SP330018B00080001.pdf
PDF 86 KB Posted
- Solicitation number
- SP330018B0008
- Issued by
-
Defense Logistics Agency Distribution
About this file
Amendment 0001 Questions and Answers
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
4. REQUISITION/PURCHASE REQ. NO.
See Block 14
5. PROJECT NO. (If applicable)
P.2018.01170.001, .002
6. ISSUED BY CODE SP3300 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
SP330018B0008
X
2018 AUG 25
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
12. ACCOUNTING AND APPROPRIATION DATA (If required)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print)
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
(a) By completing Items 8 and 15, and returning
DLA DISTRIBUTION
ACQUISITION OPERATIONS (J7)
430 MIFFLIN AVENUE SUITE 3102A
NEW CUMBERLAND PA 17070-5008
15C. DATE SIGNED 16C. DATE SIGNED
D. OTHER (Specify type of modification and authority)
3. EFFECTIVE DATE
28 AUG 2018
See Attached Continuation Sheet(s).
(X)
CHECK ONE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 2 OF 3 PAGES
SP330018B0008 - 0001
CONTINUED ON NEXT PAGE
Amendment 0001 is hereby incorporated into Invitation For Bid SP3300-18-B-0008.Amendment 0001 is issued to answer vender questions. Please see below for questions and answers.
Question 1. Is it acceptable for one individual to serve as superintendent, QC, and SSHO (triple hat).
Answer 1. These specific positions are not required of this project. However an overall safety first approach is.
See Safety Plan as pre-construction submittal in attached Statement of Work. REV1 .
Question 2. Please confirm or clarify the quantity of twist timer controls needed.
Answer 2. 34 twist timers shall be installed (see revised SOW) For building 30 the Statement of Work states to provide 31 twist timer controls in building 30; however only 6 controls are shown. If the Dayton 5VD63 heaters (center gas heaters between the conveyor isles) require individual controls for a total of 23, then the total of controls needed is 29 controls. Shall the center gas heaters each receive a timer control, or should there be a control per location/row? Please clarify.
For building 57, the Statement of Work states to provide 30 twist timer controls; however only 19 twist timer controls are shown on the plans. Please clarify
Question 3. There are Big Ass Fans inline where the government indicates new gas heater placement in building 30.
Please advise on how the government intends to proceed with the placement of these heaters?
Answer 3. See revised drawing. Tube heaters shall be offset as shown and shall be tilted toward the work areas/ stations
Question 4. Please specify the type of roof for venting and patching purposes. Does the government have pictures of a typical roof?
Answer 4.
On Building 30 Sections 1-4, the following were installed:
1) The flutes on the metal roof was filled with EPS or polyiso flute fill insulation mechanically attached between the existing flutes to create flush substrate.
2)Then a 3/8” Securock roof board mechanically attached to existing standing seam metal roofing panels.
3)Then the 50 mil Duro-Last PVC roofing system mechanically attached.
On Building 57 Section 1:
1)Existing -- Steel deck, 5” od ISO insulation, ¾” fiber board, adhered PVC membrane to top of fiber board.
2)Overlaid on top of the existing: New – ¼” Securock mechanically attached, then 50 mil Duro-Last PVC roofing system, mechanically attached.
Question 5. Please confirm if weekend work will be required, and if so, to what extent.
Answer 5. Weekend work will be required for the installation portion that is directly over the UGR assembly lines in Building 30-2, and the overhead work on the shipping side (west end) and the north side of the conveyors in Building 30-1. The rest of the work can be managed during normal business hours if the contractor blocks off the overhead area according to the submitted schedule.
Question 6. Please provide a demand load for the two existing circuits in building 30, panel 1LC that are servicing existing heaters. If the new heater loads exceed the allowable ampacity of the existing breakers, how does the government want to proceed? A subpanel may be required.
Answer 6. There are three, 20A breakers in that panel. After the site visit, the government has decided to remove the existing radiant heaters to avoid any unknown power conflicts.
Question 7. In building 57, there are no spare circuits in panel RP1402. Please advise on the demand load of the existing heater loads. If the new heater loads exceed the allowable ampacity of the existing breakers, then how does the government want to proceed? Some workstations in the warehouse have been removed. It was suggested that the government may want to modify the scope of work to delete the placement of heaters where the workstations are no longer present.
Answer 7. Since the new heaters are on individual timer controls, the contractor shall assume sufficient capacity on existing breakers/circuits. The heaters will only draw current during start-up/ignition. Install as per existing drawing.
Question 8. Some workstations in the warehouse have been removed. It was suggested that the government may want to modify the scope of work to delete the placement of heaters where the workstations are no longer present.
Answer 8. Install as per existing drawing.
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 3 OF 3 PAGES
SP330018B0008 - 0001
SECTION J - LIST OF ATTACHMENTS
Header C1
List of Attachments
File Name Description ATTACH_3_revised_Drawi ngs Attachment 3 Radiant
Heaters B30 a ATTACH_2_revised_SOW Attahment 2 SOW Radiant
Heating Sy