during the same construction season.

WMD - SPEC Page 1 of 3 Section 105

Section 105. — CONTROL OF MATERIAL

105.01 Source of Supply and Quality Requirements. Follow the requirements of FAR Clause 52.236- 5 Material and Workmanship.

Select sources and submit acceptable material. Notify the CO of proposed sources before delivery to the project to expedite material inspection and testing. Do not incorporate material requiring submittal into the work until approved.

Material may be approved at the source of supply before delivery to the project. Approval of a material source does not constitute acceptance of material submitted from the source. If an approved source fails to supply acceptable material during the life of the project, further use of that source may be denied.

Submit samples of material for source quality verification testing for material required to conform to Sections 703, 704, and 705.

105.02 Material Sources.

(a) Government-provided sources. The Government will acquire the permits and rights to remove material from provided sources identified in the contract and to use such property for a plant site and stockpiles. Test reports and available historical material data will be furnished to the Contractor upon request.

Do not perform work within a source until a source development plan is approved. Allow 7 days for approval. Include the following as applicable:

(1) Requirements of written agreements;

(2) Requirements in Sections 107, 157, 204, 205, 624, and 625;

(3) Source development details;

(4) Restoration details; and

(5) Abandonment details.

Perform work necessary to produce acceptable material including work required by the approved source development plan.

The quality of material is generally acceptable. Variations in quality should be expected as it is not feasible to ascertain the quality of material for an entire deposit from exploratory samples.

Determine the quantity, type of equipment, and work necessary and produce acceptable material to be incorporated into the work. Do not perform aggregate source quality tests listed in the Sampling, Testing, and Acceptance Requirements table of other Sections when using Government-provided sources. Perform quality control sampling and testing according to the

WMD - SPEC Page 2 of 3 Section 105 approved Contractor Quality Control Plan in Section 153 and the applicable Sampling, Testing, and Acceptance Requirements tables included at the end of each Section. Allow the CO the opportunity to witness sampling and splitting of the test material.

(b) Government-provided material stockpile. The quality of the material in the stockpile has been preapproved unless otherwise noted and is considered acceptable for the application for which it has been designated. Perform quality control sampling and testing according to the approved Contractor Quality Control Plan in Section 153 and the applicable Sampling, Testing, and Acceptance Requirements table included at the end of each Section. Test results submitted will be for the Government’s information only. Allow the CO the opportunity to witness sampling and splitting of the test material.

(c) Contractor-located sources. The Contractor is responsible for Contractor-located material sources, including established commercial material sources. Use sources that fulfill the contract quantity and quality requirements. Determine the quantity, type of equipment, and work necessary to select and produce an acceptable material. Secure permits and clearances for use of the source and submit copies of the documents to the CO. Follow the environmental requirements of Subsection 107.10(d). Submit available historical data indicating acceptable material can be produced from the source. Perform quality control sampling and testing according to the approved Contractor Quality Control Plan in Section 153, aggregate source quality tests, and applicable Sampling, Testing, and Acceptance Requirements table included at the end of each Section. Allow the CO the opportunity to witness sampling and splitting of the test material.

105.03 Material Source Management. Notify the CO at least 14 days before starting operations in the source. Develop and operate according to the approved source development plan for Government-provided sources or written agreement for Contractor-located sources.

Before developing a material source, measure the sediment content of bodies of water adjacent to the work area that will receive drainage from the work area. Perform erosion and sediment control according to the source development plan and the "Storm Water Pollution Prevention Plan (SWPPP)" or "Erosion Control Plan".

Do not remove material measured in-place from borrow sources or Government-provided stockpiles until initial ground survey measurements have been taken according to Subsection 204.16(b) and approved. Perform final ground survey measurements according to Subsection 204.16(b).

Dispose of rejected material in an approved manner.

105.04 Handling and Storing Material. Handle and store material to preserve its quality and fitness for the work.