Specification.pdf
PDF 1 MB Posted
- Attached to
- CGC TAMPA DS FY25
- Solicitation number
- 70Z08024QMECP0033
About this file
This document is a performance specification that outlines the requirements for dockside repairs to the USCG Cutter TAMPA (WMEC 902) for fiscal year 2025. The specification covers a range of work items including testing and renewing various electrical systems and components, inspecting and repairing the helicopter landing grid, preserving the helicopter operating areas, repairing the hangar expansion joint, and cleaning and inspecting the aviation fuel service tanks. The work items contain details on the required materials, equipment, procedures, tests, and inspections. The specification also includes general requirements for the contractor such as environmental protection, preservation, welding, and quality control measures. The accompanying federal contract opportunity solicits bids for these dockside repairs to be performed at a Coast Guard facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 00001_TAMPA.pdf | ||
| Price Schedule.xls | XLS spreadsheet | |
| 70Z08024QMECP0033_TAMPA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC TAMPA (WMEC 902)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2025
Developed By: Courtney K Brewbaker
(Rev-0, 24 June 2024)
USCGC TAMPA (WMEC-270A) DOCKSIDE AVAILABILITY FY2025
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: 28 Volt DC Helo Power Supply, Load Test WORK ITEM 2: 400 Hz Power Supply (FCX Systems Inc), Load Test WORK ITEM 3: Windspeed Transmitter, Anemometer, Renew WORK ITEM 4: Flow Meter (Aviation Fuel), Calibrate WORK ITEM 5: Helo Talon Grids, Inspect and Test WORK ITEM 6: Decks, Helicopter Operating Areas, Preserve WORK ITEM 7: Hangar Expansion Joint Seal, Renew WORK ITEM 8: Helo Talon Grid Structural Recess, Repair WORK ITEM 9: Helo Tie-Down Fittings, Renew WORK ITEM 10: Tanks, Aviation Fuel Service, Clean And Inspect iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 113-001, Rev E, Tank Top PL & FR Fwd FR 101 Coast Guard Drawing 901 WMEC 113-002, Rev A, Tank Top PL & FR Aft 182 Coast Guard Drawing 901 WMEC 113-003, Rev G, Tank Top PL & FR, FR 101-182 Coast Guard Drawing 901 WMEC 116-001, Rev D, CVK Fwd 101 & G Long 2 Coast Guard Drawing 901 WMEC 116-002, Rev E, CVK Aft 182 Coast Guard Drawing 901 WMEC 116-003, Rev E, CVKFr 101-182 & G Long. 2&4 Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182 Coast Guard Drawing 901 WMEC 122-001, Rev H, Transv Bhds 12 & 26 Coast Guard Drawing 901 WMEC 122-002, Rev G, Transv Bhds 47, 78 & 82 Coast Guard Drawing 901 WMEC 122-003, Rev G, Transv Bhds 103, 117 Coast Guard Drawing 901 WMEC 122-004, Rev F, Transv. Bhds. 165, 169, 151.6 Coast Guard Drawing 901 WMEC 122-005, Rev F, Transv Bhds 186 & 190 Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228 & 242 Coast Guard Drawing 901 WMEC 153-001, Rev K, 03 Level Pl & Fr Coast Guard Drawing 901 WMEC 171-001, Rev J, Main Mast Coast Guard Drawing 901 WMEC 186-003, Rev -, Talon Grid Foundation & Structural Mod, 01 Level Coast Guard Drawing 901 WMEC 314-005, Rev B, 28.5 VDC Hlcptr Start Rect Replacement Diagram Coast Guard Drawing 901 WMEC 314-006, Rev D, 400Hz Hlcptr Svce Freqconv Installation Diagram Coast Guard Drawing 901 WMEC 431-003, Rev J, Main IC Switchboard Arrangements, Elem Wrg Diag
& Dets Coast Guard Drawing 901 WMEC 494-001, Rev T, Meteorological System Block & Isometric W.D.
