SOW-VESSEL AIR COMPRESSOR AND DEHYDRATOR INSPECTION-USS OHIO.docx
DOCX document 57 KB Posted
- Attached to
- USS OHIO HPAC, HPAD, LPAC, LPAD
- Solicitation number
- Not on record
- Issued by
-
Department of Defense
About this file
This is a Statement of Work (SOW) for a naval vessel maintenance contract at Puget Sound Naval Shipyard and Intermediate Maintenance Facility. The scope involves a comprehensive operational inspection and repair of high and low pressure air compressors and dehydrators for the USS Ohio, specifically targeting No. 1, No. 2, and No. 3 High Pressure Air Compressors (HPAC), No. 1 and No. 2 High Pressure Air Dehydrators (HPAD), Low Pressure Air Compressor (LPAC), and Low Pressure Air Dehydrator (LPAD).
The contract is intended to be a sole-source firm fixed price award to Curtis Wright Electro-Mechanical Corporation, with a performance period from November 2025 to December 2025. The work will be conducted in Guam and requires extensive technical inspections, replacements, and operational testing of complex air compression and dehydration equipment. The government will provide specific replacement parts and materials, and the contractor must adhere to strict naval technical manuals, safety protocols, and reporting requirements, including submitting condition found reports and acceptance test reports within 24 hours of completing each phase of work. Interested parties may identify their capabilities by responding no later than October 10, 2025, at 12:00 PM PST, though the government retains discretion on whether to conduct a competitive procurement.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
VESSEL AIR COMPRESSOR AND DEHYDRATOR INSPECTION, REPAIRS AND TESTING
1. BACKGROUND & GENERAL REQUIREMENTS: Vessel high and low pressure air compressors and dehydrators have exceeded normal run hours resulting in equipment failure. Require OEM conduct operational inspection and conduct repairs to No. 1, No. 2 and No. 3 High Pressure Air Compressors (HPAC); No. 1 and No. 2 High Pressure Air Dehydrators (HPAD); Low Pressure Air Compressor (LPAC) and Low Pressure Air Dehydrator (LPAD).
1.1. Scope: Accomplish operational inspection and repairs to No. 1, No. 2 and No. 3 High Pressure Air Compressors (HPAC), No. 1 and No. 2 High Pressure Air Dehydrator (HPAD), Low Pressure Air Compressor (LPAC), and Low Pressure Air Dehydrator (LPAD).
2. REFERENCES:
| 2.1. | COMUSFLTFORCOMINST 4790.3 - Joint Fleet Maintenance Manual | |
| 2.2. | NAVSEA S0400-AD-URM-010/TUM – Tag-out User’s Manual | |
| 2.3. | NAVSEA 389-0288, Radiological Requirements | |
| 2.4. | Northwest Regional Maintenance Center (NWRMC) Local Standard Items | |
| 2.5. | NAVSEA Technical Manual – S6220-AT-MMA-A10 Rev 00 / Chg D (HPAC) - High Pressure Air Compressor (HPAC) | |
| 2.6. | SUBMEPP Maintenance Standard – 5510-081-021 Rev E / Chg 3, Perform minor overhaul of high pressure air compressor | |
| 2.7. | NAVSEA Technical Manual – S9551-CY-MMA-010 Rev 00 / Chg - (HPAD)– High Pressure Air Dehydrator (HPAD) | |
| 2.8. | SUBMEPP Maintenance Standard – 5510-081-054 Rev A / Chg 6, Overhaul high pressure air dehydrator | |
| 2.9. | NAVSEA Technical Manual – S6220-AN-MMA-010 Rev 02 / Chg J (LPAC)-LOW PRESSURE AIR COMPRESSOR MD-663C | |
| 2.10. | SUBMEPP Maintenance Standard – 5510-081-080 Rev D / Chg 19, Restore low pressure air compressor. | |
| 2.11. | NAVSEA Technical Manual – S9551-BX-MMA-010 Rev 01 / Chg G (LPAD)-DEHYDRATOR ASSEMBLY, AUTOMATIC LOW PRESSURE AIR, TYPE III, Model Number 10300-60-2 | |
| 2.12. | SUBMEPP Maintenance Standard – 5510-081-057 Rev B / Chg 3, Overhaul service air dryer assembly | |
| 2.13. | STR-4P37- Supplementary Technical Requirement (Cleanliness requirements for hardware) |
3. WORK REQUIREMENTS:
3.1. Period of Performance: 11/14/2025 – 12/29/2025
3.2. Location of Work: Guam
3.3. All mandatory replacement materials required to complete maintenance and testing to be as identified in Equipment Guide Lists of 2.6, 2.8, 2.10, and 2.12. Replace with Original Equipment Manufacturers (OEM) repair standard parts.
