Specification REV-0 dtd 12 June 2025.pdf

PDF 2 MB Posted

Attached to
USCG ANT PUERTO RICO (55115) FY26 DD REPAIR
Solicitation number
70Z04026QSBPL0006
Issued by

About this file

This is a comprehensive technical specification for the drydock repairs and maintenance of the USCG 55' Aids to Navigation Boat (ANB), hull class 55115 (ANB-55B), for Fiscal Year 2026. The specification outlines 43 distinct work items required during a scheduled drydock availability at a commercial contractor facility.

The scope encompasses critical hull and structural repairs including ultrasonic testing of underwater hull plating, complete preservation of the underwater body surfaces and partial freeboard preservation, and general welding repairs to structural components such as bumper supports, platform ladders, and deck gratings. Propulsion system work includes removal, inspection, and installation of propeller shafts; renewal of water-lubricated shaft bearings and propeller shaft packing; propeller removal and installation; and main diesel engine alignment and isolator renewal. The specification requires comprehensive maintenance of ship systems including sea valve renewal, sea strainer overhauls with duplex strainers, fuel and potable water tank cleaning and inspection, exhaust muffler and piping cleaning, standard and non-standard hose renewal (67 total hose assemblies across fuel, steering, and hydraulic systems), compressed air receiver hydrostatic testing, and rudder assembly removal and inspection. Additional work includes cleaning and inspection of bilge systems, grey water and sewage holding tanks, steering hydraulic oil tanks, and various deck preservation tasks using authorized coating systems per SFLC Standard Specification 6310. The specification mandates drydocking and undocking operations with specific blocking requirements, temporary services provision (office space, electrical shore power at 100 amp 120VAC single phase, parking, and storage), sea trial support with dock trials preceding waterborne trials, and Level II maintenance on buoy handling equipment including crane wire rope renewal, deck winch renewal, hydraulic power unit service, and chain stopper maintenance. All work must comply with SFLC Standard Specifications 0000, 0740, 5550, 6310, 8634, and 8635, with critical-coated surfaces requiring SSPC-QP-1 certified inspectors and comprehensive quality assurance documentation per provided QA forms QA-1 through QA-5.

View the file

Other files

File Type Posted
PPQ 55115.pdf PDF
Schedule of Supplies and Services _ 55115.pdf PDF
70Z04026QSBPL0006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG 55115 (ANB 55B)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2026

Developed By: Lauren M Hughes

(Rev-0, 12 June 2025)

USCG 55115 (ANB-55B) DRYDOCK AVAILABILITY FY2026

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Critical Inspection Items ............................................................................................. ix Principal Characteristics ................................................................................................................................ x General Requirements .................................................................................................................................. xi WORK ITEM 1: General Welding, Provide WORK ITEM 2: Hull Plating, U/W Body, Ultrasonic Testing WORK ITEM 3: U/W Body, Preserve, 100 percent WORK ITEM 4: Hull Plating Freeboard, Preserve, Partial WORK ITEM 5: Appendages, U/W, Leak Test WORK ITEM 6: Accessible Spaces, Inspect WORK ITEM 7: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 8: Tanks, Potable Water, Clean and Inspect WORK ITEM 9: Weather-tight Closures, Inspect WORK ITEM 10: Main Diesel Engine(s), Align WORK ITEM 11: Isolators, Main Diesel Engine, Renew WORK ITEM 12: Propeller Shafts, Remove, Inspect, and Install WORK ITEM 13: Propeller Shaft Packing Stuffing Box, Remove and Install WORK ITEM 14: Propeller Shaft Packing, Renew WORK ITEM 15: Water Lubricated Shaft Bearings, Renew WORK ITEM 16: Propellers, Remove, Inspect and Install WORK ITEM 17: Exhaust Muffler(s), Clean and Inspect WORK ITEM 18: Exhaust Piping, Clean and Inspect WORK ITEM 19: Fuel Valves, Renew WORK ITEM 20: Standard Hoses, Renew WORK ITEM 21: Non-Standard Hoses, Renew WORK ITEM 22: Sea Valves, Renew WORK ITEM 23: Sea Strainers, All Sizes, Overhaul WORK ITEM 24: Bilges, Inspect WORK ITEM 25: Diesel Tanks, Refuel WORK ITEM 26: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift ... 80 WORK ITEM 27: Steering Hydraulic Oil Tank, Clean and Inspect WORK ITEM 28: Rudder Assembly, Remove, Inspect and Reinstall WORK ITEM 29: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 30: Sewage Holding Tanks, Clean and Inspect WORK ITEM 31: Rub Rail, Fendering System, Remove, Inspect, Install WORK ITEM 32: Decks – Exterior (Buoy), Preserve 100 Percent WORK ITEM 33: Decks - Exterior, Preserve, Non-Skid Broadcast Grit System WORK ITEM 34: Hull Identification Markings, Apply WORK ITEM 35: Cathodic Protection / Zincs, Renew WORK ITEM 36: Exterior Non-slip Pads, Renew WORK ITEM 37: Interior Hull Insulation, Inspect WORK ITEM 38: Space(s) and Component(s), Preserve WORK ITEM 39: Marine Chemist Services, Provide WORK ITEM 40: Drydock WORK ITEM 41: Temporary Services, Provide WORK ITEM 42: Sea Trial Performance, Support, Provide WORK ITEM 43: Buoy Handling Equipment, Perform Level II Maintenance iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. The information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 55B ANB 101-4, Rev-B Inboard Profile Sections and Arrangement

Coast Guard Drawing 55B ANB 101-7, Rev -, Machinery Details

Coast Guard Drawing 55B ANB 101-10, Rev A, Fuel System Diagram

Coast Guard Drawing 55B-ANB 103-001, Rev K, Outboard Profile and Arrangements

Coast Guard Drawing 55 ANB 103-2, Rev R, Outboard Profile, Sections and Arrangements

Coast Guard Drawing 55B ANB 103-2, Rev-C Inboard Profile and Arrangement 55113-55119

Coast Guard Drawing 55 ANB 112-003, Rev C, Marine Crane Foundation Mods. (55101-55122)

Coast Guard Drawing 55B ANB 1101-001, Rev B, Construction Profile Plan and Sections

Coast Guard Drawing 55B ANB 1101-2, Rev A, Construction Details (55113-55119)

Coast Guard Drawing 55B ANB 1107-1, Rev -, Deckhouse Dimensions – Window & Door

Coast Guard Drawing 55 ANB 1112-003 Rev A, (Deck Winch) Foundation Port/Starboard (A, B & C Classes)

Coast Guard Drawing 55B ANB 2000-001, Rev A, Crane & Deck Winch Hydraulics 55113-55119

Coast Guard Drawing 55 ANB 2002-002 Rev A, Crane & Deck Hydraulics

Coast Guard Drawing 55 ANB 2200-1, Rev B, Rudder Stock & Stuff Box-Hub

Coast Guard Drawing 55 ANB 2200-2, Rev A, Steering Hydraulic System

Coast Guard Drawing 55 ANB 2200-3, Rev -, Rudder Bushing Bearing Top and Bottom

Coast Guard Drawing 55B ANB-3901-1, Rev D, Insulation Application & Details

Coast Guard Drawing 55B ANB 4000-1, Rev G, Machinery Arrangement

Coast Guard Drawing 55B ANB 4000-2 Rev B, Machinery Details (55113-55119)

Coast Guard Drawing 55B ANB 4103-002, Rev C, Main Engine Cooling System

Coast Guard Drawing 55B ANB 4301-001, Rev B, Shaft Coupling

Coast Guard Drawing 55B ANB 4301-002, Rev -, Propeller Shaft (B & C Class only)

Coast Guard Drawing 55B ANB 4801-003, Rev C, Bilge Piping

Coast Guard Drawing 55B ANB-4801-4, Rev-, Sanitary Drain Systems (B Class)

