spec sheet for 61411530.docx

DOCX document 43 KB Posted

Attached to
MODULAR OFFICE
Solicitation number
SPMYM226Q7820
Issued by

About this file

This is a specification sheet for 12' x 42' stackable modular office buildings designed for Puget Sound Naval Shipyard & Intermediate Maintenance Facility (PSNS & IMF). The specification describes minimum requirements for noncombustible, open-plan office modulars with steel cage frames intended to serve as classrooms or open offices without center posts. Each modular must be stackable, interchangeable with existing PSNS units, and capable of rolling into position via casters with 6-inch x 4.5-inch mounting plate bolting patterns compatible with Caster Technology Corporation P/N 126-343 or equal. The modulars must comply with 2021 International Building Code, Type II-B construction standards, accommodate 25 PSF snow load, meet Seismic Zone 3 requirements, and achieve Class B wind exposure minimums.

The specification details comprehensive construction requirements including steel perimeter frame with W 8" x 18" rails, R-19 insulation, SpartaCote Flex flooring with granite chip finish, Taylor Metals Tuff Rib metal siding in sterling grey, TPO single-ply roofing with R-30 insulation, and three insulated half-lite exterior doors with KABA Simplex mechanical pushbutton locks keyed by customer. The modular must include a wet-type fire suppression system with concealed sprinkler heads at 0.1 gal/min/SF minimum, 120-volt electrical service with 200-amp load center, a 2-ton/8-kW Bard heat pump with programmable thermostat, comprehensive LED interior and exterior lighting, GFCI receptacles, and pre-wired communications infrastructure with CAT6A/CAT5E cabling providing 12 data drops and 6 phone drops with Ortronics connection devices. All lifting attachments must be professionally engineered with calculations certified by a licensed Professional Engineer, undergo 200% load testing or magnetic particle testing, and be accompanied by rigging isometric drawings. Third-party independent inspection and testing of all building systems, sprinkler system, network, electrical, and HVAC components must be completed before delivery, with compliance reports, As-Built drawings, and replacement parts lists submitted to PSNS & IMF C/900F. Professional engineered drawings for repeatable orders are required within 10 days of contract award with 30-day allowance for new drawings.

View the file

Other files

File Type Posted
spec sheet for 61411532.docx DOCX document
Solicitation - SPMYM226Q7820.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE

This specification describes the minimum requirements for open office stackable modulars.

Professional Engineered Drawings for repeatable orders are required 10 days after contract award date, allowing 30 days for new drawings. Modular is to be inspected and tested by independent 3rd party tester to include sprinkler system, network, electrical, and HVAC testing with sign off for compliance. Inspection to be completed upon manufacturing completion and before delivery. Compliance report, As Built Drawing, and replacement parts list shall be submitted to PSNS & IMF C/900F. All lifting or hoisting for the placement of the building sections will be performed by the government when the contract is completed. Hazardous material is strictly controlled at government facilities, do not ship any extras such as touch up paint with the building.

GENERAL INFORMATION

a) Modulars will be assembled in 12' x 42' single story modulars and must be able to roll into position with casters. Modulars will have caster mounting plates attached to accept casters. Mounting plate bolting pattern is 6 inches x 4.5 inches for Caster Technology Corporation P/N 126-343 or equal.

b) Each modular must be interchangeable with each other and existing PSNS owned modulars.

c) Building Description: 12' x 42' stackable office single-wide with steel cage frame.

d) Modular must meet or exceed all PSNS Material Lifting & Handling requirements.

e) Occupancy: B

f) Type of Construction: II-B

g) Snow Load: 25 PSF

h) Code:2021 IBC

i) State Approval(s) needed: None

j) Seismic: Zone 3

k) Interior must be open (no center posts) to allow use as a classroom or open office.

I) Wind Exposure: Class B minimum

FOUNDATION

a) Will be designed and installed by PSNS (concrete block, keel blocks, or casters).

12' x 42' NONCOMBUSTIBLE OFFICE MODULAR

(STACKABLE, FIRE SUPPRESION INSTALLED)

FRAME

a)
12' x 42' =/- perimeter style lower frame - W 8" x 18" perimeter main rails, M 8" x 6.5" cross-members.
b)
Frame to be reinforced to allow pushing or pulling modular from any side

without deformation to the frame.

c)
Columns to extend through roof with cross-member at two inner columns with

lifting eyes.

d)
Lower frame to extend on HVAC end.
e)
Frame primed with Columbia Speed Set; two coats, topcoat black.

