This Performance Work Statement (PWS) details a firm fixed-price requirement for the procurement, installation, and programming of portable radio networks for two VA Medical Centers in New York (Batavia and Buffalo). The procurement includes 52 portable radios with specific technical specifications, including 43 single-band radios with features like digital trunking, GPS, emergency buttons, and Wi-Fi capabilities, and 9 advanced single-band portable radios with enhanced connectivity and touchscreen displays. Additionally, the contract covers six standalone conventional repeaters, two Radio Frequency Distribution Systems, multiple chargers, antenna systems, and related software licenses and services.

The solicitation requires comprehensive installation services adhering to multiple safety standards, including NFPA and OSHA regulations. The contractor must provide a Project Manager, System Engineer, and System Technologist to manage the implementation, with responsibilities including site evaluation, system design, programming, integration, and acceptance testing. The contract is an unrestricted solicitation under NAICS code 334220 with a small business size standard of 1,250 employees, targeting the replacement of existing Engineering Department portable radio networks at the VA Medical Centers in Western New York.

View the file

Other files

File Type Posted
P03- Brand Name Only Above SAT Buffalo Portable Radios.pdf PDF
36C24225Q1049.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B.3. PERFORMANCE WORK STATEMENT (PWS):

B.3.1. SUMMARY

A. This firm fixed-price, brand name only, requirement is for the procurement, installation, and programing of portable radios, repeaters, ancillary equipment and supplies needed to replace the existing Engineering Department portable radio networks at the Batavia VA Medical Center located at 222 Richmond Avenue, Batavia, NY 14020, and the Buffalo VA Medical Center located at 3495 Bailey Avenue, Buffalo, NY 14215.

B.3.2. GENERAL

B.3.2.1. PROCUREMENT:

A. All equipment purchased under this agreement must be interoperable with the Motorola radios currently utilized by the facilities and meet the following requirements:

a. Supply six (6) standalone conventional repeaters capable of supporting digital IP, digital V.24, analog 4-wire, mixed mode 4-wire/V.24 hybrid circuit wireline link interfaces, and sixteen (16) sets of programmable channel configurations.

b. Supply two (2) Radio Frequency Distribution Systems (RFDS) and antenna systems consisting of a three (3) channel combining/multicoupling system with necessary filtering, antennas, transmission lines, connectors, lightning arrestors, and grounding.

c. Supply forty-three (43) single-band portable radios with:

i. Digital Trunking 9600 Baud, Analog Trunking 3600 Baud.

ii. PTT button.

iii. 16-position channel selector.

iv. Power/Volume knob.

v. Emergency button.

vi. 2850 mAh Battery.

vii. Three (3) programable side buttons.

viii. Two (2) programable front buttons.

ix. SmartConnect via Wi-Fi.

x. Frequency Bands: 7/800 MHz, UHF, VHF.

xi. 2.4 in. color display screen.

xii. 512 channel capability.

xiii. 50 zone capability.

xiv. Bluetooth capability.

xv. Wi-Fi 802.11 a/b/g/n/ac, 2.4 and 5 GHz band capability.

xvi. Radio Management (RM)

xvii. Built-in GNSS (GPS, GLONASS).

xviii. Accelerometer (Man Down/Fall Alert).

xix. Adaptive dual-sided operation.

xx. Adaptive equalization.

xxi. Adaptive gain control.

xxii. Dual High Dynamic Range Microphones.

xxiii. FIPS 140-3 Level 3, FIPS 197

xxiv. IP6x Dust protection.

xxv. IPx8 Submersion protection (2 m, 2 hr).

d. Supply nine (9) single-band portable radios with:

i. Digital Trunking 9600 Baud, Analog Trunking 3600 Baud.

ii. PTT button.

iii. 16-position channel selector.

iv. Power/Volume knob.

v. Emergency button.

vi. 3200 mAh Battery.

vii. Three (3) programable side buttons.

viii. Six (6) programable front buttons.

ix. LTE SmartConnect, Multi-net Connectivity.

x. SmartZone/SmartNet Operation Capable.