Coast Guard Drawing 55B ANB 4804-1, Rev -, Fresh Water Tank, Access & Cover

Coast Guard Drawing 55B ANB 4805-3, Rev B, Potable Water Piping (55113-55119)

Coast Guard Drawing 55B ANB 4901-002, Rev A, Compressed Air System

Coast Guard Drawing 55B-ANB-500-001, Rev -, Lines & Offsets 55113-55119 v (Rev-0)

Coast Guard Drawing 55 ANB 573-001, Rev B, Portable Chain Stopper and Mounting

Coast Guard Drawing 55 ANB 573-002, Rev A, Removable Tow Rope Guard For Chain Stopper

Coast Guard Drawing 55B ANB 5501-1, Rev A, Fuel System Diagram

Coast Guard Drawing 55 ANB 634-1, Rev -, Deck Covering

Coast Guard Drawing 55-ANB-8201-001, Rev A, Lifting Slings Arrangement & Details

Coast Guard Drawing 55-ANB-8201-002, Rev -, Boat Cradle Shipping

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing FL-85-002, Rev C, GFE Boat Hot Work Diagrams

Coast Guard Drawing FL 589-1, Rev -, Crane Wire Rope Info, Working Load Limits & Test Weights Table

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev A, Consolidated Visual ID for Cutters

COAST GUARD PUBLICATIONS

SWBS 561, Section A, Steering Gear System

SWBS Group(s) 533, Section A, Pump Freshwater

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Commandant’s Instruction Manual 16534.2 55 Aids to Navigation Boat (ANB) Operator’s Handbook (March 2007)

Coast Guard Naval Engineering Technical Standard TS-505-2 Hoses and Expansion Joints

Coast Guard Technical Publication (TP) 2048, August 1988, Manufacturer’s Information Book – SWBS Groups 233 Sections A,B,C - Main Diesel Engine – V71 Series

Coast Guard Technical Publication (TP) 2048, SWBS 233, Jun 1988, Manufacturer’s Information Book – SWBS Group 233, 55' ANB (A), (B), and (C) Type Boats, Sections A, B, and C

Coast Guard Technical Publication (TP) 3394, Jan 2006, Manufacturer’s Information Book SWBS Group 167-261

Coast Guard Technical Publication (TP) 3394, Jan, 2006, Manufacturer’s Information Book SWBS Group 167-261

Coast Guard Technical Publication (TP) 3394, January 2006, Manufacture’s Instruction Book- SWBS Group(s) 261, Section B, Globe Valves

Coast Guard Technical Publication (TP) 3394, SWBS 167-261, Jan 2006, Manufacturer’s Instruction Book, SWBS Group 167-261

Coast Guard Technical Publication (TP) 3394, SWBS 167-261, Jan 2006, Manufacturer's Instruction Book SWBS Group(s) 167-261, SWBS 241, Sec A, Marine Gear

Coast Guard Technical Publication (TP) 3395, Manufacturer’s Information Book SWBS Group 311-423.

SWBS 321, Section A, Shore Tie Connections

Coast Guard Technical Publication (TP) 3394, SWBS 233, Section B, Technical Manual, Isolators

Coast Guard Technical Publication (TP) 3395-320-A Power Distribution System (January 1999)

Coast Guard Technical Publication (TP) 3397, Manufacturer’s Instruction Book SWBS 561, Section A, Steering Gear System

Coast Guard Technical Publication (TP) 3397, Manufacturer’s Instruction Book

Coast Guard Technical Publication (TP) 3397, SWBS 529, Oct 2010, Manufacturer’s Instruction Book - SWBS Group 502-556, Section B, Bilge Pump vi (Rev-0)

Coast Guard Technical Publication (TP) 3398, May 2004, Manufacture’s Instruction Book – SWBS 625, Section A & B, Windows

Coast Guard Technical Publication (TP) 3398, May 2004, Manufacturer’s Instruction Book- SWBS 633, Section A, Zincs, Hull

