This is a Statement of Work (SOW) for geotechnical evaluation, monopole tower procurement, and foundation construction supporting the GASNT Increment 2, Block 1 system at multiple military installations nationwide. The contractor must procure 100-foot monopole towers constructed of hot-dip galvanized steel per ASTM A123, capable of supporting four vertically polarized VHF/UHF dipole antennas and a universal ring mount. The towers must feature one 10x24 inch base port and two 6x12 inch top ports, with three factory-installed grounding studs at the base and one threaded lightning protection port at the top. Foundation engineering must comply strictly with ANSI/TIA-222 (Risk Category 4) and ACI 318 standards, with anchor bolt placement tolerances of +/- 1/16 inch. Conduit requirements include two 4-inch SCH 80 PVC and one 1.5-inch SCH 80 PVC foundation conduits.

The scope encompasses complete engineering design, procurement of tower components, and foundation construction activities. All work must adhere to applicable design standards and specifications outlined in the SOW. This pre-solicitation sources sought notice is issued by 577 SWES/DIFF under the Department of the Army National Guard (Solicitation Number W50S83-26-Q-0010) for market research purposes only and does not constitute a binding commitment to award a contract. Interested contractors should note that responses to this sources sought notice will not be evaluated as proposals, and the Government will not reimburse costs incurred in responding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

577 SWES/DIFF May 13, 2026

McConnell Air Force Base, KS GASNTi2 BLOCK 1 - Tower Procurement

Project: PRQE-2026-GASNTi2-01

Prepared by:

MSgt Michael Brown DIFF GASNT Engineer 13 May 2026

SECTION 1 - GENERAL INFORMATION

PLACE OF PERFORMANCE:

Site Name/Address
Tower Site: [GPS Lat Long here]
McConnell Air Force Base, Wichita, KS
37.633213°N 97.255741°W
Tinker
35.4102889, -97.3965917
Fairchild
47.631517, -117.645809
Goldwater
33.425333, -112.013023
Grissom
40.662687, -86.155182
Kirtland
35.049508°N 106.548388°W
General Mitchell
TBD

ACCESS TO THE SITE:

Work Hours The Contractors are responsible for coordinating with the Government an acceptable time and place for delivery of materials. Construction schedule will follow the Host base work schedule. Federal holidays will affect access to the site.

Utilities An approved AF Form 103 is required before beginning any work involving excavation or utility disturbance. The Government must provide at no cost the contractor with reasonable amounts of water and electricity to support the contract. Hooking up will be to existing outlets and will be the contractor’s responsibility.

POINT OF CONTACT (POC):

Contractor:

The contractor must have an active phone number or email address that can be reached during normal business hours. Contractor is responsible for coordinating with the Government an acceptable time and place for delivery of materials. Federal holidays may affect access to the site.

THE GOVERNMENT - 577 SWES/DIFF

Attempts to reach a POC below should be made in the order they are listed. The first individual listed in the table below is the primary point of contact. All remaining individuals are listed for the purpose of increasing the availability of the team.

NAME (Last, First)
E-Mail
Phone
Brown, Michael
Michael.brown.237@us.af.mil
602-302-9339
Nichols, Dean
dean.nichols@us.af.mil
845-699-5846
DeHart, Lillian
lillian.dehart@us.af.mil
316-759-3921

MILITARY BASE SECURITY AND SAFETY REQUIREMENTS:

EMERGENCY SERVICES:

Should the contractor experience a medical or fire emergency during the delivery process, the contractor must contact local 911 services. The contractor must also notify a member on the 577 SWES/DIF as soon as possible.

ID BADGE:

The contractor may be required to wear a guest ID badge while on a military base. If a military base requires the use of a guest ID badge, the contractor must abide by the rules and requirements of the base.

TRAFFIC LAWS:

Contractor employees must comply with all base traffic regulations. Contractor employees are subject to random vehicle speed control checks. Contractor personnel cited for speeding on the installation may suffer loss of base driving privileges, debarment from the base, or other administrative action.

RANDOM PERSONNEL AND VEHICLE SEARCHES:

Contractor personnel are subject to random personnel and vehicle searches. If contractor personnel refuse to be searched, they will be denied entry to the base, and may result in loss of base driving privileges, debarment from the base, or other administrative action.

WEAPONS, FIREARMS, AND AMMUNITION:

Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor owned vehicle or privately owned vehicle while on base.

REPORTING REQUIREMENTS:

Contractor personnel must immediately report to an appropriate government authority any information or circumstances of which they are aware may pose a threat to the security of Department of Defense personnel, contractor personnel, resources, and classified or unclassified defense information.