xi. Frequency Bands: 7/800 MHz, UHF, VHF

xii. 3.4 in. front, touchscreen color display screen.

xiii. 1.2 in. top, color display screen.

xiv. 3,000 channel capability.

xv. 200 zone capability.

xvi. Bluetooth capability.

xvii. Wi-Fi 802.11 a/b/g/n/ac, 2.4 and 5 GHz band capability.

xviii. Customer programming software (CPS)

xix. Radio Management (RM)

xx. Radio Central Programing.

xxi. Built-in GNSS (GPS, GLONASS).

xxii. Accelerometer (Man Down/Fall Alert).

xxiii. Adaptive dual-sided operation.

xxiv. Two (2) internal HDR Microphones.

xxv. 256-bit AES Software Encryption.

xxvi. Single-key ADP Encryption.

xxvii. FIPS 140-2 Level 1 xxviii. FIPS 140-3 Level 3, FIPS 197

xxix. Multi System Over The Air Rekeying (MS OTAR).

xxx. IP6x Dust protection.

xxxi. IPx8 Submersion protection (2 m, 4 hr).

e. Supply one (1) all-band portable radio base station with:

i. Digital Trunking 9600 Baud, Analog Trunking 3600 Baud.

ii. Dedicated channel knob.

iii. Dedicated volume knob.

iv. Emergency button.

v. Five (5) programable front buttons.

vi. All-band antenna

vii. Frequency Bands: 7/800 MHz, UHF, VHF

viii. SmartZone/SmartNet Operation Capable.

ix. 3,000 channel capability.

x. Enhanced Control Head.

xi. Control Station desktop microphone.

xii. Bluetooth capability.

xiii. Customer programming software (CPS)

xiv. Radio Management (RM)

xv. Radio Central Programing.

xvi. Built-in GNSS (GPS, GLONASS).

xvii. FIPS 140-3 Level 3, FIPS 197

f. Supply seven (7) Multi-Unit Desktop portable radio chargers.

g. Supply nine (9) Single-Unit Desktop portable radio chargers.

h. Supply two (2) properly sized storage rack assemblies to house all necessary RFDS equipment.

i. Supply two (2) 60 A, 120 Vac, Power Distribution Units (PDU) with breakers and power strips.

j. Supply all required ancillary equipment, hardware, and materials needed to ensure proper installation and operation of the portable radio networks.

Table 1 – Product Summary (Including Software, Licenses)

Item #
Description
Qty
H15XDF9PW6AN
APX N30 UHF MODEL 2 PORTABLE RADIO
43
QA02756AB
TRUNKNG BAUD SINGLE SYSTEM (ADD-ON)
43
QA01843AR
FALL ALERT / MANDOWN (ADD-ON)
52
PMPN4594A
CHGR DESKTOP MULTI UNIT
7
H35XDT9PW8AN
APX N70 UHF MODEL 4.5 PORTABLE RADIO
9
H499KC
ENH: SUBMERSIBLE (DELTA T)
9
H38DA
ADD: SMARTZONE OPERATION.
9
Q806CH
ADD: ASTRO DIGITAL CAI OPERATION.
9
Q361CD
ADD: P25 9600 BAUD TRUNKING.
9
Q15AK
ADD: AES/DES-XL/DES-OFB ENCRYPTION & ADP
9
PMPN4604A
CHARGER, DESKTOP SINGLE UNIT IMPRES 2 FAST
9
PMKN4265A
RADIO DATA CABLE.
1
STANDALONE
ANTENNA SYSTEM
2
T7039
GTR 8000 BASE CONVENTIONAL REPEATERS
6
M37TSS9PW1 N
MOBILE RADIO APX8500 ALL BAND MP.
1
W665
ADD: BASE STATION OP APX.
1
G91
ADD: CNTRL STATION PWR SUPPLY.
1
GA01513
ADD: ALL BAND MOBILE ANTENNA (7/8/V/U).
1
G66BN
ADD: DASH MOUNT E5.
1
G51
SOFTWARE LICENSE ENH:SMARTZONE.
1
G806
SW LICENSE ENH: ASTRO DIG CAI OP APX.
1
GA01670
ADD: APX E5 CONTROL HEAD.
1
G361
SW LICENSE ENH: P25 TRUNKING SW APX.
1
W382
ADD: CONTROL STATION DESK GCAI MIC.
1
HKN6184C
MOBILE RADIO USB PROGRAMMING CABLE.
1