Coast Guard Drawing 901 WMEC 542-001, Rev J, JP-5 System Diagram Coast Guard Drawing 901 WMEC 542-002, Rev H, JP-5 Sys - A&D Coast Guard Drawing 901 WMEC 588-001, Rev F, Helicopter Tie Down Fittings – Arr & Dets Coast Guard Drawing 901 WMEC 588-004, Rev A, Helicopter Hangar/Hull Interface Coast Guard Drawing 901 WMEC 634-002, Rev-, 270 Ft WMEC C & A, Pnt, Dk Cov & Insul Mod Helo
Securing Grid Instl Coast Guard Drawing 901 WMEC 801-004, Rev L, General Arrangement 01 Level Coast Guard Drawing 905 WMEC 588-010, Rev D, Hangar Arr and Det v (Rev-0)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jan 2014, Coatings and Colors
Manual Coast Guard Technical Publication (TP) 2711, SWBS 437, Jan 1992, Wind Transmitter Coast Guard Technical Publication (TP) 3368, Jun 2020, Talon Helicopter Landing Grid - Type 18-22-01
Multiple Class Cutters Coast Guard Technical Publication (TP) 4931, Aug 2009, Section 321A, Precision Frequency Converters Coast Guard Technical Publication (TP) 5461, SWBS 421, Nov 2012, Anemometer – Model 120 & 122 Coast Guard Technical Publication (TP) 5486, Mar 2013, Go-No-Go Monitor and Flow Meter, 50 GPM Coast Guard Technical Publication (TP) 7099, SWBS 314, Oct 2009, Rectifier Power Supply - 28 VDC, 300 A Coast Guard Technical Specification D-123-2048, Feb 2020, 270’ WMEC A Class Fluid Handling Plan for Tank Inspections Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electrical Cable Test Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary
Machine Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN) Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment Federal Specification (Fed Spec) QQ-N-281D(2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections MIL-PRF-16173, 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application MIL-PRF-24667C, March 2018, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering
Application MIL-STD-1399 Section 300, Part 1, 25 September 2018, Low Voltage Electric Power, Alternating
Current NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P Naval Air Warfare Center (NAVAIR) Drawing 621055, Rev G, Visual Landing Aids Installation
WMEC-270 Class Ships NAVSEA Drawing 803-1916300, Rev N, Aircraft Securing and Engine Run Up NAVSEA Drawing 804-1213717, Rev H, Vehicle Lashing Sockets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets vi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
3 Y Anemometer NSN: 6600-00-709-9947 2 ea. 5,316.00 5 N Screw, Cap, 5/8-11
UNC 2A x 3in.
NSN: 5305-01-393-1827 24 ea. 25.65
5 N Screw, Cap, M12-1.75 x 42 mm
NSN: 5305-01-584-6095 12 ea. 33.75
5 N **Talon Grid Stanchion Bolt
Assembly, Including Locking Nut
NSN: 5340-01-481-3786 60 ea. 31.50
5 N Nut, Self-locking, M14x2.0-6H
NSN: 5310-01-598-3243 1 pg. 1006.80
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4 (Inspection report particulars)):
Work Item Title
5 Helo Talon Grids, Inspect and Test viii (Rev-0)
PRINCIPAL CHARACTERISTICS
270' WMEC (A-CLASS)
PHYSICAL
Length overall 270' 0" Length between perpendiculars 255' 0" Beam molded 38' 0" Depth molded, main deck amidships 01 level amidships
23' 6" 31' 4"
Full load displacement 1,902.2 long tons Draft, full load to baseline amidships 14' 3" Highest projection above baseline *height approximated
≈ 110' 0"
Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,600 BHP each Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-
1350 Generators. 475 KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4- 1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Number of propellers 2 Propeller diameter 9' 0" Number of blades, Each 4 Pitch Controllable Shaft RPM 260 Shaft diameter 10.55" at exit of hull Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 79,210 gal.
JP-5 total (95%) 25,890 gal.
Potable water total (100%) 8,553 gal.
Hydraulic & lube oil total (95%) 2,237 gal.
1 (Rev-0)
00000_0623_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jan 2014, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must
3 (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Large Quantity Generator (LQG).
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
4 (Rev-0)
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.6.1 The Contractor must obtain RapidGate Credentials for access to Base Portsmouth.
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
11 (Rev-0)
4.2 Tank and Void Assessment form.
12 (Rev-0)
13 (Rev-0)
31410_CNJ_0821_210_270
REC_31410_210_270_270 WMEC ‘A’ Class (ALL) (0221)
WORK ITEM 1: 28 Volt DC Helo Power Supply, Load Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to load test the 28 Volt DC Helo Power Supply.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 314-005, Rev B, 28.5 VDC Hlcptr Start Rect Replacement
Diagram
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 7099, SWBS 314, Oct 2009, Rectifier Power Supply - 28
VDC, 300 A
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard drawing(s) listed under Section 2 (References) for guidance in accomplishing this work item.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
14 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.3 Load test 28 VDC helo start rectifier. The Contractor must load test the 28 VDC Helo Start Rectifier in accordance with NAVAIR Air Capable Ship Aviation Facilities Bulletin (latest revision as cited in Section 2 References) and using Coast Guard Drawing 901 WMEC 314-005 and TP 7099, as guidance.
