Summary of Special Provisions for T6026-1 North River Drive Sidewalk Project
This document contains special provisions issued by the City of Sandy Springs Department of Public Works for the T6026-1 North River Drive Gap Fill Sidewalk Project located in Fulton County, Georgia. The project encompasses sidewalk construction along North River Drive, with work including saw cutting and removal of existing concrete and asphalt pavement, concrete walkways and driveways, curbing, vegetation, and debris removal. Additional work consists of supplying and grading clean fill and topsoil materials (2 inches depth minimum in greenbelt and side slope areas), relocation and repair of irrigation facilities and yard lights, independent testing services for subgrade compaction and concrete quality, and provision of pre- and post-construction video documentation. The contractor is responsible for utility coordination and must file and maintain utility locates throughout the project duration. Sod installation includes a two-year warranty requirement.
Work is restricted to weekdays Monday through Friday between 8:00 AM and 5:00 PM, with lane closures and traffic interference limited to 9:00 AM to 4:00 PM on North River Drive and adjacent side streets. No lane closures or traffic pacing are permitted between 5:00 AM and 10:00 PM during specified holiday periods. The contractor must maintain a minimum single lane of traffic at all times and provide a traffic control plan for approval at least two weeks prior to work commencement. Liquidated damages are assessed at $500 per calendar day for failure to complete work on schedule and $2,000 per day for failure to restore temporary vehicular driveway accessibility within 24 hours. The contractor must maintain traffic signal interconnect, coordinate with the Traffic/Transportation Unit before removing signage and striping, and provide 48-hour advance notice for any temporary closures. Utility companies are responsible for relocating conflicting facilities with 60-day written notice required, and the City assumes no liability for contractor delays or damages resulting from utility conflicts or interference.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB 27_018 T6026_1 North River Gap Sidewalk P.pdf | ||
| T6026_1 North River Drive Gap Fill Sidewalk.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF SANDY SPRINGS
SPECIAL PROVISIONS
All special provisions listed on this page apply to this project, T6026-1 North River Drive
Sidewalk Project. See the following pages for the special provisions:
Section 108—Prosecution and Progress
Section 150—Traffic Control
Section 210—Grading Complete
Section 890 - Seed and Sod
Section UC - Utility Conflicts
8/26/2026
Section 108 - Prosecution and Progress Page 1 of 1
DEPARTMENT OF PUBLIC WORKS
SPECIAL PROVISION
Section 108 – Prosecution and Progress
Project No.: T6026-1 Project Name: North River Drive Gap Fill Sidewalk
Fulton County
Retain GDOT Section 108 as written and revise per the following:
108.08 Failure or Delay in Completing Work on Time
Paragraph 1 of 108.08 shall be amended as follows:
Time is an essential element of the Contract, and any delay in the prosecution of The Work may inconvenience the public, obstruct traffic, or interfere with business. In addition to the aforementioned inconveniences, any delay in completion of The Work will always increase the cost of engineering. For this reason, it is important that The Work be pressed vigorously to completion. Should the Contractor or, in case of default, the Surety fail to complete The Work within the time stipulated in the Contract or within such extra time that may be allowed, charges shall be assessed against any money due or that may become due the Contractor at the rate of $500 per calendar day.
Failure to provide temporary vehicular accessibility to driveway within the same day,(24-hour period) shall result in the assessment of liquidated damages at the rate of $2,000.00 per day.
These rates are cumulative and in addition to the Liquidated Damages which may be assessed in accordance with the contract for failure to complete the overall project on time.
In the event any portion of a Subcontract is further sublet, all of the provisions governing subletting, including registration and written approval by the Engineer, shall apply.
This Sub-Section shall not apply to Contracts between the City and counties, other municipalities, or State agencies.
Spalding Drive and Pitts Road.
SPECIAL PROVISION
Project No.:
T6026-1
North River Drive Gap Fill Sidewalk
FULTON COUNTY
Section 150 – Traffic Control
Retain GDOT Section 150 as written and add the following:
150.6 SPECIAL CONDITIONS:
A. Work Hours:
This project requires the following restricted work hours: Work will be permitted during weekdays (Monday through Friday) between the hours of 8:00 AM and 5:00 PM. Lane closures, on-site detours, pacing of traffic and other activity that visibly interfere with traffic will only be permitted from 9:00 AM to 4:00 PM along North River Drive and adjacent side streets.
B. Traffic Control Plan:
A traffic control plan shall be submitted two (2) weeks prior to any work for review and approval by the Owner representative.
C. Holiday Work:
In addition, at the discretion of the Engineer and/or City personnel, no lane closures, detours, or pacing of traffic will be allowed between the hours of 5:00 AM and 10:00 PM from 12:00 PM on the day preceding any Holiday through the first workday after the Holiday.