3.4. Attend an arrival and safety brief with Project Team and Contracting Officer’s Representative (COR), for all contractor and subcontractor employees, upon arrival.
3.5. Restricted Data: Contractor employees require access to and control of RESTRICTED DATA (RD), regarding Naval Nuclear Propulsion Information (NNPI and U-NNPI), to accomplish the requirements of this contract. Safeguarding of NNPI and U-NNPI shall be per the requirements of OPNAVINST N9210.3 (current revision). Contractor employees will require access to the aft engine room compartment to conduct maintenance and modernization to systems and equipment identified in NAVSEAINST N9210.4 (current revision).
3.6. Coordinate delivery and shipment of Contractor equipment and supplies with the
COR: *****
Government Delivery and Shipping Address:
PSNS DETACHMENT N62505 SUB REFIT SITE III
APRA HARBOR GU 96915-1080
ATTN: Project Material Manager
3.7. Work Controls
3.7.1. Ship’s Force will ensure work authorization requirements of 2.1 and 2.2, and any local instructions are met in support of work, including preparation and execution of Work Authorization Forms (WAFs), isolation of work site (tag-out), and coordination in regards to WAFs and tag-outs.
3.7.2. Coordinate with Ship’s Force to clearly define work boundaries to ensure entire work site is isolated per 2.1 and 2.2.
3.8. Environmental and Safety Concerns
3.8.1. OSHA requires the use of personal protective equipment, such as hard hats, safety eyeglasses, safety shoes, and hearing protection.
3.8.2. The Contractor shall comply with all current environmental, health, safety, and hazardous waste requirements, applicable federal, state and local laws, codes, ordinances, and regulations.
3.8.3. The Contractor shall cooperate with each environmental, health, safety, and accident/mishap investigation.
3.9. Security Requirements
3.9.1. Base access to Polaris Point Naval Station, Guam shall be submitted by “Base Access Request”.
3.9.2. Security POC for Guam: M-gu-css-15-intel_comms@fe.navy.mil (Security POC Email) COMSUBRON FIFTEEN N2/N6, Security Manager/SSO/NACO/IAM, GENSER SMO: N437095, SCI SMO: N437093, Comm/DSN (671/315) 343-4029, VOIP 989-4030, Cell (671) 777-9396.
3.9.3. All references and deliverable items associated with this task are unclassified, but restricted to U.S. Citizens only (NOFORN).
3.9.4. Contractors will require access to space(s): Engine Room
3.9.5. If a Contractor has a past gross misdemeanor or felony in the past ten years, he/she may not be granted access.
3.9.6. Contractor electronic devices, including cell phones and computers shall not be capable of photography or digital recording.
3.10. Radiological Requirements:
3.10.1. Radiological Requirements: Contractor shall not accomplish work in areas that require personal monitoring of radiation, i.e. wearing a Thermoluminescent-Dosimeter (TLD) per the requirements of 2.3.
3.10.2. Planning, supervising, or performing nuclear work is not authorized without the express approval of Code 300N, Code 1200N, Code 2300, and Code 105.
3.11. Point of Contact: Contracting Officers Representative, located in the contract.
3.11.1. All technical clarifications will be coordinated through the Contracting Officer’s Representative (COR).
3.12. TECHNICAL REQUIREMENT:
3.12.1. Comply with the requirements of 099-12NW of 2.4.
3.12.2. Coordinate with Ship’s Force personnel to provide continuous operator training during inspection and repair sequences.
3.12.3. Accomplish preliminary inspection/inventory and record TRIPER Serial Number of three HPACs, two HPADs, LPAC and LPAD of 2.5 through 2.12 and OEM specifications.
3.12.3.1. Submit one legible copy, in approved transferrable media, a condition found report (CFR) of the inspection results, including any missing or damaged parts, to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the inspection. COR will forward to requirement generator. (CDRL A001, DI-MGMT-81648)
3.12.4. Accomplish the following repairs to each of the HPACs per the requirements of 2.5 and OEM specifications. Ensure cleanliness requirements are maintained during the following repairs per 2.13;
3.12.4.1. Inspect, clean, and replace O-rings inter-stage condensate separators and piping connections per paragraph 4-4-3-8 of 2.5.
3.12.4.2. Replace tube oil filter and clean crankcase oil vapor breather per paragraph 4-4-4-3 and 4-4-4-4 of 2.5.
3.12.4.3. Clean and flush silencer per paragraph 4-4-3-6-1 of 2.5.
3.12.4.4. Drain and replace crankcase oil per paragraph 4-4-4-1 of 2.5.
3.12.4.5. Remove, inspect, clean, and reseat release pressure of air relief valves per paragraph 4-4-3-6-5 of 2.5.
3.12.4.6. Dismantle, clean and inspect air valves for all stages per paragraph 4-4-3-5 of 2.5.
3.12.4.7. Replace 3rd stage valves per paragraph 4-4-3-5-2 of 2.5.
3.12.4.8. Replace 4th and 5th stage valves per paragraph 4-4-3-5-3 of 2.5.
3.12.4.9. Remove and clean 4th and 5th stage cylinders and inspect liners per paragraphs 4-4-3-1-2 and 4-4-3-1-3 of 2.5.
3.12.4.10. Remove and clean 4th and 5th stage pistons per paragraph 4-4-3-2-4 of 2.5.
3.12.4.11. Inspect 1st and 2nd stage piston rings per paragraphs 4-4-3-2-1 and 4-4-3-2- 2 of 2.5.
3.12.4.12. Inspect 1st stage cylinder liner per paragraph 4-4-3-1-1 of 2.5.
3.12.4.13. Inspect 2nd stage cylinder liner per paragraph 4-4-3-1-2 of 2.5.
3.12.4.14. Replace 3rd stage piston rings per paragraph 4-4-3-2-3 of 2.5.
3.12.4.15. Replace 3rd stage piston cylinder liner per paragraph 4-4-3-1-3 of 2.5.
3.12.4.16. Replace 4th and 5th stage sleeve seals, followers and guides per paragraph 4-4-3-2-4 of 2.5.
3.12.4.17. Replace 2nd and 3rd stage piston rod packing’s per paragraph 4-4-3-3 of 2.5.
3.12.4.18. Drain, dismantle and clean cooling water sight flow indicators and relief valves per paragraphs 4-4-5-6 and 4-4-5-5 of 2.5.
3.12.4.19. Clean and inspect main drive motor and re-grease bearing per Table 4-1-2 of 2.5.
3.12.4.20. Inspect and adjust back pressure valve per paragraph 4-4-3-6-4 of 2.5.
3.12.4.21. Inspect, clean and test Control Management System wiring harnesses and connectors shown on FO-23 of 2.5.
3.12.4.22. Inspect, clean, and run system diagnostics on Control Management System and PLC and adjust for optimum performance.
3.12.4.23. Inspect and test all solenoid actuated, pilot operated drain valve assemblies.
Test the drain system for proper operation ensuring unobstructed flow and no union or fitting leakage.
3.12.4.24. Inspect pressure transducers and temperature sensors.
(V) (G) CHECK POINT “OPERATIONAL TEST” of No. 1, 2, and 3 HPACs: Comment by Guerrero, Gabrielle M CIV USN NAVSHIPYDIMF PGS WA (USA): m
3.12.4.25. Conduct post maintenance operational test per paragraph 1.m. of 2.6.
3.12.4.26. Accomplish additional minor repairs of HPACs to correct air, oil, water leaks, and electrical discrepancies.
3.12.4.27. Submit one legible copy, in approved transferrable media, of an acceptance test report (ATR) of the inspection results, identification of any repaired or replaced parts, and test results to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the work and testing. (CDRL A002 & DI-QCIC-81891)
3.12.5. Accomplish the following repairs to each of the HPAD(s) per the requirements of 2.7 and OEM specifications. Ensure cleanliness requirements are maintained during the following repairs per 2.13.
3.12.5.1. Clean and inspect After Filter assembly per paragraph 1.k. of 2.8.
3.12.5.2. Replace filter assemblies failing inspection per paragraph 6-55 of 2.7.
3.12.5.3. Replace Pre-Filter per paragraph 6-51 of 2.7.
3.12.5.4. Inspect Tower Assemblies, remove existing desiccant and replace with new per paragraph 6-41 of 2.7.
3.12.5.5. Replace Flow Valves FV-1 and FV-2 per paragraph 6-18 of 2.7.
3.12.5.6. Replace Flow Valves FV-3 and FV-4 per paragraph 6-19 of 2.7.
3.12.5.7. Replace Vent Valves VV-1 and VV-2 per paragraph 6-17 of 2.7.
3.12.5.8. Replace Check Valves CV-2 and CV-3 per paragraph 6-56 of 2.7.
3.12.5.9. Replace Check Valves CV-4 and CV-5 per paragraph 6-62 of 2.7.
3.12.5.10. Inspect electrical enclosure per paragraph 1.m. of 2.8.
3.12.5.11. Inspect heater assembly per paragraph 1.r. of 2.8.
3.12.5.12. Inspect relief/solenoid valve per paragraph 1.l. of 2.8.
(V) (G) CHECK POINT “OPERATIONAL TEST” of No. 1, and 2 HPADs:
3.12.5.13. Conduct post maintenance operational test per paragraph 1.al. of 2.8.
3.12.5.14. Accomplish additional minor repairs of HPADs to correct air, oil, water leaks, and electrical discrepancies.
3.12.5.15. Submit one legible copy, in approved transferrable media, of an acceptance test report (ATR) of the inspection results, identification of any repaired or replaced parts, and test results to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the work and testing. (CDRL A002 & DI-QCIC-81891)
3.12.6. Accomplish the following repairs to the LPACs per the requirements of 2.9 and OEM specifications. Ensure cleanliness requirements are maintained during the following repairs per 2.13;
3.12.6.1. Drain and flush Separator Tank, per paragraph 4-17 of 2.9.
3.12.6.2. Clean and inspect Seal Water Strainer per paragraph 4-19 of 2.9.
3.12.6.3. Clean, flush with fresh water, and inspect Filter-Silencer element per paragraph 4-22 of 2.9.
3.12.6.3.1. Submit one legible copy, in approved transferrable media, a condition found report (CFR) of the inspection results, including any missing or damaged parts, to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the inspection. COR will forward to requirement generator. If cleanliness cannot be met, contractor will submit a CFR to the COR. (CDRL A001, DI-MGMT-81648)
3.12.6.4. Clean and inspect Check Valves per paragraph 4-16 of 2.9.
3.12.6.5. Clean and inspect Automatic Drain Trap of 2.9.
3.12.6.6. Clean and inspect Flow Control Valve. Acceptance Criteria - Nozzle should be tight with minimal erosion of 2.9.
3.12.6.6.1. Submit one legible copy, in approved transferrable media, a condition found report (CFR) of the inspection results, including any missing or damaged parts, to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the inspection. COR will forward to requirement generator. (CDRL A001, DI-MGMT-81648)
3.12.6.7. Inspect orifice plates per paragraph 1.r. of 2.10.
3.12.6.7.1. Submit one legible copy, in approved transferrable media, a condition found report (CFR) of the inspection results, including any missing or damaged parts, to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the inspection. COR will forward to requirement generator. (CDRL A001, DI-MGMT-81648)
3.12.6.8. Inspect gage glass fitting and glass per paragraphs 1.u. and 1.v. of 2.10.
(V) (G) CHECK POINT “OPERATIONAL TEST” on LPAC:
3.12.6.9. Conduct post maintenance operational test per paragraph 1.ar. of 2.10.
3.12.6.10. Accomplish additional minor repairs on LPAC to correct air, oil, water leaks, and electrical discrepancies.
3.12.6.11. Submit one legible copy, in approved transferrable media, of an acceptance test report (ATR) of the inspection results, identification of any repaired or replaced parts, and test results to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the work and testing. (CDRL A002 & DI-QCIC-81891)
3.12.7. Accomplish the following on Low Pressure Air Dehydrator in accordance with the requirements of 2.11 unless otherwise indicated below. Ensure cleanliness requirements are maintained during the following repairs per 2.13;