Submit completed Data Sheet via CFR.
3.3.1 In the event the load test for the 28 VDC helo start rectifier fails, the Contractor must troubleshoot and identify faulty component and submit CFR for repairs.
3.3.2 Once repairs are complete, the Contractor must re-conduct load test in accordance with paragraph
3.3 (Load test 28 VDC helo start rectifier).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.5 Report. The Contractor must submit a CFR for the completed Data Sheet in Section 4.1.
4. NOTES
4.1 Data sheet.
15 (Rev-0)
28 VOLT DC HELO START POWER SUPPLY TEST DATA SHEET (SHEET 1 OF 2)
HULL NUMBER_________________
TABLE 1: PERFORMANCE TEST DATA1
AMPS OUTPUT
VOLTS2 NOMINAL ACTUAL
1. The calibrated load bank must be connected to the Power Supply using the helo start cable supplied with the cutter used for starting the aircraft. The cable must be adjusted prior to conducting the test so that its length is sufficient to service the aircraft in its normal landing position on the flight deck. If required to make connections to the load bank, it is permissible to conduct the test before installing the helicopter end plug.
2. The voltage at the aircraft end of all installed system servicing cables must be between 24.0 to 29.0 volts for steady state load currents from 0 to 300 amperes.
3. Perform full load test at 300A for 60 minutes. Record values at the conclusion of the full load test.
Increase no-load voltage to 28.5V prior to start of this burn-in test to ensure output voltage will not drop below 24.0 during the burn-in period.
16 (Rev-0)
28 VOLT DC HELO START POWER SUPPLY TEST DATA SHEET (SHEET 2 OF 2)
Name Plate Data of the Power Supply
Make________________________________ Model_______________________________
Serial No.____________________________
Calibrated Load Bank Information
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
Calibrated Hand Held Voltage Meter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
Certification of Test Results
The voltage at the aircraft end of all installed system servicing cables must be between 24.0 to 29.0 volts for steady state load currents from 0 to 300 amperes.
Name of Testing Facility or Company_____________________________________
Test Conductor_____________________________________ Date_________________
Test Supervisor/QC_________________________________ Date__________________
17 (Rev-0)
31420_CNJ_0921_210_270
REC_31420_210_270_270 WMEC ‘A’ Class (ALL) (0221)
WORK ITEM 2: 400 Hz Power Supply (FCX Systems Inc), Load Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to load test the 400 HZ FCX power supply.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 314-006, Rev D, 400Hz Hlcptr Svce Freqconv Installation
Diagram
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 4931, Aug 2009, Section 321A, Precision Frequency
Converters Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P MIL-STD-1399 Section 300, Part 1, 25 September 2018, Low Voltage Electric Power, Alternating Current
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard drawing(s) listed under Section 2 (References) as guidance in accomplishing this work item.
3.1.1 CIR.
None.
3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Technical Representative who is
18 (Rev-0) familiar with the FCX Systems Inc. PFC 400 Hz Power Supply equipment/system, to accomplish the following on site:
• Advise on manufacturer's proprietary system information.
• Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, and reassembly as applicable.
3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.
3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR
3.3 Load test. The Contractor must perform load test of the 400 HZ FCX Solid State Frequency Converter in accordance with MIL-STD-1399 Section 300, Part 1 and NAVAIR Air Capable Ship Aviation Facilities Bulletin (latest revision as cited in Section 2 References), using Coast Guard Drawing 901 WMEC 314-006 and TP 4931 as guidance. Submit a CFR.
3.3.1 In the event the load test for the 400 HZ (FCX) Power Supply fails, troubleshoot and identify faulty component and submit CFR for repairs.
3.3.2 Once repairs are complete, re-conduct load test in accordance with paragraph 3.3 (400 HZ (FCX) Power Supply, load test). Submit CFR.
3.4 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.5 Report. The Contractor must submit a CFR for the completed Data Sheet in Section 4.1.
