SPEC 45676.pdf
PDF 1 MB Posted
- Attached to
- Dry-Dock: USCG STA FREEPORT (45676) FY23 DD
- Solicitation number
- 70Z04023QSBPL0023
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Additional Contract requirements 45676.pdf | ||
| Schedule of Supplies and Services _ 45676.pdf | ||
| SF-30 _70Z04023QSBPL0023_0_US.pdf | ||
| PPQ 45676.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG Station Freeport 45676 (RB-M 45)
SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS
FY2023
Developed By: Shaun M Mathews
(Rev-0, 14 April 2023)
USCG 45676 (RB-M-45) UNPLANNED AVAILABILITY FY2023
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Ultrasonic Testing (UT) (100) Shots, Perform WORK ITEM 2: Hull Plating (U/W Body), Inspect WORK ITEM 3: Main Diesel Engine(s) To MEPS Generator(s) And Jet Drive(s), Align WORK ITEM 4: Water Jet-Inspect, Perform Service WORK ITEM 5: Jet Drive Anodes, Renew WORK ITEM 6: Fender Faying Surfaces, Preserve, 100 percent WORK ITEM 7: Water Jet Drive, Preserve WORK ITEM 8: U/W Body, Preserve (100%) WORK ITEM 9: Drydock WORK ITEM 10: Temporary Services, Provide WORK ITEM 11: Sea Trial Performance, Support, Provide WORK ITEM 12: Lazarette Bilge, Preserve WORK ITEM 13: Tow Reel, Anchor Reel - Preserve WORK ITEM 14: Fendering System, Inspect WORK ITEM 15: Diesel Fuel Tank, Clean and Inspect WORK ITEM 16: Diesel Tanks, Refuel WORK ITEM 17: Marine Chemist Services, Provide WORK ITEM 18: Fendering System, Repair WORK ITEM 19: Fender System, Renew iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 45 RB-M 084-002, Rev -, Docking Plan
Coast Guard Drawing 45 RB-M 084-002, Rev –, Docking Plan
Coast Guard Drawing 45 RB-M 110-001, Rev -, Hull Structure
Coast Guard Drawing 45 RB-M 110-002, Rev -, Hull Structure Module A
Coast Guard Drawing 45 RB-M 110-003, Rev -, Hull Structure Module B
Coast Guard Drawing 45 RB-M 114-001, Rev -, Fendering Arrangement
Coast Guard Drawing 45 RB-M 170-002, Rev B, Folding Mast
Coast Guard Drawing 45 RB-M 185-001, Rev A, Auxiliary System Foundations
Coast Guard Drawing 45 RBM 201-001, Rev B, Main Engine Arrangement
Coast Guard Drawing 45 RBM 247-002, Rev -, Water Jet Propulsor Arrangement
Coast Guard Drawing 45 RB-M 247-002, Rev -, Water Jet Propulsor Arrangement
Coast Guard Drawing 45 RB-M 256-002, Rev -, Cooling System Propulsion
Coast Guard Drawing 45 RB-M 261-001, Rev -, Fuel Supply System Schematic
Coast Guard Drawing 45 RB-M 261-002, Rev -, Fuel Supply System
Coast Guard Drawing 45 RB-M 261-002, Rev -, Fuel Supply System
Coast Guard Drawing 45 RB-M 261-004, Rev -, Fuel Supply System Tubes
Coast Guard Drawing 45 RB-M 261-005, Rev -, Fuel Supply System - Pipe Assemblies
Coast Guard Drawing 45 RB-M 261-100, Rev -, Fuel Fill and Vent Schematic
Coast Guard Drawing 45 RB-M 261-101, Rev -, Fuel Fill and Vent Arrangement
Coast Guard Drawing 45 RB-M 261-101, Rev -, Fuel Fill and Vent Arrangement
Coast Guard Drawing 45 RBM 311-004, Rev -, APU Generator Drive System
Coast Guard Drawing 45 RB-M 581-001, Rev A, Anchoring Handling and Stowage System
Coast Guard Drawing 45 RB-M 582-002, Rev -, Mooring and Towing System
Coast Guard Drawing 45 RB-M 631-001, Rev A, Painting Layout
Coast Guard Drawing 45 RB-M 633-002, Rev -, Cathodic Protection Sacrificial Anode
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual v (Rev-0)
Coast Guard Technical Publication (TP) 5737, SWBS 247, Jun 2014, Water Jet – Model FF375S
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services
OTHER REFERENCES
1), 2015, Solvent Cleaning
2), 2004, Mechanical Tool Cleaning
45 RB-M Water Jet Disassembly / Assembly Procedures
ASTM International (ASTM) D4138, Rev A, 2007 (R 2022), Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2019, Occupational Safety and Health Standards for Shipyard Employment
Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
REQUIREMENTS
Rolls-Royce Kamewa Water Jet Assembly Drawing 376 000 49
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 2 (SSPC-SP
The Society for Protective Coatings (SSPC), 2015 (E 2017), Paint Application Specification No. 2 (PA- 2), Procedure for Determining Conformance to Dry Coating Thickness Requirements
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-WJ-2/NACE WJ-2, 2012 Water Jet Cleaning of Metals-Very Thorough Cleaning vi (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
3 Y * MDE/ TO GENERATOR
ALIGNMENT TOOL
PN: MMRBM0030 1 ea.
