The file's text, extracted by GovTribe without its formatting.
BaseYear
| Attachment 3 - Schedule of Supplies/Services ; SP3300-18-Q-5040 | | | | |
| CLIN | DESCRIPTION | QTY | U/I | UNIT PRICE | TOTAL PRICE |
| Base Year: 09/19/2018 - 09/18/2019 | | | | |
| 0001 | Firm-Fixed-Price | | | | |
| Annual Calibration and Preventive Maintenance (PM) Service for Weigh Scales IAW Paragraph 1.0 in the Statement of Work. (Quantity: 76 units @ 1 calibration and inspection each per year.) | 76 | EA | $ - 0 | $ - 0 |
| 0002 | Firm-Fixed-Price | | | | |
| Contractor Manpower Reporting | 1 | YR | $ - 0 | $ - 0 |
| 0003 | Time | | | | |
| Hourly labor rate to perform equipment repairs in conjunction with Remedial Maintenance IAW Paragraph 2.0 in the Statement of Work. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 50 | HR | $ - 0 | $ - 0 |
| 0004 | Material | Ceiling Price |
| Replacement Parts for Equipment Repairs in conjunction with Remedial Maintenance. This is an estimated amount for replacement parts required for Remedial Maintenance of the Weigh Scales. Contractor will be reimbursed for the actual cost of replacement parts IAW Paragraph 4.0 in the Statement of Work. | $10,000 |
SOURCE SELECTION INFORMATION SEE FAR 2.101 & 3.104
| Total Ceiling Price - Base Year | $10,000.00 |
| Total Ceiling Price - Option Year 1 | $ 10,000.00 |
| Total Ceiling Price - Option Year 2 | $10,000.00 |
| Total Ceiling Price - Base + 2 Option Year Periods | $ 30,000.00 |
SOURCE SELECTION INFORMATION SEE FAR 2.101 & 3.104
Option Year 1
| Attachment 3 - Schedule of Supplies/Services ; SP3300-18-Q-5040 | | | | |
| CLIN | DESCRIPTION | QTY | U/I | UNIT PRICE | TOTAL PRICE |
| Option Year 1: 09/19/2019 - 09/18/2020 | | | | |
| 0001 | Firm-Fixed-Price | | | | |
| Annual Calibration and Preventive Maintenance (PM) Service for Weigh Scales IAW Paragraph 1.0 in the Statement of Work. (Quantity: 76 units @ 1 calibration and inspection each per year.) | 76 | EA | $ - 0 | $ - 0 |
| 0002 | Firm-Fixed-Price | | | | |
| Contractor Manpower Reporting | 1 | YR | $ - 0 | $ - 0 |
| 0003 | Time | | | | |
| Hourly labor rate to perform equipment repairs in conjunction with Remedial Maintenance IAW Paragraph 2.0 in the Statement of Work. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 50 | HR | $ - 0 | $ - 0 |
| 0004 | Material | Ceiling Price |
| Replacement Parts for Equipment Repairs in conjunction with Remedial Maintenance. This is an estimated amount for replacement parts required for Remedial Maintenance of the Weigh Scales. Contractor will be reimbursed for the actual cost of replacement parts IAW Paragraph 4.0 in the Statement of Work. | $10,000 |
SOURCE SELECTION INFORMATION SEE FAR 2.101 & 3.104
Option Year 2
| Attachment 3 - Schedule of Supplies/Services ; SP3300-18-Q-5040 | | | | |
| CLIN | DESCRIPTION | QTY | U/I | UNIT PRICE | TOTAL PRICE |
| Option Year 2: 09/19/2020 - 09/18/2021 | | | | |
| 0001 | Firm-Fixed-Price | | | | |
| Annual Calibration and Preventive Maintenance (PM) Service for Weigh Scales IAW Paragraph 1.0 in the Statement of Work. (Quantity: 76 units @ 1 calibration and inspection each per year.) | 76 | EA | $ - 0 | $ - 0 |
| 0002 | Firm-Fixed-Price | | | | |
| Contractor Manpower Reporting | 1 | YR | $ - 0 | $ - 0 |
| 0003 | Time | | | | |
| Hourly labor rate to perform equipment repairs in conjunction with Remedial Maintenance IAW Paragraph 2.0 in the Statement of Work. The number of hours shown is an estimate only. Contractor will be paid only for the actual number of hours worked. | 50 | HR | $ - 0 | $ - 0 |
| 0004 | Material | Ceiling Price |
| Replacement Parts for Equipment Repairs in conjunction with Remedial Maintenance. This is an estimated amount for replacement parts required for Remedial Maintenance of the Weigh Scales. Contractor will be reimbursed for the actual cost of replacement parts IAW Paragraph 4.0 in the Statement of Work. | $10,000 |
SOURCE SELECTION INFORMATION SEE FAR 2.101 & 3.104
SOURCE SELECTION INFORMATION SEE FAR 2.101 & 3.104