3.12.7.1. Replace Pre-Filter Cartridges per paragraph 4-8 of 2.11.
3.12.7.2. Clean and inspect silencer per paragraph 4-9 of 2.11.
3.12.7.3. Inspect Selector Valve per paragraph 4-10 of 2.11.
3.12.7.4. Inspect refrigeration system.
3.12.7.4.1. Clean and inspect Condenser per paragraph 1.m. of 2.12.
3.12.7.4.2. Inspect hot gas bypass valve and accumulator per paragraph 1.n. of 2.12.
3.12.7.4.3. Inspect thermostatic expansion valve per paragraph 1.o. of 2.12.
3.12.7.4.4. Inspect refrigerant distributor per paragraph 1.p. of 2.12.
3.12.7.5. Inspect temperature sensing element, thermos-switch and flow switch per paragraph 1.s. of 2.12.
3.12.7.6. Replace desiccant per paragraph 4-11 of 2.11.
3.12.7.7. Inspect immersion heater per paragraph 1.d.(2) of 2.12. (See Note 4.1)
3.12.7.7.1. If heating elements are replaced they should be baked at operating temperature for 12 hours, and checked for shorts prior to installation.
3.12.7.8. Inspect purge air check valves per paragraph 1.e. of 2.12
3.12.7.9. Replace After-Filter element, after each tower completes one generation cycle, following desiccant replacement per paragraph 4-14 of 2.11.
3.12.7.10. Clean and inspect Control Panel per OEM’s specifications.
3.12.7.11. Clean and inspect Tower Swing Check Valves per paragraph 1.h. of 2.12.
3.12.7.11.1. Submit one legible copy, in approved transferrable media, a Condition Found Report (CFR) of the inspection results, including any missing or damaged parts, to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the inspection. COR will forward to requirement generator. (CDRL A001, DI-MGMT-81648)
3.12.7.12. Test automatic dump valve for proper operation.
3.12.7.13. Inspect fan per paragraph 1.u. of 2.12.
3.12.7.14. Inspect motor per paragraph 1.v. of 2.12.
3.12.7.15. Perform electrical test per paragraph 1.ag. of 2.12.
(V) (G) CHECK POINT “OPERATIONAL TEST” on LPAD:
3.12.7.16. Conduct post maintenance operational test per paragraph 1.ah. of 2.12.
3.12.7.17. Accomplish additional minor repairs of LPAD to correct air, oil, water leaks, and electrical discrepancies.
3.12.7.18. Submit one legible copy, in approved transferrable media, of an acceptance test report (ATR) of the inspection results, identification of any repaired or replaced parts, and test results to the Contracting Officer’s Representative (COR) for each piece of equipment inspected within 24 hours of completing the work and testing. (CDRL A002 & DI-QCIC-81891)
4. GOVERNMENT FURNISHED MATERIAL/SERVICES/PROPERTY:
4.1. Government provided services:
4.1.1. HAZMAT/ HAZWASTE disposal.
4.1.2. Remove, dispose, and replenish all required fluids.
4.1.3. Paint equipment.
4.1.4. Forklift, crane and rigging services as required
4.2. Government will supply the following:
| Detail Dwg/Rev/PC |
| Description |
| NIIN |
| Act Qty |
| UI |
10262-10/M/17 10278-8/E/2
| DESICCANT,ACTIVATED, FOR USE IN HPAD/LPAD ***AUL EXEMPT - ARTICLE DESICCANT (DEHUMIDIFIER) PACKETS, VOLATILE CORROSION INHIBITORS (E.G. VCI-111 EMITTERS) ANY SIZE*** |
| 00-738-1672 |
| 1 |
| DR |
| PL10101-11/N/52 |
| VALVE, 1/8" CARTRIDGE VV1, VV2, RTV1, RTV2 & RTV3 W/O HANDLE |
| 01-188-1285 |
| 10 |
| EA |
| PL10101-11/N/50 |
| VALVE, 1/4" CARTRIDGE FV3 & FV4 W/O HANDLE |
| 00-355-7688 |
| 4 |
| EA |
| PL10101-11/N/51 |
| VALVE,GLOBE, VALVE,GLOBE 3/8" IPS FV1 & FV2 |
| 01-218-1904 |
| 4 |
| EA |
| PL10101-11/N/103 |
| PACKING, O-RING SIZE-012, 90 DUROMETER 0.364" ID X .070" ROUND CROSS SECTION, -30/+500 DEG F |
| 00-166-1084 |
| 20 |
| EA |
| PL10101-11/N/104 |
| O-RING, O-RING SIZE-120, 90 DUROMETER |
| 01-106-0942 |
| 20 |
| EA |
| PL10101-11/N/169 |
| RETAINER, RING, PN PRP2103-120 |
| 00-376-8653 |
| 10 |
| EA |
| PL10101-11/N/106 |
| PACKING,, PACKING, PREFORMED RBR, SIZE -014, 90 DUROMETER |
| 00-166-1086 |
| 8 |
| EA |
| PL10101-11/N/107 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE-216, 90 DUROMETER |
| 00-166-1110 |
| 8 |
| EA |
| PL10101-11/N/168 |
| RETAINER, PACKING, RETAINER, PACKING |
| 01-066-3936 |
| 4 |
| EA |
| PL10101-11/N/102 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE-114, 90 DUROMETER |
| 01-133-9790 |
| 22 |
| EA |
| PL10101-11/N/167 |
| RETAINER,PACKING, RETAINER, PACKING |
| 00-582-1536 |
| 1 |
| PG |
| PL10101-11/N/100 |
| O-RING, O-RING, SIZE -920, 90 DUROMETER |
| 01-024-2512 |
| 4 |
| EA |
| PL10101-11/N/101 |
| PACKING, PREFORMED R, PACKING, PREFORMED RBR, SIZE-218, 90 DUROMETER |
| 01-106-7288 |
| 4 |
| EA |
| PL10101-11/N/114 |
| PACKING, PREFORMED, PACKING, PREFORMED RBR, SIZE-210, 90 DUROMETER |
| 01-127-0971 |
| 22 |
| EA |
| PL10101-11/N/90 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE-908, 90 DUROMETER |
| 00-167-5173 |
| 16 |
| EA |
| PL10101-11/N/57 |
| FILTER ELEMENT,FLUI, FILTER ELEMENT,FLUID 5 MICRON NOM. 18 MICRON ABS. |
| 01-038-7413 |
| 4 |
| EA |
| PL10101-11/N/48 |
| VALVE,CHECK, VALVE,CHECK CV4 & CV5 |
| 01-091-5538 |
| 4 |
| EA |
| PL10101-11/N/109 |
| SEAL, O-RING O.D.V. |
| 01-121-1248 |
| 4 |
| EA |
| PL10101-11/N/108 |
| SEAL, O-RING I.D.V |
| 01-117-4730 |
| 4 |
| EA |
| PL10101-11/N/49 |
| VALVE,SAFETY RELIEF, VALVE,SAFETY RELIEF CV2 & CV3 |
| 01-090-9654 |
| 4 |
| EA |
| PL10101-11/N/112 |
| SEAL, SEAL SAFETY CHECK VALVE GASKET O.D.V. |
| 01-117-4731 |
| 6 |
| EA |
| PL10101-11/N/113 |
| GASKET, GASKET SAFETY CHECK VALVE GASKET I.D.V. |
| 01-143-9723 |
| 8 |
| EA |
| PL10101-11/N/111 |
| SEAL RING METAL, BOSS SEAL |
| 01-091-7651 |
| 2 |
| EA |
| PL10101-11/N/47 |
| CARTRIDGE,SHUT-OFF, NEEDLE VALVE PV |
| 01-091-4360 |
| 2 |
| EA |
| 10262-10/M/5 |
| RING AND ROD ASSEMB, P/N: 6455-2 |
| 01-204-8040 |
| 4 |
| EA |
| 10262-10/M/9 |
| RETAINER,PACKING, P/N: 8-343N300-90 |
| 00-003-5490 |
| 4 |
| EA |
| 10262-10/M/8 |
| O-RING, SIZE -343, 90 DUROMETER |
| 01-212-4624 |
| 4 |
| EA |
| 10262-10/M/13 |
| PACKING, O-RING 0.755" ID X .097" ROUND CROSS SECTION, -30/+500 DEG F SIZE -910, 90 DUROMETER |
| 00-167-5174 |
| 8 |
| EA |
| 10262-10/M/16 |
| O-RING, SIZE -244, 90 DUROMETER |
| 01-043-1904 |
| 4 |
| EA |
| 10262-10/M/2 |
| FILTERING DISK,FLUI, ASSY P/N: 10122-3 |
| 01-130-5391 |
| 4 |
| EA |
| 10262-10/M/18 |
| FILTER ASSEMBLY, LOWER P/N: 10122-13 |
| 01-138-0337 |
| 4 |
| EA |
| 10320-5/E/6 |
| FILTER ELEMENT, PRE-FILTER ASSEMBLY FOR #1 AND #2 HPAD |
| 01-108-2589 |
| 2 |
| EA |
| 10320-5/E/7 |
| O-RING, SIZE-038, 90 DUROMETER |
| 01-148-2691 |
| 2 |
| EA |
| 10320-5/E/8 |
| O-RING, SIZE-327, 90 DUROMETER |
| 01-289-3214 |
| 2 |
| EA |
| 10320-5/E/NONE |
| CARTRIDGE,VALVE,CHE, VALVE, CHECK |
| 01-118-2633 |
| 2 |
| EA |
| 10320-5/E/9 |
| RETAINER,PACKING, BACKUP RING -038 |
| 00-003-5491 |
| 2 |
| EA |
| 10320-5/E/10 |
| RETAINER,PACKING, BACKUP RING -327 |
| 00-171-5071 |
| 2 |
| EA |
| 10262-10/M/3 |
| RETAINER ASSEMBLY, PLUG ASSY |
| 01-122-4480 |
| 4 |
| EA |
| PL10101-11/N/117 |
| GASKET, FACE SEAL, I.D.V. SILVER SURFACE TREATMENT FOR #1 AND #2 HPAD |
| 01-058-5324 |
| 4 |
| EA |
| PL10101-11/N/43 |
| VALVE,GLOBE, BLOWDOWN VALVE (BDV) FOR #1 AND #2 HPAD |
| 01-126-3736 |
| 2 |
| EA |
| PL10101-11/N/87 |
| O-RING, O-RING SIZE -904, 90 DUROMETER 0.351" ID X .072" ROUND CROSS SECTION, -30/+500 DEG F |
| 00-167-5172 |
| 28 |
| EA |
| PL10101-11/N/88/89 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -906, 90 DUROMETER |
| 00-165-1981 |
| 16 |
| EA |
| PL10101-11/N/91 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -912, 90 DUROMETER |
| 00-167-5175 |
| 4 |
| EA |
| PL10101-11/N/93 |
| O-RING, O-RING SIZE -127, 90 DUROMETER |
| 00-166-1104 |
| 2 |
| EA |
| PL10101-11/N/105 |
| O-RING, SIZE -222, 90 DUROMETER FOR #1 AND #2 HPAD |
| 01-006-2129 |
| 12 |
| EA |
| PL10101-11/N/115 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -212, 90 DUROMETER |
| 00-166-1109 |
| 4 |
| EA |
| PL10101-11/N/116 |
| GASKET, FACE SEAL I.D.V. SILVER SURFACE TREATMENT FOR #1 AND #2 HPAD |
| 01-058-4590 |
| 8 |
| EA |
| PL10101-11/N/210 |
| O-RING, O-RING SIZE -127, 90 DUROMETER |
| 00-166-1104 |
| 2 |
| EA |
| 10262-10/M/10 |
| O-RING, SIZE -342, 90 DUROMETER FOR #1 AND #2 HPAD |
| 01-212-4623 |
| 8 |
| EA |
| 10300-60-2/H/59 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -916, 90 DUROMETER |
| 00-167-5176 |
| 5 |
| EA |
| 10300-60-2/H/104 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -221, 75 DUROMETER |
| 00-166-8412 |
| 2 |
| EA |
| 10300-60-2/H/160 |
| PACKING, PREFORMED, PACKING, PREFORMED, SIZE -216 75 DUROMETER |
| 00-165-1942 |
| 3 |
| EA |
| 10300-60-2/H/159 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -125, 75 DUROMETER |
| 00-322-6397 |
| 6 |
| EA |
| 10300-60-2/H/148 |
| PACKING, O-RING 0.755" ID X .097" ROUND CROSS SECTION, -30/+500 DEG F SIZE -910, 90 DUROMETER |
| 00-167-5174 |
| 2 |
| EA |
| 10300-60-2/H/103 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -012 75 DUROMETER |
| 00-166-0980 |
| 8 |
| EA |
| 10300-60-2/H/99 |
| O-RING, O-RING SIZE -904, 90 DUROMETER 0.351" ID X .072" ROUND CROSS SECTION, -30/+500 DEG F |
| 00-167-5172 |
| 4 |
| EA |
| 10300-60-2/H/98 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -010, 75 DUROMETER |
| 00-166-0969 |
| 10 |
| EA |
| 10300-60-2/H/15 |
| SWITCH,THERMOSTATIC, P/N: 1822L4-8-15, FOR LPAD OPEN @ 248 DEGREES F, CLOSE @ 221 DEGREES F |
| 01-093-8296 |
| 1 |
| EA |
| 10300-60-2/H/44 |
| VALVE,SUCTION, REFRIGERANT SERVICE P/N: 31529-1 |
| 01-091-7750 |
| 1 |
| EA |
| 10300-60-2/H/43 |
| VALVE,DISCHARGE, REFRIGERANT SERVICE |
| 01-091-7749 |
| 1 |
| EA |
| 10300-60-2/H/34 |
| VALVE,LINEAR,DIRECT, 4-WAY MANIFOLD MOUNTED |
| 01-091-1494 |
| 1 |
| EA |
| 10300-60-2/H/31 |
| VALVE, TOWER SWING CHECK, 3/4” |
P/N: 5299-003
| 00-483-0680 |
| 2 |
| EA |
| 10300-60-2/H/39 |
| FILTER-D, DRYER, REFRIGERANT |
| 00-950-6997 |
| 1 |
| EA |
| 6680-38/D/3 |
| FILTER ELEMENT, AFTER FILTER |
| 00-780-7565 |
| 3 |
| EA |
| 6680-38/D/13 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -906, 90 DUROMETER |
| 00-165-1981 |
| 1 |
| EA |
| 6680-38/D/2 |
| PACKING, PREFORMED, PACKING, PREFORMED SIZE -345 75 DUROMETER |
| 00-184-3472 |
| 1 |
| EA |
| 10278-8/E/7 |
| GASKET, 50" X 50" X 1/16" THK. |
| 01-392-2760 |
| 1 |
| SH |
| 10278-8/E/3 |
| DISK ASSEMBLY, DESICCANT TOWERS |
| 01-168-9565 |
| 2 |
| EA |
| 10340-4/C/2 |
| FILTER ELEMENT, PREFILTER |
| 00-864-7737 |
| 3 |
| EA |
| 10340-4/C/4 |
| SEAL,PLAIN, FOR PREFILTER |
| 01-311-5916 |
| 1 |
| EA |
| 10340-4/C/9 |
| GASKET, FOR PREFILTER AUTO DUMP |
| 01-094-0043 |
| 1 |
| EA |
| 10340-4/C/5 |
| VALVE ASSY, AUTO-DUMP |
| 01-101-7431 |
| 1 |
| EA |
| 15-0181/J/1-W |
| VALVE, CHECK |
| 01-301-9076 |
| 1 |
| EA |
| 15-0181/J/5-D |
| VALVE, CHECK |
| 00-451-2682 |
| 1 |
| EA |
| 15-0181/J/35 |
| ORIFICE PLATE, BRASS |
| 01-091-4069 |
| 1 |
| EA |
| 15-0181/J/47 |
| ORIFICE PLATE, BRASS |
| 01-125-5543 |
| 1 |
| EA |
| 0501-6// |
| PARTS KIT, AUTO DRAIN, PC5,7,12,19,21,22,23,&34 |
| 00-112-0079 |
| 1 |
| KT |
| GREASE,B, ROLLER BEARING |
| 00-149-1593 |
| 1 |
| CN |
| LUBE OIL, 7.75 GALLONS, PER COMPRESSOR |
| 01-370-2583 |
| 5 |
| CN |
| DICHLORODIFLUOROMETHANE, REFRIGERANT R-12, 10LB CYL |
| 00-264-9089 |
| 1 |
| CY |
| CYLINDER, COMPRESSED EMPTY R-12 BOTTLE, 42 LBS |
| 01-355-4017 |
| 1 |
| EA |
5. QUALITY ASSURANCE SURVEILLANCE PLAN:
5.1. Purpose: To ensure that the Government has an effective and systematic method of surveillance for the services in the SOW. The QASP will be used primarily as a tool to verify that the contractor is performing all services and delivery/installation of replacement parts required by the SOW in a timely, accurate and complete fashion.
6. DELIVERABLE ITEMS:
6.1. Provide deliverables as described in the Statement of Work (SOW) and as outlined for format and delivery schedule in Contract Data Requirements Lists (CDRLs):
| Number |
| Name |
| Frequency |
| Quantity |
A001 Condition Found Report one time one each
A002 Acceptance Test Report (ATR) one time one each
File details come from the government source that posted it. Updated .