EMPLOYMENT:

The contractor must not employ person for the delivery of materials if such employee is identified to the contractor as a potential threat to the health, safety, security, general well-being or operational mission of the military base and its population. Employees of the contractor may be subject to a criminal background check and must be legally employed in the United States.

SAFETY

The contractor must comply with all applicable laws and safety regulations. Compliance with OSHA and other applicable laws and regulations for the protection of employees is exclusively the obligation of the contractor, and the government will assume no liability or responsibility for the contractor compliance or noncompliance with such responsibilities.

DELIVERY AREA

Upon delivery, the contractor must leave the delivery area in a clean, neat, safe and workmanlike condition.

EQUIPMENT AND TOOLS

Notify the government project manager prior to delivery of any material or equipment to the site. The contractor must ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, must not be accepted and turned away. All equipment and tools needed to accomplish the delivery of materials must conform to applicable federal, state and local safety requirements.

Disposal of materials and cleanup The contractor must not use any government disposal bins, dumpsters or trash receptacles for any reason at any time. The contractor must provide appropriate disposal bins/trash receptacles. Approval of disposal bins/trash receptacle’s location(s) must be coordinated through government project manager. The contractor must not allow debris to leave the work area due to potential damage to aircraft engines. Contractor must coordinate with the base Environmental Management Office (EMO) prior to disposing of any materials off base. All debris or trash must be disposed of off base. All demolition debris must be disposed of at a permitted landfill, with landfill authorization, unless other arrangements have been coordinated through the EMO. Provide proof of landfill disposal from the landfill that accepts the materials. This may be accomplished by providing the government project manager with landfill receipts; waste manifests, or weight tickets from the landfill that accepts the construction debris. Contractor must clean up after each work period and dispose of all debris at the close of each day.

CONTRACTOR PERSONNEL

QUALIFICATIONS

The contractor must ensure that affected employees have current professional certifications and/or licenses necessary before starting work. The Government reserves the right to require the contractor to furnish proof of certifications and/or licenses necessary from any employees engaged by the contractor for the accomplishment of work involved under this contract.

CONFLICT OF INTEREST:

The contractor must not employ any person who is an employee of the United States Government if employing that person would create a conflict of interest.

Materials The contractor shall not order, deliver or install any materials without the Governments approval or remove any materials on site, which have not been properly approved.

SECTION 2 – SCOPE OF WORK

1. Overview & Governing standards

Requirement
Detail
Project Objective
Perform required geotechnical evaluations for 100-foot monopole tower design.

Procure and deliver a 100-foot monopole tower and construct its supporting foundation in preparation for tower erection by others, to host the GASNT Increment 2, Block 1 system.

Primary Design Standard

ANSI/TIA-222 (latest revision at time of contract award) must serve as the governing document for all tower structural design and foundation engineering.

ANSI/TIA-222 Risk Category

Risk Category 4

Procurement and Technical Specifications

Specification
Detail
Tower Type
100-foot monopole (hot-dip galvanized steel per ASTM A123).

Pre-Procurement Approval

Submit manufacturer's final, PE-stamped tower and foundation drawings to the Government for written approval before procurement.

Payload

Support for four (4) Vertically Polarized VHF/UHF Dipole Antennas (116” L, 3.0” D, 15 lbs each). [Provided by others. Further details provided in drawings]

Payload attachments

Universal ring mount [Provided by others. Further details provided in drawings]

Payload Standoffs/mounts

Horizontal spacing: 10 feet 8 inch minimum between antennas Vertical spacing:

[Provided by others. Further details provided in drawings]

Port Configuration

One (1) 10x24 inch port (minimum size) at the bottom (base) and two (2) 6x12 inch ports (minimum size) 180° apart from each other at the mounting locations for the antennas for a total of (4) total ports at the top. Tower must have internal J Hook strain reliefs/ anchor brackets attachment points at all 4 ports of the top of the tower to support coaxial cabling.

Tower Grounding

Three (3) factory-installed grounding studs must be provided at the base of the tower

Lightning Protection Port

One (1) factory-installed threaded port for a lightning protection rod/system at the top of the tower.

Conduit Requirements

Two 4-inch SCH 80 PVC conduits, poured into the concrete base, with a minimum bend radius of 24 inches or greater. Conduits must exit the top of the base inside the pole, extend 6 inches above the top of the base, and not interfere with the mounting of the pole. The conduits must exit the base 5 feet min depth or 6 inches below the frost line and extend a minimum of 10 feet beyond the vertical edge of the base and be temporary capped to prevent ingress of debris. An additional 1.5-inch SCH 80 PVC conduit will also be installed with the same specifications as the 4-inch conduit.

Obstruction Lighting Port

A port for obstruction lighting at the top of the tower.

