TAB_2-Performance_Work_Statememt.pdf

PDF 188 KB Posted

Attached to
F-16 Static Display Transport and Reassemble Federal contract opportunity
Solicitation number
SP4703-18-Q-0064
Issued by
Defense Logistics Agency Aviation

About this file

sow

View the file

Other files for this federal contract opportunity

Other files attached to F-16 Static Display Transport and Reassemble, newest first.
File Type Posted
Amendment_1.pdf PDF
TAB_25-SP4703-18-Q-0064_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

F-16 AIRCRAFT

RELOCATION

1.0 SCOPE

This SOW outlines the requirements for the transportation and reassembly of one F-16 Aircraft, Tail # 790342 for Static Display from Davis-Monthan Air Force Base, Tucson, AZ (FB2373) to DLA, Defense Supply Center-Richmond (DSCR), Richmond, VA 23297. .

2.0 TASK REQUIREMENTS

2.1 Transport and ship candidate aircraft IAW paragraphs 4.2 and 4.3 below.

2.2 Reassemble candidate aircraft at the shipping destination IAW paragraph 3.6.

3.0 REQUIREMENTS

3.1 Move and ship 1 each F-16 Aircraft Tail # 790342 Static Display per instructions listed in paragraphs 4.2 and 4.3 below.

3.2 Reassemble 1 each F-16 Aircraft Tail # 790342 Static Display to its original configuration at the shipping destination, Defense Supply Center-Richmond, 8000 Jefferson Davis Hwy, Richmond, VA 23297.

3.3 The Contractor/Supplier shall conduct a turnover of the F-16 Aircraft Tail # 790342 Static Display with the requiring activity upon completion of aircraft assembly to its original configuration.

3.4 The Contractor shall properly dispose all materials used for crating and shipping of the F16 Aircraft Static Display.

4.0 DELIVERABLES:

4.1 Supplier will provide DSCR Requisition and Inventory/Shipping Document Form (DD1149) prior to starting the project.

4.2 Ship item to DLA, Defense Supply Center-Richmond, 59C, 8000 Jefferson Davis Hwy, Richmond, VA 23297, Matt Maddux, at 804-279-3854, or Rogel Pagaduan, at 804- 279-1380.

ATTN: Matt Maddux

Defense Supply Center-Richmond 59C, 8000 Jefferson Davis Hwy, Richmond, VA 23297 DSN: 695-2385/ Commercial: 804-279-2385.

4.3 The F16 Aircraft Static Display is currently located at 309th Aerospace

Maintenance and Regeneration Group/MXDSP (AMARG), Davis-Monthan Air Force Base, Tucson, AZ (FB2373). The aircraft will be loaded onto the contractor supplied vehicle. The contractor shall secure the aircraft to the vehicle as necessary for safe travel to the destination. The contractor needs to coordinate with the POC the time and date when the contractor can arrive to pick up the air craft. The POC is Doug Maloney, Douglas.maloney@us.af.mil, 520-228-8019, DSN 228-8019

4.4 The Contractor/Supplier shall develop and provide a checklist detailing disassembled and assembled aircraft components. This checklist will be used during the turnover of F-16 Aircraft Static Display as stated in paragraph 3.3 above.

6.0 DEFENSE SUPPLY CENTER RICHMOND (DSCR) INSTALLATION

SECURITY REQUIREMENTS

CONTRACTOR ACCESS AND USE OF PREMISES

Security Requirements Defense Supply Center Richmond (DSCR):

No employee or representative of the Contractor will be admitted to the work site unless he/she furnishes satisfactory proof that he is a citizen of the United States or an alien who has been lawfully admitted for permanent residence, or who presents evidence from the Immigration and Naturalization Service that employment will not affect his immigration status. Personnel Information: All authorized non-military personnel utilizing the base are required to have in their possession at all times an installation visitor pass or access control badge. This pass is issued by the DSCR Welcome Center, located at Building

210. The Welcome Center is open Monday through Friday except federal holidays from 6:30 a.m. to 4:30 p.m. In order to obtain pass/badge, the Contracting Officer or designee will request personal identifiable information (PII) from each contractor and submit it to Security a minimum of 7 working days prior to start of work.

Official Capacity: The Contractor shall comply with visitor pass requirements for the performance of work at DSCR.

The DSCR Security Department will run a criminal history check on Contractor employees as a condition of employment. Official proof of identity or naturalization papers may be required, which will be returned once entered into the security computer system. Based on the results of the criminal history check, the Vetting Official (VO) will or will not grant entry to the installation based on guidance set forth by the Installation Commander.

If entry is denied, the Contractor will be immediately notified. DSCR Security may require updating or rechecking criminal history based on the duration of the contract.

NOTE: The VO will deny access to any person who the Installation commander has deemed unfit for unaccompanied access.

Proof of Identity: Official identification consists of any current Government issued picture identification. Examples- of official identification are valid state issued driver's license, military ID card, military dependent ID card, green card, etc. Expired identification is not valid.

Pass or Badge Management: Expired, invalid, inaccurate, inoperative or terminated Pass or Access Control Badge shall be returned to the Contracting Officer or his designee for disposition immediately after pass is no longer required or inoperative. These cards are the property of the U.S. Government and shall not be retained by the cardholder upon expiration, replacement, or when the DoD affiliation of the employee has been terminated. The Contract Officer or his designee shall deliver all returned contractor badges to Chief, Security Operations or designee at the Welcome Center within 5 business days after completion of contract. If the Pass or Access Control Badge is lost or stolen, a police report will be completed and the Contracting Officer or designee will submit a new request. Compliance with this requirement is mandatory and certification thereof to the Contracting Officer is required prior to submitting final invoices. Failure to return badges will hold up final payment to the Contractor.

Contractor Security Responsibilities: The contractor is responsible for employees and subcontractors under their employment. Contractors shall ensure that employees are familiar with and obey installation traffic, safety, and security regulations. Contractor employees, including subcontractors, are required to wear the ID card conspicuously on their outer clothing and above the waist at all times while working on this Center.

FOR OFFICIAL USE ONLY

Personnel are subject to challenge and removal from the work area if the ID card is not conspicuously visble. It is the Project Manager's responsibility to enforce this requirement. Failure to do shall be just cause for ordering that work on a contract be stopped.

Unofficial photography, cameras, or photographs are prohibited on DSCR property.

Contractors that would like to take photographs on DSCR must follow the camera policy.

Firearms, Weapons, Alcoholic Beverages, Illegal Drugs, and Contraband are prohibited on DSCR property. Violators may be prosecuted. State issued/authorized concealed weapons permits are not valid on Federal (DSCR) property. Trusted Traveler Program (TTP): Contractors are not authorized to use the TTP to escort individuals on to the installation.

7.0 TRUCK DELIVERIES ON DSCR

It is the contractor's responsibility to notify the Contracting Officer of truck deliveries and escort trucks from the truck gate to its destination. DLA Police will not do this. All commercial vehicles will enter the installation through the Commercial gate adjacent to the North Gate access control point (ACP). All commercial vehicles will also depart the installation via the North Gate. Commercial vehicles include, but are not limited to, semi-trucks, box trucks, passenger busses, cargo vans, dump trucks and walk-in vans.

All such vehicles entering the gate will be processed through an entrance security inspection point before continuing onto the Installation.

Vehicle Inspection: DLA police per the most current Police Standard Operating Procedure will conduct Commercial/large vehicle inspections on all vehicles. The inspection may be upgraded based upon Force Protection Conditions (FPCON).

Shipment Validation: All deliveries to DSCR will have some form of identifying documentation. For example, a bill of lading must identify: 1) a DSCR POC and 2) a delivery location. Validation will consist of reviewing the delivery documentation by DLA police officers as provided by the delivery truck driver. Failure to do so may result in delivery delay or denial of the delivery. The source of delivery will be identified and verified by DLA police officers.

Driver Vetting: DLA police officers will vet all delivery/commercial truck drivers prior to allowing entrance onto DSCR. Vetting will consist of conducting a background check of the driver and all passengers using Virginia Criminal Information Network (VCIN).

Any driver or passenger having an outstanding warrant will be handled in accordance with DLA/DSCR procedures. If the driver and/or passengers have personal weapons (firearms) or dangerous weapons, they will not be authorized entrance to the facility. If procedural requirements have not been met, the driver will not gain access.

Increased FPCON requires increased screening requirements. FPCON Charlie and Delta require the opening and visual inspection of each package.

8.0 SAFETY REQUIERMENTS

The Contractor shall comply with all applicable federal and state safety rules and regulations pertaining to this SOW including OSHA and US Army Corps of Engineering, Engineering Manual, EM 385-1-1.

Contractors shall notify the Project Manager and the DLA Richmond Safety Office immediately after an accident/incident results in damage to DLA property or equipment, injury or occupational illness to DLA personnel, or a fatality, loss of an eye, inpatient hospitalization, or amputation to any of the contractor's employees. A DLA Form 1591 or equivalent form will be submitted to the DLA Richmond Safety Office through the Project Manager.

A report on each job connected injury, property damage, or motor vehicle mishap will be written by the Contractor and submitted to the CO or his/her designated representative within 5 days following the event. The Contractor and CO or his/her designated representative will complete the Mishap Report (DLA Form 1591) per DSCR guidelines.

The estimated absence in days, if any, by employee due to injury and/or cost or property or vehicle damages shall be included.

9.0 PERMITS

The Contractor shall, without additional expense to the Government, obtain all appointments, licenses, and permits etc. required to perform under this contract.

Evidence of such permits and licenses shall be provided to the Contracting Officer and/or his designated representative when requested.

10.0 INVOICING AND PAYMENTS

The invoice shall be submitted no more than once a month. The invoice should include the specific performance standards performed and accepted, and associated performance payments being invoiced for the month. Invoices are to be sent directly to the Project Manager electronically at the address included in this SOW. Within seven days of the receipt of the invoice, the Project Manager will review for accuracy and payment will be certified in the WAWF system by the CO. The requirements of a proper invoice are subject to FAR 52.232‐25 - Prompt Payment. The vendor may check on the status of their invoice(s) by registering for My Invoice at https://myinvoice.csd.disa.mil/ or contacting DLA at (800) 756-4571.

The following correct information constitutes a proper invoice per the Prompt Payment Act standards, and/or is required documentation for payment requests submitted electronically into the Wide Area Work Flow (WAWF) System - Hard copy invoices cannot be accepted.

Contract number (including the order/call number where applicable), or other authorization for delivery of goods or services. Note: DO NOT USE THE BID OR SOLICITATION NUMBER. Invoice number, account number, and/or any other identifying number agreed to by contract. Shipment Number, including the date (where applicable). Same as Block

2 of the DD Form 250. (See “Shipment Number Construction and Usage”, page 13 for format).

Description: line item number, National Stock Number, Manufacture’s Part Number, unit of measure, quantity shipped, unit price, and extended amount, where applicable.

Shipping and payment terms (unless mutually agreed that this information is only required in the contract); including terms of any discount for prompt payment offered.

Electronic Funds Transfer (EFT) banking information, unless agency procedures provide otherwise, or except in situations where the EFT requirement is waived under 31 CFR 208.4.

Point of Contact (POC) name (where practicable), title and telephone number of person to notify in the event that the invoice is defective. Other substantiating documentation or information required. The contractor’s failure to include the necessary information will result in invoices being rejected.

Back up documentation (such as timesheets, receiving reports etc.) can be included and attached to the invoice in WAWF. Attachments created in any Microsoft Office product are attachable to the invoice in WAWF. Maximum size limit of each attachment is 2 Megabytes (MB). Total size limit for all files is 5MB. After clicking the “submit” button, a Notice of Successful/Unsuccessful Submission will appear. This screen contains a “Send More E‐Mail Notifications” button. Click on this button and add the email addresses for the Program Office and others as desired.

Notification shall be provided for each invoice submitted.

WAWF Tools and Help The vendor may have their CAGE code activated (required only first time) in WAWF by calling 866‐618‐5988. Once activated, the vendor should self‐register at the web site https://wawf.eb.mil.

Vendor training is available at: http://www.wawftraining.com. Additional support can be obtained by calling the DISA Ogden Help Desk at 1‐866‐618‐5988 or e‐mailing to cscassig@ogden.disa.mil.

WAWF Vendor “Quick Reference” Guides are located at:

https://acquisition.navy.mil/rda/home/acquisition_one_source/ebusiness/don_ebusiness_s olutions/wawf_overview/vendor_information.

11.0 PERIOD OF PERFORMACE

The contractor shall complete the transport and reassembly of the aircraft no later than 120 business days after the notice to proceed. Work hours on DSCR shall be between 7am-5pm Monday through Friday. No weekend or holiday work is permitted without advance written. In the event DSCR is closed for any other reason the contractor is not permitted to work.

approval from the Contracting Officer. In the event DSCR is closed for any other reason the contractor is not permitted to work.

12.0 ENVIRONMENTAL REQUIREMENTS

The contractor shall comply with all applicable federal, state, local, Defense Logistics Agency (DLA), and DSCR environmental laws, statutes, regulations, executive orders, permits.

Contractor shall immediately report any conflicts between applicable federal, state, local, DLA and DSCR, and any specifications within this contract to the Project Manager and the DLA Installation Operations at Richmond, Environmental Office (Environmental Office).

13.0 Quality Requirements

The Project Manager will inspect the F-16 Aircraft static display to ensure successful completion and adherence to the terms of the SOW. Contract payment will not be made until inspection and approval by the Project Manager.

14.0 CONTRACTOR MANPOWER LANGUAGE

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil.

POINTS OF CONTACT

CONTRACTING OFFICER

Primary: Allison Douglewicz Comm. Phone: (804) 279- 2915 Email: Allison.douglewicz@dla.mil DLA Contracting Services Office (Richmond) 8000 Jefferson Davis Highway Richmond, Virginia 23297-5441

CONTRACT SPECIALIST

Name: Kiara Leslie Comm. Phone: (804) 279- 6566 Email:Kiara.leslie@dla.mil DLA Contracting Services Office (Richmond)

Richmond, Virginia 23297-5441

PROJECT MANAGER

Michael OConnor Comm. Phone: (804) 279- 4799 Email: michael.oconnor@dla.mil DLA Installation Operations Richmond

Richmond, Virginia 23297-5000

ATTACHMENT 1

SAFETY AND HEALTH REQUIREMENTS

Contractors shall comply with all federal, state, and local occupational safety and health regulations, such as but not limited to US Department of Labor and Industry Occupational Safety and Health Administration (OSHA) , 29 CFR 1910,1926,1960 or whichever is applicable; in addition to safety requirements of US Army Corps of Engineers EM385-1-1 (latest edition), National Electric Codes (NEC), National Fire Codes (NFC), Defense Logistics Agency (DLA) safety regulations, or other safety requirements as established for the life of the contract. The safety provisions listed above are only general in nature and not intended to be all-inclusive.

1. VOLUNTARY PROTECTION PROGRAM (VPP)

The Defense Supply Center Richmond is an OSHA Voluntary Protection Program (VPP) site.

Contractors shall comply with all OSHA rules and regulations as applicable in addition to all other Local, State and Federal Occupational Safety and Health Regulations. The objective is for all contractors to be familiar with VPP and abide by the Defense Supply Center Richmond Safety Requirements.

DELIVERABLE

Contractors and subcontractors shall adhere to all safety and health regulations and be aware of The Defense Supply Center OSHA VPP initiative. Contractors and subcontractors shall read the Visitor & Contractor Safety at Defense Supply Center Richmond Brochure prior to performance of any on-site work. This is a one-time process but should be completed for all new contractors. Contractors shall acknowledge and document that all Contractor and subcontractor employees have read the Visitor & Contractor Safety at Defense Supply Center Richmond Brochure Contractors and subcontractors shall document receipt of a physical copy of the Visitor & Contractor Safety at Defense Supply Center Richmond Brochure by detaching the tear-off and leaving it with the COR, COTR or CO who, in return, will forward it to the Occupational Safety and Health Office (DS- FRES, building 80, 2nd Floor) before coming on site.

2. SAFETY PLAN DELIVERABLE

a. The Contractor shall submit a site specific Occupational Safety and Health Plan (OSHP) for approval within 10 days from the date of award for any on-site work for this SOW.

Failure to submit an OSHP will delay contracted activities. All site specific OSHP shall be developed to comply with all federal, state, and local occupational safety and health regulations, consensus standards, and any trade specific practices which will include but not limited to the following; Occupational Safety and Health Administration (OSHA)29 CFR General Industry - 1910, Construction Standards – 1926, Federal Employee – 1960; Army Corps of Engineers EM385-1-1 manual; National Electric Codes (NEC);

National Fire Protection Association (NFPA) Codes; American Conference of Industrial Hygienist (ACGIH); and must at a minimum, be strictly adhered to by all contracted personnel. The following are required and must be submitted to the safety office via the

PM;

b. Contractor safety plan, site specified activity hazard analysis, OSHA 300A, Safety Data Sheets and Contractor safety toolbox meetings.

c. An OSHP will be required for all contracted services involving the construction, alteration, and/or repair, including painting or decorating of government buildings, public works, and equipment in addition to all activities using/applying products requiring safety data sheets (formerly material safety data sheets (MSDS)). OSHPs will also be required for all activities were there are potential health hazards that could be a result of the contracted services (i.e. hazardous material surveys and clean up, confined space entry, etc.). All contractors who are subjected to the submittal of OSHP shall also submit their most recent OSHA 300 log in accordance with 29 CFR 1904.

d. An OSHP will not be required for non-personal services contracts including, but not limited to, those, which are administrative only, deliveries/pickups, transportation, or for nondestructive surveys. However, if contracted services specify a DSCR provided workspace the contractor should submit an OSHP or provide their COR and/or COTR with a letter stating that they will adopt and operate under DSCR's written occupational safety and health control programs. For all non-personal service contracts not requiring an OSHP, please adhere to the Visitor and Contractor Safety Brochure which can be obtained from the COR and/or COTR. Please contact the Occupational Safety and Health office at 804-279-4830 if you need assistance in determining if your contracted services apply to an OSHP submittal.

e. All Contracted services requiring an OSHP where operations involving demarcating work areas with protective coverings, shields, protective barriers, barricades, warning signs and the like, will be furnished and installed by the Contractor where a hazard or potential hazard exists. Notices shall be provided twenty-four (24) hours prior to the planned installation of protective barriers and barricades, the Contractor will coordinate with the COR and/or COTR for concurrence. Barricades and barriers will be removed by the Contractor at the completion of the work in the area.

3. ACCIDENT/INCIDENT

Contractors shall notify the Contracting Officer Representative (COR)/Project Manager and the DLA Richmond Safety Office immediately after an accident/incident results in damage to DLA property or equipment, injury or occupational illness to DLA personnel, or a fatality, loss of an eye, inpatient hospitalization, or amputation to any of the contractor's employees. A DLA Form 1591 or equivalent form will be submitted to the DLA Richmond Safety Office through the COR.

4. MISHAP REPORTING

A report on each job connected injury, property damage, or motor vehicle mishap will be written by the Contractor and submitted to the CO or his/her designated representative. The Contractor and CO or his/her designated representative will complete the Mishap Report (DLA

Form 1591) per DSCR guidelines. The estimated absence in days, if any, by employee due to injury and/or cost or property or vehicle damages shall be included.

5. SAFETY AND HEALTH VIOLATIONS

a. The Army Corps of Engineers Manual EM 385-1-1, Safety and Health Requirements

Manual, 29 CFR 1910/1926/1960, General Industry/Construction Standards/Federal Employee (OSHA), National Electric Code (NEC) and National Fire Protection Association (NFPA) Codes, American Conference of Industrial Hygienist (ACGIH) must, at a minimum, be strictly adhered to by all contractors. After consultation with the contracting officer, the Installation’s Safety and Health Manager reserves the right to contact the Virginia Occupational Safety and Health (VOSH) Office for assistance if there are frequent safety and health violations bycontractors.

b. DSCR Safety Specialists or Industrial Hygienists shall perform unannounced inspections of Contractor job sites to ensure compliance with applicable standards.

Violations shall be reported to the CO, or his/her authorized representative. The Safety Specialist or Industrial Hygienist reserves the right to stop operations when violations could cause severe injury, death, and/or serious property damage. The Safety Specialist or Industrial Hygienist reserves the right to stop any activitywhere DSCR employees are impacted. Frequent safety violations shall be reported to the Virginia Occupational Safety and Health (VOSH) Office.

c. The DSCR Safety and Health Manager or Staff shall be available to provide technical assistance as required and may be contacted by calling (804) 279-4830 from a cell phone or extension 4830 from a Government phone.

ATTACHMENT 2

ENVIRONMENTAL REQUIREMENTS

1. COMPLIANCE WITH ENVIRONMENTAL LAWS AND REGULATIONS Contractor shall comply with all applicable federal, state, local, Defense Logistics Agency (DLA), and Defense Supply Center Richmond (DSCR) environmental laws, statutes, regulations, executive orders, permits. Contractor shall immediately report any conflicts between applicable federal, state, local, DLA and DSCR, and any specifications within this contract to the Contracting Officer Representative (COR) and the DLA Installation Operations Richmond, Environmental Division.

2. COMPLIANCE WITH GREEN PROCUREMENT REQUIREMENTS

Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) for acquisition of building materials and products and select materials that have a long life cycle;

the least toxic materials; recyclable materials; materials that are resource- efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.

3. REPORTING NONCOMPLIANCE

Contractor shall immediately report any nonconformance and/or noncompliance with applicable federal, state, local, DLA and installation environmental regulations and laws to the COR and Environmental Division. Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action.

Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.

4. AWARENESS AND CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT

SYSTEM

DLA Installation Operations Richmond currently maintains an ISO 14001 registered Environmental Management System. This system is applicable to those individuals working on our behalf. The Environmental Policy Statement and our List of Significant Aspects are available from the Environmental Division. Contractor personnel shall be aware of their potential contribution to the success of this Environmental Management System and the potential implications of not performing within its requirements. Contractor personnel shall be competent to perform the work specified within the contract. Contractor personnel shall also take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of environmental contamination, or can negatively affect the natural and/or human environment.

5. PROTECTION OF WORK SITE RESOURCES

Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Contractor shall notify the Environmental Division if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless the Environmental Division has granted permission.

6. NOTIFICATION OF FEDERAL AND STATEREGULATORS

Contractor shall immediately notify the COR and Environmental Division of the arrival on site of any federal, state, and/or Department of Defense (DoD) environmental regulator or enforcement agent and/or the receipt of any correspondence from a federal, state and local environmental agency.

7. CULTURAL RESOURCES PROTECTION

a. This project has been identified as having the potential to affect a resource eligible for listing in the National Register of Historic Places.

b. In accordance with Section 106 of the National Historic Preservation Act, a Section

106 Review must be initiated to identify and assess any adverse effects that may result from this project. The contractor shall not begin fieldwork on the actual resource until the process is complete and documentation from the State Historic Preservation Office has been received stating either the project will not have an adverse effect on the historic resource or that any adverse effect has been mitigated. Administrative and planning efforts may proceed while the review process is occurring.

8. FEDERAL AND STATE LAND DISTURBING REQUIREMENTS

a. Any land disturbing activities with a footprint of greater than 5,000 square feet must satisfy Unified Facilities Criteria on Low Impact Development (UFC 3-210-10) requirements per Section 438 of the Energy Independence and Security Act as to maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow. These requirements do not apply to internal renovations, maintenance, or resurfacing of existing pavements.

b. Land disturbance projects greater than 10,000 square feet are subject to Virginia Erosion and Sediment Control Regulations per 9VAC25-840. An Erosion and Sediment Control Plan must be submitted to the Virginia Department of Environmental Quality for approval prior to the start of any qualify disturbance activities. Exempt activities include: the installation of individual service connections; installation, maintenance, or repair of any underground public utility lines when such activity occurs on existing hard surfaced road, street, or sidewalk, provided the disturbing activity is confined to the area of the road, street, or sidewalk that is hard surfaced; septic tank lines or drainage fields; installation of fence/sign posts, telephone/electric poles, and other kinds of posts/poles; and emergency work to protect life, limb, or property, and emergency repairs.

c. Land disturbance projects greater than 1 acre are subject to Virginia Stormwater Management Program Regulations per 9VAC25-870. Stormwater Pollution Prevention Plans and applicable fees must be submitted to the Virginia Department of Environmental Quality for approval prior to the start of disturbance activities upon issuance of VAR10 permit coverage. Routine maintenance that is performed to maintain the original line and grade, hydraulic capacity, or original construction is exempt from permit coverage.

Performance under this contract may require the contractor to obtain a Common Access Card (CAC). If CACs are issued under this contract, the contractor shall complete and comply with the following steps to obtain, control, and turn-in Government-issued CACs, as well as establish procedures to control and account for contractor CACs at all times. This process is only for the issuance and accountability of CACs. Contractors may be required to provide additional forms and follow additional procedures for other forms of access and/or background/security checks depending on local site/installation requirements.

1. The contractor has each contractor employee requiring a CAC complete and sign Sections I and II of the DD Form 1172-2. The instructions for completing the DD Form 1172-2 are located at http://www.cac.mil/docs/1172-2-Instructions.pdf.

o For Section II, Block 22 - If the contractor employee signs and the DD Form 1172-2 it is then forwarded by the contractor. This provides verification for the employee information. If the contractor is submitting a DD Form 1172-2 for him/herself (e.g., the owner), with no higher authority above them for verification, then the signature in Block 22 must be notarized to verify identity.

2. The contractor forwards the DD Form(s) 1172-2 via hand-carry, secure mail, or encrypted email to (NOTE: The contractor may forward these forms individually or as a group):

o The Contracting Officer’s Representative (COR) for the contract, if a COR was designated.

o The Contracting Officer (CO) for the contract, if no COR was designated.

3. Each contractor employee must verify his/her account information upon receipt of an email from the Government containing a username and password for the Trusted Associate Sponsorship System (TASS). The web link for TASS is included in the email.

4. Each contractor employee will receive an email via TASS when his/her account has been approved. The email will notify the employee to obtain a Government-issued CAC from the nearest Real-Time Automated Personnel Identification System (RAPIDS) office. The email will also provide a link that identifies the locations of RAPIDS offices.

5. Each contractor employee shall obtain his/her issued CAC from the RAPIDS office.

6. The contractor, within one (1) business day of issuance, provides written notice via email to the COR (or the CO, if no COR was designated) for each contractor CAC issued identifying the contractor employee’s name, the date of issuance, and the date of expiration of the CAC. This notification may be made individually for each contractor employee or together for a group of contractor employees.

7. The contractor establishes procedures to control and account for Government-issued contractor CACs at all times, to include the following:

ATTACHMENT 3

Common Access Card (CAC) Procedures o Ensure contractor CACs issued for this contract are only used for the purpose of performing under this contract.

o Ensure contractor CACs are secured in a manner that precludes unauthorized use and that recognizes the CAC is the property of the U.S. Government.

o Ensure contractor employees do not abuse or place holes in their CACs.

o Ensure contractor employees do not display their CACs in public.

8. If a contractor CAC is lost or stolen:

o The contractor employee shall immediately notify the contractor that the contractor CAC has been lost or stolen.

o The contractor shall immediately notify the COR (or the CO, if no COR was designated), detailing the circumstances regarding the lost or stolen contractor CAC, as follows:

In person, followed within one (1) business day by a written notice via email, or In writing, via email, or By telephone, followed within one (1) business day by a written notice via email.

o The contractor shall report the lost or stolen CAC card to the local DLA

Police/host installation police, who will provide the contractor a police report. If there is no local DLA Police/host installation police, or no police report is provided, the contractor shall provide information to the COR/CO, as applicable, detailing the circumstances of how the CAC was lost or stolen. The COR/CO will provide a memorandum for the contractor employee to support issuance of new CAC.

o The contractor has the contractor employee bring the report/memorandum to the nearest RAPIDS office. If the CAC can be reissued within 24 hours, bring the report/memorandum to the nearest CAC office for reissue. If the CAC cannot be reissued in 24 hours, follow the steps for a new CAC, beginning at Step 1.

9. If the expiration date for a contractor CAC is prior to completion of the contract and the contractor employee is to continue working under the contract and still requires a CAC, the contractor:

o Notifies the COR as follows:

In person, followed within one (1) business day by a written notice via email, or In writing, via email, or By telephone, followed within one (1) business day by a written notice via email.

o No less than two (2) weeks prior to the current CAC’s expiration date, completes and complies with the steps above beginning with Step 2 for issuance of a new contractor CAC for the employee.

o Brings the expiring CAC to the RAPIDS office for turn-in and receives new CAC.

o Notifies the COR once a new CAC has been issued.

10. The contractor/contractor employee turns in any found CACs immediately, via hand-carry, to the nearest Federal law enforcement office.

11. The contractor immediately collects all contractor CAC(s) from the contractor employee(s) at:

o Contract completion or termination o Termination/Reassignment of an employee (this includes any reason the employee is no longer working for the contractor under the contract or otherwise no longer requires a CAC)

12. The contractor:

o For contract completion or termination – within one (1) business day after collecting the contractor CAC(s), arranges for turn-in via one of the below methods:

i. If the COR/CO is co-located or near enough that in-person transfer of CACs can be arranged, the contractor:

Arranges to meet the COR (or the CO, if no COR was designated) to turn-in the collected contractor CAC(s).

Hand-carries all collected contractor CACs for turn-in to meet the COR (or the CO, if no COR was designated).

Completes and signs the Government-Issued Contractor CAC Turn-In Receipt with the COR (or the CO, if no COR was designated). The contractor is provided a copy of the receipt.

ii. If in-person transfer of CAC cannot be arranged, the contractor:

Sends, via certified mail, the CACs to the COR/CO. The contractor includes in the package the Government-Issued Contractor CAC Turn-In Receipt, with signed acknowledgement of contractor turn-in.

Notifies COR/CO that CACs have been sent via certified mail.

Receives a completed copy of the receipt from the COR/CO once the COR/CO has received the CACs.

o For termination/reassignment of an employee:

i. Immediately notifies the COR (or the CO, if no COR was designated) that the employee is no longer working for the contractor under the contract or otherwise no longer requires a CAC, as follows:

In person, followed within one (1) business day by a written notice via email, or

In writing, via email, or By telephone, followed within one (1) business day by a written notice via email.

ii. Follows the turn-in procedures above for contract completion or termination, as applicable.

Contractor Reporting Requirements: The contractor is required to submit, on a monthly basis, to the COR (or the CO, if no COR was designated) a report of all employees working on the contract who have been issued CAC cards and a verification of whether each listed employee still requires a CAC. The report must note where changes have occurred (additions or deletions) since the previous month. Contractor employees who already have a CAC related to another DLA or DoD contract must be included in the monthly report. Contractor shall note the issuing organization and the CAC expiration date. Contractor is still responsible for notifying the COR/CO when the individual is no longer working under the subject contract.

The above procedures have been established as a DLA security measure. Contractors are advised that failure to comply with any of the above requirements will be considered a violation of the terms and conditions of the contract and the Contracting Officer may take action to remedy such violations. Specifically, failure to safeguard, follow these procedures, including reporting requirements, or turn-in CACs within the established timeframes may result in the following actions, which are in addition to other actions the Contracting Officer may take under governing law and regulation and the terms and conditions of the contract:

Immediate work stoppage (issuance of a stop work order), not to be lifted until resolution of CAC issue

Disapproval of invoices and delay of payment Withholding of final payment (in accordance with FAR 52.204-9) Documentation of CAC Non-Compliance in the Contractor Performance Assessment

Reporting System (CPARS)

File details come from the government source that posted it.