This Statement of Work (SOW) details fire suppression system repair requirements for Yosemite National Park residences and facilities. The project encompasses 51 locations representing 73 individual fire suppression systems across the El Portal Rancheria Residential Area, El Portal Maintenance Complex, and Mather District. Specific repair tasks include installing missing signage, replacing out-of-date gauges, adding appropriate wrenches and heads to head boxes, replacing recalled and painted sprinkler heads, adjusting water flow alarms, installing electric bells, performing 5-year inspections, and ensuring compliance with National Fire Protection Association (NFPA) standards.
The contractor must provide all necessary parts, materials, labor, supervision, transportation, and equipment to complete the work within the performance period. Work will primarily be conducted during normal business hours (8 a.m. to 5 p.m., Monday through Friday), with special considerations for the remote location and potential connectivity issues. Additional requirements include obtaining passing inspection reports acceptable to the California State Fire Marshall and properly disposing of construction debris outside Yosemite National Park. The project also includes specific safety guidelines, such as bear and animal safety protocols, and hauling restrictions due to ongoing rockslide repairs in the area.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8525Q0024_Amd_0002.pdf | ||
| Sol_140P8525Q0024_Amd_0001.pdf | ||
| SF24_Bid_Bond.pdf | ||
| Sol_140P8525Q0024.pdf | ||
| Wage_Determination_CA20240029_02-21-25.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E X P E R I E N C E Y O U R A M E R I C A The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Statement of Work Repair Fire Suppression Deficiencies at Parkwide Locations
Objective
Yosemite National Park (YOSE) has a need for repair of fire system deficiencies identified during the annual testing. After repairs are made to the systems, interval testing and inspections (annual or 5-year) will be performed to achieve a passing report. All required inspections, testing, and maintenance to be performed as per the National Fire Protection Association (NFPA) 25, Standard for Inspections, Testing, and Maintenance of Water- Based Fire Protection Systems and all other associated NFPA Standards. This is considered a remote location, and connectivity can be an issue.
Background
YOSE has over 138 fire suppression systems in buildings parkwide. Each system is inspected each year and deficiencies identified. This project is to bring the fire suppression systems in the El Portal Residences, El Portal Roads Shop, and a Mather residence into compliance with NFPA requirements. This project encompasses a total of 51 locations and represents 73 individual systems.
The contractor will perform tasks to rectify the deficiencies identified during the annual inspections. Deficiencies include the following, but not limited to interval testing, replace missing signage, replacing air and water gauges, installing electric bells, replacing recalled sprinkler heads, adding wrenches and heads for head boxes, replacing painted sprinkler heads, adjustment of water flow switches, and performing system inspections with passing reports.
Scope
The contractor shall provide all parts, materials, labor, supervision, management, transportation, and equipment necessary to perform the work.
The contractor shall maintain an adequate workforce to complete the work associated with the contract in a timely manner, within the period of performance.
The contractor shall perform a field review of the deficiencies identified by others (HCI Systems, Inc and Friendly Fire Systems, Inc.) and included in this scope for work to confirm their validity and accuracy (see attached).
Contractor shall perform all inspections and testing required at intervals equal to or greater than yearly: including, but not limited to: 5 year internal pipe exams, 3 year leak test of dry pipe systems, and annual testing.
All required inspections, testing, and maintenance to be performed as per the National Fire Protection Association (NFPA) 25, Standard for Inspections, Testing, and Maintenance of Water-Based Fire Protection Systems and all other associated NFPA Standards.
The contractor shall provide an inspection report of a passed inspection of all the fire suppression systems that are a part of this contract. The inspection report shall be accepted by the State of California State Fire Marshall.
The contractor shall dispose of all construction debris, including any items removed from government property, outside of Yosemite National Park.
Yosemite National Park
Carrie Toepper Supervisory Facility Operations Specialist Buildings and Grounds Phone: 209-379-1089
National Park Service U.S. Department of the Interior
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Locations –
The locations included in the contract are in the El Portal Rancheria Residential Area and El Portal Maintenance Complex, El Portal, CA 95318 and the Mather District, 9007 Meadowview Lane, Hodgden, CA 95321 (maps included):
Residences:
1 - EPQ 703 – 9761 River View Lane – Residential 13D Wet Pipe system Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install electric bell for water flow alarm – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
2 - EPQ 704 – 9759 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install electric bell for water flow alarm – 1 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
3 - EPQ 705 – 9757 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Valve, and 911 Bell – 3 ea Contractor shall adjust water flow for alarm bell to alert within 30-90 seconds – 1 ea Contractor shall add appropriate heads to head box – 2 ea Contractor shall remove VK453 brass head from head box – 1 ea Contractor shall replace recalled sprinkler heads – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
4 - EPQ 711 – 9763 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall install required pipe bracing in garage – 2 ea Contractor shall replace recalled sprinkler heads - 11 ea Contractor shall install gauge on riser – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
5 - EPQ 713 – 9755 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall replace alarm bell – 1 ea Contractor shall replace recalled sprinkler heads – 12 ea Contractor shall perform 5-year inspection with passing report – 1 ea
6 - EPQ 714 – 9760 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall remove copper wire from sprinkler pipe – 1 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
7 – EPQ 715 – 9754 River View Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell to alert within 30-90 seconds – 1 ea Contractor shall replace recalled sprinkler heads – 12 ea Contractor shall perform 5-year inspection with passing report – 1 ea
8 – EPQ 716 – 9754 River View Lane – Residential 13D Wet System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Contractor shall adjust water flow for alarm bell to alert within 30-90 seconds – 1 ea Contractor shall replace painted sprinkler head – 1 ea Contractor shall add appropriate heads and wrench to head box – 7 ea Contractor shall clean loaded sprinkler head @ hallway – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
9 – EPQ 717 – 9752 River View Lane (Childcare Center) – Residential 13D Wet System Contractor shall install missing signage – Control Valve, Test/Drain, and 911 Bell – 3 ea Contractor shall replace escutcheon @ north side room – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall trouble shoot and repair water flow device, failed to operate – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
10 – EPQ 719 – 9730 Barium Mine Road – Residential 13D Wet System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve Contractor shall add appropriate heads and wrenches to head box – 3 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install alarm bell and wiring – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
11 – EPQ 720 – 9721 Barium Mine Road – Residential 13D Wet System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea Contractor shall add appropriate heads and wrench to head box – 7 ea Contractor shall replace recalled sprinkler heads – 12 ea Contractor shall perform 5-year inspection with passing report – 1 ea
12 – EPQ 721 – 9723 Barium Mine Road – Residential 13D Wet System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install alarm bell and wiring – 1 ea Contractor shall replace recalled sprinkler heads – 10 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
13 – EPQ 724 – 9725 Barium Mine Road – Residential 13D Wet System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall install alarm bell and wiring – 1 ea Contractor shall replace recalled sprinkler heads – 12 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
14 – EPQ 726 – 9724 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall clean sprinkler leads @ kitchen and back bedroom – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
15 – EPQ 727 – 9744 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
16 – EPQ 728 – 9746 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall replace painted sprinkler head @ dining room – 1 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Contractor shall add appropriate wrench to head box – 1 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds -1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
17 – EPQ 730 – 97545 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain, Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea Contractor shall replace recalled sprinkler heads – 14 ea Contractor shall perform 5-year inspection with passing report – 1 ea
18 – EPQ 731 – 9741 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea Contractor shall replace recalled sprinkler heads – 14 ea Contractor shall perform 5-year inspection with passing report – 1 ea
19 – EPQ 732 – 9743 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 7 ea Contractor shall replace recalled sprinkler heads – 13 ea Contractor shall perform 5-year inspection with passing report – 1 ea
20 – EPQ 733 – 9745 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 7 ea Contractor shall replace recalled sprinkler heads – 10 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
21 – EPQ 734 – 9747 Red Bud Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 5 ea Contractor shall replace recalled sprinkler heads – 10 ea Contractor shall perform 5-year inspection with passing report – 1 ea
22 – EPQ 737 – 9752 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea Contractor shall replace recalled sprinkler heads – 12 ea Contractor shall install broken sprinkler head to Inspector’s Test Valve – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
23 – EPQ 738 – 9751 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve, and 911 Bell – 3 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 5 ea Contractor shall replace recalled sprinkler heads – 14 ea Contractor shall replace water gong - bell did not sound when tested – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
24 – EPQ 740 – 9862 Rancheria Flat Road – Residential 13R Wet Pipe System
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Riser 1 – Contractor shall install missing signage – Control Valve, Test/Drain, and 911 Bell – 3 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and head to head box – 2 ea Contractor shall replace sprinkler head @ basement – 1 ea Contractor shall install missing semi-recessed escutcheon – 1 ea Riser 2 – Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Riser 4 - Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 8 ea Apt. B – Contractor shall replace recalled sprinkler heads – 12 ea Apt. C – Contractor shall replace recalled sprinkler heads – 10 ea Apt. D – Contractor shall replace recalled sprinkler heads – 8 ea Contractor shall replace missing escutcheon @ kitchen – 1 ea Apt. E – Contractor shall replace recalled sprinkler heads – 9 ea Apt. F – Contractor shall replace recalled sprinkler heads – 10 ea Apt. G – Contractor shall replace recalled sprinkler heads – 12 ea Apt. H – Contractor shall replace recalled sprinkler heads – 7 ea Contractor shall perform 5-year inspection with passing report – 4 ea
25 – EPQ 741 – 9860 Rancheria Flat Road – Residential 13R Wet Pipe system Riser 1 – Contractor shall install missing signage – 911 Bell – 1 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and head to head box – 2 ea Contractor shall replace recalled sprinkler heads @ basement – 2 ea Riser 2 – Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell for 30-90 seconds – 1 ea Riser 4 - Contractor shall replace out-of-date gauge – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 9 ea Apt. B – Contractor shall replace recalled sprinkler heads – 11 ea Apt. C – Contractor shall replace recalled sprinkler heads – 11 ea Apt. D – Contractor shall replace recalled sprinkler heads – 11 ea Apt. E – Contractor shall replace recalled sprinkler heads – 9 ea Apt. F – Contractor shall replace recalled sprinkler heads – 11 ea Apt. G – Contractor shall replace recalled sprinkler heads – 11 ea Apt. H – Contractor shall replace recalled sprinkler heads – 9 ea Contractor shall perform 5-year inspection with passing report – 4 ea
26 – EPQ 742 – 9858 Rancheria Flat Road – Residential 13R Wet Pipe System Riser 1 – Contractor shall install missing signage – 911 Bell – 1 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and head to head box – 2 ea Contractor shall replace recalled sprinkler heads @ basement – 9 ea Contractor shall adjust water flow for alarm bell for 30-90 seconds – 1 ea Contractor shall install missing escutcheon @ laundry – 1 ea Riser 2 – Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell for 30-90 seconds – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell for 30-90 seconds – 1 ea Riser 4 - Contractor shall replace out-of-date gauge – 1 ea Contractor shall adjust water flow for alarm bell for 30-90 seconds – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 10 ea Apt. B – Contractor shall replace recalled sprinkler heads – 10 ea Apt. C – Contractor shall replace recalled sprinkler heads – 10 ea Apt. D – Contractor shall replace recalled sprinkler heads – 7 ea Apt. E – Contractor shall replace recalled sprinkler heads – 10 ea Apt. F – Contractor shall replace recalled sprinkler heads – 12 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Apt. G – Contractor shall replace recalled sprinkler heads – 10 ea Apt. H – Contractor shall replace recalled sprinkler heads – 8 ea Contractor shall perform 5-year inspection with passing report – 4 ea
27 – EPQ 743 – 9737 Barium Mine Road – Residential 13R Wet Pipe System Riser 1 – Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 2 ea Contractor shall replace recalled sprinkler heads @ basement – 12 ea Riser 2 – Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Riser 4 - Contractor shall replace out-of-date gauge – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 9 ea Apt. B – Contractor shall replace recalled sprinkler heads – 12 ea Apt. C – Contractor shall replace recalled sprinkler heads – 10 ea Apt. D – Contractor shall replace recalled sprinkler heads – 9 ea Apt. E – Contractor shall replace recalled sprinkler heads – 9 ea Apt. F – Contractor shall replace recalled sprinkler heads – 12 ea Apt. G – Contractor shall replace recalled sprinkler heads – 11 ea Apt. H – Contractor shall replace recalled sprinkler heads – 9 ea Contractor shall perform 5-year inspection with passing report – 4 ea
28 – EPQ 744 – 9757 Barium Mine Road – Residential 13R Wet Pipe System Riser 1 – Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall replace recalled sprinkler heads @ basement – 14 ea Riser 2 – Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Riser 4 - Contractor shall replace out-of-date gauge – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 11 ea Apt. B – Contractor shall replace recalled sprinkler heads – 11 ea Apt. C – Contractor shall replace recalled sprinkler heads – 12 ea Apt. D – Contractor shall replace recalled sprinkler heads – 10 ea Apt. E – Contractor shall replace recalled sprinkler heads – 8 ea Apt. F – Contractor shall replace recalled sprinkler heads – 12 ea Apt. G – Contractor shall replace recalled sprinkler heads – 12 ea Apt. H – Contractor shall replace recalled sprinkler heads – 10 ea Contractor shall perform 5-year inspection with passing report – 4 ea
29 – EPQ 745 – 9757 Barium Mine Road – Residential 13R Wet Pipe System Riser 1 – Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Riser 2 – Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Apt. A – No deficiencies Apt. B – No deficiencies Apt. C – No deficiencies Apt. D – No deficiencies Apt. E – Contractor shall replace painted sprinkler head (155*, ½” white, semi-recessed pendant) @ living room – 1 ea Contractor to install missing white escutcheon @ hallway – 1 ea Apt. F – No deficiencies Apt. G – No deficiencies Apt. H – No deficiencies Contractor shall perform 5-year inspection with passing report – 3 ea
30 – EPQ 746 – 9731 Barium Mine Road – Residential 13R Wet Pipe System Riser 1 – Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall replace recalled sprinkler heads @ east basement – 6 ea Contractor shall replace recalled sprinkler heads @ west basement – 6 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Riser 2 - Contractor shall replace out-of-date gauge – 1 ea Riser 3 - Contractor shall replace out-of-date gauge – 1 ea Riser 4 - Contractor shall replace out-of-date gauge – 1 ea Riser 5 - Contractor shall replace out-of-date gauge – 1 ea Riser 6 - Contractor shall replace out-of-date gauge – 1 ea Apt. A – Contractor shall replace recalled sprinkler heads – 12 ea Apt. B – Contractor shall replace recalled sprinkler heads – 11 ea Apt. C – Contractor shall replace recalled sprinkler heads – 12 ea Apt. D – Contractor shall replace recalled sprinkler heads – 11 ea Apt. E – Contractor shall replace recalled sprinkler heads – 11 ea Apt. F – Contractor shall replace recalled sprinkler heads – 9 ea Apt. G – Contractor shall replace recalled sprinkler heads – 12 ea Apt. H – Contractor shall replace recalled sprinkler heads – 12 ea Apt. I - Contractor shall replace recalled sprinkler heads – 12 ea Apt. J - Contractor shall replace recalled sprinkler heads – 11 ea Apt. K - Contractor shall replace recalled sprinkler heads – 11 ea Apt. L - Contractor shall replace recalled sprinkler heads – 9 ea Contractor shall perform 5-year inspection with passing report – 6 ea
31 – EPQ 850 – 9758 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads for the head box – 2 ea Contractor shall install missing escutcheon @ upstairs bathroom – 1 ea Contractor shall replace corroded sprinkler heads @ upstairs bathroom and hallway – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
32 – EPQ 851 – 9767 River View Road – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain and Inspector’s Test Valve – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads for the head box – 2 ea Contractor shall install missing escutcheon – 1 ea Contractor shall replace recalled sprinkler heads – 14 ea Contractor shall install faucet for water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
33 – EPQ 856 – 9754 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contactor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace painted sprinkler heads @ water heater closet and living room – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
34 – EPQ 857 – 9756 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contactor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace painted sprinkler heads @ water heater closet and living room – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
35 – EPQ 858 – 9758 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contactor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace painted sprinkler heads @ entry – 1 ea Contractor shall install escutcheon @ entry and basement – 2 ea Contractor shall replace 1” gate valve @ Main Drain – 1 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
36 – EPQ 859 – 9760 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contactor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 5 ea Contractor shall replace painted sprinkler heads @ upstairs bathroom – 1 ea Contractor shall replace 155* SR heads with white 135*QR, semi-recessed, ½” pendants @ downstairs bathroom and hallway – 2 ea Contractor shall perform 5-year inspection with passing report – 1 ea
37 – EPQ 860 – 9762 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contactor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 5 ea Contractor shall replace painted sprinkler head @ basement bathroom – 1 ea Contractor shall replace 155* SR heads with white 135*QR, semi-recessed, ½” pendants @ left basement bedroom and water heater closet – 2 ea Contractor shall adjust water flow for alarm bell to 30-90 seconds – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
38 – EPQ 861 – 9759 Boulder Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Main Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 3 ea Contractor shall replace painted sprinkler heads, 135*QR, semi-recessed, white – 3 ea Contractor shall replace obstructed sprinkler head (kitchen) w/ 401 style – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
39 – EPQ 862 – 9788 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to head box – 1 ea Contractor shall replace escutcheon (white) @ downstairs family room – 1 ea Contractor shall replace sprinkler heads @ laundry room, hallway, and upstairs bathroom – 3 ea Contractor shall replace Main Drain valve – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
40 – EPQ 863 – 9812 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Main Drain – 1 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall install escutcheon (white) @ water heater closet – 1 ea Contractor shall replace painted sprinkler head @ upstairs dining room and living room – 2 ea Contractor shall replace 1” water flow device – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
41 – EPQ 864 – 9816 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall replace painted sprinkler heads @ laundry room and 1st bedroom – 2 ea Contractor shall replace 155* SR pendant in 2nd Bedroom, with white, semi-recessed 135* QR pendant – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
42 – EPQ 865 – 9820 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauges – 2 ea Contractor shall add appropriate wrench to the head box – 1 ea Contractor shall replace recalled sprinkler heads – 15 ea
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
43 – EPQ 866 – 9824 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to head box – 4 ea Contractor shall replace recalled sprinkler heads – 15 ea Contractor shall perform 5-year inspection with passing report – 1 ea
44 – EPQ 867 – 9828 Rancheria Flat Court – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace recalled sprinkler heads – 17 ea Contractor shall trouble shoot and repair audible alarm, did not activate during water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
45 – EPQ 871 – 9747 Elderberry Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace recalled sprinkler heads – 11 ea Contractor shall trouble shoot and repair horn strobes, did not activate during water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
46 – EPQ 872 – 9743 Elderberry Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench to the head box – 1 ea Contractor shall replace recalled sprinkler heads – 11 ea Contractor shall trouble shoot and repair/replace water flow device, did not activate during water flow test – 1 ea Contractor shall perform 5-year inspection with passing report – 1 ea
47 – EPQ 873 – 9746 Elderberry Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace recalled sprinkler heads – 15 ea Contractor shall perform 5-year inspection with passing report – 1 ea
48 – EPQ 874 – 9742 Elderberry Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace recalled sprinkler heads – 16 ea Contractor shall perform 5-year inspection with passing report – 1 ea
49 – EPQ 875 – 9738 Elderberry Lane – Residential 13D Wet Pipe System Contractor shall install missing signage – Control Valve and Test/Drain – 2 ea Contractor shall replace out-of-date gauge – 1 ea Contractor shall add appropriate wrench and heads to the head box – 4 ea Contractor shall replace recalled sprinkler heads – 15 ea Contractor shall perform 5-year inspection with passing report – 1 ea
50 – EPB 755 – Roads Shop – 5083 Foresta Road – Commercial 13 Dry Pipe System Contractor shall replace compressor @ welding shop – 1 ea Contractor shall perform annual inspection with passing report – 1 ea
51 – MAQ 6160 A & B – 9007 Meadowview Lane – Commercial 13 Wet Pipe System
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Contractor shall install missing signage – as needed Contractor shall add appropriate wrench to head box – 1 ea Contractor shall replace pressure reducing back-flow device (Wilkins, 2”, FEBCO825Y S/N016820) – 1 ea Contractor shall add coolant solution – up to 25 gallons Contractor shall perform 5-year inspection with passing report – 1 ea
Additional Information
HAULING RESTRICTIONS: Vehicles over 45 feet are prohibited and 1-way controlled traffic for all other vehicles 20 miles East of Mariposa (Mariposa County) 24 hours per day, seven days per week due to rockslide repairs.
ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
BEAR/ ANIMAL SAFETY: Bears and other animals are active in Yosemite and surrounding areas. It is necessary for all visitors to practice bear and animal safety. Food items are not to be left in work trucks or anywhere else.
The NPS provides bear boxes in campgrounds for food storage. Bear incidents are a ticketable offense in Yosemite.