Climbing System

Contractor to provide a compatible Tug-Tuff cable climbing system and all necessary mounting hardware with the tower.

Step Bolts and Hardware

Step bolts and mounting hardware.

Base Construction (Foundation)

Requirement
Detail

Engineering Compliance

The foundation must be engineered in strict accordance with ANSI/TIA-222 and ACI 318 standards.

Anchor Bolts

Placement tolerance of +/- 1/16 inch, verified against the manufacturer’s provided template prior to the concrete pour.

Site Restoration

The Contractor must return the work area to its pre-construction condition, including replacing any pavements, curbs, or landscaping that were cut or damaged.

Contractor Responsibilities

Responsibility
Detail

Regulatory & Building Codes

The Contractor must ensure all work, materials, design, and construction comply with all applicable Federal, State, and local building codes and regulations.

Interoperability Guarantee

The Contractor is solely responsible for ensuring anchor bolt templates, base plates, and hardware are 100% compatible.

Licensed Professional Engineer

All final drawings must be stamped by a Professional Engineer who is licensed in the state where the project is operating within.

Exclusions The following tasks are strictly excluded from this agreement and will be performed by either the Government or the designated follow-on system installation entity:

Excluded Task
Performing Entity
Detail
Site Grounding
Government

Installation of lightning protection and grounding fields. (Note: The factory-installed lightning port and grounding studs on the tower are still required from the Contractor).

Active Equipment
Follow-on installation entity

Installation of the physical antennas, coaxial cabling, and active electronic cabinets.

Cabling
Follow-on installation entity

Routing of coax or fiber through the tower ports and internal conduits.

System Testing
Follow-on installation entity

RF sweeps, PIM testing, or commissioning of the GASNTi2 system.

FAA Form 7460-1
Government / Host Base

Government is responsible for ensuring the site is FAA compliant.

Tower Installation
Government / Follow-on entity

Installation of the tower structure is strictly excluded and is not the responsibility of the Contractor.

section3 - DELIVERABLES AND QUALITY ASSURANCE

Deliverables & Warranty

Item
Requirement

QA Inspection Notice

Mandatory 24-hour notice prior to the concrete pour. This period will allow the Government (COR) to approve or deny the configuration prior to concrete pour.

As-Built Drawings

Final PE-stamped drawings (ANSI/TIA-222 compliant). Final payment is contingent upon Government approval.

Warranty

Minimum 1-year warranty beginning on the date of final project acceptance by the Government.

Warranty Documentation

Manufacturer warranties for procured components, transferred/assigned to the Government, plus your contract warranty.

Geotechnical surveys and reports

Provide site-specific foundation engineering/construction, and PE-stamped drawings for each location stated within the Place of Performance section of this document.

Structural Design Calculations

The PE calculations behind the stamped drawings (wind/ice loads per TIA-222, antenna payload, base reactions).

Manufacturer data for the tower, galvanizing (ASTM A123), conduit, climbing system (Tug-Tuff), step bolts, anchor bolts.

Permits & Regulatory Approvals (copies)

Evidence that any required permits were obtained.

Certificate of Compliance (codes/standards)

Contractor will provide a single signed statement that all work complies with TIA-222, ACI 318, ASTM A123, and applicable codes.

Concrete Test Reports

Cylinder break tests / compressive strength results proving design strength was achieved.

Materials Certifications

Galvanizing certs (ASTM A123), steel mill certs, concrete mix design.

Inspection/Test Reports

If local code or ACI 318 requires special inspection (rebar placement, concrete), capture the reports and provide to the Government.

Photo Documentation

Photos of rebar, conduit placement, and embedment before pour.

Letter of Compatibility

As-built bolt survey + cure cert + erection drawings/torque + as-builts.

Approval of the "Letter of Compatibility" is a prerequisite for final payment.

Operations & Maintenance (O&M) Manuals

Manufacturer O&M for the tower, climbing system, and step bolts — for the Government's long-term sustainment.

Spare Parts List / Recommended Spares

Bill of Materials

Inventory of Delivered Tower Components

Schedule Sites must be completed prior to the No Later Than (NLT) date shown. Total project must not exceed 12 months from date of award.

Site Name/Address
Complete NLT
McConnell Air Force Base, Wichita, KS
1 Nov 2026
Goldwater
1 Dec 2026
Fairchild
1 Feb 2027
Tinker
1 Mar 2027
Grissom
1 Apr 2027
Kirtland
1 May 2027
General Mitchell
1 July 2027

ACRONYMS

COR - Contracting Officer Responsible NLT – No later than O&M - Operations & Maintenance PE - Professional Engineer TIA – Telecommunications Industry Association image1.png image2.jpeg