3 Y * MDE/ TO JET DRIVE
ALIGNMENT TOOL
PN: MMRBM0451 1 ea.
3 Y * ENGINE LIFTING BAR PN: MMRBM0956 1 ea.
4 N Stainless Steel Ball Joint NSN: 3040016152117 or PN:
59915K483 10 ea. 12.26
4 N Stainless Steel Threaded Rod
NSN: 5306016152224 or PN:
93250A140
1 ea. 10.67
4 N Bearing Bushing NSN: 3120014555212 or PN:
10106911
4 ea. 9.80
4 N Bearing Bushing NSN: 3120580006242 or PN:
36M05101
4 ea. 49.00
4 N **Socket Head Screw NSN: 5305016171580 or PN:
91210050
16 ea. 2.71
4 N **Bolt Kit NSN: 2815016171688 or PN:
93112085A
2 ea. 15.64
4 N **Key NSN: 5315016166360 or PN:
10100824
3 ea. 28.14
4 N Seal NSN: 5330580006238 or PN:
10118902
2 ea. 4.35
4 N Bushing NSN: 3120580006239 or PN:
10105511
2 ea. 48.19
4 N Bearing Bushing NSN: 3120014555272 or PN:
10105111
4 ea. 35.33
4 N **Bolt Kit NSN: 2815016171974 or PN:
93112080F
2 ea. 6.13
4 N **Bolt Kit NSN: 5340016167191 or PN:
93112065K
12 ea. 13.07
4 N Bearing Unit NSN: 3110016166342 or PN:
37506201
2 ea. 614.35
4 N Bushing NSN: 3120580006240 or PN:
10106011
4 ea. 47.21
4 N **Set Screw NSN: 5305016020672 or PN:
91608012
6 ea. 0.58
4 N **Bolt Kit NSN: 5305016173161 or PN:
93112090K
10 ea. 12.56
4 N O-ring NSN: 5331580006241 or PN:
10202606
6 ea. 14.56
4 N **Mechanical Sealing NSN: 4320580006403 or PN:
10203870
2 ea. 1052.97
4 N Bolt Kit NSN: 5306016164058 or PN: 6 ea. 1.92 vii (Rev-0)
93310030E 4 N O-ring NSN: 5331016020679 or PN:
10202631 2 ea. 4.39
4 N O-ring NSN: 5331016020680 or PN:
10202625
4 ea. 15.15
4 N Sealing NSN: 5365016233174 or PN:
41018801
2 ea. 8.87
4 N O-ring NSN: 5331016200368 or PN:
10202611
2 ea. 5.21
4 N Seal Lip NSN: 4730016204613 or PN:
10202590
4 ea. 39.47
4 N Sealing NSN: 5330016163186 or PN:
45002010
2 ea. 535.93
4 N **Lock Nut NSN: 5310016162982 or PN:
10202908
2 ea. 16.63
4 N Lock Washer NSN: 5310016232756 or PN:
10203008
2 ea. 2.34
4 N **Ring Nut NSN: 5310016164016 or PN:
10202912
2 ea. 32.60
4 N Seal NSN: 5330016243735 or PN:
10202540R
6 ea. 19.68
4 N **Screw NSN: 5305016162955 or PN:
93305025
8 ea. 0.28
4 N **Washer NSN: 5310016162966 or PN:
912505
8 ea. 0.06
4 N Gasket NSN: 5330016232867 or PN:
37527805
2 ea. 63.43
4 N Bushing NSN: 5365016202680 or PN:
10108416
8 ea. 15.91
4 N **Bolt Kit NSN: 5305016242899 or PN:
93110060A
4 ea. 12.91
4 N **Bolt Kit NSN: 5305016242922 or PN:
99110040G
14 ea. 6.60
4 N Bushing NSN: 3120014555268 or PN:
10106902
8 ea. 7.90
4 N Gasket NSN: 5330016163014 or PN:
10108901
2 ea. 5.65
4 N **Bolt Kit NSN: 5305016231019 or PN:
93110090A
4 ea. 5.05
4 N Lock Washer NSN: 5310016232699 or PN:
10203012
2 ea. 5.62
4 N O-ring NSN: 5331016242120 or PN:
10202603
2 ea. 3.89
4 N **Screw, Countersunk NSN: 5305016309734 or PN:
99106016
8 ea. 5.65
4 N Seal/Gasket NSN: 1040016337691 or PN:
45011611
2 ea. 57.64
4 N Woodruff Key NSN: 5315016172999 or PN:
10100823
2 ea. 19.09 viii (Rev-0)
