SP-13.pdf
PDF 92 KB Posted
- Solicitation number
- 36C24226R0036
About this file
This document is a Design Review and Completion Schedule (SP-13) for a Plumbing GF Mitigation project with Project No. 630-26-801. The schedule outlines a comprehensive three-phase design process for an architectural/engineering (A/E) contractor working with the VA, with specific timelines and review stages for each phase.
The project is divided into three distinct phases: Phase 1 - Schematics (Concept) Design, Phase 2 - Design Development, and Phase 3 - Contract Documents (for Bid). Each phase includes multiple submission points at 35%, 65%, and 100% completion, with corresponding VA review periods and project review meetings. The total project timeline is 180 calendar days, with consistent review cycles of 15 days for submissions, 7 days for VA reviews, and 1-day project review meetings. The final phase involves submitting 100% documents for bidding purposes, with 10 days allocated for document preparation and 7 days for VA review.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VA Notice of Limitations on Subcontracting.docx | DOCX document | |
| 36C24226R0036.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP-13 DESIGN REVIEW AND COMPLETION SCHEDULE
Project Title: Plumbing GF Mitigation Project No.: 630-26-801
The A/E shall perform the work required by this contract within the limits of the following schedule. He/she shall provide professional architects and engineers as directed by the Contracting Officer who are familiar with the work to attend the Design reviews on the following dates:
Start Work (Notice to Proceed)
Phase 1 – Schematics (Concept) Design
Review existing drawings/field verifications and site survey reports..….. 15 days Submit 35% Conceptual Design Phase for VA review………….………. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting………………………………………... 1 day
Submit 65% Concept Design Phase for VA review……………..………. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting………………………………………... 1 day
Submit 100% Concept Design Phase for VA review…….…….……….. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting……………………………………….. 1 day
Phase 2 – Design Development
Submit 35% Design Development for VA review……………….…….. 15 days VA review………………………………………………….………….... 7 days VA-A/E Project Review Meeting……………………………………….. 1 day
Submit 65% Design Development for VA review……………….…….. 15 days VA review………………………………………………….…………… 7 days VA-A/E Project Review Meeting……………………………………….. 1 day
Submit 100% Design Development for VA review……………….….... 15 days VA review………………………………………………….………….... 7 days VA-A/E Project Review Meeting……………………………………….. 1 day
Phase 3 – Contract Documents (for Bid)
Submit 100% Documents for Bid………………………………….……. 10 days VA review………………………………………………….……………. 7 days
Deliver Final 100% Documents for Bidding Purposes .………………………… 10 days
Total calendar days to complete………………………………...……………. 180 days