4.1 Data sheet.
19 (Rev-0)
400 HZ HELICOPTER POWER SUPPLY TEST DATA SHEET (SHEET 1 OF 2)
HULL NUMBER___________________
TABLE 1: PERFORMANCE TEST DATA1,2
AMPS3
(NOMINAL)
VOLTS4,5 AMPS6 FREQUENCY6,7
AN BN CN A B C
Continuity between pins “E” and “F” Satisfactory □
Plug pin “N” grounded to the ship’s hull and not interrupted by the disconnect switch. Satisfactory □
1. The 400Hz Helicopter Service System must be tested by connection to a suitably sized load bank and operated at loads from 2 amps up to the load specified for the Coast Guard H-65 Helicopter (10 KVA).
2. The power supply must be connected to the load bank using the cable supplied to the cutter for aircraft servicing.
If necessary to make the connection to the load bank, the test may be conducted prior to attachment of the helicopter end plug. The cable must be adjusted to the length necessary to service the aircraft in its normal landing position on the flight deck.
3. The required amperage for this test is calculated as:
I = P/[(E)(3)1/2] At P = 10 kVA (for H-65 Helicopter), and E = 200V (line to line), the maximum current required is 28.9 amps.
4. Verify the voltage output is between the limits of 113.0 to 118.0 Volts RMS, line-to-neutral, for steady state loads from no load to full rated load , at 0.7 lagging power factor. To allow for flexibility in loading techniques, the acceptable power factor range is from 0.7 lagging to 0.8 leading power factor.
5. The maximum allowable voltage unbalance is 3.0 volts RMS throughout the load range. Voltage unbalance = maximum difference between RMS phase voltage amplitudes at the utilization equipment terminals (Vmax – Vmin).
6. Verify the phase rotation and frequency is in accordance with Type III power requirements of MIL-STD-1399 Section 300, Part 1.
7. Frequency range must be between 398 to 402 Hz (400 Hz +/- 0.5%).
8. Perform burn-in test at 29A for 60 minutes. Record values at the conclusion of the full load test.
20 (Rev-0)
400 HZ HELICOPTER POWER SUPPLY TEST DATA SHEET (SHEET 2 OF 2)
4.1.1 Name Plate Data of the Power Supply
Make________________________________ Model_______________________________
Serial No.____________________________
4.1.2 Calibrated Load Bank Information
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.3 Calibrated Hand Held Voltage Meter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.4 Calibrated Hand Held Ammeter
Make________________________________ Model_______________________________
Serial No.___________________________________ Calibration Due Date_________________
4.1.5 Certification of Test Results
• The phase rotation and frequency is IAW the Type III power requirements of MIL-STD-1399
Section 300 Part 1.
• Voltage does not fall outside of the range of 118 Volts to 113 Volts, line-to-neutral, for the entire load range at 0.7 lagging power factor. To allow for flexibility in loading techniques, the acceptable power factor range is from 0.7 lagging to 0.8 leading power factor.
• Frequency must not fall outside of the range of 398 Hz to 402 Hz.
• Continuity must exist between pins “E” and “F”. Plug pin “N” must be grounded to the ship’s hull and not be interrupted by the disconnect switch.
Name of Testing Facility or Company_____________________________________
Test Conductor_____________________________________ Date_________________
Test Supervisor/QC_________________________________ Date__________________
21 (Rev-0)
43700_0324_210_270
REC_43700_270A WMEC (0420)
WORK ITEM 3: Windspeed Transmitter, Anemometer, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew both port and stbd anemometer wind speed transmitters.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y Anemometer NSN: 6600-00-709-9947 2 ea. 5,316.00
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 171-001, Rev J, Main Mast Coast Guard Drawing 901 WMEC 431-003, Rev J, Main IC Switchboard Arrangements, Elem
Wrg Diag & Dets Coast Guard Drawing 901 WMEC 494-001, Rev T, Meteorological System Block & Isometric
W.D.
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 2711, SWBS 437, Jan 1992, Wind Transmitter Coast Guard Technical Publication (TP) 5461, SWBS 421, Nov 2012, Anemometer – Model 120
& 122 Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
OTHER REFERENCES
22 (Rev-0)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Height above the main deck.
• Electrical wiring.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.3 Wind speed transmitter renewal. The Contractor must renew port and stbd windspeed transmitters using the Government-furnished anemometers listed above; turn over the removed anemometers to the Coast Guard Property Administrator as MTI. Make all electrical and mechanical connections using Coast Guard Drawings 901 WMEC 171-001, 901 WMEC 431-003, 901 WMEC 494-001; and TPs 2711 and 5461 as guidance.