FLOOR

a)
Bottom boards: Fs-25 mobile flex
b)
Insulation: R-19 unfaced (Protected from rodents with flat 30-gauge galvanized

metal)

c)
Joists: 2x6 Hf#2 at 16" o/c longitudinal
d)
Rim Joists: Double 2x6 Hf #2
e)
Decking: ¾" T&G UDLX plywood
f)
¼" underlayment installed over plywood with staggered seams
g)
Covering: Flooring will be a SpartaCote Flex, Base Color Light Grey, ¼" Chip -

Granite with clear topcoat.

h)
Base Trim: Standard 4" Rubber Cove Base, Black in color

EXTERIOR WALLS

a) Studs: 2x6 Hf stud grade at 16" o/c

b) Sheathing: 3/8" CDX plywood at outside face of framing

c) Sheathing:½" sound board

d) Insulation: R-19 unfaced with vapor barrier

e) Siding: Taylor Metals Product Tuff Rib 26-gauge metal siding, manufacturer standard pattern, sterling grey in color

f) Trim: 24-gauge metal trim

g) Skirting: Not applicable

h) Fasteners: All fasteners shall be stainless steel.

i) All exterior penetrations shall be sealed with a ¼" diameter continuous bead of sealant.

INTERIOR WALLS

a) Covering: VOG (Vinyl over Gypsum)

b) Trim: Alpine Oak inside corner trim.

c) Sheathing:½: sound board VOG (Vinyl over Gypsum)

ROOF

a) Framing: 2x10 Hf#2 rafters at 16" o/c

b) Slope: The roof will be sloped towards the 42' exterior wall.

c) Ceiling Height: 7' 9" +/- finished ceiling height

d) Insulation: R-30 unfaced batt with vapor barrier in cavity

e) Sheathing:½" CDX plywood

f) Roofing: Thermoplastic Polyolefin single-ply roofing membrane

g) Overhang: None

h) Mansard: None

i) Venting:None

j) Gutters & Downspouts: None

EXTERIOR DOORS

a) Three (5) each: 3/0 x 6/8 metal insulated half lite door with knockdown hollow metal jamb. The doors will have a half lite window installed; window will be made of tempered glass with laminated safety film applied (3M Scotchshield Ultra S600) to interior glass surface for improved shatter resistance. Provide built-in weather protection for door header & threshold. Door headers shall extend past the frame of the doors. Insulated 18-gauge steel with half lite exterior doors are acceptable (galvanized preferred). Knock down 16-gauge galvanized steel exterior door frames are acceptable. Three doors will have KABA, Simplex L1041 mechanical pushbutton locks installed. Supply "best" brand cores to be keyed by customer.

b) Part# 1041B26D41 - Kaba Simplex 1041B-03-41 Lever Mechanical Pushbutton Lock.

c) Part# 1C7A1626 - Best lC standard core, 7 pin A keyway, uncombinated, 626 finish.

WINDOWS

a) Four (4) each: 3/0x4/0 Prime, or equal, horizontal slider with bug screen, white vinyl frame, double glazed, low-E tinted solar gray.

b) All windows shall have laminated safety film applied (3M Scotchshield Ultra S600) to interior tempered glass surface for improved shatter resistance.

c) Window flanges will be installed under siding. Windows should be on the long sides.

d) Bottom of rough opening at 36" above finished floor.

MISCELLANEOUS

a) Certified Scale Weight shall be provided upon completion. Certified Gross Weight shall be stenciled on two sides of lower frames (3" letters minimum in height).

b) Four (4) each lifting eye locations marked with "LIFT HERE" stencils (3" letters minimum in height).

c) 3rd party MT weld inspection results for all lifting point attachments to be included with each modular.

d) Four (4) each rigging isometric drawings.

e) Manufacturer's data plate shall be located above the electrical panel inside modular office and outside of the modular office on the same side as the HVAC units.