B.3.2.2. SERVICES:

Table 2 – Services Summary

Brief Description of Service

Qty (Months)

LSV01S03082A
RADIOCENTRAL PROGRAMMING.
12
SSV01S01406A
APX NEXT SMARTCONNECT SUBSCRIPTION.
12
INSTALLATION & PROGRAMMING
1
POJECT MANAGEMENT, SYSTEM TECHNOLOGIST
1

A. All services performed under this procurement shall comply with the requirements of the latest edition of:

1. National Fire Protection Association (NFPA) 70 – National Electric Code, 2023 Edition.

2. NFPA 70E – Standard for Electrical Safety in the Workplace, 2024 Edition.

3. NFPA 99 – Health Care Facilities Code, 2024 Edition.

4. NFPA 101 – Life Safety Code, 2024 Edition.

5. Occupational Safety & Health Administration (OSHA) Title 29, Code of Federal Regulations (CFR), Part 1910 Subpart J – The Control of Hazardous Energy (lockout/tagout) (1910.147).

6. OSHA Safety and Health Regulations for Construction Title 29, CFR Part 1926, Subpart K – Electrical (1926.400-1926.449).

7. Veterans Affairs Western New York Healthcare System (VAWNYHS) Medical Center Policy (MCP) 138-15 – Electrical Safety Program.

8. VAWNYHS MCP 00-190 – Control of Hazardous Energy Program.

B. Should a conflict arise between VA requirements and nationally recognized codes and standards, the conflict shall be brought to the attention of the VA. The resolution of conflict must be made by the VA Authority Having Jurisdiction (AHJ).

C. In the event of a conflict between the text of this document and nationally recognized codes and standards, the nationally recognized codes and standards takes precedence.

D. Nothing in this document supersedes applicable laws and regulations unless a specific exemption has been obtained.

E. The selection, assignment, and management of Contractor’s employees are the responsibility of the Contractor. The Contactor shall not employ any individual identified as a potential threat to the health, safety, security, and general wellbeing, or operation of the VAMC or its customers and personnel. The Contractor is fully responsible for the performance and conduct of their employees while on VAMC property. The Contractor shall not allow any employee to perform work under this contract while under the influence of alcohol, drugs, incapacitating agent or illness.

F. Should the need arise, VAWNY Electrical staff shall perform the means of disconnecting and reconnecting the electrical power supply for the equipment being installed.

G. The Contractor shall perform a site evaluation of the system installation locations.

H. The Contractor shall develop a system fleetmap to understand the operational requirements and document effective system user groups.

I. The Contractor shall provide a Project Manager (PM) to serve as the single point of contact (POC) for all system activities and issues and will be responsible for coordinating team resources. The PM shall ensure contract obligations are addressed efficiently, timely, and in a professional manner with minimal impact on the current radio network operations.

J. The Contractor shall provide a System Engineer (SE) who will be responsible for the technical design of the contracted system. The SE will gather and validate the requirements to finalize the design of the system ensuring it meets all VA requirements. The SE shall provide system design documentation, resolution of any technical issues, and system support during implementation and testing.

K. The Contractor shall supply all labor, parts, and materials required to install the portal radio networks covered under this agreement.

L. The Contractor shall uninstall and remove existing system antennas, cables, and equipment, as required and in accordance with the implementation and cutover plans. Uninstalled equipment will be delivered to the Government for disposal.

M. The Contractor shall provide “as-installed” documentation of the system upon completion.

N. The Contractor shall supply and utilize all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely in accordance with OSHA Standard 29 CFR 1910.335. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E.

O. The Contractor shall provide a System Technologist (ST) to finalize the system implementation to include in-field programming, system configuration, integration, and acceptance testing.

P. The VA agrees to provide the Contractor free access to all equipment necessary to conduct work, and free access to all rooms or areas housing such.

Q. At any time, the Contracting Officer’s Representative (COR) may deem any tool, technician, or method unacceptable based on the authority of inspection/acceptance of services.

B.3.3. CONTRACTOR QUALIFICATIONS:

A. All Contractor employees shall readily have access to the Codes, Directives, Manuals, Policies, Specifications, and Standards listed under Section B.3.2.A of this solicitation.

B. Contractor employees performing work on the equipment covered under this agreement shall be fully trained and certified by the OEM(s) to perform such tasks.

C. All Contractor technicians working on-site shall have completed an OSHA approved 10-hour construction safety training course.

D. All Contractor supervisors working on-site shall have completed an OSHA approved 30-hour construction safety training course.

B.3.4. SAFETY:

A. In the performance of this contract, the contractor shall take all precautions necessary to protect persons and property from injury or damage.

B. The COR or designee shall notify the Contractor of any safety issues and the action necessary to correct the issues. Such Notice, when served to the Contractor or their representative at the work site shall be deemed sufficient for the corrective actions to be taken.

C. If the Contractor fails or refuses to comply promptly with notified safety deficiencies, the Contracting Officer may issue an order stopping all or part of the work and hold the Contractor in default.

D. Work being performed inside the facility may require infection control measures. This may include negative pressure equipment and isolation barriers. Should infection control measures be required the Contractor shall be responsible for installation and removal of these measures and shall meet with the COR and Infection Control Department to determine specific needs for each task.

E. All work areas must be clean at the close of the day and shall be left in the same condition as before work started. No tools or equipment shall be left unattended.

B.3.5. SCHEDULE:

A. The following are Federal Holidays observed by the VA and the Contractor shall not expect access to VA facilities or VA staff on these dates unless notified otherwise by the COR. Preventive maintenance or other services are not to be scheduled on these dates:

1. New Year’s Day

2. Martin Luther King, Jr. Day

3. Washington’s Birthday

4. Memorial Day

5. Juneteenth

6. Independence Day

7. Labor Day

8. Columbus Day

9. Veteran’s Day

10. Thanksgiving Day

11. Christmas Day

B.3.10. RECORDS MANAGEMENT:

A. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.

B. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

C. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.

D. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

E. The Government Agency owns the rights to all data/records produced as part of this contract.

F. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

G. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format (paper, electronic, etc.) or mode of transmission (email, fax, etc.) or state of completion (draft, final, etc.).

H. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.

I. Contractor is required to obtain the Contracting Officer’s approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.

B.3.11. IDENTIFICATION, PARKING, SMOKING, AND VAMC REGULATIONS/KEY CONTROL:

A. All Contractor employees who have access to VA facilities are subject to the same level of investigation as VA employees. Security and badging process to be determined by COR. Contractor employees shall wear visible identification at all times while on the premises of the VAMC.

B. It is the responsibility of the vendor to park in the appropriate designated parking areas. Information on parking is available from the VA Police. The VAMC will not invalidate or make reimbursement of parking violations of the Contractor under any conditions.

C. Smoking is prohibited on VAMC property to include inside privately owned vehicles (POV) parked on VAMC property. Smoking shall only be allowed off VAMC property.

D. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

E. The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.

F. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of rekeying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.

B.3.12. INVOICES:

A. All invoices shall be submitted upon completion of respective service and submission of reports to the COR.

B. Invoices shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.

C. Invoices must include, at minimum, the following information:

1. Contractor Name,

2. Contract Number,

3. Current Purchase Order Number,

4. Date(s) of Service,

5. Itemized Charges.

6. Contract Line-Item Number (CLIN)

B.3.13. QUALITY ASSURANCE:

A. The Government may inspect each task as completed.

B. The Contractor shall be notified within 3 duty days of unacceptable service.

C. The Contractor shall re-perform service within 15 duty days of notification of unacceptable service.

D. The COR or designee will verify that the equipment is working within manufacturer’s specifications after completion of service or repair.