SOW74.pdf
PDF 108 KB Posted
- Attached to
- Cobblestone 103 IRA - Kitchen Design
- Solicitation number
- 2110946
- Issued by
- Wayne County, New York City, New York
About this file
The document provided is a Scope of Work for a kitchen renovation project at the 103 Cobblestone Terrace facility in Newark, New York, managed by the New York State Office for People with Developmental Disabilities (OPWDD). The Design Vendor shall provide comprehensive drawing designs and specifications in accordance with various New York state and federal regulations and codes. The design documents must be submitted at 90% and 100% completion, and the Design Vendor shall provide two sets of 24"x36" blueprints upon project completion. A mandatory site visit is scheduled for June 26, 2024 at 9:00 AM, and bids will not be accepted from vendors that do not attend.
The related state and local contract opportunity is for the 103 Cobblestone Terrace IRA Kitchen Design project, with a due date of July 5, 2024. The contract term is 30 days after project completion, and the project location is 103 Cobblestone Terrace, Newark, NY 14513 in Wayne County. This project is not a Service-Disabled Veteran-Owned Set Aside, and prevailing wage is not a requirement. Interested vendors must submit a request for an invitation to bid on company letterhead, including current contact information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tab185.pdf | ||
| RFQ93.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SCOPE
DESCRIPTION:
The Design Vendor shall provide all labor and materials necessary to complete a fully comprehensive drawing design and specification generation of the services required in a professional manner. Refer to the attached specifications (if applicable) for the following OPWDD Requirements of the Project Scope of Work.
All projects are subject to Environmental Surveying, which shall be conducted outside this Scope of Work and shall be completed before work commences on all properties.
SCOPE OF WORK includes, but is not necessarily limited to the following:
A. Design Services:
1. Reference attached specific OPWDD Requirements (if applicable) of the
Renovations/Replacements being designed. (eg: Kitchen, Bathroom, Roof, FACP, Generator, Sidewalks, Windows, Abatement, etc.)
2. Drawing Designs and Specifications are to be in accordance with:
a. 14 NYCRR 635, Subpart 635-7
b. 19 NYCRR 1201 and 1204.
c. OPWDD Specifications,
d. NFPA (NFPA 101 - Life Safety Code)
e. NYS Uniform Building Code,
f. NYS Environmental and Energy Code Regulation Compliance.
g. NFPA 101A – Guide on Alternative Approaches to Life Safety.
3. Product Specification Data.
a. Construction details, material descriptions, dimensions, profiles, finishes, and applicable schematics, and cut sheets.
4. All Design and Specification documents shall be provided on Adobe (.pdf), CAD Files should be provided to OPWDD for future use and records.
5. Document Submissions to be provided to OPWDD Point of Contact (POC) at routine
Intervals:
a. 90% Completion (Issued for Permitting- signed and stamped),
b. 100% Completion
6. Internal Construction Permitting to be completed by the Maintenance Supervisor with necessary OPWDD Agency Personnel in Central Office.
Facility:
103 Cobblestone Terrace
Facility Address:
103 Cobblestone Terr, Newark, NY 14513
Point of Contact:
Geoffrey Miller
Contact Phone Number:
315-604-1430
Project Title:
103 Kitchen
Summary of Work: Full Renovation
7. Design Vendor shall provide (2) sets of 24” x36” blueprints upon completion, mailed to POC, listed above.
8. Design Proposal shall include:
a. A time schedule for the Design Services based on current workload within the
Design Firm.
b. A Probable Construction Cost Estimate, based on current pricing, materials and supplies.
9. Generalized Statements required by OPWDD POC for protection of Service Recipients and Operations, on a case-by-case basis.
B. Construction Administration Services are to include but not limited to:
1. None for this project.
GENERAL REQUIREMENTS:
1. Any unforeseen conditions that may alter the established proposal price are to be reported to the Plant Superintendent or POC listed above, immediately upon discovery.
2. All applicable environmental testing associated with this work will be completed independently by OPWDD.
3. OPWDD Point of Contact must receive from designing vendor:
a. Appendix A document.
b. Certificate of Liability Insurance.
c. NY Forward Documentation:
1) Reopening Safety Plans, Business Attestation and Protocols for Enhanced Protections.
4. OPWDD does not provide partial payments on design services. Only projects Invoiced at 100% Completion shall be processed for payment.
5. OPWDD will not provide payment Services until project is Permitted and Completed.
6. A site visit is mandatory. The site visit date is scheduled for Wednesday, June 26, 2024 @ 9:00am at the project site. All prospective bidders are encouraged to attend.
| All projects are subject to Environmental Surveying, which shall be conducted outside this Scope of Work and shall be completed before work commences on all properties. |
| SCOPE OF WORK includes, but is not necessarily limited to the following: |
| A. Design Services: |
| 1. Reference attached specific OPWDD Requirements (if applicable) of the Renovations/Replacements being designed. (eg: Kitchen, Bathroom, Roof, FACP, Generator, Sidewalks, Windows, Abatement, etc.) |
| 2. Drawing Designs and Specifications are to be in accordance with: |
| a. 14 NYCRR 635, Subpart 635-7 |
| b. 19 NYCRR 1201 and 1204. |
| c. OPWDD Specifications, |
| d. NFPA (NFPA 101 - Life Safety Code) |
| e. NYS Uniform Building Code, |
| f. NYS Environmental and Energy Code Regulation Compliance. |
| g. NFPA 101A – Guide on Alternative Approaches to Life Safety. |
| 3. Product Specification Data. |
| a. Construction details, material descriptions, dimensions, profiles, finishes, and applicable schematics, and cut sheets. |
| 4. All Design and Specification documents shall be provided on Adobe (.pdf), CAD Files should be provided to OPWDD for future use and records. |
| 5. Document Submissions to be provided to OPWDD Point of Contact (POC) at routine Intervals: |
| a. 90% Completion (Issued for Permitting- signed and stamped), |
| b. 100% Completion |
| 6. Internal Construction Permitting to be completed by the Maintenance Supervisor with necessary OPWDD Agency Personnel in Central Office. |
| 7. Design Vendor shall provide (2) sets of 24” x36” blueprints upon completion, mailed to POC, listed above. |
| 8. Design Proposal shall include: |
| a. A time schedule for the Design Services based on current workload within the Design Firm. |
| b. A Probable Construction Cost Estimate, based on current pricing, materials and supplies. |
9. Generalized Statements required by OPWDD POC for protection of Service Recipients and Operations, on a case-by-case basis.
| B. Construction Administration Services are to include but not limited to: |
| 1. None for this project. |
| 1. Any unforeseen conditions that may alter the established proposal price are to be reported to the Plant Superintendent or POC listed above, immediately upon discovery. |
| 2. All applicable environmental testing associated with this work will be completed independently by OPWDD. |
| 3. OPWDD Point of Contact must receive from designing vendor: |
| a. Appendix A document. |
| b. Certificate of Liability Insurance. |
| c. NY Forward Documentation: |
| 1) Reopening Safety Plans, Business Attestation and Protocols for Enhanced Protections. |
| 4. OPWDD does not provide partial payments on design services. Only projects Invoiced at 100% Completion shall be processed for payment. |
| 5. OPWDD will not provide payment Services until project is Permitted and Completed. |
| 6. A site visit is mandatory. The site visit date is scheduled for Wednesday, June 26, 2024 @ 9:00am at the project site. All prospective bidders are encouraged to attend. |