Holiday Dates
Columbus Day October 10, 2026 – October 12, 2026 (weekend)
Veteran’s Day November 11, 2026
Thanksgiving Day November 26, 2026 – November 29, 2026 (weekend)
Christmas Day December 24, 2026 – December 27, 2026
New Year’s Day December 31, 2026 – January 3, 2027
Martin Luther King, Jr. Day January 16, 2027 – January 18, 2027 (weekend)
President’s Day February 13, 2027 – February 15, 2027 (weekend)
Memorial Day May 28, 2027 – May 31, 2027 (weekend)
Juneteenth June 19, 2027
Independence Day July 3, 2027 – July 5, 2027 (weekend)
Labor Day September 4, 2027 – September 6, 2027 (weekend)
Columbus Day October 9, 2027 – October 11, 2027 (weekend)
Veteran’s Day November 11, 2027
Thanksgiving Day November 25, 2027 – November 28, 2027 (weekend)
Christmas Day December 24, 2027 – December 26, 2027
New Year’s Day December 31, 2027 – January 2, 2028
D. Maintenance of Traffic:
The Contractor is required to maintain a minimum of a single lane of traffic throughout the construction project. Temporary closures within a single work day and/or flagging will be allowed only with prior approval of City of Sandy Springs.
A minimum 48-hour notice is required for a request for closure. A minimum of a single lane of traffic adequate for emergency services is required to be maintained always when the Contractor is not actively working on site. All traffic control shall conform to GDOT Standard Specification 150 and the MUTCD.
E. Maintaining Traffic Signals:
The Contractor shall maintain interconnect to the traffic signals at all times.
Failure to maintain interconnect to the traffic signals will result in assessment of non-refundable deductions.
7/1/2024
SPECIAL PROVISION
Project: T6026-1 North River Drive Sidewalk Project
Section 210 – Grading Complete
In addition to the standard provisions in GDOT Grading Complete Standard 210-0100, Grading
Complete shall include the following provisions and their cost:
1. Saw cutting of concrete and asphalt pavement to construct the project.
2. Including but not limited to the removal of asphalt and concrete pavement, the removal of concrete walkways and driveways, the removal of granite, concrete and stone curbing, miscellaneous stone, site materials, including vegetation (trees, stump’s, shrubs and ground cover) and other debris removal required to construct the project.
3. The supply and grading of clean, suitable fill and plant top soil material to construct the sidewalk, greenbelt and side slope areas. Clean topsoil to be supplied in greenbelt and side slopes areas at 2” depth. No rock or construction debris can be used to construct fill slopes.
4. The relocation and repair of any irrigation facilities and yard lights damaged during project construction activities.
5. The Contractor shall file & maintain utility locates.
6. The Contractor shall be solely responsible for utility coordination on the project and will provide a contact to the City at the pre-construction conference.
7. The Contractor shall provide independent testing services for the project which will include sub-grade compaction and concrete testing as directed by the Engineer.
Documentation will be provided at time of payment request.
8. The Contractor must provide a video of the project area before the project begins and after the project is complete. Each video will be provided to the City once it is complete in an acceptable format.
9. The contractor will coordinate with Sandy Springs Traffic/Transportation Unit before removal any traffic signage and striping.
8/26/26
SPECIAL PROVISION
Project: T6026-1 North River Drive Gap Fill Sidewalk Project
Section 890 – Seed and Sod
Retain Section 890 as written and add the following:
890.2.02 SPECIAL CONDITIONS
D. MATERIALS WARRANTY:
4. Sod installation shall include a 2 year warranty.
8/26/26
CITY OF SANDY SPRINGS
SPECIAL PROVISION
Project: T6026-1 North River Drive Gap Fill Sidewalk Project
Section UC – Utility Conflicts
Utility companies having known facilities that conflict with the construction of this project have been directed by the City to adjust or relocate their facilities and will be notified of the contract award.
Conform to all requirement of the Specifications as they relate to cooperation with utility owners and the protection of utility installations that exist on the project. Refer to the requirements of Section 107, Legal Regulations and Responsibility to the Public, with attention to Subsection 107.21.
Coordinate the Work with any work to be performed by others in any right of way clearance and arrange a schedule of operations that will allow for completion of the
Project within the specified contract time. Where stage construction is required, notify the utility owner when each stage of work is completed, and the site is available for utility work to proceed.
Information concerning utility facilities known to exist within the project limits, including the list of owners, is shown on the plans.
Under Georgia Code Section 32-6-171, utilities are required to remove or relocate their facilities.
The Contractor is required to give the utility at least 60 days written notice directing the removal and relocation, and the utility is required to begin removal within a reasonable time thereafter.
Under the agreements with the City, all local service telephone companies, all Electric
Membership Cooperatives and certain other utilities, are liable for delays to construction that is due to the utility’s failure to clear conflicts within reasonable time.
In accordance with Subsection 105.06 of the Specifications, the City of Sandy Springs and the Georgia Department of Transportation will not be liable for payment of any claims due to utility delays, inconvenience or damage sustained by the Contractor due to interference of any utilities or appurtenances, or the operation of moving them.