Coast Guard Technical Publication (TP) 3487, April 2012, Manufacturer’s Instruction Book-SWBS Group(s) 589, Section A, Crane Model MCK-420KM and Section B, Hydraulic Planetary Hoist – Model BG6A & BG6B

Coast Guard Technical Publication (TP) 3923, Manufacturer’s Information Book, April 2004, Ships Service Diesel Generator Set - MDKBE

Coast Guard Technical Publications (TP) 3397, Manufacturer’s Instruction Book-

Coast Guard Technical Publications (TP) 55B ANB 3397-529-B Drainage and Ballasting System, (January 1999)

Coast Guard Technical Publication (TP) 4993, Oct 2011, Manufacturer’s Information Book SWBS 634, Nonskid Pads, Peed & Stick Catalog

Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects

American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) A53, 2005, Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets vii (Rev-0)

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2019, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust- Petrolatum

Commercial Item Description (CID) A-A-59316, Abrasive Materials for Blasting

Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-G-24716A, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

Naval Sea Systems Command (NAVSEA) S9AA0-AB-GOS-010/GSO, Aug 2000, General Specifications for Overhaul of Surface Ships, Section 305, Electrical and Electronic Designating and Marking

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams

NAVSEA Drawing 803-5001027, Electric Plant Installations, Standard Methods, Section 1, Group B, Sheet 5

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

Preparation Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric viii (Rev-0)

Society of Automotive Engineers (SAE) Standard J1475, 2009, Hydraulic Hose Fittings for Marine Applications

Society of Automotive Engineers (SAE) Standard J1942, 2009, Hose and Hose Assemblies for Marine Applications

Society of Automotive Engineers (SAE) Standard J1942-1, 2010, Qualified Hoses for Marine Applications

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC), Surface Preparation Standard SSPC-SP 1, November 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, July 2012, Near-White Blast Cleaning

Quincy Compressor QTS Industrial Series Model QTS-3 Manual ix (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars):

Work Item

Title

2 Hull Plating, U/W Body, Ultrasonic Testing

3 U/W Body, Preserve, 100 percent

5 Appendages, U/W, Leak Test

6 Accessible Spaces, Inspect

7 Tanks, MP Fuel Service, Clean and Inspect

9 Weathertight Closures, Inspect

12 Propeller Shafts, Remove, Inspect, and Install

13 Propeller Shaft Packing Stuffing Box, Remove and Install

14 Propeller Shaft Packing, Renew

17 Exhaust Muffler(s), Clean and Inspect

18 Exhaust Piping, Clean and Inspect

21 Non-Standard Hoses, Renew

23 Sea Strainers, Duplex, All Sizes, Overhaul

26 Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift

28 Rudder Assembly, Remove, Inspect and Reinstall

31 Rub Rail, Fendering System, Remove, Inspect, Install

32 Decks, Exterior (Buoy), Preserve 100 Percent x (Rev-0)

PRINCIPAL CHARACTERISTICS

55' ANB

PHYSICAL

Length overall 58' 4" Length overall - hull only 55' 0" Height – Fixed 14’7” Height – Unfixed 25’0” Operating displacement 64,620 lbs.

Cargo, maximum 4,000 lbs.

Full load displacement 68,620 lbs.

Draft at operating displacement 5' 0" Draft at full load 5' 11" Freeboard fwd @ full load displ 5' 9-7/8" Freeboard aft @ full load displ 4' 9-1/8" Hoisting weight 63,900 lbs.

Shipping weight 54,630 lbs.

HULL

Hull material Aluminum Hull 10 each, bolted Propeller Shaft: 2 per shaft Frame spacing FR 1 to 2 3' 6" FR 2 to 8 4' 0" FR 8 to 9 3' 3" FR 9 to 10 3' 0" FR 10 to 13 3' 3" FR 13 to 15 3' 7"

MACHINERY

Engine details Gm 12v-71, 540 HP @ 2300 rpm, twin disc 514m gear, 2.5:1 reduction, 920 srpm Electrical system 120/240 VAC 30 KW single phase, 24 VDC Propeller details 38" D x 32" P, 3-blade R & L, 2-3/4" bore, Columbian "Hydroflite" Maximum speed 22 knots Cruise speed 18 knots Fuel capacity (diesel) 1,045 gal.