ELECTRICAL

a) Electrical meter base: Will be provided by PSNS

b) Building Service: Will be provided by PSNS

c) One (1) each safety switches/emergency disconnect, SQD DU324RB

d) One (1) each transformers, 240/480 -120/240 lPH Square D Transformer (no exceptions) with an appropriate KVA rating for the expected load calculations. The transformer shall be capable of transforming 480V 3PH into 120/240V lPH. The transformer shall have a 50 ft. supply cable of 4 AWG copper, 4 conductor cable, Type W for power installation/hookup. 50 ft. Supply cable will have 480VAC pin and sleeve plug with closure cap for connection by shipyard to electrical supply. Connections to the high and low side of the transformer shall be mechanical connection.

e) Wiring: Conductors, conduits and connections from transformer to safety switch and to load center shall be included. Power connections to transformer will be responsibility of PSNS.

f) Load center: 120/240-volt, single phase, 200 amps, rain tight SQD QO120-40M200RB, surface mounted

g) Wiring: Nonmetallic shielded copper (12-2 W/G minimum)

h) 7 each LED Interior lights, Lithonia LBL4-LP835 Surface mount led with wrap around diffuser. (People complain that these LEDs are obnoxiously bright- need a softer output??)

i) Five (5) each Exterior Lights: Vandal resistant, low profile (not to exceed beyond steel frame) LED exterior lights at exterior doors with photocell (1) porch light at each entry on all trailers.

j) Five (5) each Egress Light: Exit/Emergency light with battery pack, exit/emergency light at each point of exit above door.

k) Nineteen (19), or to meet code @ every 4', each Receptacles along interior walls: GFCI Duplex 110-volt, 20 Amp for computer terminals (GFCI receptacles or breakers), 18" Height I) Two (2) each Receptacles: WP GFCI at exterior (one on each end of each modular).

m) Dedicated 120 volt non GFCI circuit with one (1) duplex receptacle located inside at communication port entry.

n) Switching: Standard switching per room, 3-way switching as required

o) Interior Communication Cabling, Boxes & Conduit: Modular to be pre-wired for phone and data.

p) Twelve (12) data drops, 6 per side and six (6) phone drops, three (3) boxes per side, labeled D1-D24 and V1-V12 recessed in wall. All conduits concealed and terminated at separate 12 port patch panels and phone blocks to be located near the respective communication entry port. Plenum rated CAT6A or CAT5E cabling is to be installed with appropriate jacks & boxes terminated using T-568B scheme. Ortronics brand connection devices/faceplates shall be used for all data/phone runs. Data shall be identified with blue colored wall jacks, phone jacks identified with orange.

q) One (1) Data Cable Entry Ports per modular, one in each opposing corner (i.e. 1 port in each modular). Ports will be just below ceiling tiles, minimum 3" diameter, with threaded cap and lanyard.

r) One (1) Phone Cable Entry Ports per modular, one in each opposing corner (i.e. 1 port in each modular). Ports will be just above floor tiles, minimum 3/4" diameter, with threaded cap and lanyard.

s) Rough-in wiring for badge readers at each entry at each point of entry.

PLUMBING

NONE

FIRE SPRINKLERS

a) Sprinkler system must be a wet system. Minimum 0.1 gal/min/SF with concealed, automatic sprinkler heads. PSNS personnel will connect water supply (approximately 75 PSI). Each assembled modular will have one supply connection. PSNS will connect supply lines between modulars when modular assembled. Shutoff valves will be included at each side of connection. Pipe ends will be a minimum of 6 feet apart and have standard external pipe threads. All supply connections will have threaded caps and lanyards to be used when not connected.

b) Each assembled modular will have one external audible alarm. Alarm and Flow Switch must be equal to or better than a Potter M/N PBA1208 and M/N VS-SP, respectively.

c) Each assembled modular will have one interior, 120 volt powered audible and visual alarm with a separate exterior bell.

d) Each assembled modular will have one interior 120-volt powered smoke detector with audible alarm, strobe, and a separate exterior bell. Smoke detector must be equal to or better than a Kidde i12080. Smoke detector wires need to be run to the exterior of the modular and terminated in a terminal block inside a red exterior electrical box. The wires on the exterior of the modular will be to connect to other modulars when stacked together.

e) System shall have two external overflow pipes per assembled modular. Overflow will have standard pipe thread on the outlet and drain to exterior at ground level and have external standard pipe threads at outlet. Each overflow line will have an internal shutoff valve that is accessible from inside the modular.

f) The system shall be hydrostatically tested (75psi min.) for any leakage and operationally checked prior to shipment.

g) All exterior piping to be galvanized & connection height to be 6" above finished floor height.

