3652 SPECS COMBINED-Attachment F.pdf

PDF 616 KB Posted

Attached to
MISCELLANEOUS IMPROVEMENTS DOORS, CARPET, PAINTING AND CANOPY FOR DDSP
Solicitation number
SP3300-09-B-5008
Issued by

About this file

Attachment F of the Solicitation - Specifications for Project 3652 Building 81-Miscellaneous Improvements Doors Carpet Painting and Canopy

View the file

Other files

File Type Posted
AMD 0001 09B5008.pdf PDF
Site Visit Attendance.pdf PDF
Items Discussed 6-25-09.pdf PDF
Security Attachments - A - E.pdf PDF
Davis Bacon WD PA10 - Attachment H.txt TXT text file
Solicitation SP3300-09-B-5008.pdf PDF
3652 DRAWINGS COMBINED-Attachment G.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEFENSE LOGISTICS AGENCY

DEFENSE DISTRIBUTION DEPOT SUSQUEHANNA

PENNSYLVANIA

NEW CUMBERLAND, PA 17070-5002

SPECIFICATIONS

FOR

PROJECT NO. 3652 - BUILDING 81

DOORS, CARPET, PAINTING & CANOPY

FACILITIES ENGINEERING DIVISION

APRIL 2009

SP3300-09-B-5008 ATTACHMENT F

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01011 SPECIAL REQUIREMENTS Section 01140 WORK RESTRICTIONS Section 01320 PROJECT SCHEDULE Section 01330 SUBMITTAL PROCEDURES Section 01451 CONTRACTOR QUALITY CONTROL Section 01525 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS Section 01780 PROJECT CLOSEOUT

DIVISION 08 – DOORS AND WINDOWS

Section 08210 WOOD DOORS Section 08710 DOOR HARDWARE Section 08800 GLAZING

DIVISION 09 – FINISHES

Section 09680 CARPET Section 09900 PAINT AND COATINGS

DIVISION 12 – FURNISHINGS

Section 12930 SITE FURNISHINGS

SECTION 01011 Page 1

SECTION 01011

SPECIAL REQUIREMENTS

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The project consists of performing work, but not limited to, as summarized below. Provide the necessary material and labor as required by the drawings and specifications for the following tasks:

1. Install wood full glass double doors on existing hollow metal frames with hardware where indicated on the drawings.

2. Remove two 6 raised panel wood doors and hardware, hardware to be salvaged. Install two new wood full glass doors and reinstall existing hardware.

3. Remove sheet carpet to the extents shown on the drawings and install new 24 inch square carpet tile.

4. Paint existing painted gypsum board walls, hollow metal frames and metal railing only where indicated on the drawings.

5. Provide and install canopy at South end of the Building.

1.1.2 Location

The work shall be located at the Defense Distribution Depot Susquehanna, New Cumberland, Pennsylvania, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2 SUBMITTALS

Government approval is required for the submittals with a "G" designation;

submittals without a "G" designation are for information only. The following shall be submitted in accordance with Section 01330 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Schedule of Values

List of Recycled Materials to be used on the project

SD-11 Closeout Submittals

Dollar Value and Content of Recycled Materials

1.3 EXISTING WORK

In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND FACILITIES

Scan the construction site with electromagnetic or sonic equipment and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered using scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 3 working days prior to starting excavation work. Contact PA One Call 1-800-242-1776 three working days prior to excavating. Contractor is responsible for marking all utilities not marked by the utility owners.

1.5 GOVERNMENT-FURNISHED EQUIPMENT/MATERIALS

The Contractor, with his own forces, shall transport all Government-furnished equipment/materials described in the Task Order. The equipment/materials will be transported from the Government storage area to the work site indicated on the Task Order.

1.6 ENVIRONMENTAL PROTECTION

1.6.1 Solid, Liquid and Gaseous Contaminants

The Contractor shall be responsible for the proper disposal of all solid, liquid and gaseous contaminants in accordance with all local codes and regulations, together with the following requirements:

a. Discharge gaseous contaminants so that they will be sufficiently diluted with fresh air to reduce the toxicity to an acceptable level.

b. Liquid contaminants may, subject to local utility standards, be diluted with water to a level of quality acceptable in the local sewer system, or shall be disposed of in approved vessels at approved sites.