3.3.1 Certification documentation. Provide the COR with all manufacturer’s or third party test facility certification documentation which may accompany new windspeed transmitters/anemometers.
3.3.2 Electrical checks. Perform continuity checks and insulation resistance measurements for the newly installed anemometers in accordance with SFLC Std Spec 3041. Submit a CFR.
3.4 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition.
• Port and Stbd Anemometers
This section is not applicable to this work item.
23 (Rev-0)
50400_0221_210_270 REC_50400_210_270_270’ WMEC ‘A’ Class (ALL) (0620)
WORK ITEM 4: Flow Meter (Aviation Fuel), Calibrate
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect and calibrate the instrumentation identified in Table 1.
TABLE 1 - INSTRUMENTATION
DESCRIPTION SYSTEM USE RATING
1 ½ inch Flow meter JP-5 Helicopter refueling 50 GPM
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 542-001, Rev J, JP-5 System Diagram Coast Guard Drawing 901 WMEC 542-002, Rev H, JP-5 Sys - A&D
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 5486, Mar 2013, Go-No-Go Monitor and Flow Meter, 50
GPM
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
24 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• Aviation fuel piping and contents
• Fluid pressure.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR
3.3 Instrument inspection and calibration. The Contractor must remove, clean, inspect, calibrate and reinstall the instrumentation identified in Table 1 in accordance with the referenced Coast Guard TP in Section 2 (References). The Contractor must refer to the Coast Guard drawings listed in Section 2 (References) for guidance while accomplishing this work item.
3.3.1 Cleaning and inspection. The Contractor must disassemble the flow meter sufficiently to expose the gears, rotors and metering chamber. Inspect and clean gear teeth, rotors and internal housing surfaces.
Submit a CFR. A soft wire brush may be used to clean surfaces, taking care not to alter the contour of the part surfaces. Remove nicks or burrs with a stone. Ensure all parts are clean and free of foreign matter prior to reassembly. Renew all disturbed seals, packing and gaskets.
3.3.2 Calibration. The Contractor must test for meter accuracy prior to disassembly and cleaning; and again after reassembly. Submit a CFR for each accuracy test. The Contractor must calibrate the meter using a certified calibration facility. The Contractor must provide a certificate of calibration to the COR.
3.3.3 Renewal. The Contractor may choose, at no additional cost to the Government, to renew the designated flow meter rather than clean, inspect and disassemble the existing meter. If the Contractor chooses to renew the flow meter, dispose of the existing meter in accordance with all Federal, State and local regulations. The Contractor must provide a certificate of calibration to the COR for the new flow meter.
3.4 Leak test. After completing all authorized repairs, the Contractor must test the JP-5 flow meter operation using the system fluid at normal operating pressure. Ensure zero visible leakage from or deformation of mechanical parts by repairing all leaks and discrepancies. Submit a CFR.
Coast Guard personnel will operate all shipboard machinery and equipment
25 (Rev-0)
3.5 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR
4. NOTES
4.1 Recirculation. After Contractor reinstallation of flow meter, Ship’s force will recirculate the fuel until it is clear and bright and passes the MK I and MK III detector kit tests. Flush all disturbed lines, pipes, and fittings before placing the JP-5 system back in service.
26 (Rev-0)
58840_ESD_0324_FLT
REC_58840_FLT_270’ WMEC 'A' Class (ALL) (0420)
WORK ITEM 5: Helo Talon Grids, Inspect and Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect and test the helo talon grid system, located on the flight deck.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST
($/UNIT)
N Screw, Cap, 5/8-11 UNC 2A x 3in. NSN: 5305-01-393-1827 24 ea. 25.65
N Screw, Cap, M12-1.75 x 42 mm NSN: 5305-01-584-6095 12 ea. 33.75
N **Talon Grid Stanchion
Bolt Assembly, Including Locking Nut
NSN: 5340-01-481-3786 60 ea. 31.50
N Nut, Self-locking, M14x2.0-6H NSN: 5310-01-598-3243 1 pg. 1006.80
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 186-003, Rev -, Talon Grid Foundation & Structural Mod 01
Level Coast Guard Drawing 901 WMEC 634-002, Rev-, 270 Ft WMEC C & A, Pnt, Dk Cov & Insul
Mod Helo Securing Grid Instl
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3368, Jun 2020, Talon…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .