About this file
This is Amendment 0001 to a solicitation for warehouse trailers issued by the Defense Logistics Agency Distribution for facilities in Corpus Christi, Texas. The amendment extends the quote submission deadline to 12:00 PM EST on May 1, 2026, and provides clarification on six vendor questions regarding trailer specifications and operational requirements.
Key specification clarifications include: powder coat finish is required and two-part epoxy is not acceptable; either a step-on floor lock or tongue-actuated brake is acceptable (one or the other, not both); front axle steer only is required, with quad steer steering explicitly not acceptable; the 36-inch fixed pipe end rack specification has been deleted; 6.00-9/10 ply pneumatic tires are not acceptable for the 20-inch diameter pneumatic tires due to operational concerns regarding cargo damage; and the trailers will not exceed towing speeds of 25 mph. The solicitation number is SP3300-26-Q-0123, issued by DLA Distribution in New Cumberland, Pennsylvania, with point of contact Tom Semones (thomas.semones@dla.mil). All other terms and conditions of the original solicitation remain in effect.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SP3300-26-Q-0123 - Amendment 0002.docx | DOCX document | |
| Attachment 2 - Specifications.xlsx | XLSX spreadsheet | |
| SP3300-26-Q-0123.pdf | ||
| Attachment 1 - Schedule of Supplies or Services and Prices.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP3300-26-Q-0123
Amendment 0001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
| PAGE |
| 1 of 2 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE NO. |
| 5. PROJECT NO. (If applicable) |
| 0001 |
| 4/28/2026 |
| 6. ISSUED BY |
| CODE |
| SP3300 |
| 7. ADMINISTERED BY (If other than Item 6) CODE |
DEFENSE LOGISTICS AGENCY
DLA DISTRIBUTION
430 MIFFLIN AVENUE, SUITE 3102A
NEW CUMBERLAND, PA 17070-5007
POC: Tom Semones, thomas.semones@dla.mil
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code)
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
SP3300-26-Q-0123
| CODE: |
| FACILITY CODE: |
| X |
| 10B. DATED (SEE ITEM 13) |
4/16/2026
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| A |
| THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A. |
| B |
| THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b). |
| C |
| THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF: |
| D |
| OTHER (Specify type of modification and authority. |
E. IMPORTANT: The Contractor is not, X is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE ATTACHED PAGES
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15a. NAME AND TITLE OF SIGNER (Type or print) |
| 16a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
BY_________________________________________
BY_________________________________________
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
1. The purpose of this amendment is to extend the due date for quotes and answer vendor questions
2. SP3300-26-Q-0123, Section One: Notice to Quoters, Paragraph 5. The closing date and time for quotes is extended to 12:00PM EST on May 1, 2026.
3. Answers to vendor’s questions are provided as follows:
Question 1. Is a 2 Part Epoxy finish an acceptable alternative to Electrostatic (Power Coat) finish? Color match is not an issue.
Answer 1. No, powder coat is required
Question 2. Do they need both the step on floor lock and the tongue actuated brake or is it one or the other?
Answer 2. One or the other, manufacturers equivalent
Question 3. Do these trailers require Front axle steer only (5th wheel steering) or double fifth wheel steer (Quad Steer Steering).
Answer 3. Front axle steer only, quad steer is NOT acceptable
Question 4. Is the "One approximately 36" tall fixed pipe end rack with crossbars" located on the front or rear of the trailer? Is it permanently attached or removable?
Answer 4. This specification is deleted
Question 5. Will 6.00-9/10 ply pneumatic tires be an acceptable option for the 20" diameter pneumatic tires?
Answer 5. No, these trailers are utilized indoor and outdoor and in unimproved (unpaved) lots, smaller tires create rougher rides and can make cargo shift and get damaged.
Question 6. Can you advise the speeds at which the trailers will be getting towed.
Answer 6. Not more than 25mph