HVAC

a) One (1) each Heat/Cool: Manufacturer standard wall hung heat pump units. Minimum: Bard WH241-A08 (2 ton/ 8Kw heat strip) with corrosion resistance coated coils, or equal.

b) WH241-A08 (2 ton/ 8Kw heat strip) with corrosion resistance coated coils, or equal.

c) One (1) each Thermostats: 7-day Programmable Honeywell 8000 TH8320R1003 or equal. Thermostat will have a clear combination locking cover over the controls.

d) Heat/Cool unit discharges through undamped supply air grill on interior of end wall. Return air through exterior wall at Heat/Cool unit.

LIFTING ATTACHMENTS DESIGNED AND FABRICATED BY OTHERS

INTENT

The technical requirements shown here shall be incorporated into specifications for equipment fabricated outside PSNS & IMF which is intended to be lifted/handled at PSNS & IMF. These requirements are intended to provide design specifications for a qualified engineer to incorporate into the design of integral equipment lifting points. Lifting points/lugs as addressed here are commonly called padeyes and generally consist of a hole in an attached plate, or other structural member, designed to accept a shackle pin for connection to other standard rigging gear. It is expected that design, analysis and testing of lifting points shall be performed to the requirements specified below by the fabricator providing the equipment, unless other arrangements have been made for the Government to satisfy these requirements. Contact PSNS Code 711.11, (360) 476-4281, for equipment lift point design or lifting arrangements outside the scope of what is described here.

REQUIREMENTS

a) The allowable bending strength shall be based upon 1/3 of the yield stress of 1/5 of the ultimate strength, whichever is the most conservative, of the lifting attachment material.

b) The shear strength shall be based upon the Von Mises factor (1/v3) (or about .5777, the equivalent to ) times the allowable design bending strength.

c) The bearing strength shall be based upon 1/5 of 150% of the ultimate strength of the lifting attachment material.

d) The lifting attachments shall be sized for the design load plus 10% for unexpected growth in the weight of the load. The resulting value shall be further increased to reflect the loads induced by the angle the slings make to the plane the lifting attachments lie on. The attachments shall be oriented so the slings shall not pull out of the plane of the individual lifting attachment by more than 5° unless they are designed to withstand the resulting side load. In addition, the individual loads for each point shall be calculated based on the configuration of the rigged equipment and the location of its center of gravity.

e) When installing 3 or more lifting attachment, only 2 shall be assumed to carry the load (paragraph 4) unless a spreader or strongback is used. The use of spreaders or strongbacks shall be kept to a minimum, but if they are deemed necessary, a lift sketch detailing the required spread, capacity and orientation of that gear shall be provided for review at the time of the submittal of the equipment design.

f) The structure supporting the lifting attachments shall be designed to sustain the various lateral loads imparted by the arrangement of the lifting attachments and the induced sling angle loads (paragraph 4 & 5) based on a buckling analysis per AISC, Allowable Stress Design.

g) The lifting attachments are required to withstand a load test of 200% +5%-0% of the working load limit (WLL) for 2 minutes. Acceptance criteria shall be: No bending, cracking or permanent deformation of the lifting attachments or associated structure. The contractor's certified representative will perform the load testing plus a pre- and post-load VT per AWS D1.1 and submit documentation of the satisfactory results of all the various tests. The lifting attachments shall be labeled with the WLL and the test date.

h) In certain cases, with prior concurrence of the cognizant technical Code at Puget Sound Naval Shipyard, the load test may be waived and a magnetic particle test (MT) of the attachment weld substituted, meeting the acceptance criteria of MIL-STD-2035, Class 3 or equivalent standard as approved by the government, provided the testing is performed by a certified third party and documentation of the satisfactory results is provided with the receipt of the equipment.

i) All calculations required for the design of the lift points shall be performed by a Structural Engineer and/or certified by a Professional Engineer, subject to availability and shall be provided for review at the time of the submittal of the equipment design.

DELIVERY AND SET UP

REQUIREMENTS

a) The Contractor is responsible for all required permits, transportation and delivery to Puget Sound Naval Shipyard & Intermediate Maintenance Facility, Bremerton, WA 98314.

b) Shipyard personnel will be responsible for placing the modular on site and all required set up (Blocking, leveling, telephone outlets, site preparation, etc.)

c) Shipyard personnel will be responsible for building any stairs, platforms, staging and ramps or decks as needed.