1.6.2 Disposal of Refuse

Refuse shall be disposed of off site and in accordance with local, state and federal regulations.

1.6.3 Covered Chutes

All chutes for refuse, and the like, shall be covered or of such a design to fully confine the material to prevent the dissemination of dust.

SECTION 01011 Page 2

1.7 CONSTRUCTION SITE MAINTENANCE

All supplies and equipment on the project site shall be stored so as to preclude mechanical and climatic damage. The project site shall be maintained in a neat and orderly manner.

1.8 NOISE CONTROL

The Contractor shall comply with all applicable state and local laws, ordinances and regulations relative to noise control.

1.9 SECURITY

The Contractor shall provide adequate protection for all parts of the building wherever work under this contract is performed.

1.9.1 Cameras

Possession or use of cameras on Government property is forbidden without prior written approval by the Security Officer or his designated representative. Requests for possession and/or use of cameras on Government property shall be in writing to the Security Office via the Contracting Officer and contain sufficient information to provide requirements for the use of photographic equipment.

1.10 EQUIPMENT ON THE PROJECT SITE

The Contractor shall cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss. The Contractor shall store equipment that is removed in performance of work where directed or reuse in work as required by drawings and specifications.

Equipment temporarily removed shall be protected, cleaned and replaced equal to its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.

1.10.1 Equipment History

a. If any equipment is to be furnished by the Contractor under the contract, the Contractor shall be required to furnish the necessary information on all equipment installed such as compressors, boiler, air conditioners, doors, elevators, fans, fuel and solvent dispensers, heaters, generators, kitchen equipment, drinking fountains, motors, emergency lighting, pumps, refrigerators, sprinklers/fire alarm systems, fire hydrants, dehumidifying units, valves, water heaters, transformers or whatever may apply under the contract. The following information on each piece of equipment shall be required on equipment history forms furnished under this contract:

(i) Building number

(ii) Manufacture number

(iii) Year of manufacture

(iv) Manufacturer model number

(v) Description of equipment

(vi) Serial number

(vii) Location in building

SECTION 01011 Page 3

(viii) Size

(ix) Unit of measure

(x) Date installed

(xi) Cost

(xii) Warranty information

b. Copies of these forms will be available from the Contracting Officer's Representative. In addition to furnishing information on the equipment installed, the Contractor shall be entirely responsible for painting a four character identification number on each piece of equipment installed. The identification numbers shall be obtained from the COR and painted on the equipment as directed.

Color of paint for identification numbers shall be selected by the COR. Identification numbers must be applied using stencils and free from smudges. The identification letters will vary dependent upon the piece of equipment being marked. Generally, two inch height for the characters will be sufficient. The Government reserves the right to withhold payment until equipment history forms are received and identification numbers are painted on all new equipment.

1.11 TRUCKING

The Contractor shall load all trucks leaving the site with loose debris in a manner that will prevent dropping of materials on streets. The Contractor shall fasten suitable tarpaulins over the load before they enter surrounding streets.

1.12 TOILET FACILITIES

Contractor shall provide a temporary toilet facility for his personnel.

Verify location with Contracting Officer or his designated representative.

1.13 ELEVATORS

Any temporary use of an existing elevator shall be by arrangement with the COR and subject to his controls. Such use will be of an intermittent nature.

The Contractor shall provide and maintain suitable and adequate protection covering for the elevator machinery, the hatchway entrance, and the interior of the elevator during the period of temporary use. Loads in excess of the rated capacity of the elevator will not be permitted. The Government will bear the cost of the electrical current for the operation of the elevator.

On completion of the work, the Contractor shall remove the protection coverings together with any resultant dirt and debris, and leave the equipment in a condition equal to that in which he found it.

1.14 SAFETY AND HEALTH

1.14.1 General

a. Applicable Publications: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

b. Code of Federal Regulations (CFR)

OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206; OSHA Construction Industry Standards (29 CFR

SECTION 01011 Page 4

1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety and health. It is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402.

National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61).

Federal Standard (Fed Std): Material Safety Data Sheets 313A

Safety and Health Requirements Manual. EM 385-1-1

Use of Asbestos Containing Material. ETL 1110-1-118

Policy and Guidelines for Asbestos Management. DA Circular 40-834

1.14.2 Work Covered by This Section

This section is applicable to all work covered by this contract.

1.14.3 Definition of Hazardous Materials

Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910; and to others as additionally defined in Fed Std 313.

Those most commonly encountered include asbestos, polychlorinated biphenyls (PCBs), explosives, and radioactive material, but may include others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, and pipe covering.

1.14.4 Asbestos

a. THE CONTRACTOR IS WARNED THAT EXPOSURE TO AIRBORNE ASBESTOS HAS BEEN

ASSOCIATED WITH FOUR DISEASES: LUNG CANCER, CERTAIN GASTROINTESTINAL

CANCERS, PLEURAL OR PERITONEAL MESOTHELIOMA AND ASBESTOSIS. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke, and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.

b. The Contractor is advised that friable and/or nonfriable asbestos-containing material may be encountered in area(s) where contract work is to be performed. Friable asbestos-containing material means any material that contains more than one percent asbestos by weight that hand pressure can crumble, pulverize or reduce to powder when dry. Nonfriable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturant, impregnant or coating. Nonfriable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end use.

However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities.

c. Care must be taken to avoid releasing, or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA)

SECTION 01011 Page 5 has set standards at 29 CFR 1910.1001 for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures and others measures must be taken when working with or around asbestos-containing materials. 29 CFR 1910.1001 has been identified as applicable to construction (29 CFR 1926.55 gases, vapors, fumes, dusts and mists). The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.140-156 for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.

d. Friable asbestos containing materials are not permitted by current criteria and shall not be used in new construction or modification projects (ETL 1110-1-118, 27 MAY 1983). Plans and specifications for all new construction and modification projects will be reviewed to insure that the use of friable asbestos-containing materials is not called for.

e. Maintenance, modification or demolition activities where exposure to asbestos dust may occur from previously installed friable or nonfriable asbestos-containing material will be identified. All precautions, to include proper work practices, medical surveillance, respiratory protection, industrial hygiene and environmental protection requirements of OSHA (29 CFR 1910.1001), EPA (40 CFR 61.140-156) and DA Circular 40-83-4, as applicable, shall be strictly adhered to.

1.14.5 Safety Assurance

a. Preconstruction Safety Meeting: Representatives of the Contractor shall meet with the Contracting Officer and his representative(s) prior to the start of repair, alteration or construction activities for the purpose of reviewing the Contractor's safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under the contract.

The Contractor shall be prepared to discuss, in detail, the measures he intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract. This meeting may be held in conjunction with the preconstruction conference, if so directed by the Contracting Officer. The conduct of the meeting is not contingent upon a general preconstruction meeting. The level of detail for the safety meeting is dependent upon the nature of the work and the potential inherent hazards. The Contractor's principal on-site representative(s), the general superintendent and his safety representative(s) shall attend this meeting.

b. Compliance With Regulations: All work, including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1926/1910. Work involving the disturbance or dismantling of asbestos or asbestos containing materials; the demolition of structures containing asbestos; and/or the disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subparts A and B, ETL 1110-1-118 and DA Circular 40-83-4. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.

SECTION 01011 Page 6

c. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work, and shall hold the Government harmless for any action on his part or that of his employees or subcontractors, which results in illness, injury or death.

d. Inspections, Tests and Reports: The required inspections, tests and reports made by the Contractor, subcontractors, specially trained technicians, equipment manufacturers, and others as required, shall be at the Contractor's expense for line items used during the contract.

(1) Materials and Equipment: Special features, devices, equipment, clothing and similar items used by the Contractor in the execution of work shall comply with the applicable regulations.

(2) Hazardous Materials: The Contractor shall bring to the attention of the Contracting Officer any material suspected of being hazardous which he encounters during execution of the work. A determination will be made by the Contracting Officer as to whether the Contractor shall perform tests to determine if the material is hazardous. If the Contracting Officer directs the Contractor to perform tests, and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required subject to equitable adjustment under the terms of the contract.

1.14.6 Recording and Preserving Historical and Archeological Finds

All items having an apparent historical or archeological interest which are discovered in the course of any construction activities shall be carefully preserved. The Contractor shall leave the archeological find undisturbed and shall immediately report the find to the Contracting Officer so that the proper authorities may be notified.

1.14.7 Contractor Staff

The Contractor shall be required to maintain a qualified Engineer staff and a dedicated Quality Control position to respond to requirements set forth in this solicitation. The Contractor will not be required to provide an onsite trailer for use as office space during the term of the contract.

1.14.8 Utilities (Work Related)

a. When available, water and electrical services may be used in this work at no cost to the Contractor. The Contractor shall make arrangements for such services with the Contracting Officer or his designated representative.

b. All temporary outages of any utility services required for the performance of work shall be scheduled with the Contracting Officer's Representative (COR) no less than 3 working days in advance of such outages unless otherwise specified in the Task Order.

SECTION 01011 Page 7

1.14.9 Standards of Conduct

All Defense Logistics Agency (DLA), Higher Headquarters and Depot regulations pertaining to conduct shall be adhered to by Contractor personnel. Good conduct and judgment is expected of all people entering the installations. Fighting, profane language, reckless driving or failure to respond to direct orders from any depot employee acting in an official capacity (i.e., Security Guards or Firemen) shall be sufficient reason to remove the disorderly individual from the Depot. A list of Depot rules and regulations will be provided to the Contractor during the preconstruction meeting by the Security Office representative.

1.14.10 Additional Requirements

Refer to Section 01525 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS.

1.15 SHOP DRAWING REQUIREMENTS

The Contractor will be required to bring all shop drawings to the preconstruction meeting. This meeting will be scheduled a few weeks after award to allow the Contractor time to assemble the shop drawings. Shop drawings not provided at the preconstruction meeting are to be identified in the project submittal schedule.

1.16 BUY RECYCLE PROGRAM

1.16.1 Mandated Requirements

The Contractor shall comply with Public Law 42 U.S.C. 6962, Resource Conservation and Recovery Act, 1994 Resource Conservation and Recovery Act (RCRA) and Presidential Executive Order 12873, Federal Acquisition Recycling, and Waste Prevention, 22 October 1993, relating to specific designated items in this contract for which recycle content standards have been established. Compliance with this program does not relieve the Contractor from meeting all other specification requirements.

1.16.2 Administrative Requirements

Where possible the contractor shall in performance of the daily activities associated with the contract assignment utilize products containing recycled components in the following categories:

a. Paper and Paper Products

b. Lubricating Oils Containing Re-refined Oil

c. Retread Tires

d. Transportation (traffic control) Products

e. Non-Paper Office Products

1.17 PAYMENTS AND SCHEDULE OF VALUES

1.17.1 Schedule of Values

The Contractor shall submit a schedule of values of the Work including quantities and unit prices, aggregating the Contract Price. This provision applies to lump sum contracts and to lump sum items in unit price contracts.

This schedule shall be satisfactory in form and substance to the Contracting Officer and shall subdivide the Work into component parts in sufficient

SECTION 01011 Page 8 detail to serve as the basis for progress payments during construction. Upon approval of the schedule of values by the Contracting Officer, it shall be incorporated into the form of application for payment furnished to the Contracting Officer. The schedule shall indicate the percent of work completed for each component during the payment period. No payments will be made until the schedule of values has been submitted and approved by the Contracting Officer.

1.17.2 Application for Payment

The date for presentation of monthly applications for progress payments to the Depot shall be established at the preconstruction conference and will govern all such applications unless modified by the Depot and the Contractor at least twenty days prior thereto.

1.18 CONSTRUCTION PROGRESS SCHEDULE

The Contractor shall prepare and submit a construction progress schedule in accordance with Section 01320, PROJECT SCHEDULE.

PART 2 PRODUCTS

2.1 BUY RECYCLED MATERIALS

The Contractor shall certify the products purchased under the terms of the contract meet the minimum recycle material standards for each item. The Contractor shall submit a list of the applicable materials to be procured with recycled material content for each delivery order assignment and submit with the preconstruction documents The materials in this contract that fall under this program are listed below.

1. Cement and Concrete Containing Fly Ash - Section 03300

2. Building Insulation Products - Sections 07212, 07214, 07220

3. Structural Fiberboard and Laminated Paper - Sections 09250, 09510, 09640, 09840

4. Plastic Pipe and Fittings - Sections 02620, 02621, 02721, 02722, 16050 (conduit)

5. Geotextiles and Related Products Sections 02270, 02373

6. Carpet - Section 09680

7. Floor Tiles and Patio Blocks - Section 09310

8. Shower and Restroom Dividers - Section 10153

9. Latex Paint - Section 09900

10. Playground Surfaces and Running Tracks (by individual assignment)

11. Park and Recreation Products (by individual assignment)

12. Landscaping Products - Sections 02100, 02480

13. Thermal Insulation for Mechanical Systems – Sections 02546 and

15080

Prior to application for final payment, the Contractor shall provide a report to the COR specifying the dollar value of items purchased that are manufactured with recycled content and the percentage of recycled content for each items.

PART 3 EXECUTION

Not used.

SECTION 01011 Page 9

-- End of Section --

SECTION 01011 Page 10

SECTION 01140

WORK RESTRICTIONS

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01330

SUBMITTAL PROCEDURES:

Completed Special Access Determination Form; G

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. The DDSP will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity.

b. Permission to interrupt any Activity roads and/or utility service shall be requested in writing a minimum of 7 calendar days prior to the desired date of interruption.

c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.3.2 Working Hours

Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer, normally Monday through Friday, 7:30 a.m. to 4:30 p.m., excluding Government holidays.

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 7 calendar days prior to such work to allow arrangements to

Section 01140 Page 1 be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.3.4 Occupied and Existing Building(s)

The Contractor shall be working in an existing building and around existing buildings which are occupied.

The existing buildings and their contents shall be kept secure at all times.

Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the work area during the construction period.

Relocate movable furniture away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location(s) upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.

The Government will remove and relocate other Government property in the areas of the building(s) scheduled to receive work.

1.3.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

d. Operation of Station Utilities: The Contractor shall be responsible for the operation of control devices in the DDSP utilities system, including water, sewer, electrical, and steam services. The Government will provide supervision and direct which control devices to operate. The Contractor shall not operate control devices except when the COR is present. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.

Section 01140 Page 2

1.4 SECURITY REQUIREMENTS

1.4.1 Personnel and Vehicle Security

1.4.1.1 Commercial Vehicles

Vehicle passes will be issued to each commercial vehicle that is required for the job, authorizing entry and parking within the DDSP. Every vehicle entering the DDSP will display the pass on the dashboard or visor (facing outward). The pass will be visible at all times while in the DDSP. Parking is limited to those areas that are specifically identified on the pass. If additional passes are required, present adequate justification to the Pass and ID Office via the Contracting Officer.

1.4.1.2 Parking

Do not park on or block the marked fire lanes or crane rail traveling zones (marked in yellow) at any time. An exception may be made for vehicles which are part of the equipment needed to do the required work.

1.4.1.3 Vehicle Searches

Vehicles are subject to search while entering, remaining in, or leaving the Depot.

1.4.1.4 Areas Not Covered by Contract

Contractor personnel will not be permitted to enter Depot buildings, spaces, and areas not covered by this contract except on prior approval of the Depot department/office/shop having jurisdiction of the areas. Coordinate action with the Contracting officer to obtain such entry approval.

Contractor employees will be allowed to use the following DDSP cafeterias during normal hours of operation:

a. Building 2001 EDC

b. Building 54-3

c. Building 300-Golf Club.

1.4.1.5 Identification Badges

Comply with the following:

a. Submit a Visit Request (VR) and Special Access Determination (SAD) for each person listed to the Security Officer via the Contracting Officer at least 1 week prior to the start date.

b. Employees and representatives requiring access are U.S. citizens or

U.S. Nationals.

c. Under no circumstances shall personnel hand carry their own visit request.

d. Employees shall provide documented proof of U.S. citizenship to the

Pass and ID Office prior to being issued a Depot badge.

Section 01140 Page 3

e. Employees shall be available for interviews upon request by the Depot Security Specialist.

f. Employees shall wear and display the Depot badge at all times while entering, remaining in, and exiting Depot spaces and each badge shall be used only by the specific individual named on the badge.

g. Maintain strict accountability over identification badges and passes issued by the Pass and ID Office. Return badges/passes to the Pass Office immediately upon termination of any employee, expiration, completion of contract, or when no longer required.

1.4.2 Photographs

Photography is prohibited on the Depot. When operationally required, submit a written request containing specific justification and details to the Security Officer via the COR.

--End of Section--

Section 01140 Page 4

SECTION 01320

PROJECT SCHEDULE

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Progress, Schedules, and Network

Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01330

SUBMITTAL PROCEDURES:

Construction Project Schedule; G

PART 2 PRODUCTS (NOT APPLICABLE)

3.1 GENERAL REQUIREMENTS

Pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS, a Project Schedule as described below shall be prepared. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.

SubContractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The approved Project Schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of all progress payments.

3.2 BASIS FOR PAYMENT

The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the Contracting Officer to evaluate Contractor's progress for the purposes of payment. Failure of the Contractor to provide all information, as specified below, shall result in the disapproval of the entire Project Schedule submission and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting

Section 01320 Page 1

Officer may hold retainage up to the maximum allowed by contract, each payment period, until revisions to the Project Schedule have been made.

3.3 PROJECT SCHEDULE

The computer software system utilized by the Contractor to produce the Project Schedule shall be capable of providing all requirements of this specification. Failure of the Contractor to meet the requirements of this specification shall result in the disapproval of the schedule. Manual methods used to produce any required information shall require approval by

3.3.1 Use of Critical Path Method

The Critical Path Method (CPM) of network calculation shall be used to generate the Project Schedule. The Contractor shall provide the Project Schedule in the Precedence Diagram Method (PDM).

3.3.2 Level of Detail Required

The Project Schedule shall include an appropriate level of detail. Failure to develop or update the Project Schedule or provide data to the Contracting Officer at the appropriate level of detail, as specified by the Contracting Officer, shall result in the disapproval of the schedule. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the Project Schedule:

3.3.2.1 Activity Durations

Contractor submissions shall follow the direction of the Contracting Officer regarding reasonable activity durations. Reasonable durations are those that allow the progress of activities to be accurately determined between payment periods.

3.3.2.2 Design and Permit Activities

Design and permitting activities, including necessary conferences and follow-up actions and design package submission dates, shall be integrated into the schedule.

3.3.2.3 Procurement Activities

Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 90 days. Examples of procurement process activities include, but are not limited to: submittals, approvals, procurement, fabrication, and delivery.

3.3.2.4 Critical Activities

The following activities shall be listed as separate line activities on the Contractor's project schedule:

a. Submission and approval of design drawings, calculations and specifications.

Section 01320 Page 2

b. Submission and approval of mechanical/electrical layout drawings.

c. Submission and approval of O&M manuals.

d. Submission and approval of as-built drawings.

e. Submission and approval of 1354 data and installed equipment lists.

f. Submission and approval of testing and air balance (TAB).

g. Submission of specialist TAB specialist design review report.

h. Submission and approval of fire protection specialist.

i. Submission and approval of testing and balancing of HVAC plus commissioning plans and data.

j. Air and water balance dates.

k. HVAC commissioning dates.

l. Controls testing plan.

m. Controls testing.

n. Performance Verification testing.

o. Other systems testing, if required.

p. Prefinal inspection

q. Correction of punchlist from prefinal inspection.

r. Final inspection.

3.3.2.5 Government Activities

Government and other agency activities that could impact progress shall be shown. These activities include, but are not limited to: approvals, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.2.6 Responsibility

All activities shall be identified in the project schedule by the party responsible to perform the work. Responsibility includes, but is not limited to, the subcontracting firm, Contractor work force, or government agency performing a given task. Activities shall not belong to more than one responsible party. The responsible party for each activity shall be identified by the Responsibility Code.

3.3.2.7 Modification or Claim Number

Any activity that is added or changed by contract modification or used to justify claimed time shall be identified by a mod or claim code that changed

Section 01320 Page 3 the activity. Activities shall not belong to more than one modification or claim item. The modification or claim number of each activity shall be identified by the Mod or Claim Number. Whenever possible, changes shall be added to the schedule by adding new activities. Existing activities shall not normally be changed to reflect modifications.

3.3.2.8 Phase of Work

All activities shall be identified in the project schedule by the phases of work in which the activity occurs. Activities shall not contain work in more than one phase of work. The project phase of each activity shall be by the unique Phase of Work Code.

3.3.2.9 Category of Work

All Activities shall be identified in the project schedule according to the category of work which best describes the activity. Category of work refers, but is not limited to the procurement chain of activities including such items as design package submissions, design reviews, review conferences, permits, submittals, approvals, procurement, fabrication, delivery, installation, start-up, and testing. The category of work for each activity shall be identified by the Category of Work Code.

3.3.3 Scheduled Project Completion

The schedule interval shall extend from NTP to the contract completion date.

3.3.3.1 Project Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. The Contractor shall include as the first activity in the project schedule an activity called "Start Project". The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.

3.3.3.2 Constraint of Last Activity

Completion of the last activity in the schedule shall be constrained by the contract completion date. The Contractor shall include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the completion date for the project, and a zero day duration.

3.3.3.3 Early Project Completion

In the event the project schedule shows completion of the project prior to the contract completion date, the Contractor shall identify those activities that have been accelerated and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. Contractor shall specifically address each of the activities noted in the narrative report at every project schedule update period to assist the Contracting Officer in evaluating the Contractor's ability to actually complete prior to the contract period.

Section 01320 Page 4

3.3.4 Interim Completion Dates

Contractually specified interim completion dates shall also be constrained to show negative float if the early finish date of the last activity in that phase falls after the interim completion date.

3.3.4.1 Start Phase

The contractor shall include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the NTP was acknowledged, and a zero day duration.

3.3.4.2 End Phase

The contractor shall include as the last activity in a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the completion date for the project, and a zero day duration.

3.3.4.3 Phase X

The contractor shall include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" activity shall be logically tied to the earliest and latest activities in the phase.

3.3.5 Default Progress Data Disallowed

Actual Start and Finish dates shall not be automatically updated by default mechanisms that may be included in scheduling software systems. Actual Start and Finish dates on the schedule shall match those dates provided from Contractor Quality Control Reports. Failure of the Contractor to document the Actual Start and Finish dates on the Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's schedule and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes.

3.4 PROJECT SCHEDULE SUBMISSIONS

The Contractor shall provide the submissions as described below. The data required for each submission are contained in paragraph SUBMISSION

REQUIREMENTS.

3.4.1 Initial Project Schedule Submission

The Initial Project Schedule, defining the Contractor's planned operations for the entire project shall be submitted for approval at the preconstruction conference.

Section 01320 Page 5

3.4.2 Periodic Schedule Updates

Based on the result of progress meetings, specified in "Periodic Progress Meetings," the Contractor shall submit periodic schedule updates. These submissions shall enable the Contracting Officer to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgement of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.

3.4.3 Standard Activity Coding Dictionary

The Contractor shall use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11, Appendix A. This exact structure is mandatory, even if some fields are not used.

3.5 SUBMISSION REQUIREMENTS

The following items shall be submitted by the Contractor for the initial submission, and every periodic project schedule update throughout the life of the project:

3.5.1 Data Disks

Two data disks containing the project schedule shall be provided. Data on the disks shall adhere to the SDEF format specified in ER 1-1-11, Appendix A.

3.5.1.1 File Medium

Required data shall be submitted on CD, unless otherwise approved by the Contracting Officer.

3.5.1.2 Disk Label

A permanent exterior label shall be affixed to each CD submitted. The label shall indicate the type of schedule Initial, Update, or Change), full contract number, project name, project location, data date, name and telephone number of person responsible for the schedule.

3.5.1.3 File Name

Each file submitted shall have a name related to either the schedule data date, project name, or contract number. The Contractor shall develop a naming convention that will ensure that the names of the files submitted are unique. The Contractor shall submit the file naming convention to the Contracting Officer for approval.

3.5.2 Narrative Report

A Narrative Report shall be provided with the initial and each update of the project schedule. This report shall be provided as the basis of the Contractor's progress payment request. The Narrative Report shall include:

a description of activities, a description of current and anticipated

Section 01320 Page 6 problem areas or delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. The narrative report is expected to relay to the Government, the Contractor's thorough analysis of the schedule output and its plans to compensate for any problems, either current or potential, which are revealed through that analysis.

3.5.3 Approved Changes Verification

Only project schedule changes that have been previously approved by the Contracting Officer shall be included in the schedule submission. The Narrative Report shall reference all changes made since the previous period and relate each change to documented, approved schedule changes.

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

Diagrams shall show a continuous flow form left to right with no arrows from right to left. The activity number, description, duration, and estimated earned value shall be shown in the diagram.

3.5.4.2 Project Milestone Dates

Dates shall be shown on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.5.4.3 Critical Path

The critical path shall be clearly shown.

3.5.4.4 Banding

Activities shall be grouped to assist in the understanding of the activity sequence. Typically, this flow will group activities by category of work, work area and/or responsibility.

3.6 PERIODIC PROGRESS MEETINGS

Progress meetings to discuss payment shall include a monthly onsite meeting or other regular intervals mutually agreed to at the preconstruction conference. During this meeting the Contractor shall describe, on an activity by activity basis, all proposed revisions and adjustments to the project schedule required to reflect the current status of the project. The Contracting Officer will approve activity progress, proposed revisions, and adjustments as appropriate.

3.6.1 Meeting Attendance

The Contractor's Project Manager and Scheduler shall attend the regular progress meeting.

3.6.2 Update Submission Following Progress Meeting

A complete update of the project schedule containing all approved progress, revisions, and adjustments, based on the regular progress meeting, shall be submitted not later than 4 working days after the monthly progress meeting.

Section 01320 Page 7

3.6.3 Progress Meeting Contents

Update information, including Actual Start Dates, Actual Finish Dates, Remaining Durations, and Cost-to-Date shall be subject to the approval of the Contracting Officer. As a minimum, the Contractor shall address the following items on an activity by activity basis during each progress meeting.

3.6.3.1 Start and Finish Dates

The Actual Start and Actual Finish dates for each activity currently in-progress or completed .

3.6.3.2 Time Completion

The estimated Remaining Duration for each activity in-progress. Time-based progress calculations shall be based on Remaining Duration for each activity.

3.6.3.3 Cost Completion

The earnings for each activity started. Payment will be based on earnings for each in-progress or completed activity. Payment for individual activities will not be made for work that contains quality defects. A portion of the overall project amount may be retained based on delays of activities.

3.6.3.4 Logic Changes

All logic changes pertaining to NTP on change orders, change orders to be incorporated into the schedule, Contractor proposed changes in work sequence, corrections to schedule logic for out-of-sequence progress, lag durations, and other changes that have been made pursuant to contract provisions shall be specifically identified and discussed.

3.6.3.5 Other Changes

Other changes required due to delays in completion of any activity or group of activities include: 1) delays beyond the Contractor's control, such as strikes and unusual weather. 2) delays encountered due to submittals, Government Activities, deliveries or work stoppages which make re-planning the work necessary. 3) Changes required to correct a schedule which does not represent the actual or planned prosecution and progress of the work.

3.7 REQUESTS FOR TIME EXTENSIONS

In the event the Contractor requests an extension of the contract completion date, or any interim milestone date, the Contractor shall furnish the following for a determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract:

justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is obligatory to any approvals.

Section 01320 Page 8

3.7.1 Justification of Delay

The project schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request.

The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information.

Actual delays that are found to be caused by the Contractor's own actions, which result in the extension of the schedule, will not be a cause for a time extension to the contract completion date.

3.7.2 Submission Requirements

The Contractor shall submit a justification for each request for a change in the contract completion date of under 2 weeks based upon the most recent schedule update at the time of the NTP or constructive direction issued for the change. Such a request shall be in accordance with the requirements of other appropriate Contract Clauses and shall include, as a minimum:

a. A list of affected activities, with their associated project schedule activity number.

b. A brief explanation of the causes of the change.

c. An analysis of the overall impact of the changes proposed.

d. A sub-network of the affected area.

Activities impacted in each justification for change shall be identified by a unique activity code contained in the required data file.

3.7.3 Additional Submission Requirements

For any requested time extension of over 2 weeks, the Contracting Officer may request an interim update with revised activities for a specific change request.