4 N Washer, Sealing NSN: 5310016452084 or PN:
8755000050
24 ea. 0.06
4 N Screw, Connection NSN: 5305016476396 or PN:
91212045L
16 ea. 6.45
5 N Anode, Inspection Hatch (Port & Stbd)
NSN: 5342580003759 or PN:
10108231
2 ea. 46.63
5 N Transom Anode NSN: 5342016020658 or PN:
10108230
4 ea. 52.76
5 N Tunnel Anode NSN: 5342016020668 or PN:
10108220
4 ea. 26.88
5 N Impeller Housing/Bucket/Interceptor
Anode
NSN: 5342226078672 or PN:
10107701
10 ea. 24.94
5 N Guide Vane Chamber Anode
NSN: 5342016020669 or PN:
37517411
2 ea. 44.43
5 N Anode, Anode Hatch NSN: 5342251465439 or PN:
10108210
2 ea. 28.20
5 N Screw Connection NSN: 5305016022100 or PN:
93310025H
4 ea. 2.52
5 N Screw Connection NSN: 5305016275854 or PN:
93308025H
14 ea. 1.30
5 N Screw Connection NSN:5305016022105 or PN:
91206020E
8 ea. 0.49
5 N Screw Connection NSN: 5340016243271 or PN:
93308025E
8 ea. 1.00
5 N O-ring NSN: 5331016020670 or PN:
10202639
2 ea. 6.60
5 N Screw Connection NSN: 5305016240905 or PN:
93310016E
8 ea. 1.58
5 N Screw Connection NSN: 5306016309800 or PN:
93312030E
2 ea. 2.42
5 N Screw Connection NSN: 5305016204602 or PN:
91212025E
8 ea. 1.93
5 N O-ring NSN: 5331226078691 or PN:
10202626
2 ea. 9.26
5 N Tube Extension NSN: 4730016210708 or PN:
37610802
2 ea. 148.88
5 N Tube Clamp NSN: 4730016200951 or PN:
10217881
2 ea. 20.05
5 N Screw Connection NSN: 5305016022101 or PN:
93310030H
2 ea. 2.08
5 N Connecting Cable NSN: 6145016203663 or PN:
10234301
4 ea. 21.23
5 N Screw Connection NSN: 5305016176732 or PN:
93306016E
8 ea. 0.44
5 N Anode, Corrosion NSN: 5340015899440 or PN:
51125
2 ea. 32.56
5 N Anode, Corrosion NSN: 5340015899425 or PN:
89287
2 ea. 12.34 ix (Rev-0)
15 N Gasket (Manhole Cover) NSN: 5330-01-134-1986 PN:
3560BN
4 ea. 16.98
18 N Repair Kit, Fender NSN: 2090-01-589-9430 or
PN: RBM-SRK
1 ea. 398.88
19 N Fender, Marine – (PC# 12)
NSN: 2040-01-612-5130 or
PN: 207587
1 ea. 1,239.63
19 N Fender, Marine – (PC#
13) (3 Port and 3
Starboard)
NSN: 2040-01-612-5132 or
PN: 205064
1 ea. 1,260.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
1 Ultrasonic Testing (UT) (100) Shots, Perform
3 Main Diesel Engine(s) To MEPS Generator(s) And Jet Drive(s), Align
4 Water Jet-Inspect, Perform Service
6 Fender Faying Surfaces, Preserve, 100 percent
7 Water Jet Drive, Preserve
8 U/W Body, Preserve (100%)
12 Lazarette Bilge, Preserve
14 Fendering System, Inspect xi (Rev-0)
PRINCIPAL CHARACTERISTICS
45' RB-M
PHYSICAL
Length overall 44 feet, 10.5 inches Unfixed height 20 feet 9 inches Beam, maximum 14 feet, 7.75 inches Full load draft 3 feet, 4 inches Full load displacement 36,500 pounds Max sustained speed 42.5 knots Range 250 nautical miles at 30 knots Mission limits 8 foot seas / 30 knot winds Survivability limits 12 foot seas / 50 knot winds
HULL
Hull manufacturer Marinette Marine Corp.
5086 (GRADE) Aluminum Hin- 2009
MACHINERY
Type 6, cylinder diesel engine Number of units 2, MTU's 60 series 825 hp Propulsion type 2, Rolls-royce water-jet
TANKS
1 (Rev-0)
00000_0521_FLT
REC_00000_FLT_Boats @ Commercial Facility (0121)
General Requirements
1.1 SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
1.2 REFERENCES
1.2.1 COAST GUARD DRAWINGS
None
1.2.2 COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
1.2.3 Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
1.2.4 OTHER REFERENCES
None
1.3 REQUIREMENTS
1.3 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
2 (Rev-0)
1.4 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
1.5 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
1.5.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
1.5.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
1.6 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
1.7 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
1.7.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability.
Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
1.7.2 Test and procedures. The Contractor must be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
1.7.3 Regulatory notifications. The Contractor must be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer.
The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
1.7.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project and must be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
3 (Rev-0) ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
1.7.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities for HW disposal.
1.8 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).
1.8.1 Coast Guard turn-over preparation. The Contractor must be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew must be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:
1.8.1.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.
1.8.1.2 The Contractor may commence/continue work during these time frames.
1.8.1.3 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.
1.8.1.4 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.
1.9 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
1.9.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:
1.10 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.
1.10.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three-inch minimum may be approved by the KO on a case-by-case basis provided sufficient clearance is maintained for welding and inspection requirements.
The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable.
The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.
1.10.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:
Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.
For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.
Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch
4 (Rev-0)
NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”
to allow for shrinkage when welded.
Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.
Corners at an existing seam or butt shall intersect at a 90-degree angle.
Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus
15 degrees.
In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.
Existing welds crossed by the cut shall not be cut back.
1.10.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.
1.10.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.
1.11 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.
1.11.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.
1.11.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.
1.11.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:
Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).
Fitted with fasteners that permit rapid installation and removal.
Able to support a minimum of 150 pounds per square foot for horizontal deck closures.
Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.
1.11.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.
5 (Rev-0)
1.4 NOTES
1.12 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE
MANUFACTURER:
ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
4.2 Tank and Void Assessment form.
13 (Rev-0)
14 (Rev-0)
10000_AKP_0121_45RBM
WORK ITEM 1: Ultrasonic Testing (UT) (100) Shots, Perform
1. Scope
1.1 Intent. This work item describes the requirements for the Contractor to take 100 UT shots.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.3 Reporting
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
15 (Rev-0)
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 UT measurement. The Contractor must perform a total of 100 UT measurements in accordance with SFLC Std Spec 0000 and SFLC Std Spec 0740.
3.2.1 Standard measurements. The Contractor must take 70 standard thickness measurements for the designated locations numbered 1 thru 70 between the boot top and keel, (Refer to Figure 1 and Figure 2).
3.2.1.1 The Contractor must record each measured metal thickness in the Standard Underwater (U/W) Body Test Results Report, (Refer to Table 1 and Table 2).
3.2.1.2 The Contractor must calculate each percent loss.
3.2.1.3 The Contractor must record each percent loss in the Standard U/W Body Test Results Report.
3.2.2 Additional measurements. The Contractor must take 30 additional thickness measurements at locations designated by the Coast Guard inspector and numbered 1A through 30A between the boot top and keel, (Refer to Figure 1 and Figure 2).
3.2.2.1 The Contractor must record each measured metal thickness in the Additional U/W Body Test Results Report, (Refer to Table 3).
3.2.2.2 The Contractor must calculate each percent loss.
3.2.2.3 The Contractor must record each percent loss in the Additional U/W Body Test Results Report.
3.2.3 Minimum thickness. The Contractor must record the minimum thickness found for each designated hull section. (A, B, and C) in the Underwater Hull Body Minimum Thickness Test Results Report, (Refer to Table 4).
3.3 Reporting. The Contractor must submit a CIR to include a marked up drawing of Figure 1 and 2 and the completed tables.
4. NOTES
4.1 Coast Guard Personnel. The Coast Guard inspector will witness all readings.
16 (Rev-0)
FIGURE 1. BOTTOM SHELL PLATING EXPANDED
17 (Rev-0)
FIGURE 2. STERN SECTION SHELL PLATING
TABLE 1 - STANDARD U/W BODY TEST RESULTS REPORT
DATE: ____________________________
*CALCULATING PERCENT LOSS = 100- (UT READING / DESIGN THICKNESS X 100)
18 (Rev-0)
19 (Rev-0)
TABLE 2 - STANDARD U/W BODY TEST RESULTS REPORT (STERN)
*CALCULATING PERCENT LOSS = 100- (UT READING / DESIGN THICKNESS X 100)
LOCATION
AREA
DESIGN
THICKNESS
MINIMUM
ALLOWABLE THICKNESS
UT
READINGS
*PERCENT LOSS
STERN SECTION “C”
61 .250 .187 62 .250 .187 63 .250 .187
STERN SECTION “B”
64 .250 .187 65 .250 .187 66 .250 .187 67 .250 .187
STERN SECTION “A”
68 .250 .187 69 .250 .187 70 .250 .187
20 (Rev-0)
TABLE 3 - ADDITIONAL U/W BODY TEST RESULTS REPORT
*CALCULATING PERCENT LOSS = 100- (UT READING / DESIGN THICKNESS X 100)
LOCATION AREA DESIGN
THICKNESS
MINIMUM
ALLOWED
THICKNESS
UT READING *PERCENT LOSS
PORT SIDE AREAS “A, B, C”
1A .250 .187 2A .250 .187 3A .250 .187 4A .250 .187 5A .250 .187 6A .250 .187 7A .250 .187 8A .250 .187 9A .250 .187
10A .250 .187 11A .250 .187 12A .250 .187
STARBOARD SIDE AREAS “A, B, C”
13A .250 .187 14A .250 .187 15A .250 .187 16A .250 .187 17A .250 .187 19A .250 .187 20A .250 .187 21A .250 .187 22A .250 .187 23A .250 .187 24A .250 .187
STERN AREAS “A, B, C”
25A .250 .187 26A .250 .187 27A .250 .187 28A .250 .187 29A .250 .187 30A .250 .187
21 (Rev-0)
TABLE 4 - UNDERWATER HULL BODY MINIMUM THICKNESS TEST RESULTS REPORT
DATE: ______________________
LOCATIONS MIN. THICKNESS FOUND DESIGN
THICKNESS
MINIMUM
ALLOWED
THICKNESS
AT 25%
LOSS
MINIMUM
ALLOWED
THICKNESS AT
50% LOSS
(A) (B) (C)
Port Hull: Boot Top to Keel
.250 .187 .125
STBD Hull: Boot Top to Keel
Stern Hull: Boot Top to Keel
Comments:
22 (Rev-0)
11000_AKP_0822_45RBM
WORK ITEM 2: Hull Plating (U/W Body), Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 45 RB-M 084-002, Rev -, Docking Plan
Coast Guard Drawing 45 RB-M 110-001, Rev -, Hull Structure
Coast Guard Drawing 45 RB-M 631-001, Rev A, Painting Layout
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D4138, Rev A, 2007 (R 2022), Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
The Society for Protective Coatings (SSPC), 2015 (E 2017), Paint Application Specification No.
2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
23 (Rev-0)
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor must accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using Coast Guard Drawings 45 RB-M 084- 002, 45 RB-M 110-001, 45 RB-M 631-001, and SFLC Std Spec 0000 as guidance. The Contractor must provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor must inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor must inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. The Contractor must inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Water jet drive. The Contractor must inspect the water jet drive assembly for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks. Inspect all linkages for any missing fasteners, physical damage, pitting, or other conditions effecting usage.
3.2.4 Transducers. The Contractor must check general condition of the transducers for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness and inspect cables for chafing and other damage.
3.2.6 Zinc anodes.
24 (Rev-0)
3.2.6.1 The Contractor must remove all marine growth and oxide coating from all hull, rudder, shaft strut, welds, water jet drives, and sea chest anodes, as applicable, using a light-wire brush.
3.2.6.2 The Contractor must visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.7 Coating system inspections. The Contractor must accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).
Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.7.1 The Contractor must perform a visual inspection of the existing U/W body coating system.
3.2.7.2 The Contractor must take total dry film thickness (DFT) measurements of the U/W body coating system, in accordance with SSPC-PA 2. Ensure that film thickness measurement is taken with a suitable eddy current gauge, for non-ferrous metal substrate.
4. NOTES
4.1 Definitions.
4.1.1 “Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 “Partial - Condition B”: The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but the u/w body hull substrate is not exposed in any location.
4.1.3 “Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoat; the epoxy undercoating system is not exposed in any location.
4.1.4 “100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
25 (Rev-0)
24000_AKP_0121_45RBM
WORK ITEM 3: Main Diesel Engine(s) To MEPS Generator(s) And Jet Drive(s), Align
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to align the designated Main Diesel Engine(s) (MDE) and Reduction Gear(s) selected in Table 1, to the MEPS Generator(s) and Jet Drive(s).
TABLE 1 - MAIN DIESEL ENGINE AND REDUCTION GEAR
SELECT ENGINE AND REDUCTION
XX Port Main Diesel Engine and Reduction Gear XX Starboard Main Diesel Engine and Reduction Gear
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y * MDE/ TO GENERATOR
ALIGNMENT TOOL
PN: MMRBM0030 1 ea.
Y * MDE/ TO JET DRIVE
ALIGNMENT TOOL
PN: MMRBM0451 1 ea.
Y * ENGINE LIFTING BAR PN: MMRBM0956 1 ea.
*Government-loaned property, which must be returned to the vessel upon completion of the availability.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 45 RBM 201-001, Rev B, Main Engine Arrangement
Coast Guard Drawing 45 RBM 247-002, Rev -, Water Jet Propulsor Arrangement
Coast Guard Drawing 45 RBM 311-004, Rev -, APU Generator Drive System
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
None
26 (Rev-0)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.3.1 MDE/ MEPS Generator Preliminary Alignment Check
3.3.2 MDE to Jet Drive Preliminary Alignment Check
3.3.3 Engine Mounts
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Primary Fuel Filter Assembly
Marine Interface Module
NOTE
Coast Guard personnel will operate all vessel machinery and equipment.
3.2 Operational test - initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
CAUTION
The Coast Guard crew will complete Red Danger Tags IAW COMDTINST
9077.1 (series) and attach them to the following:
Circuit Breaker CB2, ENGINE PRIMARY, Power Panel 24 VDC ENGINE
BUS 24P2, “OFF”.
Circuit Breaker CB1, ENGINE SECONDARY, Power Panel 24 VDC VITAL
BUS 24P1, “OFF”.
Affected MDE Propulsion Raw Water Suction Valve, Lazarette, “CLOSED”.
Affected MDE Propulsion Raw Water De-Icing Valve, Lazarette, “CLOSED”.
Affected MDE Fuel Shutoff Valve, Engine Room, “CLOSED”.
Affected MDE Secondary Fuel Filter Shutoff Valve, Engine Room, "CLOSED".
3.3 Preliminary alignment checks. The Contractor must conduct preliminary alignment checks on the Main Diesel Engine(s) (MDE) to the MEPS Generator(s) and the MDE(s) to Jet Drive(s) selected in Table
27 (Rev-0)
1, in accordance with Coast Guard Drawings 45 RBM 201-001, 45 RBM 247-002, 45 RBM 311-004 and SFLC Std Spec 0000.
3.3.1 MDE to generator preliminary alignment check. The Contractor must conduct a preliminary alignment check. Submit A CIR.
3.3.1.1 Remove the generator drive shaft.
3.2.1.2 Remove the three roll pins from the Overhung Load Adapter (OHLA) shaft flange, (Refer to Figure 1).
3.3.1.3 Install the MDE to generator alignment tool, (Refer to Figure 2).
Align the generator alignment tool flange (Item 1) to the OHLA shaft (Item 2) and install.
Slide the alignment sleeve (Item 4) onto the generator alignment pin.
Align the MDE alignment tool flange (Item 5) to the MDE adapter (Item 6).
3.3.1.4 Check the MDE to generator alignment, (Refer to Figure 3).
CAUTION
Do not force the alignment sleeve when checking MDE-to-Generator alignment. Forcing the alignment sleeve will cause the alignment sleeve to bind, damaging the surfaces of the alignment sleeve and the alignment sleeve pins.
Slide the alignment sleeve (Item 1) towards the MDE adapter…
This is the start of the file's text. The full file is on GovTribe.