SOW81.pdf

PDF 108 KB Posted

Attached to
Ontario IRA - Deck Design
Solicitation number
2111100
Issued by
Wayne County, New York

About this file

This document is a Project Scope Description for the design of a deck renovation project at the Ontario IRA Facility located at 2420 Trimble Rd, Ontario, NY 14519. The Finger Lakes DDSO is soliciting bids for an Architect/Engineer to provide drawing designs and specifications in accordance with various codes and regulations. The scope includes design services such as providing product specification data, document submissions, and a design proposal. Construction administration services are not required for this project. There is a mandatory site visit scheduled for July 3, 2024 at 9:30 AM, and bids will not be accepted from vendors that do not attend this site visit. The project is not subject to prevailing wage requirements, and the contract term is 30 days after completion of the project.

The design proposal shall include a time schedule and a probable construction cost estimate. OPWDD does not provide partial payments and will not provide payment until the project is accepted for construction and permitted. All applicable environmental testing will be completed independently by OPWDD. The project is not a Service-Disabled Veteran-Owned Set Aside, and the due date for bids is July 12, 2024 at 8:00 PM.

View the file

Other files

File Type Posted
RFQ100.pdf PDF
Bid Tab193.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCOPE

DESCRIPTION:

The Design Vendor shall provide all labor and materials necessary to complete a fully comprehensive drawing design and specification generation of the services required in a professional manner. Refer to the attached specifications (if applicable) for the following OPWDD Requirements of the Project Scope of Work.

All projects are subject to Environmental Surveying, which shall be conducted outside this Scope of Work and shall be completed before work commences on all properties.

SCOPE OF WORK includes, but is not necessarily limited to the following:

A. Design Services:

1. Reference attached specific OPWDD Requirements (if applicable) of the

Renovations/Replacements being designed. (eg: Kitchen, Bathroom, Roof, FACP, Generator, Sidewalks, Windows, Abatement, etc.)

2. Drawing Designs and Specifications are to be in accordance with:

a. 14 NYCRR 635, Subpart 635-7

b. 19 NYCRR 1201 and 1204.

c. OPWDD Specifications,

d. NFPA (NFPA 101 - Life Safety Code)

e. NYS Uniform Building Code,

f. NYS Environmental and Energy Code Regulation Compliance.

g. NFPA 101A – Guide on Alternative Approaches to Life Safety.

3. Product Specification Data.

a. Construction details, material descriptions, dimensions, profiles, finishes, and applicable schematics, and cut sheets.

4. All Design and Specification documents shall be provided on Adobe (.pdf), CAD Files should be provided to OPWDD for future use and records.

5. Document Submissions to be provided to OPWDD Point of Contact (POC) at routine

Intervals:

a. 90% Completion (Issued for Permitting- signed and stamped),

b. 100% Completion

6. Internal Construction Permitting to be completed by the Maintenance Supervisor with necessary OPWDD Agency Personnel in Central Office.

Facility:

Ontario IRA

Facility Address:

2420 Trimble Rd, Ontario, NY 14519

Point of Contact:

Geoffrey Miller

Contact Phone Number:

315-604-1430

Project Title:

Ontario Deck

Summary of Work: Full Renovation

7. Design Vendor shall provide (2) sets of 24” x36” blueprints upon completion, mailed to POC, listed above.

8. Design Proposal shall include:

a. A time schedule for the Design Services based on current workload within the

Design Firm.

b. A Probable Construction Cost Estimate, based on current pricing, materials and supplies.

9. Generalized Statements required by OPWDD POC for protection of Service Recipients and Operations, on a case-by-case basis.

B. Construction Administration Services are to include but not limited to:

1. None for this project.

GENERAL REQUIREMENTS:

1. Any unforeseen conditions that may alter the established proposal price are to be reported to the Plant Superintendent or POC listed above, immediately upon discovery.

2. All applicable environmental testing associated with this work will be completed independently by OPWDD.

3. OPWDD Point of Contact must receive from designing vendor:

a. Appendix A document.

b. Certificate of Liability Insurance.

c. NY Forward Documentation:

1) Reopening Safety Plans, Business Attestation and Protocols for Enhanced Protections.

4. OPWDD does not provide partial payments on design services. Only projects Invoiced at 100% Completion shall be processed for payment.

5. OPWDD will not provide payment until project is “accepted for construction” and Permitted.

6. A site visit is mandatory. The site visit date is scheduled for Wednesday, July 3, 2024 @ 9:30am at the project site. All prospective bidders are encouraged to attend.

All projects are subject to Environmental Surveying, which shall be conducted outside this Scope of Work and shall be completed before work commences on all properties.
SCOPE OF WORK includes, but is not necessarily limited to the following:
A. Design Services:
1. Reference attached specific OPWDD Requirements (if applicable) of the Renovations/Replacements being designed. (eg: Kitchen, Bathroom, Roof, FACP, Generator, Sidewalks, Windows, Abatement, etc.)
2. Drawing Designs and Specifications are to be in accordance with:
a. 14 NYCRR 635, Subpart 635-7
b. 19 NYCRR 1201 and 1204.
c. OPWDD Specifications,
d. NFPA (NFPA 101 - Life Safety Code)
e. NYS Uniform Building Code,
f. NYS Environmental and Energy Code Regulation Compliance.
g. NFPA 101A – Guide on Alternative Approaches to Life Safety.
3. Product Specification Data.
a. Construction details, material descriptions, dimensions, profiles, finishes, and applicable schematics, and cut sheets.
4. All Design and Specification documents shall be provided on Adobe (.pdf), CAD Files should be provided to OPWDD for future use and records.
5. Document Submissions to be provided to OPWDD Point of Contact (POC) at routine Intervals:
a. 90% Completion (Issued for Permitting- signed and stamped),
b. 100% Completion
6. Internal Construction Permitting to be completed by the Maintenance Supervisor with necessary OPWDD Agency Personnel in Central Office.
7. Design Vendor shall provide (2) sets of 24” x36” blueprints upon completion, mailed to POC, listed above.
8. Design Proposal shall include:
a. A time schedule for the Design Services based on current workload within the Design Firm.
b. A Probable Construction Cost Estimate, based on current pricing, materials and supplies.

9. Generalized Statements required by OPWDD POC for protection of Service Recipients and Operations, on a case-by-case basis.

B. Construction Administration Services are to include but not limited to:
1. None for this project.
1. Any unforeseen conditions that may alter the established proposal price are to be reported to the Plant Superintendent or POC listed above, immediately upon discovery.
2. All applicable environmental testing associated with this work will be completed independently by OPWDD.
3. OPWDD Point of Contact must receive from designing vendor:
a. Appendix A document.
b. Certificate of Liability Insurance.
c. NY Forward Documentation:
1) Reopening Safety Plans, Business Attestation and Protocols for Enhanced Protections.
4. OPWDD does not provide partial payments on design services. Only projects Invoiced at 100% Completion shall be processed for payment.
5. OPWDD will not provide payment until project is “accepted for construction” and Permitted.
6. A site visit is mandatory. The site visit date is scheduled for Wednesday, July 3, 2024 @ 9:30am at the project site. All prospective bidders are encouraged to attend.

File details come from the government source that posted it. Updated .