This document is a Request for Proposals (RFP) from the United States Coast Guard Station South Padre Island for replacing and extending a front station gate. The project involves installing a 24-foot custom aluminum sliding high-security gate with hydraulic or electromagnetic actuation, including safety loop systems and integration with existing access controls. If approved, the project will also include extending a 670-foot 7-foot black chain link security fence with barbed wire along the top.

The scope of work requires the contractor to provide all labor, parts, and equipment for gate and fence installation, with specific requirements including commercial-grade aluminum gate materials, in-ground detection loops, and complete installation of posts and hardware. The project must be completed within 90 days of contract award, with work performed during normal operating hours (7:30am to 4:00pm Monday through Friday). Contractors must comply with strict safety regulations, provide appropriate documentation, and coordinate closely with the Contracting Officer's Representative. The project location is 1 Wallace Reed Rd, South Padre Island, Texas 78597.

View the file

Other files

File Type Posted
70Z02925QGALV0009_0_US.pdf PDF
Attachment B (INSTRUCTIONS).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

STATION SOUTH PADRE ISLAND

SPECIFICATIONS

FOR

REPLACE AND EXTEND FRONT STATION GATE

General: United States Coast Guard Station South Padre Island, TX is accepting proposals for qualified individuals or firms to acquire and conduct installation of a 24' custom aluminum high security hydraulic or electromagnetic actuated sliding gate, associated safety systems, and a if approved, a 670-foot extension of a 7' black chain link security fence. Prior to submitting a quote, it is mandatory to examine the scope of work, and it is highly recommended to visit the facility to take field measurements, evaluations, trace windows, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Coast Guard Station South Padre Island.

Location:

United States Coast Guard Station South Padre Island.

1 Wallace Reed Rd South Padre Island, Tx 78597

I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 7:30am to 4:00pm Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.

II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.

III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities.

MKCS Timothy A. Jenkins Timothy.A.Jenkins@uscg.mil 956-592-5679

IV: Recycling and Disposal of Refuse: Minor refuse, excess or waste materials resulting from construction operations may be disposed of in base dumpsters. All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk waste shall be disposed of in contractor provided with dumpsters.

V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.

VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.

VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work, and vegetation. Any damage shall be repaired at the contractor’s expense.

VIII. Contractor Identification: The contractor and subcontractor personnel shall, always, wear company identification.

IX. Existing Utilities: The Contractor shall verify all utility locations before commencing work.

This shall include, but not be limited to, the use of visual, sonic, electronic, or magnetic detection devices. Contractors shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.

X: Regulations while onboard Coast Guard Station South Padre Island:

1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on the Base will face the main flagpole & maintain silence and all vehicles & equipment will halt during these brief events.

2. The construction site shall be always maintained in a clean condition. This included daily clean-ups of the construction and storage areas. The site shall be well lit and well barricaded/cordoned off as appropriate.

3. Absolutely no firearms or weapons of any kind are allowed onboard Station South Padre Island.

4. Only American citizens and permanent resident aliens are allowed onboard Station South Padre Island Facilities. Absolutely no foreign nationals are permitted on the premises.

5. Notice shall be given to the Coast Guard’s representative 1 week in advance of any planned power, water, and sewage or lighting outages.

6. The contractor shall provide a consolidated list of all contracted personnel including their driver’s license numbers (or other valid gov’t issued ID number) who will be working on Facilities either the day of or prior to the notice to proceed date.

7. Should warnings of gale force or stronger winds, or other inbound natural disasters be issued, the contractor shall take every practicable precaution to minimize the danger to persons, to the work, and the adjacent property. These precautions shall include closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding, securing field trailers, and other appropriate equipment and other temporary work.

8. No personnel other than the contracting officer has the authority to alter the terms of any contract or to issue any change orders.

9. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times, due to security and operational needs, the contractors are subject to orders to evacuate the property at any time.

10. Due to the emergency response function of Station South Padre Island, contractor shall not block or impede movement of trailered small boats, or F-450 trucks used to tow small boats.

VIII: SCOPE OF WORK:

The objective of this project is to replace the existing front gate with a 24' custom aluminum sliding high security hydraulic or electromagnetic actuated gate and, if approved, extend the current fence 670-feet out past boat yard and closing off at front North corner of Coast Guard Station South Padre Island.

1. Contractor shall provide all parts, labor, and equipment to complete the following work:

2. A. Sliding Gate Installation

• Install one (1) 24' custom 7' high aluminum sliding gate o Gate to be commercial-grade, corrosion-resistant aluminum o Hydraulic or Electromechanical (not chain driven) o Includes all hardware and structural components

• Install commercial-grade gate operator o Includes full integration with safety and exit loop systems

• Install safety loop and exit loop o In-ground detection loops for vehicle exit and safety compliance o Proper trenching, conduit, and sealing as required

• Demo existing gate operator (if applicable) o Safe removal and disposal of the existing operator

• Connect to existing key pad or provide key pad capable of reading CAC

3. Security Fence Extension (IF APPROVED)

• Install 670 linear feet of 7' black chain link fence o Fabric to be black vinyl-coated chain link o Fence to include top rail and bottom tension wire o Includes barb wire extension (3-strand) along the top

• Installing all posts and hardware o Line posts, terminal posts, and gates posts set in concrete o Includes all fittings, caps, and tensioning hardware

• Complete installation with all required parts and materials

4. Deliverables

• Fully operational 24' sliding aluminum gate with functional operator

• Installed and tested safety and exit loop systems

• 670 linear feet of secure 7' black chain link fence with barb wire (If approved)

• Final walk-through and operational demonstration with client

• Job site clean-up and removal of all construction debris

5. Considerations

• Electrical work beyond connection of gate operator to existing power

• Landscaping or paving restoration beyond trenching area

• Permitting (unless otherwise agreed upon)

6. Safety and Equipment

• Contractor to provide all appropriate tools and equipment to complete the job, including digging equipment.

• Contractor is required to contact the “Call before You Dig” number prior to digging.

7. Required within 90 days of contract award.

Contractors shall protect all equipment, property, and merchandise in work locations and ensure safety within the work area.

All work must be approved by the Contracting Officer’s Representative.

Figure 1

FRONT GATE

FIGURE 2

FRONT GATE CONTROL UNIT

FIGURE 3

FRONT GATE BREAKER PANEL

FIGURE 4

FRONT GATE MAIN DISCONNECT

FIGURE 5

FENCE EXTENSION LOCATION

FIGURE 6

FENCE EXTENSION LOCATION ROAD

FIGURE 7

FENCE EXTENSION TERMINATION POINT

BLACK-GATE/FENCE REMOVAL

BLUE-GATE/FENCE RELOCATION

YELLOW-VEHICLE GATE/PEDESTRIAN GATE

FIGURE 8

FENCE TO BE REMOVED

FIGURE 9

LANCHA YARD FENCE EXT

Location: