This statement of work outlines requirements for the removal and disposal of sludge from the Defense Distribution Center in Susquehanna, Pennsylvania. The contractor shall remove up to 430,000 gallons of liquid sludge and 70 tons of solid sludge annually from the sewage treatment plant, and remove up to 24,000 gallons of liquid sludge and 13 tons of solid sludge from installation lift stations. The contractor must transport the sludge to a Pennsylvania DEP approved disposal facility, obtain samples from each load and provide analytical results to verify solids content, and submit all required documentation to the government point of contact within 14 days. The work must be performed between 6 AM and 1:30 PM Monday through Friday, in accordance with all applicable environmental, health and safety regulations.

View the file

Other files

File Type Posted
Amendment 0002 Attachment 3 Schedule of Services.xlsx XLSX spreadsheet
Amendment 0002_SP330022Q0089.pdf PDF
Attachment 5 DL1818.pdf PDF
Amendment 0001_SP330022Q0089.pdf PDF
Attachment 4 Analytical Results.pdf PDF
SP3300-22-Q-0089 CSS Amendment 0001.docx DOCX document
Attachment 2 US Department of Labor Wage Determination.pdf PDF
Attachment 1 Statement of Work.docx DOCX document
Attachment 3 Schedule of Services.xlsx XLSX spreadsheet
SP3300-22-Q-0089.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 1

STATEMENT OF WORK

FOR

SLUDGE REMOVAL FROM

DEFENSE DISTRIBUTION CENTER, SUSQUEHANNA

NEW CUMBERLAND, PA

DESCRIPTION/SPECS/WORK STATEMENT

1. The Contractor shall remove and dispose of up to 430,000 gallons of municipal non-hazardous liquid wastes (referred to as sludge in the remainder of the SOW) annually from the Defense Distribution Center, Susquehanna (Installation) Sewage Treatment Plant aerobic digester, SBR, and post aeration tank. The cost should include all labor, equipment, vehicles, transportation, and disposal necessary to complete CLIN X001

The Contractor shall remove and dispose of up to 70 tons of municipal non-hazardous solid wastes (referred to as sludge in the remainder of the SOW) annually from the Installation Sewage Treatment Plant aerobic digester, SBR, and post aeration tank, and from lift stations located throughout the Installation. The cost should include all labor, equipment, vehicles, transportation, and disposal necessary to complete CLIN X002.

The Contractor shall remove and dispose of up to 24,000 gallons of residual non-hazardous liquid wastes (referred to as sludge in the remainder of the SOW) annually from Installation lift stations. The cost should include all labor, equipment, vehicles, transportation, and disposal necessary to complete CLIN X003.

The Contractor shall remove and dispose of up to 13 tons of residual non-hazardous solid wastes (referred to as sludge in the remainder of the SOW) annually from Installation lift stations. The cost should include all labor, equipment, vehicles, transportation, and disposal necessary to complete CLIN X004.

The Contractor shall perform up to 10 confined space entries in accordance with regulatory and Installation requirements. New CLIN 0005 to modify the existing contract.

Contractor is responsible to ensure none of the maximum limitations outlined above (i.e. dispose of up to 100,000 gallons of non-hazardous liquid wastes) are exceeded during the year and to notify the Installation GOVERNMENT POC when limitations are within 20% of the maximum limitations outline above.

Contractor will transport waste to a DEP approved facility.

However, if the any of the maximum limits identified above are met and additional requirements for the same item will exist prior to the contract expiring, the contractor will complete the item at no increase in the unit cost identified in completed contract. For unforeseen circumstances such as large quantities of oil or filamentous bacteria, the contractor will provide a separate quote for sludge removal and wait for approval to remove the sludge.

2. All actions by the contractor or subcontractor shall comply with all United States Department of Labor Occupational Safety and Health Administration (OSHA), United States Environmental Protection Agency, Pennsylvania Department of Environmental Protection (DEP), York County and any other local laws and regulations governing the project. The prime contractor is responsible for overseeing all subcontractors utilized to complete the project.

3. While removing sludge from the plant, the Contractor will need to back into the site and position the truck on the road adjacent to the removal site. If removing sludge from the digester, connect to the offloading valve to remove sludge. If removing sludge from other areas of the plant, drag a house to the location to remove sludge. If removing sludge from lift stations position the truck on the road adjacent to the lift station and drag a hose to the lift station to remove sludge. After removing sludge from Installation, Contractor shall provide copies of all manifests, bills of lading, etc. signed by the final disposal facility for each load of sludge removed from the installation to the GOVERNMENT POC within 14 days of the removal date.

4. The contractor shall obtain a sample of sludge from each load of sludge taken offsite and deliver it to a laboratory certified to analyze the sample to determine the percent solids in each load. Contractor must ensure samples arrive at the certified laboratory to allow analysis before the hold-time expires.

5. The Contractor shall supply the Environmental Office with all information required by the United States Environmental Protection Agency, Pennsylvania Department of Environmental Protection (DEP), York County and any other local agencies within 14 days of the sludge removal including but not limited to:

a. Final signed copies of waste manifests, bills of lading, etc.

b. Total gallons of sludge removed.

c. Laboratory analytical results for the percent of solids in each load including quality assurance data.

d. Disposal site, county, and permit number.

e. Hauler permit number.

f. How the final sludge was used - Agricultural utilization, composting, landfill, or identify other.

The contractor shall attach all required documents identified in 5a and 5c to the request for payment in Wide Area WorkFlow (WAWF).

6. Arrival at the Installation to conduct operations must occur between the hours of 6:00 AM through 1:30 PM, Monday through Friday. In some cases, such as removal of sludge from the lift station in Building 2001, the removal will be conducted outside of the times listed above due to ongoing operations. Installation personnel will schedule these removal operations with the contractor. Sludge removal will not normally occur on Federal holidays or weekends.

7. The Defense Logistics Agency Installation Management Susquehanna Environmental Division or plant operators will notify the contractor and set up times for sludge removal. If the Contractor varies from his proposed schedule without informing the GOVERNMENT POC in advance, there is no guarantee that the Sewage Treatment Plant gates will be open, and the Contractor could experience a lengthy delay gaining access to the Sewage Treatment Plant. The Contractor shall provide the required information to the DLA Installation Management Susquehanna Environmental Division or plant operators prior to arrival at the installation for contractor representatives who will enter the Installation and need to obtain an Installation Pass. DLA Installation Management Susquehanna Environmental Division or plant operators will make proper arrangements for contractor entry to the Installation.

8. In accordance with the York County Solid Waste and Refuse Authority (Municipal Waste Collection and Transportation Licensing Rules and Regulations), all persons engaged in the collection or transportation of wastewater treatment sludge, whether generated or disposed of in the county, shall obtain a license issued by the authority. A VALID DECAL ISSUED BY THE COUNTY MUST BE DISPLAYED DURING COLLECTION AND TRANSPORTATION OF THE SLUDGE. Disposal of sewage treatment plant sludge shall be at a designated disposal site permitted by the Commonwealth of Pennsylvania. Failure to comply with these conditions shall result in revocation to collect or transport sewage sludge from the Installation.

9. The Contactor must state with his offer, the name, address, and telephone number of the permitted disposal/treatment facility (to include the permit number) that will receive the sewage sludge for final disposition. Contractor must also submit sub-contractors name, address, telephone number, and permit numbers with offer. If contractor wishes to make substitutions in disposal sites, haulers, or sub-contractors, during the duration of the contract, the GOVERNMENT POC must approve the substitution prior to use.

10. Confined space entry is required for some areas. Contractor will be responsible for all confined space operations including safety equipment and procedures. Contractor will follow all requirements identified by the OSHA and/or the DLA Installation Management Susquehanna Confined Space Entry Procedure manual or applicable document/procedure.

11. The Prime Contractor shall provide the haulers current certification/permits/licenses to transport sewage sludge. The Prime Contractor shall also be responsible for obtaining all necessary notarized documents from the haulers, if required. All transportation shall be in accordance with the Department of Transportation 49 CFR 100-199. The contractor shall comply with all local, state, and/or federal requirements including all necessary permits, licenses, and approvals.

12. The Environmental Office requests the option to review offerer submissions prior to the award of the sewage sludge contract to review the above-mentioned requirements.

13. The contractor shall perform all operations in accordance with all local, state, and federal environmental rules, regulations, and requirements

14. Installation will be responsible for testing the sewage sludge to determine if it is a hazardous waste in accordance with 40 Code of Federal Regulations 261. Any additional sampling will be the responsibility of the Contractor.

15. Contractor is responsible for obtaining any necessary certifications, licenses and permits, and for complying with any applicable local, state, and/or federal laws, codes, and regulations in connection with the prosecution of work without additional expense to the Government. This includes acquiring any required certifications, permits or registrations necessary to operate on the Installation.

16. Contractor shall perform all operations in a prudent, conscientious, safe, and professional manner. At a minimum, contractor's personnel and equipment shall comply with applicable local, state, and/or federal laws.

NOTE: It is the recommendation of the Pennsylvania Department of Environmental Protection (specifically the Sewage Treatment Plant Permit Inspector from PADEP) the sludge disposal contractor is located in the state of Pennsylvania in order to assure compliance with sludge removal regulations.