SPEC_263343-STATIC UPS -ReplaceUPSBattery-626-24-1-4123-0173.docx

DOCX document 29 KB Posted

Attached to
J061--Combined Synopsis/Solicitation- 626-24-1-4123-0173 -Replace UPS Batteries
Solicitation number
36C24924Q0048
Issued by

About this file

This document is a technical specification for replacing batteries in a static uninterruptible power supply (UPS) system at a Department of Veterans Affairs medical facility. Key details include:

  • The specification covers furnishing and installing replacement batteries for an existing //kVA, //kW, //non// //N+1// redundant UPS system to provide a discharge time of 15 to 240 minutes at 25 degrees Celsius. The new batteries must be capable of delivering 125 percent of the UPS's full rated output load.

  • Technical requirements include specifications for the battery type, construction, cabinet, cables, and disconnect switch. Load, voltage transient response, and overcurrent protection tests are to be performed, along with a 24-hour continuous load test at varying levels, a full load battery discharge test, and a complete battery discharge and recharge test while recording instrument readings.

  • The related federal contract opportunity is solicitation number 36C24924Q0048 for replacing the UPS batteries at Department of Veterans Affairs medical center location 626-24-1-4123-0173.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-22

SECTION 26 33 53

Static UNINTERRUPTIBLE POWER SUPPLY

PART 1 GENERAL

1.1 DESCRIPTION

A. This section specifies the furnishing, installation, connection, and testing of the static uninterruptible power supply, indicated in this section as UPS.

1.2 RELATED WORK - NA

1.3 qualITY ASSURANCE A. Quality Assurance shall be in accordance with Eaton UPS Battery Installation Manual standards.

1.4 SUBMITTALS

A.Submit in accordance with Statement of Work, and the following requirements:
1.Certifications: Two weeks prior to final inspection, submit the following.
a.Certification by the Contractor that the UPS has been properly installed, adjusted, and tested.

1.5 APPLICABLE PUBLICATIONS

A.Publications listed below (including amendments, addenda, revisions, supplements, and errata), form a part of this specification to the extent referenced. Publications are referenced in the text by basic designation only.
B.Institute of Engineering and Electronic Engineers (IEEE):
C57.110-08Recommended Practice for Establishing Transformer Capability When Supplying Nonsinusoidal Load Currents
C62.41.1-02Surge Environment in Low-Voltage (1000 V and Less) AC Power Circuits
C62.41.2-02Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits
450-20Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications
485-20Sizing Lead-Acid Batteries for Stationary Applications
C.International Code Council (ICC):
IBC-18International Building Code
D.National Electrical Manufacturers Association (NEMA):
PE 1-12Uninterruptible Power Systems - Specification and Performance Verification
E.National Fire Protection Association (NFPA):
70-23National Electrical Code (NEC)

PART 2 PRODUCTS

2.1 GENERAL REQUIREMENTS

A.System Capacity: Unless stated otherwise, the parameters listed are under full rated output load at a minimum of 0.9 power factor, with batteries fully charged and floating on the DC bus and with nominal input voltage. Overall //kVA, // //kW, //non// //N+1// redundant, at 40 C.
B.Battery Capacity: Discharge time to end voltage: 15 to 240 minutes, at 25 C (77 F). Battery shall be capable of delivering 125 percent of full rated output load at initial start-up.
C.System Bus Bracing: Braced for amperes symmetrical interrupting capacity as shown on drawings.
D.AC Input:
1.Voltage 208 volts line-to-line.
2.Number of phases: 3-phase, 3-wire, plus ground.
3.Voltage Range: Plus 10 percent, minus 15 percent, without affecting battery float voltage or output voltage.
4.Frequency: 60 Hz, plus or minus 5 percent.
5.Total harmonic current distortion (THD) reflected into the primary line: //5// //10// percent maximum.
E.AC Output
1.Voltage //208// volts line-to-line, //120// volts line-to-neutral.
2.Number of phases: 3-phase, //3-wire// //4-wire//, plus ground.
3.Voltage regulation:
a.Balanced load: Plus or minus 1.0 percent.
b.100 percent load imbalance, phase-to-phase: Plus or minus 3 percent.
4.Frequency: 60 Hz.
5.Frequency regulation: Plus or minus 0.05 percent.
6.Harmonic content (RMS voltage): 5 percent maximum total harmonic distortion with 100% nonlinear load.
7.Load power factor operating range: 1.0 to 0.8 lagging.
8.Phase displacement:
a.Balanced load: Plus or minus 1 degree of bypass input.
9.Overload capability (at full voltage) (excluding battery):
a.125 percent load for 10 minutes.
b.150 percent load for 1 minute.
F.Voltage Transient Response:
1.100 percent load step: Plus or minus 5 percent.

2.2 BATTERY SYSTEM

A.General: A storage battery with sufficient ampere-hour rating to maintain UPS output at full capacity for the specified duration shall be provided for each UPS module.
B.Battery Type: Lead calcium.
C.Battery Construction: The battery shall be of the valve-regulated, sealed, non-gassing, recombinant type.

D. Battery Cabinet: The batteries shall be furnished in a battery cabinet matching the UPS. The battery cabinet shall be provided with smoke and high temperature alarms.

E. Battery Cables: Battery-to-battery connections shall be stranded cable with proper cable supports.

F. Battery Disconnect: Each battery cabinet shall have a fused disconnect switch or circuit breaker, lockable in the “off” position, provided in a NEMA 1 enclosure.

PART 3 EXECUTION

3.1INSTALLATION
A.The UPS shall be set in place, wired, and connected in accordance with the approved shop drawings and manufacturer's instructions.
3.2Acceptance Checks and Tests
A.An authorized representative of the UPS manufacturer shall technically supervise and participate during all of the field adjustments and tests. Major adjustments and field tests shall be witnessed by the COR. The manufacturer’s representative shall certify in writing that the equipment has been installed, adjusted, and tested in accordance with the manufacturer’s recommendations.
B.Perform manufacturer’s required field tests in accordance with the manufacturer's recommendations. In addition, include the following:
1.Visual Inspection and Tests:
a.Inspect physical, electrical, and mechanical condition.
b.Verify appropriate anchorage, required area clearances, and correct alignment.
c.Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey after energization.
d.Verify grounding connections.
e.Vacuum-clean enclosure interior. Clean enclosure exterior.
f.Verify the correct operation of all alarms and indicating devices.
g.Check and test controls for proper operation.
h.Check doors for proper alignment and operation.
i.Check and test each protective device for proper mechanical and electrical operation.
j.Verify protective device overcurrent trip settings against approved coordination study.
k.Confirm correct operation and sequencing of key-type mechanical interlock systems.
2.Load Test: The UPS shall be load tested for a continuous 24 hour period by means of resistive load banks, sized for full rated output load and provided by the UPS manufacturer, after the first quarter maintenance inspection, estimated to be on or around April 2024. The UPS shall be continuously tested at 1/2 load for 8 hours, 3/4 load for 8 hours and full load for 8 hours. If a failure occurs during the burn-in period, the tests shall be repeated. Instrument readings shall be recorded every half hour for the following:
a.Input voltage and current (all three phases, for each module).
b.Input and output frequency.
c.Battery voltage for each module.
d.Output voltage and current (all three phases, for each module).
e.Output kilowatts for each module.
f.Output voltage and current (all three phases).
g.Output kilowatts.
3.Full Load Battery Burn In Test: The UPS shall undergo a full load battery test by means of resistive load banks, sized for full rated output load and provided by the UPS manufacturer. If a failure occurs during the battery discharge time, the tests shall be repeated. Instrument readings shall be recorded every half hour as above.
a.With the UPS carrying full rated output load and operating on battery power, switch //100 percent// //50 percent// of load bank capacity on and off a minimum of five times within the battery discharge time.
4.Battery Discharge and Recharge Test: With the battery fully charged, the UPS shall undergo a complete battery discharge test to full depletion followed by a full recharge. Instrument readings shall be recorded every minute during discharge for the following:
a.Battery voltage and current// for each module//.
b.Output voltage and current (all three phases)// for each module//.
c.Output kilowatts// for each module//.
d.Output voltage and current (all three phases).
e.Output kilowatts (system).
f.Output frequency.

3.3 Follow-Up Verification

A. After completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the UPS is in good operating condition and properly performing the intended function.

---END---