This is a Request for Quotations (RFQ) issued by DLA Weapons Support, ASC Commodities Division, for the procurement of bolts with externally relieved bodies (NSN 5306-00-083-7025).

The solicitation requests quotations for 814 units of the bolt item with a firm fixed price and a 60-day delivery requirement from the award date. The delivery destination is DLA Distribution Depot Oklahoma in Tinker, Oklahoma, with inspection and acceptance at origin. A separate first article test (FAT) requirement is included, with one unit due within 180 days and final production delivery within 142 days after FAT approval, totaling 562 days for complete FAT compliance. The Government's cost for FAT testing is $27,885.00, which will be added to the offered price for evaluation purposes. Quotations are due by October 20, 2026. This is a critical application item designated for Air Force use and an Air Force Critical Safety Item (CSI), requiring all requests for waivers or deviations to be submitted to the DSC Contracting Officer for review and approval. The item has export-controlled technical data subject to ITAR/EAR restrictions, and offerors must have approved US/Canada Joint Certification Program certification and DLA approval to access such data. Quality requirements include SAE AS9100 standards, MIL-STD-1916 sampling procedures, and compliance with various technical and packaging specifications. Payment will be processed through the Wide Area Workflow (WAWF) system. The solicitation incorporates numerous FAR and DFARS clauses covering representations, certifications, compliance requirements, and standard contract terms applicable to federal procurements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATIONS THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

4. CERT.FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

5. ISSUED BY

7. DELIVERY

9. DESTINATION

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5 ON OR

BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (See Continuation Sheets)

12. DISCOUNT FOR PROMPT PAYMENT

d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

14. SIGNATURE OF PERSON AUTHORIZED TO SIGN

QUOTATION

16. SIGNER

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not useable

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

SPE4A6-27-Q-0035

1. REQUEST NO.

2026 OCT 06

2. DATE ISSUED

7016226594

3. REQUISITION/PURCHASE REQUEST NO.

DO-C9

RATING

DLA WEAPONS SUPPORT

ASC COMMODITIES DIVISION

6090 STRATHMORE ROAD

RICHMOND VA 23237

USA

Buyer: Tywanda MADDOX ADDINGTON DTM0185 Tel: 0001 Email: TYWANDA.MADDOXADDINGTON@DLA.MIL

SEE SCHEDULE

6. DELIVER BY (Date)

8. TO:

c. CITY

d. STATE

b. STREET ADDRESS

a. NAME OF CONSIGNEE

e. ZIP CODE

a. 10 CALENDAR DAYS

b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS

15. DATE OF QUOTATION

a. NAME (Type or Print)

AREA CODE

c. TITLE (Type or Print)d. CITY

c. COUNTY

b. STREET ADDRESS

e. STATE f. ZIP CODE

See Schedule

2026 OCT 20

NUMBER

FOB DESTINATION

OTHER

(See Schedule)

CAGE

b. TELEPHONE

See attached schedule to complete quote information.

Quoter must also complete the following:

a. Quotation is valid for 90 days from date specified in Block 10 above unless otherwise indicated: _____________ .

b. Prices quoted are:

___ Contained in Commercial Catalog or Published Price List No. ___________________ dated _______________ page __________ .

___ Contained in Internal Price List No. _______________dated ____________________, which may be examined at our facility.

___ Commercial sales of comparable quantities: Quantity ____________ ; Price _____________;

___ Customer ________________________.

___ Other (provide basis) ______________________________________ _______________________________________ .

c. FOB Point: ____ Destination ____ Origin Shipping Point (City, State) _________________________________________ .

d. If delivery period shown in Block 6 is unacceptable, provide best possible delivery: _________________________________.

e. Remittance Address (Name, Street, City, State, ZIP): Same as Block 13 unless otherwise indicated below:

f. Vendor FAX Number: ____________________ Vendor Toll-Free Number: ____________________ Vendor E-mail: ______________________________

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED:

CONTINUED ON NEXT PAGE

PAGE 2 OF 31 PAGES

SPE4A6-27-Q-0035

The following Procurement Guidance Notices (PGNs) are incorporated by reference.

The full text of the notices can be found at: https://www.dla.mil/Aviation/Business/DAANS.

PGN-13-01 Evaluation and Award for Simplified Acquisitions (August 2024)

(a) AWARD. The Government intends to evaluate quotations. The award will be made to the quoter whose quote conforms to the terms and conditions of the solicitation and represents the best value to the Government. Therefore, award may be made to other than the lowest priced or the highest technically rated quote.

(b) RELATIVE IMPORTANCE AND TRADE-OFFS. The Government will base the determination of best value on a comparative assessment of the quoters' prices, past performance, and the other evaluation factors identified elsewhere in this solicitation. The determination of best value also considers the relative importance of the evaluation factors. All evaluation factors, when combined, are:

[ ] significantly more important than cost or price. As other evaluation factors become more equal, the evaluated cost or price becomes more important.

[X] approximately equal to cost or price; or

[ ] significantly less important than cost or price. As the evaluated cost/price becomes more equal, relative importance of all other evaluation factors becomes more significant.

The final award decision may involve a trade-off among cost or price and the non-price factors. Factors that may be considered in the trade-off process include, but are not limited to:

Item criticality and weapons system application

Current inventory status

Historical delivery or quality problems

Concerns over limited supply sources and industrial base

Benefits from obtaining new sources

(c) COST OR PRICE. The Government will evaluate the quoted cost or price. The Government will add any other cost or price evaluation factors identified elsewhere in this solicitation (e.g., Buy American Act or FOB Origin transportation costs) to arrive at the quoter's evaluated cost or price. The evaluated cost or price will be used in conjunction with the other non-price factors to determine the best value to the Government.

(d) PAST PERFORMANCE. Past performance includes, but is not limited to, the quoter's record of conforming to contract requirements and standards of good workmanship; adherence to contract schedules, including the administrative aspects of performance; the quoter's reputation for reasonable and cooperative behavior and commitment to customer satisfaction; and generally, the quoter's business-like concern for the customer's interest.

(1) The Supplier Performance Risk System (SPRS) is the current term for past performance that is formerly known as Past Performance Information Retrieval System –

Statistical Reporting (SPRS), as applicable, will be used to evaluate quality and past performance on DLA awards (refer to Procurement Note L08).

(e) PAST PERFORMANCE EVALUATION FACTORS. The Government will use the past performance evaluation factors marked below in addition to cost or price and other evaluation factors specified in the solicitation. Unless indicated otherwise, past performance is significantly more important than other non-price factors. Within the past performance subfactors, SPRS assessments (as applicable) will be weighed most heavily. Historical quality history and delivery schedule compliance (not captured in SPRS) will be weighed more heavily than the remaining past performance subfactors. All other non-price evaluation factors specified in this solicitation weigh equally, unless otherwise indicated.

[X] SPRS Assessments ( PROC NOTE L08)

[ ] Historical Quality (not captured in SPRS)

[ ] Historical Delivery Schedule Compliance (not captured in SPRS)

[ ] Other (specify):

(End of Notice)

PGN-13-01 (ALT I) Evaluation and Award for Simplified Acquisitions (March 2018)

(a) Quoted Delivery. The Government will evaluate the quoter’s compliance with the delivery schedule specified in the solicitation. Quoting a greater number of days delivery than requested under the solicitation will result in the quote being evaluated less favorably than a quote meeting the requested delivery schedule. There will be no evaluation preference for quoted delivery which is earlier than the requested delivery schedule.

(b) Non-Price Factors. Quoted delivery and past performance will be evaluated equally, unless indicated otherwise below.

PAGE 3 OF 31 PAGES

SPE4A6-27-Q-0035

[ ] Quoted delivery is weighed more heavily than past performance.

[ ] Past Performance is weighed more heavily than quoted delivery.

PAGE 4 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION B

SUPPLIES/SERVICES: 5306-00-083-7025

ITEM DESCRIPTION:

BOLT,EXTERNALLY RELIEVED BODY

RA001: THIS DOCUMENT INCORPORATES TECHNICAL AND/OR QUALITY REQUIREMENTS

(IDENTIFIED BY AN 'R' OR AN 'I' NUMBER) SET FORTH IN FULL TEXT IN THE

DLA MASTER LIST OF TECHNICAL AND QUALITY REQUIREMENTS FOUND ON THE WEB

AT:

http://www.dla.mil/HQ/Acquisition/Offers/eProcurement.aspx

FOR SIMPLIFIED ACQUISITIONS, THE REVISION OF THE MASTER IN EFFECT ON THE

SOLICITATION ISSUE DATE OR THE AWARD DATE CONTROLS. FOR LARGE

ACQUISITIONS, THE REVISION OF THE MASTER IN EFFECT ON THE RFP ISSUE DATE

APPLIES UNLESS A SOLICITATION AMENDMENT INCORPORATES A FOLLOW-ON

REVISION, IN WHICH CASE THE AMENDMENT DATE CONTROLS.

RP001: DLA PACKAGING REQUIREMENTS FOR PROCUREMENT

RQ011: REMOVAL OF GOVERNMENT IDENTIFICATION FROM NON-ACCEPTED SUPPLIES

RQ017: PHYSICAL IDENTIFICATION/BARE ITEM MARKING

SAMPLING:

THE SAMPLING METHOD SHALL BE IN ACCORDANCE WITH MIL-STD-1916 OR ASQ

H1331, TABLE 1 OR A COMPARABLE ZERO BASED SAMPLING PLAN UNLESS OTHERWISE

SPECIFIED BY THE CONTRACT. IF THE APPLICABLE DRAWING, SPECIFICATION,

STANDARD, OR QUALITY ASSURANCE PROVISION (QAP) SPECIFIES CRITICAL, MAJOR

AND/OR MINOR ATTRIBUTES, THEY SHALL BE ASSIGNED VERIFICAITON LEVELS OF

VII, IV AND II OR AQLS OF 0.1, 1.0 AND 4.0 RESPECTIVELY. UNSPECIFIED

ATTRIBUTES SHALL BE CONSIDERED AS MAJOR UNLESS SAMPLING PLANS ARE

SPECIFIED IN APPLICABLE DOCUMENTS. FOR MIL-STD-1916, THE MANUFACTURER

MAY USE THE ATTRIBUTE OR VARIABLE INSPECTION METHOD AT THEIR OPTION OR

PER THE CONTRACT. MIL-STD-105/ASQ Z1.4 MAY BE USED TO SET SAMPLE LOT

SIZE, BUT ACCEPTANCE WOULD BE ZERO NON-CONFORMANCES IN THE SAMPLE LOT

UNLESS OTHERWISE SPECIFIED IN THE CONTRACT.

Item Unique Identification is not required by request of the Service customer. DFARS 252.211-7003(c)(1)(i) applies.

RT001: MEASURING AND TEST EQUIPMENT

RD005: Cybersecurity Maturity Model Certification (CMMC) Level 2 Certified Third-Party Assessment Organization (C3PAO)

RQ032: EXPORT CONTROL OF TECHNICAL DATA

This item has technical data some or all of which is subject to export-control of either the International Traffic in Arms regulations (ITAR) or the Export Administration Regulations (EAR), and cannot be exported without prior authorization from either the Department of State or the Department of Commerce. Export includes disclosure of technical data to foreign persons and nationals whether located in the United States or abroad. This requirement applies equally to foreign national employees and U.S. companies and their foreign subsidiaries. DFARS 252.225-7048 is applicable to this data.

The Defense Logistics Agency (DLA) limits distribution of export-control technical data to DLA contractors that have an approved US/Canada Joint Certification Program (JCP) certification, have completed the Introduction to Proper Handling of DOD Export-Controlled Technical Data Training and the DLA Export-Controlled Technical Data Questionnaire (both are available at the web address given below), and have been approved by the DLA controlling authority to access the export-controlled data. Instructions for obtaining access to the export-controlled data can be found at:

https://www.dla.mil/Logistics-Operations/Enhanced-Validation/

To be eligible for award, offerors and any sources of supply proposed for use are required to have an approved JCP certification and have been approved by the DLA controlling authority to access

PAGE 5 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION B

SUPPLY/SERVICE: 5306-00-083-7025 CONT'D

export-controlled data managed by DLA. DLA will not delay award in order for an offeror or its supplier to apply for and receive approval by the DLA controlling authority to access the export-controlled data.

RQ009: INSPECTION AND ACCEPTANCE AT ORIGIN

RD002, COVERED DEFENSE INFORMATION APPLIES

RQ039: Non-Tailored Higher-Level Quality Requirements (SAE AS9100) for Manufacturers and Non-Manufacturers

RQ002: CONFIGURATION CHANGE MANAGEMENT - ENGINEERING CHANGE PROPOSAL

REQUEST FOR VARIANCE (DEVIATION OR WAIVER)

RC001: DOCUMENTATION REQUIREMENTS FOR SOURCE APPROVAL REQUEST (SAR)

QAP EQ003 APPLIES

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

Unless otherwise stated, identification marking shall be in accordance with paragraph 4.1.b(2) of MIL-STD-130N. This is in addition to any required manufacturer's logo, lot number, and material identification markings.

THIS IS AN AIR FORCE DESIGNATED CRITICAL SAFETY

ITEM (CSI).

ALL REQUESTS FOR WAIVERS OR DEVIATIONS MUST BE

FORWARDED TO THE DSC CONTRACTING OFFICER

FOR REVIEW AND APPROVAL.

ALL ITEMS OF SUPPLY SHALL BE MARKED IAW

MIL-STD-129. IN ADDITION, EACH UNIT PACK WILL

BE MARKED WITH LOT AND SERIAL NUMBER (IF AVAILABLE)<(>,<)>

CONTRACTOR'S CAGE CODE, ACTUAL MANUFACTURER'S

CAGE CODE AND PART NUMBER.

CRITICAL APPLICATION ITEM

SPS Technologies, LLC DBA 80539 P/N 703556

PARAMOUNT MACHINE COMPANY, INC. 2T575 P/N 703556

RTX CORPORATION 52661 P/N 703556

RTX CORPORATION 77445 P/N 463547

RTX CORPORATION 77445 P/N 703556

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 VIS-15

REVISION NR B DTD 08/16/1976

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA310

REVISION NR BG DTD 06/15/2012

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA360

REVISION NR U DTD 02/21/2013

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA-S-7452

REVISION NR A DTD

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA578

PAGE 6 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION B

SUPPLY/SERVICE: 5306-00-083-7025 CONT'D

REVISION NR F DTD 09/17/1996

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE QAP 13873 QAP-EQ003

REVISION NR D DTD 02/09/2023

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE QAP 77445 703556

REVISION NR DTD 01/25/1971

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 MPM

REVISION NR H DTD 05/20/1986

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA355

REVISION NR AC DTD 12/19/2012

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 MPS111

REVISION NR C DTD 11/12/1984

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 77445 PWA-S-2416

REVISION NR D DTD 11/03/2011

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE QAP 14153 QAP-CSI000837025

REVISION NR DTD 11/07/2019

PART PIECE NUMBER:

TDP Rev B Gen 2

IAW REFERENCE DRAWING NR 13873 EI-000837025

REVISION NR DTD 04/09/2026

PART PIECE NUMBER:

Critical Safety Item

DLA issues this document using the DoD authorized unit of issue, please refer to the following URL to determine the corresponding ANSI X12 unit of issue.

https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fwww.dla.mil%2FPortals%2F104%2FDocuments%2FDLMS% 2FeApplications%2FLogDataAdmin%2FUnit_of_Issue_and_Purchase_Unit.xlsx&wdOrigin=BROWSELINK

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT .

0001 5306-00-083-7025 814.000 EA $ ________________ $ ________________

ROD,TIE,FRT CPRSR

PRICING TERMS: Firm Fixed Price

QTY VARIANCE: PLUS 0% MINUS 0%

INSPECTION POINT: ORIGIN

ACCEPTANCE POINT: ORIGIN

FOB: ORIGIN DELIVERY DATE: 60 DAYS ADO

PREP FOR DELIVERY:

PKGING DATA - MIL-STD-2073-1E

QUP:001 PRES MTHD:33 CLNG/DRY:1 PRESV MAT:00

WRAP MAT:00 CUSH/DUNN MAT:NA CUSH/DUNN THKNESS:C

UNIT CONT:BE OPI:M

PAGE 7 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION B

SUPPLY/SERVICE: 5306-00-083-7025 CONT'D

INTRMDTE CONT:E5 INTRMDTE CONT QTY:AAA

PACK CODE:U

MARKING SHALL BE IN ACCORDANCE WITH MIL-STD-129.

SPECIAL MARKING CODE:00 -00 No special marking

PALLETIZATION SHALL BE IN ACCORDANCE WITH RP001: DLA PACKAGING

REQUIREMENTS FOR PROCUREMENT

PARCEL POST ADDRESS:

SW3211

DLA DISTRIBUTION DEPOT OKLAHOMA

3301 F AVE CEN REC BLDG 506 DR 22

TINKER AFB OK 73145-8000

US

FOR TRANSPORTATION SEE DLAD DLAD PROC NOTE C19. FOR FIRST DESTINATION TRANSPORTATION SEE DLAD PROC NOTE C20 AND

CONTRACT

FREIGHT SHIPPING ADDRESS:

SW3211

DLA DISTRIBUTION DEPOT OKLAHOMA

3301 F AVE CEN REC BLDG 506 DR 22

TINKER AFB OK 73145-8000

US

Government First Article Test Government First Article Test – The number of units shown signifies the test requirement. See FAR clause 52.209-4 for the actual quantity required to be tested.

DLA issues this document using the DoD authorized unit of issue, please refer to the following URL to determine the corresponding ANSI X12 unit of issue.

https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fwww.dla.mil%2FPortals%2F104%2FDocuments%2FDLMS% 2FeApplications%2FLogDataAdmin%2FUnit_of_Issue_and_Purchase_Unit.xlsx&wdOrigin=BROWSELINK

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT .

0002 0001 - S00000052 1.000 EA $ ________________ $ ________________

PRICING TERMS: Firm Fixed Price

FOB: DELIVERY DATE: 180 DAYS ADO

PREP FOR DELIVERY:

Not Applicable

GOVT USE

External External External Customer RDD/ ITEM PR PRLI PR PRLI Material Need Ship Date .

0001 7016226594 0001 N/A N/A N/A 03/10/2027

0002 N/A N/A N/A N/A N/A N/A

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 8 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION C - SPECIFICATIONS/SOW/SOO/ORD

C03 CONTRACTOR RETENTION OF SUPPLY CHAIN TRACEABILITY DOCUMENTATION (JUN 2023)

SECTION E - INSPECTION AND ACCEPTANCE

E08 FIRST ARTICLE TESTING REQUIREMENTS (MAR 2025)

(1) If there is not a separate contract line item number (CLIN) for FAT, the offeror shall include all costs and risk associated with completion of the FAT requirement in the production CLIN price.

(2) If there is a separate FAT CLIN, the offeror shall include all costs and risk associated with completion of the FAT requirement in the FAT CLIN price.

The unit of issue for the FAT CLIN, EACH, is equal to one First Article Test (1EA=1FAT). To receive payment for any costs associated with FAT, the offeror shall propose costs associated with FAT on a separate CLIN. The offeror shall base the production CLIN price solely on all costs associated with completion of the production units and shall exclude all FAT-related costs.

(3) The contracting officer will use the total award price in selecting the best value offer from among all eligible offerors. However, for an offeror to be eligible for award, the contracting officer must determine that the FAT CLIN price (unless FAT is waived) and the production CLIN price are fair and reasonable; and, if set-aside under FAR Part 19, a fair market price. The offeror shall not propose a FAT CLIN price that is materially unbalanced in relation to the production CLIN price. In the event an offeror receives a waiver of the FAT requirement, the contracting officer will deduct the FAT CLIN price for the waived source in determining the total award price.

(4)(a) Notwithstanding the conditions for waiving first article, the contracting officer may order an additional first article sample, or portion thereof, in writing if there is a --

(i) Major change to the technical data;

(ii) Lapse in production for a period in excess of 90 days; or

(iii) Change in the place of performance (manufacturing facility), manufacturing process,material used, drawing, specification or source of supply.

(b) When conditions in paragraphs (4)(a)(i), (ii), or (iii) occur, the contractor shall notify the contracting officer; who will determine whether to order an additional first article sample or portion thereof and provide instructions concerning the submission, inspection, and notification of results. The contractor shall bear the costs of the additional first article testing resulting from any of the causes in paragraphs (4)(a)(i)-(iii) instituted by the contractor and not due to changes directed by the Government.

(5) Waivers. The offeror may submit a request for FAT waiver to the contracting officer, who may waive the FAT requirement when all of the following criteria apply:

(a) The offeror requesting waiver has successfully manufactured, delivered and the government accepted the item or a similar item. The offeror shall provide the following information and be prepared to provide documentary evidence upon the contracting officer's request:

(i) Contract number(s), date(s), and issuing Government agency or agencies.

(ii) Description of item previously furnished, identified by part number, type, model number and/or other identifying information. If the item previously furnished is similar but not identical to the item being acquired under the current buy, the offeror shall explain why manufacture of the item previously furnished is sufficient to demonstrate its ability to manufacture the item being acquired under the current buy without need for a first article test.

(iii) Engineering control document/change number of item previously furnished.

(b) There have been no changes to manufacturing processes, tooling, or place of performance.

(c) There have been no changes to manufacturing data (e.g., drawing revisions that change materials, dimensions, processes, inspection or testing requirements; or subcontractors used to manufacture the items successfully in the past).

(d) The offeror shall supply an item of the same design and manufactured by the same method at the same facilities as the item or similar item previously furnished and accepted under subparagraph (5)(a).

(6) Contractor-Performed FAT.

(a) The contractor shall test the quantities as outlined in paragraph (a) of FAR clause 52.209-3 as specified in the contract. The contractor shall submit reports in accordance with paragraph (b) of FAR clause 52.209-3, as supplemented in this procurement note.

(b] For test report preparation and delivery of contractor FAT, the contractor shall --

(i) Use the data item description DI-NDTI-80809B report format.

(ii)] Mark the test report with the following: “First article test report - Contract number:[ ] and lot/item number: [ ].

(iii) Sign the FAT Report, accompanied by the system of record receiving report (i.e, WAWF or] DD Form 250) and contractor confirmation that the same process and facilities used to manufacture the first article units will be used to manufacture the production units, to the contracting officer at the applicable address shown below:

(A) For awards issued by DLA Aviation; or DLA Troop Support Clothing and Textile (C&T), Medical Materiel, or Subsistence, submit the report to the procuring activity in Block 6 of the DD Form 1155, Block 7 of Standard Form (SF) 33, Block 5 of SF 26, or Block 9 of SF 1449 award.

(B) For awards issued by DLA Land (SPE7L), submit the report to the following address:

DLA Land - FLSEB ATTN: FAT Monitor P. O. Box 3990 Columbus, OH 43218-399, or email to: Land.FAT.Monitor@dla.mil.

(C) For awards issued by DLA Maritime (SPE7M), submit the report to the following address:

DLA Maritime - FMSE ATTN: FAT Monitor P. O. Box 3990 Columbus, OH 43218-3990, or email to: maritime.fat.monitor@dla.mil.

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 9 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION E - INSPECTION AND ACCEPTANCE (CONTINUED)

(D) For awards issued by DLA Troop Support Construction and Equipment (SPE8E), email the report to Construction and Equipment FAT Monitor at trpsptcandefatmonitor@dla.mil. If report exceeds email limitations, submit the report to the following address:

DLA Troop Support ATTN: First Article Testing Monitor Building 3, 700 Robbins Avenue Philadelphia, Pennsylvania 19111.

Preferred electronic submissions: Hardware FAT Monitor at DLAHardwareFATMonitor@dla.mil.

(7) The contractor shall --

(a) Provide and maintain an inspection system acceptable to the Government in accordance with FAR Clause 52.246-2 or 52.246-3;

(b) Maintain and make available all records evidencing those details at the Government's request.

(c) At least fourteen (14) calendar days (or as otherwise specified in the contract) prior to shipment to the Government, provide written notice to the contracting officer and to the cognizant DCMA Functional Specialist when full administration or Quality Support administration is delegated to DCMA.

(8) Government-performed FAT. The contractor shall --

(a) For delivery of separately priced Government first article samples for Government performed FAT ship the units and system of record receiving report (i.

e., WAWF or DD Form 250) to the test facility specified in paragraph (a) of FAR clause 52.209-4.

(b) For delivery of Government first article samples that are not separately priced, ship the units with a commercial shipping document to the test facility.

(c) Prepare the shipping container(s) by marking the external packages in bold letters, “First Article Exhibits - Do Not Post to Stock," adjacent to the MIL- STD-129 (latest revision) identification markings.

(d) Use a hard copy of the system of record receiving report (i.e., WAWF DD Form 250), or commercial shipping document as a packing list, in accordance with DFARS Appendix F.

(e) Mark the exterior of the shipping container in accordance with MIL-STD-129 (latest revision), paragraph 5.11.

(f) In the interior package, include hard copies of the contract, test reports, material certifications/process operation sheets, drawings used to manufacture the units, and a pre-paid return label or shipping account for payment.

(g) Send units by traceable means (e.g., certified or registered mail, United Parcel Service, Federal Express).

(h) Send an email with subject titled “Notification of Test Exhibits [ DODAAC OF TESTING LAB ]” to the corresponding address in (i) or (ii) below and to the contracting officer specified in the contract. In the email, provide the shipment date, contract/purchase order number, National Stock Number, means of transportation, tracking number, and summary of container contents. Attach a copy of the system of record receiving report (i.e., WAWF or DD Form 250) documenting the Government has performed the contract quality assurance within the system or record.

(i) DLA Land & Maritime - DSCCProdVerif@dla.mil

(ii) DLA Aviation - DSCR.Test & EvaluationOffice@dla.mil

(9) At its discretion, the Government may return FAT units to the contractor at no cost to the Government. The contractor shall submit the return address and pre-paid return label or shipping account for payment.

(10) If the Government disapproves or conditionally approves Government-performed FAT units, the Government will take action in accordance with FAR 52.209-4.

E10 GOVERNMENT FIRST ARTICLE TEST (FAT) INFORMATION (JUL 2022)

(1) For FAT requirements, the Government will conduct inspection at source and acceptance at destination. The FOB point is destination. Due to known systems limitations, solicitations may contain erroneous inspection, acceptance, and FOB points. This procurement note takes precedence over any conflicting terms.

(2) GOVERNMENT FAT DELIVERY SCHEDULE

(a) 180 Days: To Deliver FAT Units to the Government

(b) 240 Days: Government FAT Evaluation and Notification to Contractor

(c) 142 Days: To Deliver Final Production Quantity After Approval of FAT. If PLT applies, this line will be blank; the number of delivery days for final production quantity will appear in procurement note E03, Production Lot Testing - Contractor, or E04, Production Lot Testing - Government, as applicable]

(d) 562 Total Delivery Days for FAT (Sum of Paragraphs (2)(a) through (2)(c)).

52.246-2 INSPECTION OF SUPPLIES FIXED PRICE (AUG 1996) FAR

52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014) FAR

As prescribed in 46.311, insert the following clause:

(a) The Contractor shall comply with the higher-level quality standard(s) listed below.

Title Number Date Tailoring

[Contracting Officer insert the title, number, date, and tailoring (if any) of the higher-level quality standards.]

(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in-

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require-

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 10 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION E - INSPECTION AND ACCEPTANCE (CONTINUED)

(i) Control of such things as design, work operations, in-process control, testing, and inspection; or

(ii) Attention to such factors as organization, planning, work instruction, documentation control, and advanced metrology.

(End of Clause)

52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984) FAR

SECTION F - DELIVERIES OR PERFORMANCE

52.242-17 GOVERNMENT DELAY OF WORK (APR 1984) FAR

52.247-60 GUARANTEED SHIPPING CHARACTERISTICS (JAN 2017) FAR

(a) The offeror is requested to complete paragraph (a)(1) of this clause, for each part or component which is packed or packaged separately. This information will be used to determine transportation costs for evaluation purposes. If the offeror does not furnish sufficient data in paragraph (a)(1) of this clause, to permit determination by the Government of the item shipping costs, evaluation will be based on the shipping characteristics submitted by the offeror whose offer produces the highest transportation costs or in the absence thereof, by the Contracting Officer's best estimate of the actual transportation costs. If the item shipping costs, based on the actual shipping characteristics, exceed the item shipping costs used for evaluation purposes, the Contractor agrees that the contract price shall be reduced by an amount equal to the difference between the transportation costs actually incurred, and the costs which would have been incurred if the evaluated shipping characteristics had been accurate.

(1) To be completed by the offeror:

(i) Type of container: Wood Box [ ] Fiber Box [ ], Barrel [ ], Reel [ ], Drum [ ], Other (Specify) ;

(ii) Shipping configuration: Knocked-down [ ], Set-up [ ], Nested [ ], Other (specify) ;

(iii) Size of container: ” (Length), × ” (Width), × ” (Height) = Cubic Ft;

(iv) Number of items per container each;

(v) Gross weight of container and contents Lbs;

(vi) Palletized/skidded [ ] Yes [ ] No;

(vii) Number of containers per pallet/skid ;

(viii) Weight of empty pallet bottom/skid and sides Lbs;

(ix) Size of pallet/skid and contents Lbs Cube ;

(x) Number of containers or pallets/skids per railcar *

(A) Size of railcar

(B) Type of railcar

(xi) Number of containers or pallets/skids per trailer *

(A) Size of trailer Ft

(B) Type of trailer

* Number of complete units (line item) to be shipped in carrier's equipment.

(2) To be completed by the Government after evaluation but before contract award:

(i) Rate used in evaluation ;

(ii) Tender/Tariff ;

(iii) Item .

(b) The guaranteed shipping characteristics requested in paragraph (a)(1) of this clause do not establish actual transportation requirements, which are specified elsewhere in this solicitation. The guaranteed shipping characteristics will be used only for the purpose of evaluating offers and establishing any liability of the successful offeror for increased transportation costs resulting from actual shipping characteristics which differ from those used for evaluation in accordance with paragraph (a) of this clause.

(End of clause)

SECTION G - CONTRACT ADMINISTRATION DATA

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (PRE-FILLED) (JAN 2023) DFARS As prescribed in 232.7004 (b), use the following clause:

(a) Definitions. As used in this clause - Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

Payment request and receiving report are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation System (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

https://www.acquisition.gov/dfars/part-232-contract-financing

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 11 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION G - CONTRACT ADMINISTRATION DATA (CONTINUED)

(c) WAWF access. To access WAWF, the Contractor shall -

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https:// wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items -

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

Invoice (stand-alone) and Receiving Report (stand-alone) or Invoice and Receiving Report (combination)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either “Invoice 2in1” or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table *

Field Name in WAWF Data to be entered in WAWF Guidance

Pay Official DoDAAC See Block 12 (SF26), 15 (DD 1155), or 18a

(SF1449)

(If blank, see resulting award)

Issue By DoDAAC See Block 5 (SF26), 6 (DD 1155), or 9 (SF1449)

(If blank, see resulting award)

Admin DoDAAC See Block 6 (SF26), 7 (DD 1155), or 16 (SF1449)

(If blank, see resulting award)

Inspect By DoDAAC SEE SECTION B (If blank, see resulting award)

Ship To Code SEE SECTION B (If blank, see resulting award)

Ship From Code SEE SECTION B (If blank, see resulting award)

Mark For Code SEE SECTION B (If blank, see resulting award)

Service Approver (DoDAAC)

(If blank, see resulting award)

Service Acceptor (DoDAAC)

(If blank, see resulting award)

Accept at Other DoDAAC (If blank, see resulting award)

LPO DoDAAC (If blank, see resulting award)

DCAA Auditor DoDAAC (If blank, see resulting award)

Other DoDAAC(s) (If blank, see resulting award)

(* Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert “See Schedule” or “Not applicable.”) https://www.sam.gov https://wawf.eb.mil/ https://wawf.eb.mil/ https://wawf.eb.mil/

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 12 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION G - CONTRACT ADMINISTRATION DATA (CONTINUED)

(** Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

See administer listed on page 1

(Contracting Officer: Insert applicable information or “Not applicable.”)

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H18 DEFENSE PRIORITIES AND ALLOCATIONS SYSTEM (DPAS) RATED AWARDS (FEB 2025)

H07 SUPPLY ASSURANCE THROUGH MULTISOURCE CONTRACTING (SEP 2017)

252.223-7001 HAZARD WARNING LABELS (DEC 1991) DFARS

(a) “Hazardous material,” as used in this clause, is defined in the Hazardous Material Identification and Material Safety Data clause of this contract.

(b) The Contractor shall label the item package (unit container) of any hazardous material to be delivered under this contract in accordance with the Hazard Communication Standard (29 CFR 1910.1200 et seq). The Standard requires that the hazard warning label conform to the requirements of the standard unless the material is otherwise subject to the labelling requirements of one of the following statutes:

(1) Federal Insecticide, Fungicide and Rodenticide Act;

(2) Federal Food, Drug and Cosmetics Act;

(3) Consumer Product Safety Act;

(4) Federal Hazardous Substances Act; or

(5) Federal Alcohol Administration Act.

(c) The Offeror shall list which hazardous material listed in the Hazardous Material Identification and Material Safety Data clause of this contract will be labelled in accordance with one of the Acts in paragraphs (b)(1) through (5) of this clause instead of the Hazard Communication Standard. Any hazardous material not listed will be interpreted to mean that a label is required in accordance with the Hazard Communication Standard.

MATERIAL

(If None, Insert “None.”) ACT

(d) The apparently successful Offeror agrees to submit, before award, a copy of the hazard warning label for all hazardous materials not listed in paragraph

(c) of this clause. The Offeror shall submit the label with the Material Safety Data Sheet being furnished under the Hazardous Material Identification and Material Safety Data clause of this contract.

(e) The Contractor shall also comply with MIL-STD-129, Marking for Shipment and Storage (including revisions adopted during the term of this contract).

SECTION I - CONTRACT CLAUSES

52.202-1 DEFINITIONS (JUN 2020) FAR

52.203-3 GRATUITIES (APR 1984) FAR

52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014) FAR

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020) FAR

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 13 OF 31 PAGES

SECTION I - CONTRACT CLAUSES (CONTINUED)

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT - ALTERNATE I (NOV 2021) FAR

52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020) FAR

52.203-8 CANCELLATION, RECISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) FAR

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) FAR

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020) FAR

52.203-18 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL CONFIDENTIALITY

AGREEMENTS OR STATEMENTS-REPRESENTATION (JAN 2017) FAR

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS (JAN 2017)

FAR

252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS (SEP 2011) DFARS

252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER DEFENSE-CONTRACT-RELATED FELONIES (JAN

2023) DFARS

252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (DEC 2022) DFARS

52.204-13 SYSTEM FOR AWARD MANAGEMENT -- MAINTENANCE (DEVIATION 2026-O0038) (FEB 2026) FAR

Standard Element ZA_204_13_I has no Title

52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (DEVIATION 2026-O0038) (FEB 2026) FAR

52.204-15 SERVICE CONTRACT REPORTING REQUIREMENTS FOR INDEFINITE-DELIVERY CONTRACTS (DEVIATION 2026-O0038)

(FEB 2026) FAR

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEVIATION 2026-O0038) (FEB

2026) FAR

252.204-7004 ANTITERRORISM AWARENESS TRAINING FOR CONTRACTORS (JAN 2023) DFARS

252.204-7014 LIMITATIONS ON THE USE OR DISCLOSURE OF INFORMATION BY LITIGATION SUPPORT CONTRACTORS (JAN

2023) DFARS

252.204-7015 NOTICE OF AUTHORIZED DISCLOSURE OF INFORMATION FOR LITIGATION SUPPORT (JAN 2023) DFARS

52.209-4 FIRST ARTICLE APPROVAL - GOVERNMENT TESTING (DEVIATION 2026-O0038) (FEB 2026) FAR As prescribed in 9.308-2 (a) and (b), insert the following clause:

[Contracting Officer inserts details]

(a) The Contractor shall deliver 3 unit(s) of Lot/Item 5306000837025 within 180 calendar days from the date of this contract to the Government at FY2303 TINKER ALC TINKER AFB DDOO-SOP(FIRST ARTICLE) ATTN: FIRST ARTICLE MONITOR BLDG 469 DOOR 12 7330 SENTRY BLVD TINKER AIR FORCE BASE OK 73145-8000 [insert name and address of the testing facility] for first article tests. The shipping documentation shall contain this contract number and the Lot/Item identification. This contract elsewhere specifies the characteristics that the first article must meet and the testing requirements.

(b) Within 240 calendar days after the Government receives the first article, the Contracting Officer will notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 14 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION I - CONTRACT CLAUSES (CONTINUED)

requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval will state any further action required of the Contractor. A notice of disapproval will cite reasons for the disapproval.

(c) If the Government disapproves the first article, the Contractor, upon Government request, shall submit an additional first article for testing. After each request, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall furnish any additional first article to the Government under the terms and conditions and within the time the Government specifies. The Government will act on this first article within the time limit specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article on time, or the Contracting Officer disapproves any first article, the Contractor will have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, the Contractor --

(1) May deliver the approved first article as a part of the contract quantity, provided it meets all contract requirements for acceptance and was not consumed or destroyed in testing; and

(2) Shall remove and dispose of any first article from the Government test facility at the Contractor's expense.

(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer will, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates, the contract price, or both, and any other contractual term affected by the delay.

(g) The Contractor is responsible for providing operating and maintenance instructions, spare parts support, and repair of the first article during any first article test.

(h) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(i) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the Offeror/Contractor and have been accepted by the Government. The Offeror/Contractor may request a waiver.

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, PROPOSED FOR DEBARMENT, OR VOLUNTARILY EXCLUDED (DEVIATION 2026-O0038) (FEB 2026) FAR

252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE GOVERNMENT OF A COUNTRY

THAT IS A STATE SPONSOR OF TERRORISM (MAY 2019) DFARS

52.211-5 MATERIAL REQUIREMENTS (DEVIATION 2026-O0038) (FEB 2026) FAR

52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (DEVIATION 2026-O0038) (FEB 2026) FAR

52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (DEVIATION 2026-O0038) (FEB 2026) FAR As prescribed in 19.101(a)(2)(iii)(A), insert the following clause:

(a) Definitions. As used in this clause -- Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern --

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 15 OF 31 PAGES

SPE4A6-27-Q-0035

SECTION I - CONTRACT CLAUSES (CONTINUED)

North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition --

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .