Attachment_J.22 TE_4.5_Other_Equip_PM_Task_Codes.xlsx

XLSX spreadsheet 66 KB Posted

Attached to
Distribution and Warehouse Services - DLA Distribution Barstow, CA Federal contract opportunity
Solicitation number
SP3300-16-R-5003
Issued by
Defense Logistics Agency Distribution

About this file

Attachment J.22 - TE 4.5

View the file

Other files for this federal contract opportunity

Other files attached to Distribution and Warehouse Services - DLA Distribution Barstow, CA, newest first.
File Type Posted
Attachment_2_-_QA_Document_(11-21-16).pdf PDF
SP3300-16-R-5003_0005.pdf PDF
Attachment_1_-_Conformed_RFP_SP3300-16-R-5003_Sections_B-M_through_Amendment_0004.pdf PDF
Attachment_1_-_Revised_Attachment_J.24 TE_5_1_DDBC_Historical_Workload_DDBC_Tracked_Changes.pdf PDF
Attachment_3_-_Revised_Atch_J.32 _DDBC_Proposed_Productive_Hours.xlsx XLSX spreadsheet
Attachment_2_-_Revised_Attachment_J.25 TE_5.2__Projected_Workload_DDBC_Tracked_Changes_v4.pdf PDF
Attachment_4_-_QA_Document_(J.32_questions_only)_11-10-2016.pdf PDF
Attachment_3_-_Revised_Atch_J.32 _DDBC_Proposed_Productive_Hours.xlsx XLSX spreadsheet
SP3300-16-R-5003_0004.pdf PDF
Attachment_5_-_Revised_Attachment_J.16 _TE_3.2_Government_Training_Tracked_Changes.pdf PDF
Attachment_6_-_Revised_Attachment_J.17 TE_3.3_Government_Data_Systems_Tracked_Changes.pdf PDF
Attachment_2_-_Revised_Attachment_J.1_Section_C_-_PWS.pdf PDF
Attachment_1_-_Revised_RFP_SP3300-16-R-5003_Sections_B-M_Tracked_Changes.pdf PDF
Attachment_4_-_Revised_Attachment_J.6 GE_MHE_Changed.xlsx XLSX spreadsheet
Attachment_3_-_Revised_Attachment_J.2_Tracked_Changes.pdf PDF
Attachment_11_-_Revised_CDRL_A006_-Quality_Control_Plan.pdf PDF
SP3300-16-R-5003_0002_11-01-16.pdf PDF
SP3300-16-R-5003_0001_10-24-16.pdf PDF
Attachment_J.5 _CLIN_X006_Labor_Rate_Table.xlsx XLSX spreadsheet
Attachment_J.11 _Contract_Data_Requirements_List_CDRLs.pdf PDF
Attachment_J.33 _Proposed_Training_Hrs.xlsx XLSX spreadsheet
Attachment_J.24 TE_5_1_DDBC_Historical_Workload_for_final_RFP_9-21-16.docx DOCX document
Attachment_J.18 _TE_4.1_Contractor_Training_.docx DOCX document
Attachment_J.10 Past_Performance_Questionnaire.docx DOCX document
Attachment_J.12 TE_1.1__Contractor_Personnel_Security.docx DOCX document
Attachment_J.1 _Section_C_-_PWS.pdf PDF
Attachment_J.17 TE_3.3_Government_Data_Systems.doc DOC document
Attachment_J.16 _TE_3.2_Government_Training.docx DOCX document
Attachment_J.28 TE_5.5__Type_Physical_Inventory_Code_(TPIC)_Matrix.docx DOCX document
Attachment_J.13 TE_1.2_CAC_Procedures.docx DOCX document
Attachment_J.14 TE_2.1_Definitions _Acronyms_.doc DOC document
Attachment_J.23 TE_5.0_APLs_with_Retail.doc DOC document
RFP_SP3300-16-R-5003.pdf PDF
Attachment_J.29 TE_5.9_DSS_Load_and_Maintain_.docx DOCX document
Attachment_J.4 DD254_Barstow2016.pdf PDF
Attachment_J.25 TE_5.2__Projected_Workload_DDBC_for_final_RFP.docx DOCX document
Attachment_J.6 GE_MHE.xlsx XLSX spreadsheet
Attachment_J.32 _DDBC_Proposed_Productive_Hours_UPDATE.xlsx XLSX spreadsheet
Attachment_J.2 _PWS_Site_Specific.pdf PDF
Attachment_J.15 TE_3.1_GF-4.21.11.docx DOCX document
Attachment_J.30 _TE_6.1_Government_Forms.docx DOCX document
Attachment_J.20 TE_4.3_MHE_PM_Task_Codes.xlsx XLSX spreadsheet
Attachment_J.31 DDBC_Draft_Training_Calendar.xlsx XLSX spreadsheet
Attachment_J.27 TE_5.4_Transshipment_of_Hazardous_Assets.pdf PDF
Notice_Regarding_Restricted_Access.pdf PDF
DRAFT_RFP_Attachment_J.32 _DDBC_Proposed_Productive_Hours_UPDATE.xlsx XLSX spreadsheet
DRAFT_RFP_Section_B_Schedule.pdf PDF
DRAFT_RFP_Attachment_J.2_Section_C_-_PWS_Local.pdf PDF
DRAFT_RFP_Attachment_J.1_Section_C_-_PWS.pdf PDF
Pre-Proposal_Conference_Instructions.pdf PDF
Show all 50

Distribution and Warehouse Services - DLA Distribution Barstow, CA has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Other Equip PM Task Codes

DOCK Leveler - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
DOCK Leveler (EJON: BZ2002, BZ2003, BZ2004, BZ2005)Annual1008lube all grease zerks/oil all swivel points0.3
Annual2147check grating,frame & decking0.1
Annual3010complete operation check0.1
Annual3301safety inspection0.1
Annual4118make necessary adjustments0.3
Annual4407clean equipment0.3
LABELING Machine Packages - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
LABELING Machine Packages (EJON: YW2050)Annual1300service as needed2
LIFT Table - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
LIFT Table (EJON: BW5200,BW5201)Annual1003oil/grease as necessary0.4
Semi-Annual1300Service as needed2
Annual3301safety inspection0.1
PLATFORM Maint. Telescope - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
PLATFORM Maint. Telescope, Electric (EJON: PL0001, PL4488)90-Quarterly2244hydraulic system0.2
90-Quarterly3301safety inspection0.1
90-Quarterly4405battery,clean & service1.2
Annual1003oil/grease as necessary0.4
Annual2238brakes, check0.3
Annual3307clean,steam/vaccum0.8
Annual4002load test3
SCOOTER 3 or 4 Wheel Gas & Electric - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
SCOOTER 3 or 4 Wheel Gas (EJON: BA8530)Annual & Semi-annual1103Lubrication,chassis,etc.0.2
Annual & Semi-annual1112Check all fluid levels0.5
Annual & Semi-annual1132Tire pressure & condition0.2
Annual & Semi-annual2277Check & service air cleaner0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4416Battery service0.2
Annual1114Wheel bearing, steering1
Annual1121Engine oil & filter change0.5
Annual2271Tune engine0.5
Annual2272Check,clean,adjust,brakes0.5
Annual2272Brakes,ck,clean,adjust0.5
Annual4449Clean0.5
SCOOTER 3 or 4 Wheel Electric (EJON: BF1530, BF7225, BF2226, BF7227, BF7228, BF7229, BF1530, 0Y2963, BF4592, BF6070, BF6071)Semi-annual3301Safety inspection0.1
Semi-annual4038Clean equipment1
Semi-annual1110Check lights, tires & horn0.5
Semi-annual1120Wheel bearings, steering0.1
Semi-annual1125Lubrication chassis, etc.1.5
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual2003Check motor brushes0.5
Semi-annual2251Brakes, check, clean, adjust2
Semi-annual4403Battery, fluid, charge, clean0.8
Semi-annual4529Check chassis ground1.2
Semi-annual1036Check suspension, shocks, structure1
Semi-annual2279Check wheels1
SHRINK Wrap Machine - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
SHRINK Wrap Machine, Spiral (EJON: BX1507, BX3372, BX3373, BX3374, BX9810)Annual & Semi-annual1063Lube and adjust chain0.5
Annual & Semi-annual3010Complete operation check0.2
STRAPPER Dispensing - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
STRAPPER Dispensing (EJON: YX2026)Annual & Semi-annual2090Check burnt frayed wires0.2
Annual & Semi-annual3008Inspect for oil/hydraulic/air leaks0.1
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
SWEEPER Warehouse Riding - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
SWEEPER Warehouse Riding LPG (EJON: BC3375, BC3376)Quarterly1101Change engine oil & filter1
Quarterly4536Clean service batteries1.3
Quarterly1127Lubrication, chassis etc.0.8
Quarterly1105Check all belts0.3
Quarterly2205Check blow off radiator0.2
Quarterly2212Check hoses (LPG)0.5
Quarterly3308Clean, steam/vaccum1
Quarterly3314Clean hopper0.3
Quarterly3306Safety inspection0.5
Quarterly1110Check lights, tires & horn0.5
Quarterly1102Fluid levels, antifreeze0.2
WAREHOUSE Equipment, Miscellaneous - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Cooler - Portable Evaporative Air (EJON: BX5138, BX0114,BX0914, BX1278, BX1507, BX1671, BX1705, BX1724, BX2615, BX3363, BX3365, BX4315, BX5806, BX5808, BX5812, BX5902, BX6912, BX7012)Annual1017Grease/oil motors0.2
Annual1999Service-prevent deterioration1
Annual2076Check fan and motor0.1
Annual2077Check suction hoses0.1
Annual4010Clean equipment0.3
WOODWOKING Equipment - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
JOINTER Woodworking (EJON: BX2115)Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Band Woodworking (EJON: BX5251, BX0631)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Circular Rip Wood (EJON: BX0001, BX5248, BX5249)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Circular Tilt/table (EJON: BX5245, BX5246)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.4
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.4
SAW Circular Woodworking (EJON: BX5244, BX5247, BX5250, BX5299)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Radial Woodworking (EJON: BX5243)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SURFACER Woodworking (EJON: BX5252)Annual & Semi-annual1002Lube flange bearings0.1
Annual & Semi-annual2245Gear boxes0.1
Annual & Semi-annual3006Inspect for safety hazard0.1
Annual & Semi-annual4010Clean equipment0.3
Neighborhood Electric Vehicle (NEV) - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Neighborhood Electric Vehicle, (EJON: BA5348, BA7349)Semi-annual4403Battery, fluid, charge, clean0.8
Semi-annual2003Check motor brushes0.5
Semi-annual3301Safety inspection0.1
Semi-annual2251Brakes, check, clean, adjust2
Semi-annual2279Check wheels1
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual1125Lubrication chassis, etc.1.5
Semi-annual1036Check suspension, shocks, structure1
Semi-annual1110Check lights, tires & horn0.5
Semi-annual1120Wheel bearings, steering0.1
Semi-annual4038Clean equipment1
Semi-annual4529Check chassis ground1.2
Scooter Stand-up Solo 2 or 3 wheels, Electric - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Scooter, Stand-up, Solo, Electric (EJON: BA8316, BA8318, BA8319)Semi-annual1036Check suspension, shocks, structure1
Semi-annual4529Check chassis ground1.2
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual2279Check wheels1
Semi-annual2261Brakes, check, clean, adjust1
Semi-annual3301Safety inspection0.1
Semi-annual4038Clean equipment1
Semi-annual4404Battery service0.5
Semi-annual2003Check motor brushes0.5
Semi-annual1127Lubrication, chassis etc.0.8
Semi-annual1120Wheel bearings, steering0.1
Semi-annual1110Check lights, tires & horn0.5
Low Speed Vehicle - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Low Speed Vehicle, Electric (EJON: BA5350)Semi-annual4403Battery ,fluid, charge, clean0.8
Semi-annual3301safety check0.1
Semi-annual2251Brakes, check, clean adjust2
Semi-annual1125lubrication chassis, ect0.8
Winding Machine, Wire/Rope - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Winding Machine, Wire/Rope Electric (EJON: BR6488)Annual1140lubrication0.3
DUST Collector - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
DUST Collector Centralized (EJON: BX0226)semi-annual1113check chains and anchors0.5
semi-annual1123lubrication, chassis etc1.5
Front End Loader, Diesel - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Front End Loader, Diesel (EJON: BF5332)quarterly1101engine oil and filter, change0.3
quarterly1105fluid levels/antifreeze, check0.1
quarterly1106lubrication: chassis, etc0.3
quarterly2010hour meter, check0.2
quarterly2051hydraulic fluid & filter, change1
quarterly2062brakes, check & adjust1
quarterly2040belts, check/adjust0.2
quarterly2007brake lining, check0.3
quarterly3301safety inspection0.1
quarterly3303clean, steam/vacuum0.3
quarterly3341safety inspection0.5
quarterly1130trans filter, change0.3
quarterly1145lubricate parking brake0.1
quarterly2209fuel filter, change0.1
quarterly2037blades, check0.2
quarterly2219hydraulic oil filter, change0.2
quarterly2067engine tuneup, gas/diesel0.5
quarterly2066engine tuneup0.9
quarterly2284lights, check0.1
quarterly3070instruments & controls0.2
quarterly4406battery, check0.1
quarterly4408test run unit0.1
quarterly4501reflectors/lights0.5
quarterly1187lube unit0.2
quarterly1300service as needed2
quarterly3041inspect overall appearance0.1
Passenger Van, gasoline - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Passenger Van, gasoline (EJON/asset Number: 20149885)Semi-annual4541fuel filters2
Semi-annual1112ck all fluid levels0.5
Semi-annual1111ck hoses and fuel filter0.3
Semi-annual1132tire pressure0.1
Semi-annual2216check battery connectors0.1
Semi-annual4540change engine oil2

SP3300-16-R-5003

Attachment J.22 Technical Exhibit 4.5 Other Equip PM Task Codes

Dock Leveler

DOCK Leveler - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
DOCK Leveler (EJON: BZ2002, BZ2003, BZ2004, BZ2005)Annual1008lube all grease zerks/oil all swivel points0.3
Annual2147check grating,frame & decking0.1
Annual3010complete operation check0.1
Annual3301safety inspection0.1
Annual4118make necessary adjustments0.3
Annual4407clean equipment0.3

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

TE 4.4 Other Equip PM Task Codes &P of 1

Labeling Machine

LABELING Machine Packages - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
LABELING Machine Packages (EJON: YW2050)Annual1300service as needed2

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Lift Table

LIFT Table - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
LIFT Table (EJON: BW5200,BW5201)Annual1003oil/grease as necessary0.4
Semi-Annual1300Service as needed2
Annual3301safety inspection0.1

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Platform Maint Telescope

PLATFORM Maint. Telescope - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
PLATFORM Maint. Telescope, Electric (EJON: PL0001, PL4488)90-Quarterly2244hydraulic system0.2
90-Quarterly3301safety inspection0.1
90-Quarterly4405battery,clean & service1.2
Annual1003oil/grease as necessary0.4
Annual2238brakes, check0.3
Annual3307clean,steam/vaccum0.8
Annual4002load test3

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Scooter 3-4 whl Gas & Elect

SCOOTER 3 or 4 Wheel Gas & Electric - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
SCOOTER 3 or 4 Wheel Gas (EJON: BA8530)Annual & Semi-annual1103Lubrication,chassis,etc.0.2
Annual & Semi-annual1112Check all fluid levels0.5
Annual & Semi-annual1132Tire pressure & condition0.2
Annual & Semi-annual2277Check & service air cleaner0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4416Battery service0.2
Annual1114Wheel bearing, steering1
Annual1121Engine oil & filter change0.5
Annual2271Tune engine0.5
Annual2272Check,clean,adjust,brakes0.5
Annual2272Brakes,ck,clean,adjust0.5
Annual4449Clean0.5
SCOOTER 3 or 4 Wheel Electric (EJON: BF1530, BF7225, BF2226, BF7227, BF7228, BF7229, BF1530, 0Y2963, BF4592, BF6070, BF6071)Semi-annual3301Safety inspection0.1
Semi-annual4038Clean equipment1
Semi-annual1110Check lights, tires & horn0.5
Semi-annual1120Wheel bearings, steering0.1
Semi-annual1125Lubrication chassis, etc.1.5
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual2003Check motor brushes0.5
Semi-annual2251Brakes, check, clean, adjust2
Semi-annual4403Battery, fluid, charge, clean0.8
Semi-annual4529Check chassis ground1.2
Semi-annual1036Check suspension, shocks, structure1
Semi-annual2279Check wheels1

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Shrink Wrap Machine

SHRINK Wrap Machine - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
SHRINK Wrap Machine, Spiral (EJON: BX1507, BX3372, BX3373, BX3374, BX9810)Annual & Semi-annual1063Lube and adjust chain0.5
Annual & Semi-annual3010Complete operation check0.2

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Strapper

STRAPPER Dispensing - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
STRAPPER Dispensing (EJON: YX2026)Annual & Semi-annual2090Check burnt frayed wires0.2
Annual & Semi-annual3008Inspect for oil/hydraulic/air leaks0.1
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Sweeper Whse Riding

SWEEPER Warehouse Riding - PM Schedule
Required Preventive Maintenance based on the type of equipmentEst Hrs to Complete Each Type of PM Action
Equipment TypePM TypeTask CodePM Task Description
SWEEPER Warehouse Riding LPG (EJON: BC3375, BC3376)Quarterly1101Change engine oil & filter1
Quarterly4536Clean service batteries1.3
Quarterly1127Lubrication, chassis etc.0.8
Quarterly1105Check all belts0.3
Quarterly2205Check blow off radiator0.2
Quarterly2212Check hoses (LPG)0.5
Quarterly3308Clean, steam/vaccum1
Quarterly3314Clean hopper0.3
Quarterly3306Safety inspection0.5
Quarterly1110Check lights, tires & horn0.5
Quarterly1102Fluid levels, antifreeze0.2

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Warehouse Equip Misc.

WAREHOUSE Equipment, Miscellaneous - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Cooler - Portable Evaporative Air (EJON: BX5138, BX0114,BX0914, BX1278, BX1507, BX1671, BX1705, BX1724, BX2615, BX3363, BX3365, BX4315, BX5806, BX5808, BX5812, BX5902, BX6912, BX7012)Annual1017Grease/oil motors0.2
Annual1999Service-prevent deterioration1
Annual2076Check fan and motor0.1
Annual2077Check suction hoses0.1
Annual4010Clean equipment0.3

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Woodworking Equip

WOODWOKING Equipment - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
JOINTER Woodworking (EJON: BX2115)Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Band Woodworking (EJON: BX5251, BX0631)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Circular Rip Wood (EJON: BX0001, BX5248, BX5249)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Circular Tilt/table (EJON: BX5245, BX5246)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.4
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.4
SAW Circular Woodworking (EJON: BX5244, BX5247, BX5250, BX5299)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SAW Radial Woodworking (EJON: BX5243)Annual & Semi-annual1003Oil/grease as necessary0.4
Annual & Semi-annual3010Complete operation check0.2
Annual & Semi-annual3306Safety inspection0.2
Annual & Semi-annual4010Clean equipment0.3
SURFACER Woodworking (EJON: BX5252)Annual & Semi-annual1002Lube flange bearings0.1
Annual & Semi-annual2245Gear boxes0.1
Annual & Semi-annual3006Inspect for safety hazard0.1
Annual & Semi-annual4010Clean equipment0.3

