BARGE SERVICES FOR REFUELING OF USS JOHN P. MURTHA
Solicitation number
N00244-25-Q-0004
Issued by

About this file

This document is a Statement of Work (SOW) for tug and barge services required for the refueling of the USS John P. Murtha at the BAE shipyard in San Diego, CA. The period of performance is from November 5-8, 2024, with the actual refueling scheduled for November 7, 2024. The contractor is required to provide a barge with three 2.5m or 3.3m diameter fenders, as well as an 8", 6" or 4" hose flange with approximately 200-250' of hose. On November 6, the barge must be towed to the fuel farm at Point Loma to be loaded with 400,000 gallons of F-76 fuel. On November 7, the barge must be towed to Pier 2 at the BAE shipyard to commence refueling at 0800, with the barge required to sail back to Los Angeles at approximately 1700 that same day. The customer is responsible for coordinating the refueling with various stakeholders, including the environmental, security, and dock master teams.

View the file

Other files

File Type Posted
COMBINED SYNOPSIS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

BARGE SERVICES for REFUELING of USS JOHN P. MURTHA Pt. Loma – San Diego, CA

I. Brief Job Description:

GENERAL: This Statement of Work (SOW) covers the requirement associated with tug and barge services for USS John P. Murtha refueling on 07 November 2024. The period of performance date is 05 November 2024 to 08 November 2024 and is 4 days Refueling of barge is requested to take place on 06 November 2024, to prevent any delay in services for the actual refueling, which is scheduled for 07 November 2024. Requesting for barge to have three 2.5m or 3.3m diameter fenders, as well as an 8", 6" or 4” hose flange with approximately 200 to 250' of hose.

Targeted Schedule:

06 Nov 24 Tugs are required to two barge (barge and tugs are to be provided by contractors) to the Fuel Farm at Point Loma, to be loaded with 400,000 gallons of F-76.

07 Nov 24 Tugs are required to two barge to BAE shipyard, Pier 2 to commence refueling. Request is to commence refueling at 0800.

07 Nov 24 Barge service sail back from San Diego back to Los Angeles at approximately 1700.

II. Period of Performance: 05 November 2024 to 08 November 2024.

III. Location:

USS John P. Murtha (LPD 26) Pier 2 South BAE Shipyard, 2205 Belt St, San Diego, CA 92113

IV. Customer Responsibilities:

A. Notify Environmental, Security, and Dock Master.

B. Coordinate refueling with Jankovich Company, BAE Shipyard, as well as Engineering, and Operations Department.