C1DA--NRM-AE 630-26-801 Plumbing GF Mitigation (Design)
Solicitation number
36C24226R0036
Issued by

About this file

This document is a Design Review and Completion Schedule (SP-13) for a Plumbing GF Mitigation project with Project No. 630-26-801. The schedule outlines a comprehensive three-phase design process for an architectural/engineering (A/E) contractor working with the VA, with specific timelines and review stages for each phase.

The project is divided into three distinct phases: Phase 1 - Schematics (Concept) Design, Phase 2 - Design Development, and Phase 3 - Contract Documents (for Bid). Each phase includes multiple submission points at 35%, 65%, and 100% completion, with corresponding VA review periods and project review meetings. The total project timeline is 180 calendar days, with consistent review cycles of 15 days for submissions, 7 days for VA reviews, and 1-day project review meetings. The final phase involves submitting 100% documents for bidding purposes, with 10 days allocated for document preparation and 7 days for VA review.

View the file

Other files

File Type Posted
VA Notice of Limitations on Subcontracting.docx DOCX document
36C24226R0036.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP-13 DESIGN REVIEW AND COMPLETION SCHEDULE

Project Title: Plumbing GF Mitigation Project No.: 630-26-801

The A/E shall perform the work required by this contract within the limits of the following schedule. He/she shall provide professional architects and engineers as directed by the Contracting Officer who are familiar with the work to attend the Design reviews on the following dates:

Start Work (Notice to Proceed)

Phase 1 – Schematics (Concept) Design

Review existing drawings/field verifications and site survey reports..….. 15 days Submit 35% Conceptual Design Phase for VA review………….………. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting………………………………………... 1 day

Submit 65% Concept Design Phase for VA review……………..………. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting………………………………………... 1 day

Submit 100% Concept Design Phase for VA review…….…….……….. 15 days VA review………………………………………………….…………….. 7 days VA-A/E Project Review Meeting……………………………………….. 1 day

Phase 2 – Design Development

Submit 35% Design Development for VA review……………….…….. 15 days VA review………………………………………………….………….... 7 days VA-A/E Project Review Meeting……………………………………….. 1 day

Submit 65% Design Development for VA review……………….…….. 15 days VA review………………………………………………….…………… 7 days VA-A/E Project Review Meeting……………………………………….. 1 day

Submit 100% Design Development for VA review……………….….... 15 days VA review………………………………………………….………….... 7 days VA-A/E Project Review Meeting……………………………………….. 1 day

Phase 3 – Contract Documents (for Bid)

Submit 100% Documents for Bid………………………………….……. 10 days VA review………………………………………………….……………. 7 days

Deliver Final 100% Documents for Bidding Purposes .………………………… 10 days

Total calendar days to complete………………………………...……………. 180 days