Range at Cruise 350 miles

TANKS

Fresh water capacity 240 gal.

Sanitary water capacity 110 gal.

OTHER DATA

Special features Crane, 2,000 lbs. capacity fire pump, 500 GPM @ 231 ft xi (Rev-0)

00000_0824_FLT

REC_00000_FLT_Boats @ Commercial Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under xii (Rev-0) the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

xiii (Rev-0)

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

xiv (Rev-0)

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.6.1 Coast Guard turn-over preparation. The Contractor must be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew must be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:

3.6.1.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.

3.6.1.2 The Contractor may commence/continue work during these time frames.

3.6.1.3 Coast Guard personnel will disconnect the Detroit Diesel Electronic Control (DDEC) System and any other electronic equipment, as required to avoid damage to systems arising from hotwork on the vessel during the availability.

3.6.1.4 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.

3.6.1.5 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

xv (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

xvi (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

xvii (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

xviii (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils) xix (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

xx (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

xxi (Rev-0)

4.2 Tank and Void Assessment form.

xxii (Rev-0)

1 (Rev-0)

07400_AKP_0225_BOAT_FLT

WORK ITEM 1: General Welding, Provide

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide general welding as listed in Table 1.

TABLE 1- GENERAL WELDING

DESCRIPTION LOCATION APPROXIMATE SIZE

Repair Bumper Support – Port side Aft (Bent) 4’ x 2”

Repair Bumper Support – Starboard Stern (Outboard) (Bent) 4’ x 2”

Renew Platform Ladder (Port and Starboard) 2’ x 4’

Repair Port Stern Bitt (Bent) 12” x 12”

Repair Starboard Stern Bitt (Bent) 12” x 12”

Repair Aft Starboard Quarter Bitt (Bent) 12” x 12”

Crop and Renew Aft Deck (Warped) 3’ x 3’

Crop and Renew Workshop Cover – Bent Handle 10” x 2”

Fabricate New Metal Insert for Cabinet – Head (Deck)

Fabricate New Port Engine Room Hatch Grating 7’7” x 4’

Fabricate New Starboard Engine Room Hatch Grating 7’7” x 4’

Crop and Renew Rub Rail – Forward Bow (Mounting bolt holes) 12” x 12”

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing FL-85-2, Rev C, GFE Boat Hot Work Diagrams

2 (Rev-0)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Requirement. The Contractor shall provide general welding, including but not limited to, fabrication, brazing, inspection, plate renewal, crack repair, overlay, and associated processes on Coast Guard vessels and equipment in accordance with Coast Guard Drawing FL-85-002 and SFLC Std Spec 0740.

3.3 Bidding. The Contractor shall ensure for bidding purposes this specification will be broke down by the following:

One linear foot of welding/brazing.

Four square inches of clad/overlay welding.

One hour of fabrication.

One square foot of plate renewal.

TABLE 1 – PLATE TYPE

STEEL PLATE ALUMINUM PLATE

THICKNESS WEIGHT

PER SQFT.

TYPE/GRADE THICKNESS WEIGHT

PER SQFT

TYPE/ALLOY

3/16 (.1875) 7.66 lb 1/4 (.250) 10.21 lb 1/4 (.250) 3.53 lb

3 (Rev-0)

5/16 (.3125) 12.76 lb 5/16 (.3125) 4.41 lb 3/8 (.375) 15.31 lb 3/8 (.375) 5.29 lb 1/2 (.500) 20.42 lb 1/2 (.500) 7.06 lb

3.4 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

4. NOTES

This section is not applicable to this work item.

