SP3300-22-Q-5047 0002

Attachment 6

QUESTIONS & ANSWERS DOCUMENT

The following questions have been submitted from industry regarding solicitation SP3300-22-Q-5047. Each question has been redacted to ensure anonymity. The Government response is provided in the far right-hand column for each question.

#
Question
Government Response
1
Are there stairs involved? Elevator access? First floor? Stairs to enter building?
ADA compliant access, ramps, single story – no elevator.
2
Does this need to be GSA?
This procurement is solicited through Sam.gov and not GSA.
3
Concerning Item F2 (Wardrobe). the picture does not match the item number – please advise which takes precedence.
The Item Name description and size is correct. The item number is corrected to read C230200. (Reference revised Attachments 3 and 4)
4
How close can an 83’ tractor trailer get to the building? Delivery hours?
The access doors both approx. 50’ from where the truck could park (see attached plan with comments at doors). They are both 3’ doors.

Delivery hours would be regular working hours, 0700-1530. (Reference: Attachment 5 – restricted)

5
Do they need a design proposal along with pricing within the EXCEL sheet?
Quotes shall include technical and descriptive literature or other documents of the items being offered in sufficient detail to evaluate compliance with the minimum salient characteristics found in the schedule of supplies section.
6
Are we expected to match the National Business Furniture with items that are as close as possible?
Yes
7
Are the workstations to be electrified?
Contractors must review all contract documents to familiarize themselves with requirements. Dwg I-101, “Work Station (WS) Minimum Requirements-Isometric View “ and “Work Station (WS) Keyed Notes” details requirements. Specifically Items 5, 6, 9 12 & 13. There shall be 3 ea outlets per work station, internally wired as described. All of these wires shall be installed and provided to termination in the described power pole (characteristics as described), to include an excess whip length above the ceiling to allow final connections by the Government. Reference Attachment 2 – Drawing I-101(restricted)
8
Do you have the drawings for this RFQ? The furniture description is referencing another document.
The drawings for this acquisition are restricted – request for access shall be made through Sam.gov.
9
I am not seeing a layout or drawing attached to any of the attachments. I am specifically curious about the layout for the 5 workstations. Depending on this layout, workstations could share panels which would affect the price. Are you able to provide me with a layout?
Drawings are provided Reference Attachments 2 and 5. Drawings are restricted – Access shall be requested through Sam.gov.
10
Does this bid have to be through GSA pricing?
No - this RFQ shall follow the Instructions; Quotes must be submitted electronically via email at: david.gilson@dla.mil by the Due Date and time: 1200 EST 9/22/2022