Other Equip PM Task Codes SP3300-11-R-0011

&P of 2

NEV

Neighborhood Electric Vehicle (NEV) - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Neighborhood Electric Vehicle, (EJON: BA5348, BA7349)Semi-annual4403Battery, fluid, charge, clean0.8
Semi-annual2003Check motor brushes0.5
Semi-annual3301Safety inspection0.1
Semi-annual2251Brakes, check, clean, adjust2
Semi-annual2279Check wheels1
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual1125Lubrication chassis, etc.1.5
Semi-annual1036Check suspension, shocks, structure1
Semi-annual1110Check lights, tires & horn0.5
Semi-annual1120Wheel bearings, steering0.1
Semi-annual4038Clean equipment1
Semi-annual4529Check chassis ground1.2

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Scooter, Stand-up, Solo

Scooter Stand-up Solo 2 or 3 wheels, Electric - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Scooter, Stand-up, Solo, Electric (EJON: BA8316, BA8318, BA8319)Semi-annual1036Check suspension, shocks, structure1
Semi-annual4529Check chassis ground1.2
Semi-annual1999Check front hub levels check rear if needed3
Semi-annual2279Check wheels1
Semi-annual2261Brakes, check, clean, adjust1
Semi-annual3301Safety inspection0.1
Semi-annual4038Clean equipment1
Semi-annual4404Battery service0.5
Semi-annual2003Check motor brushes0.5
Semi-annual1127Lubrication, chassis etc.0.8
Semi-annual1120Wheel bearings, steering0.1
Semi-annual1110Check lights, tires & horn0.5

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Low Speed Vehicle

Low Speed Vehicle - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Low Speed Vehicle, Electric (EJON: BA5350)Semi-annual4403Battery ,fluid, charge, clean0.8
Semi-annual3301safety check0.1
Semi-annual2251Brakes, check, clean adjust2
Semi-annual1125lubrication chassis, ect0.8

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Winding Machine

Winding Machine, Wire/Rope - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Winding Machine, Wire/Rope Electric (EJON: BR6488)Annual1140lubrication0.3

Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Dust Collector

DUST Collector - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
DUST Collector Centralized (EJON: BX0226)semi-annual1113check chains and anchors0.5
semi-annual1123lubrication, chassis etc1.5

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Front End Loader

Front End Loader, Diesel - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Front End Loader, Diesel (EJON: BF5332)quarterly1101engine oil and filter, change0.3
quarterly1105fluid levels/antifreeze, check0.1
quarterly1106lubrication: chassis, etc0.3
quarterly2010hour meter, check0.2
quarterly2051hydraulic fluid & filter, change1
quarterly2062brakes, check & adjust1
quarterly2040belts, check/adjust0.2
quarterly2007brake lining, check0.3
quarterly3301safety inspection0.1
quarterly3303clean, steam/vacuum0.3
quarterly3341safety inspection0.5
quarterly1130trans filter, change0.3
quarterly1145lubricate parking brake0.1
quarterly2209fuel filter, change0.1
quarterly2037blades, check0.2
quarterly2219hydraulic oil filter, change0.2
quarterly2067engine tuneup, gas/diesel0.5
quarterly2066engine tuneup0.9
quarterly2284lights, check0.1
quarterly3070instruments & controls0.2
quarterly4406battery, check0.1
quarterly4408test run unit0.1
quarterly4501reflectors/lights0.5
quarterly1187lube unit0.2
quarterly1300service as needed2
quarterly3041inspect overall appearance0.1

Technical Exhibit 4.5 Other Equip PM Task Codes SP3300-11-R-0011

&P of 1

Passenger Van

Passenger Van, gasoline - PM Schedule
Required Preventive Maintenance based on the type of equipment
Equipment TypePM TypeTask CodePM Task DescriptionEst Hrs to Complete Each Type of PM Action
Passenger Van, gasoline (EJON/asset Number: 20149885)Semi-annual4541fuel filters2
Semi-annual1112ck all fluid levels0.5
Semi-annual1111ck hoses and fuel filter0.3
Semi-annual1132tire pressure0.1
Semi-annual2216check battery connectors0.1
Semi-annual4540change engine oil2