4 (Rev-0)

11010_UT_ESD_0423_FLT

REC_11010_UT_FLT_55’ ANB ‘B’ Class (ALL) (0619)

WORK ITEM 2: Hull Plating, U/W Body, Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing 55B ANB 1101-001, Rev B, Construction Profile Plan and Sections

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph:

3.2 (UT measurements).

3.1.2 Tech Rep.

Not applicable.

5 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor must perform a total of 200 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawings 55 ANB 997-001 and 55B ANB 1101-001 for guidance, in accordance with SFLC Std Spec 0740, Appendix C.

Mark up a copy of Coast Guard Drawing 55B ANB 1101-001 to show all locations selected for measurement and record all measurements in Table I (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit a CIR, to also include the marked up drawing(s) and completed Table I.

4.1 UT Table. Table 1 provided below is for the recording of all UT measurements.

6 (Rev-0)

TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT

PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE

7 (Rev-0)

63130_0523_FLT

REC_63130_100Percent_FLT_55’ ANB ‘B’ Class (ALL) (0523)

WORK ITEM 3: U/W Body, Preserve, 100 percent

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve U/W body surfaces.

NOTES

1. The purpose of the preservation tasks covered by this item is to completely remove all existing coatings and recoat the U/W body surfaces with a new coating system.

2. U/W body surfaces are as defined in 4.1 (Definitions) and exclude areas covered by docking blocks unless the vessel is fleeted for the express purpose of preserving blocked areas.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 55B ANB 1101-001, Rev B, Construction Profile Plan and Sections

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

8 (Rev-0)

3.2.3 Post-surface preparation cleaning and inspection

3.1.2 Tech Rep. The Contractor must refer to SFLC Std Spec 0000, paragraphs 3.2.4.2.1 (Painting contractor certification program requirement) and 3.2.4.2.2 (Coating Tech Rep), for applicable requirements.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection) to the following components, spaces and equipment:

All scuppers and overboard discharges.

Waterline area where U/W body coating system interfaces with freeboard coating system (unless freeboard surfaces are also being preserved).

Fathometer transducer surfaces.

Sea valve openings.

Propeller shaft bearings and seals.

Rudder bearings.

Propellers.

Zinc anodes (unless anodes are being renewed).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Sea chest grating.

3.1.5 Initial inspection. Prior to removing the existing coating system, the Contractor must inspect and verify whether all draft marks have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.

3.1.6 Water used in preparation and washing procedures. The Contractor must ensure that water used in all surface preparation tasks, including pre-surface preparation wash and water jetting, is of sufficient purity and quality that it does not prevent the surface being cleaned from achieving the required degree of surface cleanliness or non-visible contamination criteria.

3.1.6.1 Ensure that surface preparation water does not contain sediments or other impurities that are destructive to the proper functioning of the cleaning equipment.

3.1.6.2 Ensure that all water used in any surface preparation or cleaning procedures is captured, contained, and all spent water disposed of in accordance with all Federal, state and local regulations.

3.1.7 Surface preparation optional methods. The Contractor has the option of using either high/ultrahigh pressure water jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.2 (Preservation requirements). The Contractor may add abrasives to the water jet stream, for one or both of the following reasons:

Achieving greater productivity.

Achieving the required surface profile.

9 (Rev-0)

NOTES

1. Existing coating system on the U/W body surfaces may have a nominal thickness in excess of that which was originally installed, because of “patch-coats” applied during past drydock availabilities.

2. Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.

3. Whenever fleeting is required for any reason, if the U/W Body has not yet been fully preserved, the areas adjacent to all docking blocks must be fully preserved at least 2 feet in each direction prior to refloating the vessel. If the vessel will be placed onto a different blocking position, the areas in way of the new blocking position must be fully preserved.

3.2 Preservation requirements. The Contractor must accomplish the following tasks:

3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) freshwater wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.

3.2.2 Surface preparation and coating application.

The Contractor must accomplish the following tasks:

NOTE

Lists of all authorized coating materials and suppliers are listed in SFLC Std Spec 6310, Appendix C (Cutter and Boat Authorized Coatings).